North Eastern Electricity Supply Company of Odisha...
Transcript of North Eastern Electricity Supply Company of Odisha...
North Eastern Electricity Supply Company of
Odisha Limited
*****************************************
TENDER SPECIFICATION FOR
INSTALLATION/REPLACEMENT/SHIFTING OF SINGLE
PHASE/INSTALLATION OF THREE PHASE ENERGY METERS
(UNDER CAPEX PROGRAMME)
TENDER NOTICE No: NESCO/PUR/CAPEX/
INSTALLATION / 42/231 Date: 06.01.2015
1. DATE OF OPENING OF TENDER: 28.01.2015
2. TIME: 03:30 PM
3. PLACE: Corporate Office, NESCO, Januganj, Balasore –
756019
NORTH EASTERN ELECTRICITY SUPPLY COMPANY OF ODISHA LIMITED
Corporate office: Januganj, Balasore-756019, CIN:U40109OR1997PLC005106
Regd.Office: Plot No.N-1/22, Nayapalli,IRC Village, Bhubaneswar-751015,
www.nescoodisha.com, Email Id: [email protected]
TENDER NOTICE No: NESCO/PUR/CAPEX/ INSTALLATION / 42/231 Date:
06.01.2015
SECTION
NO DESCRIPTION PAGE NO
SECTION-I INVITATION FOR BIDS (IFB) 5 TO 8
SECTION-II GENERAL TERMS & CONDITIONS OF CONTRACTS (GTCC) 9 TO 30
SECTION-III ANNEXURES 31
ANNEXURE-I BID PROPOSAL LETTER 32 TO 38
ANNEXURE-II DECLARATION FORM 39
ANNEXURE-III PBG FORMAT 40-42
ANNEXURE-IV BANK GUARANTEE FOR ADVANCE PAYMENT 43-45
ANNEXURE-V POWER OF ATTORNEY FOR JOINT VENTURE 46-47
ANNEXURE-VI JOINT VENTURE AGREEMENT 48-53
ANNEXURE-VII (A&B) LETTER OF COMPLIANCE 54-60
ANNEXURE-VIII COMMERCIAL DEVIATIONS 61
ANNEXURE-IX TECHNICAL DEVIATIONS 62
ANNEXURE-X ADDITIONAL INFORMATION 63
ANNEXURE-XI WORKS COMPLETION SCHEDULE 64
ANNEXURE-XII CHECK LIST 65-66
ANNEXURE-XIII PROFORMA FOR INDEMENITY BOND 67-69
ANNEXURE-XIV SELF DECLARATION FORM 70
ANNEXURE-XV (A&B) PROFORMA FOR BG FOR EANEST BANK
GUARANTEE & EXTENTION THEREOFF 71-73
RATE OF QUOTATION 74
DRAWING FOR DTR METERING (1) & (2) 75 - 76
NORTH EASTERN ELECTRICITY SUPPLY COMPANY OF ODISHA LIMITED
(Formerly North Eastern Electricity Supply Company of Orissa Limited)
Corporate office: Januganj, Balasore-756019, CIN:U40109OR1997PLC005106
Phone No.06782-269864, Fax: 06782-263259.
Regd.Office: Plot No.N-1/22, Nayapalli,IRC Village, Bhubaneswar-751015,
www.nescoodisha.com, Email Id: [email protected]
TENDER NOTICE NO: NESCO/PUR/CAPEX/ INSTALLATION / 42/231 Date: 06.01.2015
For and on behalf of North Eastern Electricity Supply Company of Orissa Ltd. (NESCO), the undersigned invites sealed bids in duplicate on two part bidding system from qualified and eligible bidders, who comply with the terms and conditions for the following works to be executed in the respective licensed area in the State of Odisha.
Installation/Replacement/Shifting of Single Phase Meter:-
DIVISION
Total
(1Ph
Meter)
in Nos
No. of
Consumer
Metering
(3Ph WC/
HTTV )
No. of
DTR
Meterin
g
EMD
( In
Lakhs)
Required
Turn
Over
(Rs. in
Crores)
Date of
Pre-bid
Meeting
Last
date/ti
me for
submis
sion of
bids
Date
and time
of
opening
of bid
Non
refundable
Cost of Bid
document
BED,
Balasore 3873
15 80 0.19 0.1
Dt.19.01.
15
at
11.30AM
Dt.28.1.
15 at
2.00PM
Dt.28.1.
15 at
3.30PM
Rs.
6,300.00
including
VAT
@5%
For each
Package
CED,
Balasore 9792
160 250 0.50 0.25
BtED, Basta 6049 885 710 0.56 0.28
JED, Jaleswar 4155 1123 350 0.36 0.18
SED, Soro 14556 239 550 0.81 0.40
BNED,
Bhadrak 17463
60 1210 1.17 0.58
BSED,
Bhadrak 18116
112 250 0.83 0.41
BpED,
Baripada 11967
196 1150 0.93 0.47
RED,
Rairangapur 5490
94 150 0.28 0.14
UED, Udala 5609 47 450 0.40 0.20
KED,
Keonjhar 10636
38 200 0.50 0.25
JoED, Joda 11137 45 500 0.64 0.32
AED,
Anandapur 14822
65 600 0.83 0.41
JRED, Jajpur
Road 9875
53 0 0.40 0.20
KuED,
Kuakhia 14523
333 750 0.89 0.44
JTED, Jajpur
Town 16998
535 800 1.02 0.51
TOTAL 175061 4000 8000
The intending bidders can also download the tender document from our website
www.nescoodisha.com. However the bidder has to furnish a Demand Draft drawn on any Scheduled
Bank in favour of “North Eastern Electricity Supply of Orissa Ltd” payable at Balasore for the cost of the
Tender Paper indicated above, along with his bid, failing of which the bid will be rejected outright. In
the event of any specified date for the sale, submission or opening of bids being declared as holiday for
NESCO, the bids will be sold / received / opened up at the appointed time on the next working day.
NESCO also reserves the right to accept or reject any or all tenders without assigning any reason
thereof, if the situation so warrants.
For detail Tender Specification & Terms and Conditions, please visit our website www.nescoodisha.com
Dy. General Manager (C&P)
NESCO, Balasore.
SECTION – I
INVITATION FOR BIDS (IFB)
TENDER NOTICE NO: NESCO/PUR/CAPEX/
INSTALLATION/42/231 Date: 06.01.2015
1.0 NESCO invites sealed tenders from reputed Electrical Contractors with required license, either
in individual capacity or as part of a joint venture agreement / consortium for carrying out
installation/ shifting and replacement of defective single phase meters with box from inside to
outside premises and installation of 3-Ph meters for consumers and DTR metering in the
jurisdiction of their respective licensed area. The bidder must fulfil all the qualification
requirements as specified in clause 2.0 stated below. The sealed envelopes shall be duly super
scribed as “TENDER NOTICE No: NESCO/PUR/CAPEX/ INSTALLATION/ 42/231 Date: 06.01.2015
Name of
Packages
Earnest Money
Deposit
Last date/time for
submission of bids
Date and time of
opening of bid
Non refundable Cost of Bid
document*
1 2 3 4 5
As per
tender
Notice
above
As per tender
Notice above
Dt.28.01.15 till
2.00PM
Dt.28.01.15 at
3.30PM As per tender Notice above
2.0 Bidders to be considered as eligible (to bid) should meet the following qualifications;
(a) Bidder may quote for any one package or for multiple packages; however, bidder must
quote for the entire quantum of works specified under each such package(s).
(b) The bidder should have experience in installation and commissioning of quantum of work as
specified under such Packages.
(c) If the bidder(s) participate in multiple packages, the qualifying requirement for work
experience shall be considered /evaluated independently/separately for each package.
The work order shall be awarded minimum two (02) Packages to a bidder for installation of
single phase meter & 3-phase meters irrespective of nos. of packages for which he has
submitted the bid.
(d) The minimum average Annual Turnover of the bidder in any best three financial years out
of last five financial years should not be less than the annual Turn Over as mentioned in
Tender notice for all the package(s) quoted by the bidder(s).
(e) Bidder shall be financially sound and stable having liquid assets as stated in the enclosed
format and/or access to credit facility of not less than the estimated cost of the package(s) for
which he has submitted the bid.
NB: 1) Only cash at bank / in hand & fixed deposit mentioned in the audited balance
sheet of last FY shall be considered for accessing the Liquid Asset.
2) The average unutilized credit limit during the month prior to the month of bidding
shall be considered to access the credit facility.
(f) Two or more like minded contractor(s) and/or manufacturer(s) of electrical items, which are
under scope of supply of the contractor as per this tender specification, may form a joint
venture/ consortium agreement amongst themselves and apply against this tender
specification, provided they qualify the criteria. The sample format of joint venture /
consortium agreement is enclosed at Section – III of this tender specification as Annexure - VI.
NOTE: 1) Joint Venture/Consortium Partner shall be limiting to 04 (Four) Members.
2) One of the Members shall be an Electrical Contractor having valid HT License.
3) Work Order shall be issued in favour of the Lead Partner only
However, if the bidder is quoting against one or more package(s) in his individual capacity, he
cannot be a part of joint venture / consortium agreement to participate in same package(s) as
notified against this tender specification & vice versa.
(g) If the work experience of one partner is not meeting the entire qualifying criteria, the work
experience of the other partner (s) specified in the scope of work shall be added for
qualifying the bid in total.
Lead Partner shall have minimum 50% of Turn Over & 50% of work experience and other
partner(s) together shall have balance 50% Turn over & Work experience.
(h) One of the partners shall be nominated as Lead Partner and the lead partner shall be
authorized to incur liabilities and receive instructions for and on behalf of all partners of the
joint venture / consortium and entire execution of the contract including receipt of payments
shall be done exclusively through the lead partner. This authorization shall be evidenced by
submitting by a Power of Attorney signed by legally authorized signatories of all partners.
(i) All partners of joint venture / consortium shall be liable jointly and severally for the
execution of contract in accordance with the contract terms and a copy of the agreement
entered into by the joint venture / consortium partners having such a provision shall be
submitted with the Bid. A statement to this effect shall be included in the authorization
mentioned as above as well as in the Bid form and in Contract form (in case of a successful bid).
(J) In addition to above the bidder(s)/Lead Partner of the bidder(s) should submit the
following documents in part-I bid as qualifying terms.
i. Valid electrical (HT) license for electrical works.
ii. EPF registration
iii. PAN & TIN No.
iv. Service tax registration.
v. ESI registration.
vi. Labour license.
(k) The bidders who have earlier failed to execute the work order(s) of NESCO shall not be
eligible to participate in this tender.
(l) NESCO reserves the right to waive minor deviation, if they do not materially affect the
capacity of the bidder to perform the contract.
3.0 Bids specification document can be obtained from the office of the undersigned on payment of
required tender fees as per tender notice through Bank DD drawn in favour of “North Eastern
Electricity Supply Company of Orissa Ltd.” payable at Balasore, during office hours from 11.00
am to 5.00 pm till dt.27.01.15.
4.0 The tender documents can also be downloaded from any of the following websites
www.nescoodisha.com. In case tender papers are downloaded from these websites, then the
bidder has to enclose a Demand Draft, drawn on any Scheduled bank in favour of “North
Eastern Electricity Supply Company of Orissa Ltd. payable at Balasore, covering the cost of bid
documents as stated above in a separate envelope with suitable superscription “Cost of Bid
Documents: Tender Notice No.: …………………”. This envelope should accompany the Bid
Documents.
5.0 The Bids shall be submitted and received in the office of the undersigned on all office working
days up to 2.00 PM of Date 28.01.15. In the event the date of opening is a holiday, the next
working day shall be treated as the date of opening.
6.0 Part-I of the bid (Technical Bid) will be opened on Dated.28.01.15 at 3.30 PM as indicated
above, in the presence of the authorized representatives of the Bidders. Bidders shall depute
only one representative to attend pre bid meeting and tender opening if they wish to be
represented. The undersigned reserves the right to reject any or all tenders if the situations so
warrants.
7.0 All correspondence with regard to the above shall be made to the following address:
DGM (Contracts & Procurement)
CorporateOffice,NESCO,Januganj,Balasore,Odisha,Pin-
756019,[email protected]
SECTION – II
GENERAL CONDITIONS OF CONTRACT (GCC)
TENDER NOTICE NO: NESCO/PUR/CAPEX/ INSTALLATION/42/231
Date: 06.01.15
1.0 GENERAL: -
The NESCO covering around 12.5 Lac consumers in 5 districts of Orissa.
To improve the quality of services for existing and prospective customers and reduce the AT
& C loss of NESCO, Corporate Office of NESCO wishes to installation / Shifting and
replacement of defective Single Phase Meters with and without box from inside to outside
premises under CAPEX through licensed contractor with the objective to improve billing
efficiency of NESCO and quality of service to its consumers.
