NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew...

16
NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

Transcript of NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew...

Page 1: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES

2014 NWHAGeneration on the Upgrade

Matthew Wilson, P.E.

Page 3: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

GENERAL INFORMATION

• TIMELINE = FEBRUARY 2011 – JULY 2013 • PROVIDES UPSTREAM & DOWNSTREAM FISH PASSAGE

• ADDITION OF 3.6 MW

• FEDERAL ARRA GRANT = $4,671,304

• CONSTRUCTION CONTRACT = $15,087,007

• TURBINE GENERATOR AND EQUIPMENT = $4,313,723

• TOTAL LABOR HRS. WORKED = 69,823

Page 4: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.
Page 5: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

SOLIDWORKS RENDERING AERIAL PHOTO

Page 6: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.
Page 7: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

SOLIDWORKS RENDERING AERIAL PHOTO

Page 8: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

POWERHOUSE AND FISH COLLECTION

BEFORE AFTER

Page 9: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

FISH TRAM

BEFORE AFTER

Page 10: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

LESSONS LEARNED

1. Know Your Geology a) Pre-construction field studies are important but

don’t eliminate all risk.

Page 11: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

1. Know your Geology – Micropiles

Page 12: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

LESSONS LEARNED

2. Planning Space

Page 13: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

LESSONS LEARNED

2. Planning Space

Page 14: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

LESSONS LEARNED

3. Think About Maintenance

Page 15: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

LESSONS LEARNED

4. Don’t Hide the Details a) If it’s important, make it obvious b) Tell the Contractor your dimensional tolerances c) Design in such a way that eliminates Contractor

mistakes

Page 16: NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.

16

Trades Categories Journeyman Hours Apprenticeship Hours

Sub-Total Hours

Apprenticeship Share of Total Labor Hours %

Carpenters/Millwright/Diving 20,111 3,929 24,040 5.6

Laborer/Pipe layer/Fencing 13,070 3,040 16,110 4.3

Operators 9,610 1,868 11,478 2.6

Electricians 9,561 3,330 12,891 4.7

Other 4,782 522 5,364 0.8

Total 57,134 12,689 69,823 18.2

REC Credits Goal : 15% Apprenticeship

Labor

Initiative 937, approved by the voters of Washington State in November of 2006, establishedthat renewable energy projects that commence operation after December 31, 2005 having aminimum level of apprenticeship labor will obtain a credit towards the utility’s renewableenergy target.