2.0 LOCATION AND SCOPE OF WORK:
(i)The work shall cover complete installation of new 1 ph 2W meters with TP box
as per attached consumer list along with their addresses, service connection no,
meter no, last available reading /date etc (Annexure-A) in sweeping manner under
this mass meter shifting and/or replacement work for all the consumers under the
list as per following criteria:
In case of Electromagnetic meters, Hybrid type Electronic meters or Defective
Electronic Static meter with LCD display located outside the consumer premises
shall be provided or replaced with the new meter.
In case of No meter, defective meter, Electromagnetic meters, Hybrid type'
Electronic meters or Defective Electronic / Static meter with LCD display shall be
provided or replaced with the new meter. However if such meter are found inside
the consumer premises and to be replaced this needs to be shifted from inside to
outside the house at the entrance of the consumer residing dwelling.
In case of cut/joint of service connection wire found before meter the service wire
is to replaced by new one with replacement of new meter. The required service
wire for this purpose will be supplied by NESCO.
You should return the dismantled old meters and dismantled service wire if any
with list of consumers, meter sI. No., final reading etc to corresponding Section
Store with proper receipt within 7 days of dismantled. All meters issued shall be
through MMS module and all information after installation shall be entered in the
MMS module for proper documentation and necessary payment of bills.
(ii)In case of installation of new 3-Ph WC, HTTV & LTCT meters, the details of
consumer list with address are to be supplied by NESCO at the time of execution
of work for consumer metering and DTR metering.
For DTR metering, materials required for installation works are to be provided by
Contractor. Details of material requirement for DTR metering along with Drawing
is attached at Annexure-.
You shall have to complete the job within Two months from the date of awarding
of technically & commercially clear work order along with complete consumer list
and receipt of materials from NESCO excluding 15 days mobilization period for
deploying the teams, arranging storage space and failing which NESCO reserves
the right to impose penalty as mentioned.
3.0 DEFINITION OF TERMS
(i) The „Contract ‟means the agreement entered into between the Owner and the
Contractor as per the Contract Agreement signed by the parties, including all
attachments and appendices there to and all documents incorporated by reference
therein.
(ii) „Owner‟ shall mean NESCO and shall include its legal representatives, successors
and assigns.
(iii) „Contractor‟ shall mean the Bidder whose bid will be accepted by the Owner for the
award of the Works and shall include such successful Bidder‟s legal representatives,
successors and permitted assigns.
(iv) „Sub-Contractor‟ shall mean the person named in the Contract for any part of the
works or any person to whom any part of the Contract has been sublet by the
contractor with the consent in writing of the Owner and will include the legal
representatives, successors and permitted assigns of such person.
(v) „Engineer in Charge‟ shall mean the officer appointed in writing by the Owner to act
as Engineer from time to time for the purpose of the Contract.
(vi) „Specifications‟ shall mean the specifications and Bidding Document forming a part
of the Contract and such other schedules and drawings as may be mutually agreed
upon.
(vii) „Site‟ shall mean and include the land and other places on, into or through which the
works and the related facilities are to be erected or installed and any adjacent land,
paths, street or reservoir which may be allocated or used by the Owner or
Contractor in the performance of the Contract.
(viii) „Inspector‟ shall mean the Purchaser or any person nominated by the Owner from
time to time, to inspect the equipment; stores or Works under the Contract and/or
the duly authorized representative of the Owner.
(ix) „Notice of Award of Contract‟/ „Letter of Award‟ shall mean the official notice
issued by the Owner notifying the Contractor that his bid has been accepted.
(x) „Date of Contract‟ shall mean the date on which notice of Award of Contract/ Letter
of Award has been issued.
(xi) „Performance and Guarantee Tests‟, shall mean all operational checks and tests
required to determine and demonstrate capacity, efficiency, and operating
characteristics as specified in the Contract Documents.
(xii) The term „Final Acceptance‟/ „Taking Over‟ shall mean the Owner‟s written
acceptance of the works performed under the Contract, after successful
commissioning/ completion of Performance and Guarantee Tests, as specified in the
accompanying Technical Specifications or otherwise agreed in the contract.
(xiii) „Commercial Operation‟ shall mean the condition of operation in which the
complete equipment covered under the Contract is officially declared by the Owner
to be available for continuous operation at different loads up to and including rated
capacity. Such declaration by the Owner, however, shall not relieve or prejudice the
Contractor of any of his obligations under the Contract.
(xiv) Words imparting „Person‟ shall include firms, companies, corporations and
associations or bodies of individuals, whether incorporated or not.
(xv) Terms and expressions not herein defined shall have the same meaning as are
assigned to them in the Indian Sale of goods Act (1930), failing that in the Indian
Contract Act (1872) and failing that in the General Clauses Act (1897) including
amendments thereof, if any.
(xvi) In addition to the above the following definition shall also apply
a) „All equipment and materials‟ to be supplied shall also mean „Goods‟
b) „Constructed‟ shall also mean erected and installed.
c) „Contract Performance Guarantee‟ shall also mean „Contract
Performance Security‟.
4.0 PROJECT MANAGER & PROJECT ORGANISATION:
Executing Agency shall appoint a Project Manager for this Contract, within 14
days of issuance of this order & submit a chart showing proposed organization to
be established for carrying out the work including the identity of key personals.
Your Project Manager shall represent and act for you at all times during the
currency of the Contract and shall be responsible for all notices, instructions,
information and all other communications under the Contract with Engineer- in-
Charge.
5.0 SUBMISSION OF TENDER: -
5.01 Sealed tenders in Two parts each in duplicate, each complete in all respects in the
manner hereinafter specified are to be submitted at Corporate Office, NESCO,
Januganja, Balasore, PIN:-756019 on or before the date and time specified in the notice
inviting the tenders. Bids shall be submitted as per format provided in Section – III & IV.
Each copy of the bids (original and duplicate) shall be submitted in separate double
sealed envelopes superscripted on each of the covers the tender specification number
and the due date of opening of the bids on the right hand top side of the envelop. On
the left top side original/ duplicate as is relevant shall be written.
5.02 The tenders are required to be submitted in Two Parts each in separate double sealed
covers.
Part - I: Superscribed as “Technical and commercial bid for 1-Ph/3-Ph Meter” shall
contain EMD, Cost of Bid Documents and Techno commercial documents.
Part - II, Superscribed as “Price Bid for 1-Ph/3-Ph Meter”. The Part - II should contain
only Price bid.
5.03 Fax and Telegraphic tenders shall not be accepted.
5.04 Receipt of bids/ revised bids after the cut off time and date as specified in the Tender
specification shall not be permitted and such bids shall be rejected outright. The Owner
shall not be responsible for any delay in transit in post / courier etc. in this regard.
6.0 VALIDITY:-
The offer shall be valid for a period not less than 180 days from the date of bid
opening.
7.0 PRICE: -
Bidders are required to quote firm price as per the prescribed format enclosed in
Section – III. The quoted price shall be firm and inclusive of all taxes, duties, freight &
insurance and other levies, if any. Owner shall not be liable to pay anything extra over and
above the quoted price.
The price includes: Site Survey, handling & transportation of meters and associate
TP box from the NESCO's designated stores to the installation sites, unpacking,
inspection on
receipt at site, Removal/Shifting of existing/defective meter from inside to outside
of consumer premises. (Shifting to be done in case of meter inside the consumer
house) , Installation of new meter/existing meter with TP box at a location outside
the consumer premises near to the main entrance or at a place such that it could
be accessible without entering the consumer's dwelling unit.
Sealing and filling up the installation report with required data and information-
complete in all respects and return of replaced meters to section stores.
Photograph of the meter shall be taken before and after installation for both
shifting and replacement and submit the soft copy along with consumer no. to
Engineer-in-charge. The photographs taken before and after installation in a such
way that the meter reading, meter Sl. No. and consumer No. should be clearly
visible. In case the consumer No. is not written on the existing meter the same
should be written on the meter/meter box or close to the meter before taking
photograph. The file name of the photograph should be same as the consumer
number. No extra charges will be payable for this soft copy so, the price quotation
should inclusive of above.
In case of DTR metering for installation of 3-Ph LTCT meter in addition to above,
the price includes the cost of materials for construction of required structure as
per drawing for fixing the meter.
8.0 RECEIPT AND OPENING OF THE BID: -
8.01 Bids in duplicate as described under clause 4.0 shall be received in the office of the
Owner and shall be opened on the scheduled date and time. The Owner‟s authorized
representatives shall open bids in the presence of Bidders‟ representatives on the date
and time for opening of bids as specified in the Invitation to Bid or in case any extension
has been given thereto, on the extended bid opening date and time notified.
8.02 Maximum one representative for each bidder shall be allowed to witness the opening of
bids. The representative must produce suitable authorization in this regard to be eligible
to witness the bid opening on behalf of the bidder. Bidders‟ representatives who are
present shall sign in a register evidencing their attendance.
8.03 The Bidders‟ names, bid prices, modifications, bid withdrawals and the presence or
absence of the requisite bid guarantee and such other details as the Owner, at its
discretion, may consider appropriate will be announced at the opening. No electronic
recording devices will be permitted during bid opening.
8.04 Information relating to the examination, clarification, evaluation and comparison of Bids
and recommendations for the award of a contract shall not be disclosed to Bidders or
any other persons not officially concerned with such process. Any effort by a Bidder to
influence the Owner‟s processing of Bids or award decisions may result in the rejection
of the Bidder's Bid.
9.0 EVALUATION OF BIDS & AWARD OF CONTRACT:
9.01 To assist in the examination, evaluation and comparison of Bids, the Owner may, at its
discretion, ask the Bidder for a clarification of its Bid. All responses to requests for
clarification shall be in writing and no change in the price or substance of the Bid shall
be sought, offered or permitted.
9.02 Owner will examine the Bids to determine whether they are complete, whether any
computational errors have been made, whether required sureties have been furnished,
whether the documents have been properly signed, and whether the Bids are generally
in order.
9.03 Arithmetical errors will be rectified on the following basis. If there is a discrepancy
between the unit price and the total price per item that is obtained by multiplying the unit
price and quantity, the unit price shall prevail and the total price per item will be
corrected. If there is a discrepancy between the Total Amount and the sum of the total
price per item, the sum of the total price per item shall prevail and the Total Amount will
be corrected.
9.04 Prior to the detailed evaluation, Owner will determine the substantial responsiveness of
each Bid to the Bidding Documents including production capability and acceptable
quality of the Goods offered. A substantially responsive Bid is one, which conforms to all
the terms and conditions of the Bidding Documents without material deviation.
9.05 The Owner‟s evaluation of a Bid will take into account, in addition to the Bid price, the
following factors, in the manner and to the extent indicated in this Clause:
(a) Work Schedule
(b) Deviations from Bidding Documents
9.06 The Owner will award the Contract to the successful Bidder whose Bid has been
determined to be the lowest - evaluated responsive Bid,, when the lowest bidders is not
ready and/or capable to undertake the entire work envisaged, then the Owner may
explore the possibility of the execution of works through other bidders if they are willing
to execute at L1 rate. Such exploration shall be carried out in a sequential order starting
with L2 bidder then with L3 bidder and so on.
9.07 In case of omission of any item in the price bid or the price for the item has not been
quoted by the firm, then zero cost shall be loaded to the bid and the contract shall be
awarded with zero cost that means the firm will have to bear the cost of that item
entirely as the item price shall be considered as inclusive anywhere in other items. The
bidder shall have to give an undertaking to the effect that prices for any item not quoted
shall be treated as free supply or to be done free of cost.
10.0 EARNEST MONEY DEPOSIT (EMD):-
10.01 The Tender must be accompanied by Earnest Money Deposit as described in the
Tender Notice in shape of Bank Guarantee issued by a Scheduled Bank (valid for 30
days beyond the validity of bid) only and en-cashable at Balasore or in shape of
Demand Draft drawn on any scheduled bank in favour of “North Eastern Electricity
Supply Company of Orissa Ltd.” payable at Balasore. Bids without EMD deposit will be
rejected out rightly. The Bank Guarantee for EMD shall be strictly as per the format
(Annexure – XVII) prescribed by the Owner. In case of any deficiency such as the
ownership of the security bond (other than the issuing bank), deviation from the
approved format, absence of signature of witness etc. found in the EMD Bank
Guarantee, the same shall be liable for rejection upfront. The bidder will not be given
any chance to rectify the same.
NB: 1) The validity of EMD BG shall be minimum for 30 days over and above the
validity of the tender (180 days) i.e., 210 days from the date of opening of the
tender.
2) In case of Joint Venture / Consortium, EMD in shape of BG shall be provided by
the Lead Partner.
10.02 No adjustment of any previous deposit or any amount payable from Purchaser shall be
entertained for EMD. EMD amount so submitted shall not carry any interest payable to
the bidder.
10.03 The Earnest Money so deposited shall be forfeited:
(a) if the Bidder:
i) withdraws its bid during the period of bid validity specified by the Bidder in the Bid
Form; or
(b) in the case of a successful Bidder, if the Bidder fails:
(i) To sign the Contract, or
(ii) To furnish the required Contract Performance Bank Guarantee.
10.04 The EMD of unsuccessful bidders shall be returned within 30 days from the date of
finalization of the order.
11.0 OWNER’S RIGHT TO VARY QUANTITIES AT TIME OF AWARD:
While placing orders and / or during execution of contract, Owner reserve the right to
increase or decrease the quantity of goods and services specified in the Schedule of
Requirement up to 20% of the tender quantity without any change in price or other
terms and conditions.
12.0 INSPECTION AND TESTING:-
12.1 All the installations shall be inspected by the Owner or any authorized representative of
the Owner at the Consumer‟s premises/ at work site during execution or after
completion of the work.
12.2 The Engineer-in-charge shall be entitled at all reasonable times during installation to
inspect examine and test the materials at the contractor‟s premises / erection site about
workmanship of the materials to be supplied under this contract.
13.0 COMMENCEMENT & COMPLETION OF WORK:
The basic consideration and essence of the Contract is strict adherence to the
time schedule. The contract shall be performed in such a manner so as to meet
the Time for Completion i.e. within Two (2) months from the date of receipt of the
work order along with complete consumer list and receipt of materials from
NESCO. In addition to this, you shall be allowed 15 days as initial. mobilization
period for site setup and commencement of work. Looking at your performance
NESCO reserves right to place order for additional quantity of same terms and
conditions.
14.0 REJECTION OF MATERIALS: -
In the event of the materials supplied by the contractor and/or the installation works are
found to be defective in quality and the workmanship is poor or otherwise not in
conformity with the requirements of the contract, Owner shall reject such materials /
services and ask the contractor in writing to replace / rectify the defects. The contractor
on receipt of such notification shall rectify or replace the defective materials and/or re-
install the work already executed, free of cost to the Owner. If the contactor fails to do
so the Purchaser may at his option take the following actions which could be on
concurrent basis.
A) Replace or rectify such defective materials and recover the extra cost so
involved plus 25% from the Contractor.
B) Terminate the contract for balance supply and erection with enforcement of
penalty as per contract.
C) Acquire the defective materials at reduced price considered acceptable under
the circumstances.
D) Forfeit the Contract Performance Bank Guarantee.
15.0 EXPERIENCE OF BIDDERS: -
The bidders are required to furnish information regarding their experience on the
following aspects as per format provided in Section – IV, Annexure VII (A) & (B):
i. Description of similar type of work with same or higher voltage level executed
during the last three years with the name(s) of the party(s) to whom / where
supplies / erection were made.
ii. The list of testing equipments/ facilities available to execute the contract
covering both OSM and supply by the Contractor himself. Also the area of
access of the Contractor through other agency must be indicated.
iii. Purchase / work orders details (P.O / W.O No. and date only) executed
(construction work) during the last three years along with Electrical inspection
report copies and copies of user‟s performance certificates.
Bids may not be considered if the past performance is found to be un-satisfactory.
16.0 DEVIATION FROM SPECIFICATION: -
The bidders are requested to study the specification and the attached drawings
thoroughly before tendering so that if they make any deviations, the same are
prominently brought on a separate sheet under the headings “Deviations” as per
formats provided under Section IV, Annexure – VIII & IX. All such deviations to the
technical & commercial terms of the specification shall be indicated in a separate list as
indicated above. In absence of such deviation schedule, it will be presumed that the
bidder has accepted all the conditions stipulated in the tender specification, not
withstanding any deviations mentioned elsewhere in the Bid. However the acceptance
of deviation is not binding on the Owner.
17.0 CONTRACTOR TO INFORM HIMSELF FULLY: -
The contractor shall examine the instructions, general conditions of the contract,
specifications and the schedule of quantity and delivery to satisfy himself as to all the
terms and conditions and circumstances affecting the contract price. He shall quote
prices according to his own judgment and shall understand that no additional cost
except as quoted shall only be considered.
18.0 PATENT RIGHT: -
The contractor shall indemnify the Owner against all claims, actions, suits and
proceedings for the alleged infringement any patent design or copy right protected
either in country of origin or in India by the use of any equipment supplied by the
contractor but such indemnity shall not cover any use of the equipment other than for
the purpose indicated by or reasonable to be informed from the specification.
19.0 GUARANTEE PERIOD: -
19.01 The materials to be supplied by the contractor shall be guaranteed for satisfactory
operation against defects in design and workmanship for a period of 24 months from
the date of handing over the completed installations after commercial operation at
required voltage level.
19.02 The above guarantee certificate shall be furnished in triplicate to the Owner for his
approval. Any defects noticed during the above period should be rectified by the
Contractor free of cost to the Utility provided such defects are due to faulty design, bad
workmanship or bad materials used on receipt of written notice from the Owner. The
Contractor as notified by the Owner shall rectify any such defects within one month
failing which the Owner will set right the defects through other agency and recover the
cost so incurred either from any pending Invoices or Bank Guarantee.
20.0 PENALTY FOR DELAY IN COMPLETION OF CONTRACT: -
20.01 If the contractor fails to complete the works by the scheduled period or any extension
granted thereby, the contractor shall be liable for payment of penalty amounting to 0.5%
(half percent) of the contract price per week of un-finished works subject to the
maximum of 5% (five percent) of the total contract price and subject to force majeure
conditions. After receipt of LOA, the Contractor shall sign a contract agreement with the
Owner within 15 days along with the detail work plan through PERT chart/BAR chart.
The penalty for liquidated damage as mentioned above will be levied if any deviation to
be schedule on any item of work due to the fault of the contractor is observed.
20.02 Penalty amount can be realized from the proceeds of the Contract Performance Bank
Guarantee, if the situation so warrants.
20.03 Extension of delivery period could be with / without levy of penalty with the discretion of
Owner.
21.0 RIGHT OF WAY:
Right of way issues, if any, arising during execution of the works shall have no liability
on the Owner. These issues shall be settled at the sole discretion of the Contractor. The
Owner shall however extend all possible help to the Contractor including discussion with
the local authorities for early resolution of these issues.
22.0 CONTRACTOR’S DEFAULT:
22.01 If the Contractor neglects to execute the works with due diligence and expedition or
refuses or neglects to comply with any reasonable order given to him, in writing by the
Engineer in connection with the works or contravenes the provisions or the contract, the
Owner may give notice in writing to the Contractor to make good the failure, neglect or
contravention complained of. Should the Contractor fail to comply with the notice within
thirty (30) days from the date of serving the notice, the Owner shall be at liberty to
employ other workmen and forthwith execute such part of the works as the contractor
may have neglected to do or if the Owner thinks fit, without prejudice to any other right,
he may have under the Contract to take the work wholly or in part out of the
Contractor‟s hands and re-contract with any other person or persons to complete the
works or any part thereof and in that event the Owner shall have free use of all
Contractor‟s equipment that may have been at the time on the Site in connection with
the works without being responsible to the Contractor for fair wear and tear thereof and
to the exclusion of any right of the Contractor over the same, and the Owner shall be
entitled to retain and apply any balance which may otherwise be due on the Contract by
him to the Contractor, or such part thereof as may be necessary, to the payment of the
cost of executing the said part of works or of completing the works as the case may be.
If the cost of completing of works or executing part thereof as aforesaid shall exceed the
balance due to the Contractor, the Contractor shall pay such excess. Such payment of
excess amount shall be independent of the liquidated damages for delay which the
Contractor shall have to pay if the completion of works is delayed.
22.02 In addition, such action by the Owner as aforesaid shall not relieve the Contractor of his
liability to pay liquidated damages for delay in completion of works.
22.03 Such action by the Owner as aforesaid the termination of the Contract under this clause
shall not entitle the Contractor to reduce the value of the Contract Performance
Guarantee nor the time thereof. The Contract Performance Guarantee shall be valid for
the full value and for the full period of the Contract including guarantee.
23.0 TERMINATION OF CONTRACT ON OWNER’S INITIATIVE:
23.01 Owner reserves the right to terminate the Contract either in part or in full due to reasons
other than those mentioned under clause entitled „Contractor‟s Default‟. The Owner
shall in such an event give fifteen (15) days notice in writing to the Contractor of his
decision to do so.
23.02 The Contractor upon receipt of such notice shall discontinue the work on the date and to
the extent specified in the notice, make all reasonable efforts to obtain cancellation of all
orders and Contracts to the extent they related to the work terminated and terms
satisfactory or the Owner, stop all further sub-contracting or purchasing activity related
to the work terminated, and assist Owner in maintenance, protection, and disposition of
the works acquired under the Contract by the Purchaser. In the event of such a
termination the Contractor shall be paid compensation, equitable and reasonable,
dictated by the circumstance prevalent at the time of termination to be determined by
the arbitrator without stopping the work but to carry out the left over work to other
agency.
23.03 If the Contractor is an individual or a proprietary concern and the individual or the
proprietor dies and if the Contractor is a partnership concern and one of the partners
dies then unless the Owner is satisfied that the legal representatives of the individual
Contractor or of the proprietor of the propriety concern and in the case of partnership,
the surviving partners, are capable of carrying out and in the case of partnership, the
surviving partners, are capable of carrying out and completing the Contract the Owner
shall be entitled to cancel the Contract as to its uncompleted part without being in any
way liable to payment of any compensation to the estate of deceased Contractor and
/or to the surviving partners of the Contractor‟s firm on account of the cancellation of the
contract. The decision of the Owner that the legal representatives of the deceased
Contractor or surviving partners of the Contractor‟s firm cannot carry out and complete
the contract shall be final and binding on the parties. In the event of such cancellation
the Owner shall not hold the estate of the deceased Contractor and/ or the surviving
partners of the Contractor‟s firm liable to damages for not completing the Contract.
24.0 FORCE MAJEURE:
Force majeure is herein defined as: Any cause which is beyond the control of
Contractor or NESCO as the case may be Natural phenomenon including but not
limited to weather conditions, floods, draughts, earthquakes, epidemic Acts of any
Govt. authority domestic or foreign including but not limited to war, declared or
undeclared, priorities quarantines, embargoes, licensing control or production or
distribution restrictions. Accidents & disruptions including but not limited to fires,
explosions, breakdown of essential machinery or equipment and transportation delay
due to accidents Strikes & lockouts continuing for more than 3 weeks & sabotage
Failure or delay in source of supply due to Force majeure cause enumerate above.
If any of the above conditions occurs during the term of contract, contractor shall within
ten (10) days from the beginning of such delay notify the Owner in writing of the cause
of delay. The Owner shall verify the facts and grant extension as facts justify.
25.0 EXTENSION OF TIME: -
If the delivery of the equipments / materials is delayed due to reasons beyond the
control of the Contractor, the Contractor shall immediately inform within 3 days to the
Owner in writing of his claim for an extension of time. The Owner on receipt of such
notice may agree to extend the contract period as may be reasonable but without
prejudice to other terms & conditions of the contract.
26.0 ADHERENCE TO SAFETY PROCEDURES, RULES, REGULATIONS:-
Contractor shall comply with the provision of all laws including' labour laws, rules,
Electrical licenses, regulations and notifications issued there under from time to time. All
safety and labour laws enforced by statutory agencies and by NESCO shall be applicable
in the performance of Work and contractor shall abide by these laws.
Contractor shall be responsible to comply with all the statutory obligations arising out
of Law of the Land. Contractor should be duly registered with Provident Fund, ESI
authority and liability for such payment to these authorities shall be entirely borne by
contractor. NESCO shall not bear any responsibility whatsoever under this account.
Contractor shall take all measures necessary or proper to protect the personnel, work
and facilities and shall observe all reasonable safety rules and instructions. Contractor
shall adhere to all security requirement/regulations of the NESCO during the execution of
the work. NESCO's employee also shall comply with safety procedures/policy.
Contractor shall report as soon as possible any evidence, which may indicate or is
likely to lead to an abnormal or dangerous situation and shall take all necessary
emergency control steps to avoid such abnormal situations.
27.0 STORE:-
Storing of materials from supply to erection shall be arranged by the contractor at his own
cost. No compensation shall be made by the Owner for any damage or loss of materials
during storing, transit transportation and at the time of erection.
Contractor shall arrange for proper space to operate site offices & stores conveniently at
the work location, to store the materials issued by NESCO and execution of the works
free of cost. All other infrastructure, amenities, security, safety for such space shall be
arranged and managed by contractor.
28.0 WATCH & WARD:-
Contractor shall be responsible for arranging suitable watch & ward of the equipment/
materials issued to him from the time till proper installation and acceptance there-off (i.e.
signed Installation Completion Report) by the Local Site Representative. However such
acceptance does not absolve contractor from the responsibility for make good any defect
notified thereafter till taking over is completed.
29.0 TOOLS & TACKLES:-
All required tools, tackles testing, safety devices, ladder, platforms, supports
required for the execution of the work, shall have to arrange and managed by
contractor without any extra financial cost to NESCO. All Conveyance /
transportation / accommodation / lodging of contractor personnel shall be
arranged & provided by contractor. Contractor shall be responsible for Cleaning up
of Site after carrying out the work.
30.0 INSURANCE:-
Contractor shall at his/her expenses take out and maintain in effect, during the
performance of the contract suitable insurance to cover
i) Loss or damage occurring while in transit from the NESCO
stores to contractor stores until arrival at the Site.
ii) Physical loss or damage to the equipment or material at the
Site, occurring prior to acceptance of the equipment Immaterial by
NESCO.
iii) Bodily injury or death suffered by third parties and loss of or
damage to property occurring in connection with the execution of
contract.
iv) For the meters issued by NESCO, Contractor shall be liable
for insurance and give undertaking that in the event of
loss/damage of meters then the Performance Bank
guarantee (PBG)shall be made good to the extent of cost of
meters else contractor shall provide indemnity bond for the
same.
31.0 LIABILITY FOR ACCIDENT & DAMAGE:-
Contractor shall indemnify NESCO against any claims which may be made under the
workman's compensation Act 1923 or any statutory modification thereof or otherwise for
or in respect of any damages or compensation payable in consequence of any accident or
injury sustained by any workman or other person whether in contractor‟s employment or
not.
32.0 ENGINEER IN CHARGE:-
Concerned Divisional Head / authorized engineer of the Owner shall be the Engineer in
charge for the Project.
33.0 CONTRACT PERFORMANCE BANK GUARANTEE:-
33.01 Within 15 days of issue of the Work Order or Letter of Award, whichever is earlier, the
Contractor shall submit Contract Performance Bank Guarantee issued by a scheduled
Bank, in favour of the Owner, covering 10% of the total value of the work order.
33.02 The said Bank Guarantee shall be prepared in the prescribed proforma as attached in
Section IV, Annexure - III. The Bank Guarantee furnished shall be executed on Non-
judicial Stamp paper worth of Rs 100/- (Rupees Hundred only), purchased in the name
of the issuing bank, as per the prevalent rules. The Bank Guarantee so provided shall
be en-cashable on the Balasore branch of the issuing Bank.
33.03 The Contract Performance Bank Guarantee shall remain valid for a period not less than
90 days over and above the guarantee period, basing on stipulated completion period in
the W.O. towards security and acceptance thereof, failing which the work orders (W.O)
will be liable for cancellation without any further notice with forfeiture of E.M.D.
33.04 No interest shall be allowed by the Owner on the above Performance Security Deposit.
34.0 TERMS OF PAYMENT:
34.01 Paying officer shall process the bill after obtaining the following
documents. a) Invoice in triplicate duly certified by the Engineer-in-
charge.
b) Work Compilation certificate for the completed work duly certified by the
Engineer-in- charge.
c) List of meter installed and feed in MMS Module should certified by the
Engineer-in- charge.
d) Copies of all statutory documents such as valid Labour license, Valid HT or LT
license from ELBO Orissa, EPF Challan, ESI Challan, Service Tax payment
challan, WCT payment challan, PAN Card, Copy of storage cum erection
insurance any other documents as required by the paying officer.
e) Submission list of dismantled materials with proper acknowledgement.
34.02 An advance of 10% (ten percent) of total lump sum contract price shall be
paid as
Mobilization Advance, subject to the following.
a) Submission of Invoice for payment of advance.
b) Receipt and acceptance of unconditional irrevocable Contract Performance Bank
Guarantee in favour of Owner as mentioned in clause 33.01.
c) Receipt and acceptance of unconditional and irrevocable Advance Payment Bank
Guarantee in favour of Owner for an amount equivalent to the amount of advance
as per the prescribed format as provided in Section III, Annexure-III. The Bank
Guarantee so provided should be en-cashable on the Berhampur branch of the
issuing Bank.
d) Establishment of contract site office and certification by the engineer that
satisfactory mobilization for erection exists.
e) All advance payment shall be interest bearing and recovery of advance along with
the interest component on the advance amount shall be as under:
I. All advance payment made shall be recovered proportionately from each
running bill of the contractor.
II. The amount of interest to be recovered from a particular bill shall be
calculated @
10% per annum on the value of advance corresponding to the percentage of
total progressive payment being released. The period for which the interest is
to be calculated shall be reckoned from the date of release of the advance
payment to the actual date of release of the said progressive payment or the
expiry of the stipulated time frame for release of such progressive payment. If
any amount payable under any interim bill is not sufficient to cover all
deductions to be made for interest on the advance payment and other sums
deductible there from, the balance outstanding shall be recovered from the
next payments immediately falling due.
Page 23 of 77
34.03 80% (Eighty percent) of contract price on pro-rata basis along with taxes and duties shall
be paid progressively (after necessary advance adjustment with interest as applicable) for
completed work certified by the Engineer-in-charge against each calendar month by first
week of the succeeding months along with utilization certificate. No payment shall be
released if the accounts for utilization of materials unless follow with proper certification by
the concerned Engineer-in-charge within 30 days of submission of claim subject to
certification by Owner‟s Engineer-in-charge on the basis of check points involved in such
items of work.
34.04 Balance 20% (twenty percent) of contract price shall be paid after completion of all
works, envisaged under this package including any additions and alterations,
testing & commissioning, return of dismantled materials/ un-used free supply material,
taking over certificate and entire stretch is fully ready for commercial operation. The
payments shall be subjected to clearance from Engineer-in-charge.
Note: In case of joint venture/consortium Performance Bank Guarantee shall be provided
by the Lead Partner @ 10% and additional 1% by each JV Partner(s).
35.0 PAYING OFFICER:
DDO, Corporate Office, NESCO, Balasore..
36.0 OWNER’S RIGHTS: -
The Owner reserves the right to accept any bid or reject any or all bids or cancel /
withdraw invitation of bid or to vary the quantity for placement of order without
assigning any reason to such decision. Such decision by the Owner shall bear no
liability.
37.0 DISTINCT MARK ON EQUIPMENT AND MATERIALS:
The meters supplied by the owner have distinct mark of owner. The contractor is to
write down the consumer no/ account no / Date of replacement above meter box through
painting which should be clearly visible in day light in naked eye. The above points
mentioned in the meter box as such which will not obstacle at the time of meter reading.
The photographs shall be taken after writing clearly visualizing the meter Sl No., meter
reading.
38.0 DISPUTE RESOLUTION AND JURISDICTION: -
(a) Any disputes arising out of this contract shall be referred to the MD, NESCO
who shall decide the case as sole Arbitrator.
(b) For the purpose of dispute resolution, this agreement shall be governed by the
provision of Arbitration and Conciliation Act, 1996.
Page 24 of 77
(c) All disputes shall be subjected to exclusive jurisdiction of the Courts at
Balasore and the writ jurisdiction of Hon‟ble High Court of Odisha at Cuttack.
39.0 SUBCONTRACTOR:
You can subcontract a part of scope, limited to the labour and transportation
work only. All the planning, co-ordination & supervision / data updating activity
of the work shall be performed by you directly.
You shall be overall responsible for dealing with the subcontractors for all
administrative, commercial & legal issue. You shall identify and shall keep
indemnified NESCO against any losses, damages, claims in this regard. You
shall be held fully responsible for any act/omission of subcontractor during the
execution of the work.
40.0 TAKING OVER CERTIFICATE:-
i. With a minimum frequency of a month, contractor could apply the Engineer In
charge for the issue of Taking over Certificate for the works completed in all
respect. Such are quest should be accompanied with the photo copies (self
attested) of the signed Installation Completion Reports, Material Return
Receipts from the Stores In charge towards the return on meters
,Comprehensive Installation records: Consumer wise meter/seals/ initial/final
meter reading.
ii. Within 7 (Seven) days of contractor request, the Engineer in Charge shall
issue the Taking Over certificate or Otherwise it shall be deemed to be taken
over after the expiry of 7 day period.
iii. The Engineer in Charge may give instructions in writing to contractor
specifying all the work which, in the Engineer's opinion, is required to be done
by contractor before the issue of such Certificate, within the 7 days of
receiving the request for Taking Over Certificate .Contractor shall promptly
rectify the defect so noticed, to the satisfaction of the Engineer in-Charge.
Engineer In charge shall issue the Taking over Certificate for such works
within next 7 days of remedying the defect.
iv. In case it is found during revisit by the Engineer In charge at the site
where re-work has been instructed and it is found that the meter
installation is not proper again then you shall liable to pay penalty of Rs
50/- per site.
41.0 INSTALLATION WARRANTY:-
Contractor shall promptly make good the defects notified in any of the installation
during the execution period of the work attributable to the bad workmanship or
negligence or any other act carried out by Contractor as per the scope of this work
order.
Page 25 of 77
Any defect arising due to operational fault or damage or natural calamity or any defect
caused by accident, misuse, neglect, alteration, modification or substitution of any of
the components or parts, or any attempt at internal adjustment by unauthorized
service personnel, external faults will not be covered under this installation warranty.
42.0 EMBOSSING / PUNCHING / CASTING / PAINTING
The all equipments and materials supplied /erected under the CAPEX Programme
shall bear distinct mark of “Name of the Purchaser, GoO, CAPEX Programme, P.O
Order No. & Date” by a way of embossing / punching / casting / painting etc. This
should be clearly visible to naked eye. But in this case as the major material meter is
supplied by NESCO and minor material is supplied by contractor, so above clause is
not required for such minor materials.
43.0 INDEMNIFY
The Contractor, its successor and assignee shall indemnify the Owner, its successor
and assignee from all current & future liabilities that may arise out of Turn Key
Contract(s) entered into between the Owner & the Contractor under this CAPEX
Programme. The Owner in term shall indemnify the GoO & GRIDCO.
44.0 NESCO LOCAL SITE REPRESENTATIVE:
I. Respective Section in charges /sub-division in charge or any other person assigned
by Engineer in Charge shall be the NESCO's Local Site Representative for field
level coordination, monitoring, assistance and acceptance of the installations
completed.
II. The installation program shall be planned in advanced and firmed up at least 15
days. before the installation work starts in a particular area between NESCO &
contractor local site representatives.
Ill. Contractor shall work independently in the area and keep Local Site
Representatives apprised of the developments on routine basis. He / She shall
assist and co-ordinate the installation activity in his/her area. On your request
he/she shall provide access to consumer premises and arrange for shutdowns if
required.
45.0 CONSUMER LIST FOR METER REPLACEMENT:
NESCO shall provide administrative area / Binder wise complete lists of all the
consumer in whose premises meters are to be replaced or hard copy before starting of
work. These lists shall have sufficient details for locating the consumers and carrying
out the replacement/shifting work. Information such as complete address of
consumers, service connection number, Binder/route number, existing meter number
and the last meter reading /
meter status as in records. At a time meter replacement should be carried out for one
binder then to another binder/substation. The contractor will get the list from the
Engineer- in-charge at the time of execution of work. NESCO shall provide the approved
format of meter replacement. Engineer-in-charge shall responsible for providing the
approved format to the contractor. Contractor shall make multiple copies of the format
on his/her own cost and filled the format for each individual consumer in triplicate
after complete installation of work. The triplicate formats distribute as such, one copy
to consumer; two copies to Engineer-in-charge. Engineer-in-charge kept one copy and
Page 26 of 77
returns the second copy to the contractor by putting his signature as his acceptance.
Then the contractor is updating the same in MMS Module.
In case of installation of 3-Ph LTCT meters, NESCO shall provide details of distribution
substation where meters are to be installed.
46.0 IDENTITY CARDS AND AUTHORIZATION LETTER:-
a. The Engineer In charge will issue a general authorization letter for
carrying out the installation / replacement of meters at consumer
premises.
b. Contractor shall be responsible for making "the photo identity cards of all
the personnel engage by him/her in the meter installation/replacement work.
c. The personnel engaged by the contractor shall be deemed always as
his/her employees and NESCO is not concerned with his/her engagement
conditions and the remuneration. The Contractor should obtain from every
personnel an undertaking that they will not claim any benefits from NESCO
at any time and furnish the same to NESCO before commencement of the
contract.
47.0 WORK QUALITY & SCHEMATICS:-
The work shall be executed under the direct supervision of the Executive Engineer of the
respective division. The Contractor shall prepare schematics for various installation
scenarios and standard detailed work instructions for reference along with field quality
instructions manual and got the same approved from the Engineer In charge before
commencement of the work. The Contractor shall ensure regular training of the work
force and carry out safe and quality work as per the industry standards & the processes
defined.
48.0 WORK METHODOLOGY: -
A) Materials to be provided by NESCO
(a)Single Phase Meter:
i) Single phase, class 1 static meters with termination kit (if any)
ii) PVC TP Meter Boxes and accessories (as supplied).
iii) Numbered plastic/hologram security seals.
iv)PVC service wire, where service wire is to be replaced.
(b)3-Phase Meter:
i)For consumer metering 3-Ph WC meter & HTTV meter with box.
ii)For DTR metering 3-Ph LTCT meter with box.
Page 27 of 77
iii)Numbered plastic/hologram security seals.
B) Materials to be provided by Agency:
(a)Single Phase Meter:
i) PVC conduits as required with holding clamps.
ii) Conduit pipe bend for Load cable.
iii) All other minor consumable items for fixing the meter & meter box and
service cable routing over the wall and making connections including
PVC insulation tapes, Plastic Gullies, steel screws and cables ties.
iv) The agency shall also provide load cable of approved specification.
V) For shifting of meter from inside to outside of the consumer house the agency
shall be verify as per actual site requirement as certified by concerned JE/SOO.
(b)3-Phase Meter:
Installation of 3-Ph meter for DTR metering following materials are to be provided
by the agency.
i)GI Channel(75x40x6)mmx1.8mtr- 2nos.
ii)GI Flat(50x8)mmx0.82mtr – 2nos.
iii)GI nut bolt with washer – 0.5Kg.
iv)Cement, Sand and aggregate – LS. (Required as per drawing)
C) Receipt of materials & handling at site:
i. Contractor shall arrange to receive the meters and associated boxes along
with the seals from our respective divisional stores in lots of minimum
500sets.Seals shall be issued in advance in lots.
ii. Contractor shall raise the requisition of meters and all the accessories in a
phase manner as per your requirement through Meter Management System
(MMS) with help of IT. The requisition shall be approved by the MRT Heads of
NESCO or the respective EE
of the concerned divisions.
, ,
Note. -Material shall be carried, unloaded at site under proper supervision to ensure there
will be no damage to the equipment /material. All equipment, accessories,
hardware/miscellaneous items shall be stored properly as per the storage instruction of
the meter manufacturer.
Page 28 of 77
D. Removal of old meter and box & fixing of new meter and TP box:
1) At consumer premises, the installation teams shall first check the consumer's
details and match with allotted list for replacement and inform the customer about the
new meter installation. The existing meter of type - electromagnetic meters, hybrid
and defective electronic/Static meter of with LCD display shall be replaced with new
meter or in case of no meters a new meter shall be provided.
2) The Consumer load shall be disconnected from the main switch, and the
lineside and load side cables from the existing old meter terminals are removed with
utmost care and marked by tagging. The removed cable end shall' be properly
insulated to avoid any accident. The meter along with the existing old meter box (if
available) or from the wooden board shall be removed after de-energizing it.
3) The new meter shall be installed at the same location if outside the consumer
house or relocated outside the consumer premises in such a manner that all the new
installed meters are near to the main entrance of the consumer's dwelling unit or are
at a suitable place in the consumer premises, such that same could be accessible
without entering the consumer's dwelling unit.
4) For fixing the new meter box, four number holes (as per drawing of the box) or
as per the provision provided at the meter box shall be drilled on the wall or the
wooden board, as the case may be. After preparation of whole new meter box along
with electronic meters shall be fixed securely in position with the help of steel screws
and wooden / plastic gully.
5) At the new meter location, if the load cable is needed to be replaced (in case
the old cable length is not adequate for the new location) the cable should be
provided by you. It is estimated that on an average 7.5 meter load cable per
installation may be needed for this purpose. Cable routing / dressing of the new load
cable should be done neatly over the premises wall.PVC conduit pipe may be used as per
the site requirement for load side
cable.
6) The premises, where meter installation needs replacement of the complete
service cable due to relocation or poor condition of the existing cable, these locations
should be left during the drive. All such cases should be recorded in the Installation
report and a comprehensive list of all such cases shall be provided to the Engineer In
charge for his further action on fortnightly basis.
7) The Incoming and Outgoing cable should be safely inserted through the meter
box gland. In case the existing termination end are in poor shape / inadequate, it
should be prepared by peeling off the outer sheath and removing the inner insulation
to bare the conductor up to the length equivalent of the meter terminal depth in such
a fashion that the bare conductor is not seen from outside and insulation does not get
between the meter terminal cage when tightened. The bare part should be cleaned
properly before termination. The incoming cable to the meter must make from
concealed service bracket and should not be concealed in the wall.
8)The Meter should be installed at a height of 5.5 ft from floor level (Eye level
distance) Connections shall be done in proper phase sequence as per the connection
diagram of the meter. Care shall be taken for proper tightening of the terminals /
clamps to avoid any overheating, damage / malfunctioning during normal operation.
Important Note: - Suitable insulated tools / safety devices should be used for connection
removal! Cable end preparation and final termination. Depending upon the site conditions,
suitable shut downs may be called for in co-ordination with local site representative.
Page 29 of 77
E) Installation Checks & verification: -
a. On completion of the erection activity a physical verification of the
installation shall be carried out by contractor supervisor/technician
before returning the shutdown and/or restoring the power supply.
b. After completion of above steps of work, meter should be checked for
working conditions. If the meter installed is not working i.e. if there is
no change in meter reading; another meter shall be installed and
checked in the manner described above.
c. The list of non - functioning meters in detail shall be returned to the
issuing authority and take the meter returned receipt from the issuing
authority. If the meter installed is found working, the meter terminal
blocks and meter box shall be sealed with the seals already
issued to you.
d) In case detection of bypass / meter tampering / meter serial no. miss
match cases are to be reported to concerned Engineer-In-Charge
without any replacement.
F)Installation Completion Report :
On completion of work at each site meter removal/installation, sealing; you
shall fill Installation Completion Report (in triplicate) with all the relevant
mandatory data/record/information and submit it within next two (2) working
days to the Local Site Representative for his acceptance and signature. The
local site representative may verify some of the installation sites randomly.
He shall promptly return the accepted and signed Installation Completion
Reports in next two (2) working days to your authorized representative.
G. Exclusions & exceptions:
i) In case a consumer in the list is found to have a running Electronic/ Static
meter with LED display in working condition located outside the consumer
house, the same shall not be replaced or shifted. However list of such cases
needs to be provided to NESCO.
ii) In case any anomaly/defect is observed and notified by the local site
representative / Engineer In Charge in the erection workmanship / quality /
connections during site verification or on a later date on analysis of meter
data or improvement suggested in the work (within the scope) the same
shall be promptly attended and corrected without any demur and extra
charge to NESCO.
iii) The scope of work does not include supply of load or service cables, supply
and replacement of service bracket.
iv) Also the scope do not include revamping of meter installation sites and other
accessories like fuse / MCB / Distribution box, service cable drawing or any
major site modification.
v) The sites with improper condition such as (1) no space for installation of new
meter (2) disputed site, (3) consumer's objection (4) non availability of power
shutdown (5) damaged / undersized /jointed / short cables, needing
replacement. etc., due to which installation of meter may not be possible in
the consumer premises are excluded from scope of this Work Order. Record
of all exceptional cases shall be maintained during the replacement activity
Page 30 of 77
and submitted to the Engineer In Charge. NESCO should respond within a
week to you for every such site for taking suitable action. Failing which such
meters will be deemed to automatically out of scope with immediate effect
from that respective date and new list shall be provided.
v. Method of progression:- All the works related to replacement/and installation
of new meters along with repositioning (as per clause 15) for the entire
consumer as per the list provided should be taken up in a sweeping manner.
The work has to be completed in a geographic administrative area (preferably
- Subdivision -wise) in one go. You have to deploy your team accordingly.
H. Return of old meters:-
With a minimum frequency of once in a month, you have to return the dismantled
meters along with any other associated item ( meter box, meter board etc) safely to
the designated section stores obtaining a Material Return Receipt from the respective
Store In charge. The list of old meters to be returned binder wise with name,
consumer no., meter no., final reading seal no.etc
I. Data Up-dating in Meter Management System (MMS):
II. Contractor shall raise requisition of meters and other accessories in phased
manner as per your requirement through Meter Management System (M
MS).The 'requisition shall be approved by the EE, MRT head accordingly you
shall collect approved quantity of meters.
III. After the Installation of new meters, it shall be your responsibility to enter the
details of the new as well as old meter in the MMS.
IV. Contractor shall have to enter the details of Consumers and Meter serial No
where the shifting of meters from inside to outside has been done.
V. The updating activity should be ideally carried out routinely to minimize the
impact of meter replacement on NESCO reading I billing system and in no
circumstances the delay in entering details should be beyond one week of
receipt of the signed Installation Completion Report. Any delay beyond this
time shall invite penalty as per the clause No. 4.
VI. The above details have to be maintained strictly confidential by you, further for
any details entered using the Log in id and password you shall be held fully
responsible.
VII. For the purpose of MMS utilization, IT shall be responsible for training and
shall provide with log in ID and password to your authorized personal.
VIII. Contractor shall appoint your representative to work out the
methodology/process/data formats for carrying out such data updating activity
in consultation with Engineer in-charge.
IX. The above details have to be maintained strictly confidential with highest
degree of integrity and any breach of trust shall call for strict punitive action.
49.0 PROGRESS REPORTING:-
You shall report the work progress on daily basis to the Engineer In Charge as per
approved reporting format. Fortnightly abstract of above report should be submitted to
Circle head, AGM(MRT), GM(CAPEX), Sr.GM.
The monitoring of the progress of work and removal of bottlenecks shall be done by
Engineer in-charge.
Page 31 of 77
SECTION - III
ANNEXURE
Page 32 of 77
ANNEXURE – I
BID PROPOSAL LETTER
Electrical Installation of Works under NESCO
Bidder’s Name and Address:
(in case of JV/Consortium, Name of JV/Consortium)
Bid Proposal Reference:
Person to be contacted:
Designation:
Telephone No. : E-mail: Fax No. :
To,
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sir,
We the undersigned bidder have read and examined the detailed specification and bidding
documents for execution of various electrical installations works and do herewith submit our bid
for the following packages:
Sl. No. Name of the Owner Name of the Package
We declare the following:
Page 33 of 77
1.0 PRICES AND VALIDITY:
1.01 All the prices and price components stated in our bid proposal are firm and not subject to
any price adjustment, in line with the bidding documents. All the prices and other terms and
conditions of this proposal are valid for a period of 180 days from the date of opening of the bids. We
further declare that prices stated in our proposal are in accordance with “Instructions to Bidders” of
bidding documents.
1.02 We do hereby confirm that our bid prices as quoted in attached Schedules include all import
duties and levies including license fees lawfully payable by us on imported items and other taxes,
duties and levies applicable on bought – out components, materials, equipment and other items and
confirm that any such taxes, duties and levies additionally payable shall be to our account.
1.03 We confirm that the Sales tax on Works Contract, Turnover Tax or any other similar taxes
under the Sales Tax Act, as applicable, are included in our quoted bid price and there shall not be any
liability on this account to the Purchasers. We understand that Owner shall, deduct such taxes at
source as per the rules and issue TDS Certificate to us.
1.04 We confirm that, in our Bid Price, we have considered service tax in line with lawful prevalent
practice.
1.05 Price components of various items are indicated in the B.O.Q. for the respective works.
1.06 We further declare that while quoting the price, the due credit under MODVAT scheme, re-
christened as CENVAT scheme, as per relevant Government policies wherever applicable, have been
taken into account.
1.07 We, having studied the bidding document in three volumes relating to taxes & duties and
hereby, declare that if any income tax, charge on income tax or any other corporate tax is attracted
under the law, we agree to pay the same.
1.08 We are aware that the Price schedules do not generally give a full description of the supplies
to be made and work to be performed under each item and we shall be deemed to have read the
Page 34 of 77
Technical Specifications and other bidding documents and drawings to ascertain the full scope of
work included in each item while filling in the related and prices. We agree that the entered rates
and prices shall be deemed to include the full scope as aforesaid, including overheads and profits.
1.09 We understand that in the price schedule, if there is discrepancy between the unit price and
total price, the same shall be corrected as per relevant provisions.
1.10 We declare that prices for items left blank in the schedules will be deemed to have been
included in other items. The TOTAL for each schedule and the TOTAL of Grand summary shall be
deemed to be the total price for executing the facilities and sections thereof in complete accordance
with the contract, whether or not each item has been priced.
2.0 CONSTRUCTION OF THE CONTRACT
2.01 We declare that we are making the offer on the basis of indivisible supply-cum- Erection
contract on a single source responsibility basis.
3.0 BID SECURITY (EMD)
We are enclosing Bank Draft / Bank Guarantee No. dtd. amounting to Rs.------------------
--- (Rupees only) issued by Bank ------------------
---------branch, payable on Balasore towards Bid Security against our above Bid. The Bid Security
amount has been computed by adding the Estimated Cost of the package no.s ------------------- for
which we are submitting our bid.
4.0 EQUIPMENT PERFORMANCE GURANTEE
We declare that the ratings and performance figures of the equipment to be furnished and erected
by us are guaranteed. The Guaranteed particulars of different equipments are enclosed along with
our bid.
5.0 BID PRICING
We further declare that the prices stated in our proposal are in accordance with your ‘Instruction of
Bidders of Conditions of Contract, Volume-1 of the bid documents.
Page 35 of 77
6.0 PRICE ADJUSTMENT
We declare that all the prices and price components stated in our offer are on FIRM price basis.
7.0 QUALIFICATION
We confirm having submitted the Qualification Data in original plus one copy, as required by you
under clause 6.0 ‘Invitation for Bids’. Further we have filled in the information for qualification
requirements. In case you require any further information in this regard, we agree to furnished the
same in time .
8.0 DEVIATIONS
8.01 We declare that the contract shall be executed strictly in accordance with the
specifications and documents except for the variations and deviations all of which have been
detailed out exhaustively in the following schedules, irrespective of whatever has been stated to
the contrary anywhere else in our proposal.
a) Commercial Deviations Schedule
b) Cost of withdrawal of Deviations on Critical
c) Technical Deviation Schedule
8.02 We confirm that specified stipulation of following critical clauses is acceptable to us and no
deviations/exceptions are taken on any account whatsoever in the following clauses:
(a) Payment Terms :
(b) Bid Guarantee :
(c) Contract Performance Guarantee:
(d) Liquidated Damages for delay : (e) Prices and Price Adjustment : (f) Guarantee / Warrantees :
8.03 Further, we agree that the additional conditions, deviations, if any, found in our bid proposal
documents other than those stated in attached Deviation Schedules, save that pertaining to any
rebates offered, shall not be given effect to.
Page 36 of 77
9.0 ADDITIONAL INFORMATION
We have included with this proposal additional information listed. We further confirm that such
additional information does not imply any additional deviation beyond those covered in appropriate
schedules and in case of any contradiction between these additional information and other
provisions of Bid, the latter prevail.
10.0 GURANTEE DECLARATION
We guarantee that the equipment offered shall meet the rating and performance requirements
stipulated in this specification. The Guarantee Declaration which shall attract levy of liquidated
damages for non-performance is indicated in the relevant schedule.
11.0 BOUGHT-OUT AND SUB-CONTRACTED ITEM
We are furnishing herewith at appropriate Schedule, the detail of all major item of supply amounting
to more than 10% of our Bid Price, which were propose subletting giving detail of the name of sub-
contractor/sub-vendor and quantity for each item.
12.0 WORK SCHEDULE
If this proposal is accepted by you, we agree to submit engineering data, provide services and
complete the entire work from time to time, in accordance with schedule indicated in the proposal.
We fully understand that the time schedule stipulated in this proposal is the essence of the contract,
if awarded. The completion schedule of the various major key phases of the work is indicated in the
designated schedule.
13.0 CONTRACT PERFORMANCE GUARANTEE
We further agree that if our Bid is accepted we shall provide an irrevocable Bank guarantee towards
Contract Performance Guarantee, of value equivalent to ten percent (10%) of the Contract Price
initially valid up to the end of ninety (90) days after the end of the contract warranty period in the
form of Bank Guarantee in your favour within 15 (fifteen) days from the date of ‘Notice of Award of
Contract’ and enter into a formal agreement with you immediately thereafter.
Page 37 of 77
14.0 CHECK LIST
We have included a check list duly filled in Schedule. We understand that only this check list,
commercial and technical deviation will be read out during the part-I bid opening before the bidders
present.
(For Joint Venture/consortium only) We, the Partners of joint venture/ consortium submitting their
Bid, do agree and confirm that in case of Award of the Contract on the joint venture, we shall be
jointly and severally responsible for the execution of the contract in accordance with contract terms
and conditions.
We, hereby declare that only the persons or firms interested in this proposal as principals are named
herein and that no other persons or firms other that those mentioned herein have any interest in this
proposal or in the contract to be entered into if we are awarded the contract, and that this proposal
is made without any connection with any other person, firm or party likewise submitting a proposal
and that this proposal is in all respect for and in good faith, without collusion or fraud.
Dated this ………………………..day of ………………………………20…..
Thanking you,
Yours faithfully,
(Signature of the Authorized Signatory)
Name ……………………………
Designation ……………………………..
Seal of the company………..
(To be signed by lead partner in case of Joint Venture) Signature of other partner (s) in case of Joint
Venture)
Name …………………
Designation …………………..
Date : ………………………….
Place :
Page 38 of 77
(Written power of Attorney of all signatories of the bid to commit the Bidder must be enclosed with
the Bid. In case of joint venture, the written Power of Attorney of all signatories from respective
partners must be enclosed with the Bid. .
*** Applicable case of a Bid from Joint Venture of Firms. Further, the Bid must be signed by each
partner of the Joint venture.
Page 39 of 77
ANNEXURE – II
DECLARATION FORM
To,
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Sir,
Having examined the above specifications together with the Tender terms and conditions referred to
therein
1 – I / We the undersigned do hereby offer to execute the contract covered there on in complete
shape in all respects as per the rules entered in the attached contract schedule of prices in the
tender.
2 – I / We do hereby under take to have executed the contract within the time specified in the
tender.
3 – I / We do hereby guarantee the technical particulars given in the tender supported with
necessary reports from concerned authorities.
4 – I / We do hereby certify to have purchased a copy of the tender specifications by remitting Cash /
Demand draft & this has been duly acknowledged by you in your letter No…………Dt…………
5 – I / We do hereby agree to furnish the composite Bank Guarantee in the manner specified /
acceptable by NESCO (as the case may be) & for the sum as applicable to me / us as per clause No.13
of Annexure -V of this specification within fifteen days of issue of Letter of intent / Work Order , in
the event of Work order being decided in my / us favour , failing which I / We clearly understand that
the said LOI / W.O. shall be liable to be withdrawn by the Owner.
Signed this…………….Day of……………………20…
Yours faithfully
(Signature of Bidder with Seal of Company)
Page 40 of 77
ANNEXURE – III
PROFORMA FOR CONTRACT PERFORMANCE BANK GUARANTEE
(To be executed on Rs. 100/- Non-judicial Stamp Paper purchased in the name of the BG Issuing
Bank)
This Guarantee Bond is executed this ____ day of ___________________________ by us,
_____________________________________________________ Bank at ___________________
P.O.__________ P.S. ____________Dist ________________ State __________
Whereas North Eastern Electricity Supply Company of Orissa Ltd.(NESCO), Balasore ,Regd. Office: N
1/22, IRC Village, Nayapalli, Bhubaneswar – 751015 registered under the Company Act 1956 (here in
after called “Owner”) has placed Work Order No._________ Dt.___________ (hereinafter called
“Agreement”) with M/s_________________ _________________________ (hereinafter called “the
Contractor”) for supply and installation of ________________ (description of the works) and
whereas Owner has agreed (1) to exempt the Contractor from making payment of security deposit,
(2) to release 100% payment of the cost of materials as per the said agreement and (3) to exempt
from performance guarantee on furnishing by the Contractor to Owner a composite Bank Guarantee
of the value of 10% (ten percent) of the Contract price of the said Agreement.
1. Now, therefore, in consideration of Owner having agreed (1) to exempt the Contractor for
making payment of security deposit, (2) to release 100% payment to the Contractor and (3) to
exempt from furnishing performance guarantee in terms of the said Agreement as aforesaid, we the
____________________ Bank, Address ____________________________ (code No. ________)
(hereinafter referred to as “the Bank”) do hereby undertake to pay to the Owner an amount not
exceeding Rs._____________ (Rupees _______________________________ ) only against any loss
or damage caused to or suffered by the Owner by reason of any breach by the said Contractor(s) of
any of the terms or conditions contained in the said Agreement.
2. We, the ______________________ Bank do hereby undertake to pay the amounts due and
payable under the guarantee without any demur, merely on a demand from Owner stating that the
amount claimed is due by way of loss or damage caused to or suffered by Owner by reason of any
breach by the said Contractor(s) of any of the terms or conditions contained in the said Agreement or
by the reason of any breach by the said Contractor’s failure to perform the said Agreement. Any such
demand made on the Bank shall be conclusive as regards the amount due and payable by the Bank
under this Guarantee. However, our liability under this guarantee shall be restricted to an amount
not exceeding Rs.___________ (Rupees _________________________________________ ) only.
3. We, the ________________________ Bank also undertake to pay to Owner any money so
demanded not withstanding any dispute or dispute raised by the Contractor(s) in any suit or
proceeding instituted/ pending before any court or Tribunal relating thereto our liability under this
Agreement being absolute and irrevocable. The payment so made by us under this bond shall be
valid discharge of our liability for payment there under and the Contractor(s) shall have no claim
against us for making such payment.
Page 41 of 77
4. We, the _________________________ Bank further agree that the guarantee herein
contain shall remain in full force and effect during the period that would be taken for the
performance of the said Agreement and it shall continue to remain in force endorsable till all the
dues of Owner under by virtue of the said Agreement have been fully paid and its claim satisfied or
discharged or till Purchaser certifies that the terms and conditions of the said Agreement have been
fully and properly carried out by the said Contractor(s) and accordingly discharge this guarantee and
will not be revoked by us during the validity of the guarantee period.
Unless a demand or claim under this guarantee is made on us or with our Balasore branch at
________________________ (Name, address of the Balasore branch and code No.) in writing on or
before __________________ (date) we shall be discharged from all liability under this guarantee
thereafter.
5. We, the _________________________ Bank further agree that Owner shall have the fullest
liberty without our consent and without affecting in any manner our obligations hereunder to vary
any of the terms and conditions of the said Agreement or to extend time of performance by the said
Contractor(s) and we shall not be relieved from our liability by reason of any such variation or
extension being granted to the said Contractor(s) or for any forbearance act or omission on part of
Owner or any indulgence by Owner to the said Contractor(s) or by any such matter or thing
whatsoever which under the law relating to sureties would but for this provisions have effect of so
relieving us.
6. The Guarantee will not be discharged due to change in the name, style and constitution of
the Bank and or Contractor(s).
7. We, the _________________________ Bank lastly undertake not to revoke this Guarantee
during its currency except with the previous consent of the Owner in writing.
Dated ___________ the __________ day of Two thousand _________ .
Not withstanding anything contained herein above.
Our liability under this Bank Guarantee shall not exceed Rs.______________ (Rupees _______
____________________________________________________________________ ) only.
The Bank Guarantee shall be valid up to _____________________ only.
Our ………………………. branch at Balasore (Name & Address of the Balasore branch) is liable to pay the
guaranteed amount depending on the filing of claim and any part thereof under this Bank Guarantee
only and only if you serve upon us at our Balasore branch a written claim or demand and received by
us at our Balasore branch on or before Dt.__________ otherwise bank shall be discharged of all
liabilities under this guarantee thereafter.
For _____________________________________
(Indicate the name of the Bank)
Page 42 of 77
N.B.:
(1) Name of the Contractor:
(2) No. & date of the Work order/ agreement:
(3) Amount of W.O:
(4) Name of Work:
(5) Name of the Bank:
(6) Amount of the Bank Guarantee:
(7) Name, Address and Code No. of the Balasore Branch of the Issuing Bank:
(8) Validity period or date up to which the agreement is valid:
(9) Signature of the Constituent Authority of the Bank with seal:
(10) Name & addresses of the Witnesses with signature:
(11) The Bank Guarantee shall be accepted only after getting confirmation from the issuing Branch
& from main branch/specified branch at Balasore of issuing Bank.
Page 43 of 77
ANNEXURE – IV
PROFORMA OF BANK GUARANTEE FOR ADVANCE PAYMENT
(To be stamped in accordance with Stamp Act)
(To be executed on Rs. 100/- Non-judicial Stamp Paper purchased in the name of the BG Issuing
Bank)
Ref............................ Bank Guarantee No.................
Date ............................
To,
The Managing Director,
NESCO, Balasore.
Dear Sir,
In consideration of Whereas North Eastern Electricity Supply Company of Orissa Ltd. (NESCO)
(hereinafter referred to as the ‘Owner’, which expression shall, unless repugnant to the context or
meaning thereof include its successors, administrators and assigns) having awarded to
M/s.................. (hereinafter referred to as the "Contractor” which expression shall unless repugnant
to the context or meaning thereof, include its successors, administrators, executors and assigns), a
Contract by issue of Owner’s Letter of Award No.................. dated ................... and the same having
been acknowledged by the Contractor, resulting in a Contract bearing No....................... dated
.................. valued at ...................... for .................................................................. (Scope of
work)................................... (Hereinafter called the 'Contract’) and the Owner having agreed to make
an advance payment to the Contractor for performance of the above Contract
amounting................................. (in words and figures ) as an advance against Bank Guarantee to be
furnished by the Contractor.
We,................................................................................................................. (Name of the
Bank) having its Head Office at .............................. (hereinafter referred to as the ‘Bank’,
which expression shall, unless repugnant to the context or meaning thereof , include its
successors, administrators, executors and assigns ) do hereby guarantee and undertake to
pay the Owner, immediately on demand any or, all monies payable by the Contractor to the
extent of ..................................... as aforesaid at any time up to ........ @ ............... without
any demur, reservation, contest, recourse or protest and / or without any reference to the
Contractor. Any such demand made by the Owner on the Bank shall be conclusive and
binding notwithstanding any difference between the Purchaser and the Contractor or any
dispute pending before any Court, Tribunal, Arbitrator or any other authority. We agree that
the guarantee herein contained shall be irrevocable and shall continue to be enforceable till
the Owner discharges this guarantee.
The Owner shall have the fullest liberty without affecting in any way the liability of the Bank
under this guarantee, from time to time to vary the advance or to extend the time for
Page 44 of 77
performance of the Contract by the Contractor. The Owner shall have the fullest liberty
without affecting this guarantee, to postpone from time to time the exercise of any powers
vested in them or of any right which they might have against the Contractor, and to exercise
the same at any time in any manner, and either to enforce or to forbear to enforce any
covenants, contained or implied, in the Contract between the Owner and the Contractor or
any other course or remedy or security available to the Owner. The Bank shall not be
released of its obligations under these presents by an exercise by the Owner of its liberty
with reference to the matters aforesaid or any of them or by reason of any other act or
forbearance or other acts of omission or commission on the part of the Owner or any other
indulgence shown by the Owner or by another matter or thing, whatsoever, which under law
would, but for this provision have the effect of relieving the Bank.
Bank also agrees that the Owner at its option shall be entitled to enforce this Guarantee against the
Bank as a principal debtor, in the first instance without proceeding against the Contractor and
notwithstanding any security or other guarantee that the Owner may have in relation to the
Contractor'’ liabilities.
Notwithstanding anything contained hereinabove our liability under this guarantee is limited to
.................. and it shall remain in force up to and including ...........@ ........... and shall be extended
from time to time for such period (not exceeding one year ), as may be desired by M/s.
........................ on whose behalf this guarantee has been given.
The Guarantee will not be discharged due to change in the name, style and constitution of the Bank
and or Contractor(s).
All other contentions in B.G will safe guard the interest of Owner.
We, the _________________________ Bank lastly undertake not to revoke this Guarantee during its
currency except with the previous consent of Owner in writing.
Dated ___________ the __________ day of Two thousand _________ .
Notwithstanding anything contained herein above.
Our liability under this Bank Guarantee shall not exceed Rs.______________ (Rupees _______ ____)
only.
The Bank Guarantee shall be valid up to _____________________ only.
Page 45 of 77
Our ………………………. branch at Balasore (Name & Address of the Balasore branch) is liable to pay the
guaranteed amount depending on the filing of claim and any part thereof under this Bank Guarantee
only and only if you serve upon us at our Balasore branch a written claim or demand and received by
us at our Balasore branch on or before Dt.__________ otherwise bank shall be discharged of all
liabilities under this guarantee thereafter.
For _____________________________________
(indicate the name of the Bank )
Dated this .............. Day of .........20......... at .........................................
WITNESS ........................................................ ...............................................................................
(Signature) (Signature)
......................................................... ...............................................................................
(Name) (Name)
.......................................................... ...............................................................................
(Official Address) (Designation with Bank Stamp)
Attorney as per
Power of Attorney No...................
Dated ...........................................
@ This date shall be ninety (90) days after the schedule date of completion of the Contract.
Page 46 of 77
ANNEXURE – V
FORM OF POWER OF ATTORNEY FOR JOINT VENTURE
(On Non –Judicial Stamp Paper of Appropriate value
to be Purchased in the Name of Joint Venture)
KNOW ALL MEN BY THESE PRESENTS THAT WE, the Members whose details are
given hereunder…………………………….. have formed a joint Venture/Consortium and
having our Registered Office (s)/Head Office (s) at ……………………………….(hereinafter
called the „Joint Venture/Consortium‟ which expression shall unless repugnant to the context
or meaning thereof, include its successors, administrators and assigns) do hereby constitute,
nominate and appoint M/s……………………………………………. a company/Electrical
Contractor incorporated under the laws of …………..and having its Registered/Head Office at
…………….as our duly constituted lawful Attorney (hereinafter called “Attorney”
(hereinafter called Lead Member) to exercise all or any of the powers for and on behalf of the
joint venture/Consortium in regard to Tender Notice No…………….. for construction of
……………. (name of the package) of NESCO (hereinafter called the “Owner”) for which bids
have been invited by the Owner, to undertake the following acts :
(i) To submit proposal, participate and negotiate in respect of the aforesaid Bid –
Specification of the Owner on behalf of the “Joint Venture / Consortium”.
(ii) To negotiate with Owner the terms and conditions for award of the contract
pursuant to the aforesaid Bid and to sign the contract with the Owner for and on behalf of the
“Joint Venture / Consortium”.
(iii) To do any other act or submit any document related to the above.
(iv) To receive, accept and execute the contract for and on behalf of the “Joint
Venture / Consortium”.
(v) To submit the Contract performance security in the form of an unconditional
irrecoverable Bank Guarantee in the prescribed format and as per terms of the contract.
It is clearly understood that the Lead Member shall ensure performance of the contracts(s) and
if one or more Member fail to perform their respective portion of the contracts(s), the same
shall be deemed to be a default by all the Members.
It is expressly understood that this power of Attorney shall remain valid, binding and
irrevocable till completion of the Defect of liability period in terms of the contract.
Page 47 of 77
The Joint Venture / Consortium hereby agrees and undertakes to ratify and confirm all the
whatsoever the said Lead Member quotes in the bid, negotiates and signs the Contract with
the Owner and / or proposes to act on behalf of the Joint Venture / Consortium by virtue of this
Power of Attorney and the same shall bind the Joint Venture / Consortium as if done by itself.
IN WITNESS THEREOF the Members Constituting the Joint Venture / Consortium as
aforesaid have executed these presents on this ………… day of …….. under the Common
Seal (s) of their Companies
for and on behalf of
the members of Joint Ventures/Consortium
…………………………………
…………………………………
…………………………………
The Seal of the above Partners of the Joint Venture / Consortium:
The Seal has been affixed there unto in the presence of:
WITNESS
1. Signature …………………………………
Name …………………………………
Designation …………………………………
Occupation …………………………………
2. Signature …………………………………...
Name ……………………………………….
Designation …………………………………
Occupation …………………………………
Page 48 of 77
ANNEXURE – VI
FORM OF JOINT VENTURE/ CONSORTIUM AGREEMENT
(To be executed on non-judicial stamp paper of appropriate value to be purchased in the
name of executants or as required by the Jurisdiction in which executed)
THIS Joint Venture/Consortium Agreement executed on this ……….. day of …………… Two thousand
…………………… by:
M/s. …………….…………….a company/Partnership Firm/Sole Proprietorship Organization incorporated
under the …………….……………. Act/Laws and having its Registered Office/Head Office at …………….
…………….……………. ……………. (hereinafter called the "Lead Member/First Member" which expression
shall include its successors),and
M/s. …………….…………….a company/Partnership Firm/Sole Proprietorship Organization incorporated
under the …………….……………. Act/Laws and having its Registered Office/Head Office at …………….
…………….……………. ……………. (hereinafter called the " Second Member" which expression shall
include its successors),and
M/s. …………….…………….a company/Partnership Firm/Sole Proprietorship Organization incorporated
under the …………….……………. Act/Laws and having its Registered Office/Head Office at …………….
…………….……………. ……………. (hereinafter called the "Third Member" which expression shall include
its successors),and
M/s. …………….…………….a company/Partnership Firm/Sole Proprietorship Organization incorporated
under the …………….……………. Act/Laws and having its Registered Office/Head Office at …………….
…………….……………. ……………. (hereinafter called the "Fourth Member" which expression shall include
its successors).
The Lead Member/First Member, Second Member, the Third Member and the Fourth Member shall
collectively hereinafter be called as the “Joint venture/Consortium Members” for the purpose of
Page 49 of 77
submitting a bid proposal to North Eastern Electricity Supply Company of Orissa Ltd. (hereinafter
referred to as NESCO), Balasore being a company incorporated under the Companies Act. 1956
having its. Registered Office at N 1/22, IRC Village, Bhubaneswar - 15 (hereinafter called the
“Owner”) in response to the invitation of bids (hereinafter called as “Tender Notice No…………….”
Document) dated…………….. for supply, erection, Testing & Commissioning as per the scope of work
……………….(hereinafter called as “the Transaction”)
WHEREAS Clause-2 of the Invitation for Bids (IFB), stipulates that two or more bidder(s) may form a
joint venture/Consortium among them and apply against this tender specification, provided they
fulfill the following eligible criteria;
1. They should have legally valid Consortium agreement as per the prescribed format
for the purpose of participation in the bidding process. The total no of a Consortium shall be limited
to four members.
2. One of the Joint Venture/Consortium members should be a Electrical Contractor
having valid HT License.
3. Consortium as a whole shall meet the qualifying norms specified in the tender, they
participate.
4. The lead member of the Consortium should meet at least 50% of the qualifying
norms in respect to the work experience & Turn Over requirement.
5. Besides the lead member, other member(s) of the Consortium together shall meet
the balance 50% of the qualifying norms in respect to the work experience & Turn Over requirement.
6. All the Consortium member(s) shall authorize the lead partner by submitting a power
of Attorney as per the prescribed format duly signed by the authorized signatories. The lead partner
shall be authorized to receive instructions for and on behalf of all partners of the Consortium and
entire execution of the contract.
7. The Consortium and its members shall be jointly and severally responsible and be
held liable for the purpose of guaranteed obligation and any other matter as required under the
contract.
8. Any member of the Consortium member(s) shall not be eligible either in an individual
capacity or part of any other Consortium to participate in the tender, where the said Consortium
participates.
9. Work Order(s) will be placed to lead members of the Consortium.
10. In addition to the above the Lead Member of the bidder(s) should submit the
following documents in part-I bid as qualifying terms.
i. Valid electrical (HT) license for Electrical Works.
Page 50 of 77
ii. PAN & TIN No.
iii. EPF registration.
11. The Lead Member of the Bidder(s) shall have to furnish service tax registration, ESI
and Labour license within 45 days of receipt of the order.
12. The prescribed format for Power of Attorney (Annexure-V) is provided in the tender
specification as enclosures.
AND WHEREAS the members of the Joint Venture/Consortium together shall strictly comply the
eligible criteria of the Clause-2 of the Invitation for Bids (IFB).
AND WHEREAS bid has been proposed to be submitted to the Owner by Lead Member based on this
Joint Venture/Consortium agreement all the members, signed by all the members.
NOW THIS INDENTURE WITNESSETH AS UNDER:
In consideration of the above premises, in the event of the selection of Joint Venture/Consortium as
successful bidder, all the parties to this Joint Venture/Consortium Agreement do hereby agree abide
themselves as follows:
1. M/s ……………………………. Shall act as Lead Member for and on behalf of Joint
Venture/Consortium Members. The said Joint Venture/Consortium members further declare and
confirm that they shall jointly and severally be bound and shall be fully responsible to the Owner for
supply, erection, Testing & commissioning as per the scope of work and successful performance of
the works, obligations under the same by the Lead Member are as follows:
i) Despite any breach by the Lead Member or other Member(s) of the Joint
Venture/Consortium agreement, the Member(s) do hereby agree and undertake to ensure full and
effectual and successful performance of the contract with the Owner and to carry out all the
obligations and responsibilities under the said Contract in accordance with the requirements of the
Contract.
ii) If the Owner suffers any loss or damage on account of any breach in the Contract or any
shortfall in the performance of the equipment in meeting the performance guaranteed as per the
specification in terms of the Contract, the Members (s) of these presents undertake to promptly
Page 51 of 77
make good such loss or damages caused to the Owner, on its demand without any demur. It. shall
not be necessary or obligatory for the Owner to proceed against Lead Member to these presents
before proceeding against or dealing with the other Members(s). The obligation of each of the
member is absolute and not independent of the Joint Venture/Consortium or any member.
iii) The financial liability of the Members of this Joint Venture/Consortium agreement to the
Owner, with respect to any of the claims arising out of the performance of non- performance of the
obligations set forth in the said Joint Venture/Consortium agreement, read in conjunction with the
relevant conditions of the Contract shall, however, not be limited in any way so as to restrict or limit
the liabilities of any of the Partners of the Joint Venture/Consortium agreement. The liability of each
Member is absolute and not severable.
iv) It is expressly understood and agreed between the Members to this Joint
Venture/Consortium agreement that the responsibilities inter se amongst the Members shall not in
any way be a limitation of joint and several responsibilities and liabilities of the Members to the
Owner. It is clearly understood that the Lead member shall ensure performance under the
agreements and if one or more Joint venture/Consortium Member(s) fail to perform its/their
respective obligations under the agreement(s), the same shall be deemed to be a default by all the
Joint venture/Consortium Members. It will be open for the Owner to take any steps, punitive and
corrective action including the termination of contract in case of such default also.
v) This Joint Venture agreement shall be construed and interpreted in accordance with the laws
of India and the courts of Odisha shall have the exclusive jurisdiction within Balasore in all matters
arising there under.
vi) In case of an award of a Contract, all the Members to the Joint Venture/Consortium
agreement do hereby agree that Lead Partner shall furnish Performance Bank Guarantee for value of
10% of the Contract Price and additional 1% by the other Joint Venture/Consortium Member in the
form of an unconditional irrecoverable Bank Guarantee in the prescribed format and as per terms of
the contract.
vii) It is further agreed that the Joint Venture/Consortium agreement shall be irrevocable and
shall form an integral part of the Contract, and shall continue to be enforceable till the Owner
discharges the same. It shall be effective from the date first mentioned above for all purposes and
intents.
viii) Capitalized terms used but not defined herein shall have same meaning as assigned to them
in the Tender Documents and/or the agreements.
ix) In case of any dispute amongst the members of the Joint Venture/Consortium, Owner shall
not be in any way liable and also the Consortium members shall not be absolved from the
contractual obligation in any manner.
Page 52 of 77
IN WITNESS WHEREOF the Members to the Joint Venture/Consortium agreement have through their
authorized representatives executed these presents and affixed Common Seals of their companies,
on the day, month and year first mentioned above.
1. Common Seal …………….……of For Lead Member/First Member
has been affixed in my/our presence
pursuant to the Board of Director's
resolution dt.------------ (Signature of authorized representative)
Name... …………….…………….
Signature.. ………….……………. Designation …….…………….
Name …………….…………….…………… Common Seal of the company
Designation…………….…………….…. …………….…………….…………….
2. Common Seal of …………….…… For Second Member
has been affixed in my/our presence
pursuant to the Board of Director's (Signature of authorized
resolution dated representative)
Name... …………….…………….
Signature.. ………….……………. Designation ……….…………….
Name …………….…………….…………… Common Seal of the company
Designation…………….…………….… …………….…………….………….
2. Common Seal of …………….…… For Third Member
has been affixed in my/our presence
pursuant to the Board of Director's (Signature of authorized
resolution dated representative)
Page 53 of 77
Name... …………….…………….
Signature.. ………….……………. Designation ……….…………….
Name …………….…………….…………… Common Seal of the company
Designation…………….…………….… …………….…………….………….
3. Common Seal of …………….…… For Fourth Member
has been affixed in my/our presence
pursuant to the Board of Director's (Signature of authorized
resolution dated representative)
Name... …………….…………….
Signature.. ………….……………. Designation ……….…………….
Name …………….…………….…………… Common Seal of the company
Designation…………….…………….… …………….…………….………….
WITNESSES:
1.…………….…………….…………. 2.…………….…………….………….
(Signature) (Signature)
Name …………..…………….…… Name …………….…………….…
(Official address) (Official address)
Page 54 of 77
ANNEXURE – VII (A)
LETTER OF COMPLIANCE OF QUALIFYING REQUIREMENT
(In case of Bidder being a Single Firm)
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
I/We ……………. (Name of Bidder) are submitting the bid as a single firm. In support of our meeting the
Qualifying requirements (QR) for bidders, stipulated in this tender specification, we furnish herewith
the details/documents etc. as follows.
Table – A: Previous Works Experience:
Package
Quoted
for
Description
of Proposed
Works
Tender
Qty
Qty Installed & Commissioned
Sl.
No. FY
Name of
Client WO Ref
Qty
Installed
Documents
provided in
proof of having
executed the
works during
the relevant FY.
Table – B: Average Annual Turnover:
Page 55 of 77
Package Quoted for
Estimated Cost
of the Package
(Rs. in Lakh)
Annual Turnover Data
(Rs. in Lakh)
Financial Year
Turnover
(Rs. in Lakh)
Last Three Year preceding to
the year of tender
Total Estimated Cost of the
packages quoted for
Average Turnover
Table – C: Access to Credit Facility:
Package Quoted for
Estimated Cost
of the Package
(Rs. in Lakh)
Liquid Assets as on
31.03.2012 Credit Facility
Description (Rs. in Lakh) Description
(Rs. in
Lakh)
Cash in Hand Cash Credit
Cash at Bank LC
Total Estimated Cost of
the packages quoted for
Fixed
Deposits
Others (Pl
Specify)
One fifth of the total
Estimated Cost as
above.
Total Liquid
Assets
Total Credit
Facility
Note: Continuation sheets, of like size and format, may be used as per Bidder’s requirements and
annexed to this Schedule.
I/We declare that we are fulfilling the qualifying requirements as per clause no. 2.0 of Section – I,
Invitation for Bids (IFB).
For & on behalf of ………… (Name of the Bidder).
Page 56 of 77
ANNEXURE – VII (B)
LETTER OF COMPLIANCE OF QUALIFYING REQUIREMENT
(In case of Bidder being a Joint Venture / Consortium Firm)
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
I/We ……………. (Name of Bidder) are submitting the bid as a single firm. In support of our meeting the
Qualifying requirements (QR) for bidders, stipulated in this tender specification, we furnish herewith
the details/documents etc. as follows.
Name of the members of the JV / Consortium
1.
2.
3.
Table – A: Previous Works Experience: Name of the Member (any one member only)
Package
Quoted
for
Description
of Proposed
Works
Tender
Qty
Qty Installed & Commissioned
Sl.
No. FY
Name of
Client WO Ref
Qty
Installed
Documents
provided in
proof of
having
executed
the works
during the
relevant FY.
Page 57 of 77
Table – B: Average Annual Turnover: (All the members of JV/Consortium taken together)
Package Quoted for
Estimat
ed Cost
of the
Package
(Rs. in
Lakh)
Annual Turnover
(Rs. in Lakh)
Annual Turnover
(Rs. in Lakh)
Total Annual Turnover
(Rs. in Lakh)
Name of
Member 1
Name of
Member 2
Name of
Member 2
Financial Year
Turnove
r
(Rs. in
Lakh) Financial Year
Turnov
er
(Rs. in
Lakh) Financial Year
Turno
ver
(Rs. in
Lakh)
FY 2011 -12 FY 2011 -12 FY 2011 -12
FY 2012 - 13 FY 2012 - 13 FY 2012 - 13
FY 2013 - 14 FY 2013 - 14 FY 2013 - 14
Total Total Total
Total Estimated
Cost of the
packages quoted
for
Average
Turnover
Table – C: Access to Credit Facility: (All the members of JV/Consortium taken together)
Package Quoted for
Estimated Cost
of the Package
(Rs. in Lakh)
Liquid Assets as on
31.03.2014 Credit Facility
Member 1 Member 1
Description (Rs. in Lakh) Description (Rs. in Lakh)
Cash in Hand Cash Credit
Cash at Bank LC
Fixed
Deposits
Others (Pl
Specify)
Total Liquid
Assets
Total Credit
Facility
Page 58 of 77
Liquid Assets as on
31.03.2014 Credit Facility
Member 2 Member 2
Description (Rs. in Lakh) Description (Rs. in Lakh)
Cash in Hand Cash Credit
Cash at Bank LC
Fixed
Deposits
Others (Pl
Specify)
Total Liquid
Assets
Total Credit
Facility
Liquid Assets as on
31.03.2014 Credit Facility
Total for JV 2 Total for JV 2
Description (Rs. in Lakh) Description (Rs. in Lakh)
Cash in Hand Cash Credit
Cash at Bank LC
Total Estimated Cost of the
packages quoted for
Fixed
Deposits
Others (Pl
Specify)
One fifth of the total
Estimated Cost as above.
Total Liquid
Assets
Total Credit
Facility
Note: Continuation sheets, of like size and format, may be used as per Bidder’s requirements and
annexed to this Schedule.
I/We declare that we are fulfilling the qualifying requirements as per clause no. 2.0 of Section – I,
Invitation for Bids (IFB).
For & on behalf of ………… (Name of the Bidder).
(All members of JV / Consortium should sign).
Page 59 of 77
Details of qualification and experience of key personnel proposed for carrying out the works
Sl.
No
Name of
Personnel
Degree/
Diploma
Bran
ch
Year of
Passing Past Experience
From To
Name of
Employe
r
Position
Held
Responsibilitie
s/ Relevant
experience
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) …………………
Note: 1. Continuation sheets, of like size and format, may be used as per Bidder’s
requirements and annexed to this Schedule.
2. In case of Joint Venture, separate sheet for each partner of Joint Venture
should be used.
Details for sub-contracting elements amounting to more than 10% of bid price
Page 60 of 77
Sl. No Item Description
Qty. proposed to be bought-out/ Sub-
contracted Source of Supply
1.
2.
3.
4.
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) …………………
Page 61 of 77
ANNEXURE – VIII
DETAILS OF COMMERCIAL DEVIATIONS
Bidder’s Name & Address
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
Sub: Commercial Deviation for Construction of Name of the project.
The following are the Commercial Deviations and variations from and exceptions to the specifications
and documents for the subject Project. These deviations and variations are exhaustive. Except for
these deviations, the entire work shall be performed as per your specifications and documents
Volume/Clause
Ref./Page
No.
As specified in the
Specification
Commercial deviation and variation to the
specification
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) …………………
Note: 1. Continuation sheets, of like size and format, may be used as per Bidder’s requirements and
annexed to this Schedule.
2. This will be read out during opening of Part-I Bid.
Page 62 of 77
ANNEXURE – IX
DETAILS TECHNICAL DEVIATIONS
Bidder’s Name & Address
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
Sub: Technical Deviation for Construction of ………………. (Name of the Project)
The following are the Technical Deviations and variations from and exceptions to the specifications
and documents for the subject package. These deviations and variations are exhaustive. Except for
these deviations, the entire work shall be performed as per your specifications and documents
Volume/Clause Ref./Page No. As specified in the
Specification / Relevant ISS
Technical deviation and
variation to the
specification
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) …………………
Note: 1. Continuation sheets, of like size and format, may be used as per Bidder’s requirements
and annexed to this Schedule.
2. The deviations and variations, if any, shall be brought out separately for each of the equipment.
Page 63 of 77
ANNEXURE – X
ADDITIONAL INFORMATION
Bidder’s Name & Address
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
We have enclosed with our proposal the following additional information for the subject, package.
Sl. No Brief description of Information Ref.& Page No.
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) …………………
Note: Continuation sheets, of like size and format, may be used as per Bidder’s requirements and
annexed to this Schedule.
Page 64 of 77
ANNEXURE – XI
WORK COMPLETION SCHEDULE
Bidder’s Name & Address
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sir,
We hereby declare that the following Work Completion Schedule shall be followed by us for the
purpose of subject package
Sl. No Description of Work Period in Months( from the date of LOA)
1 Completion of detailed engineering
2 Procurement of raw materials
3 Establishment of site office
4 Erection
(a) Commencement
(b) Completion
5 Testing & Pre-commissioning
(a) Commencement
(b) Completion
6 Commissioning
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) ………………..
Page 65 of 77
ANNEXURE – XII
CHECK LIST
Bidder’s Name & Address
To
The Dy.General Manager (C&P),
Corporate Office, NESCO,
Januganja, Balasore,
PIN:- 756019.
Dear Sirs,
Sl.
No.
Item Description Status of the
Submission of
data
Remarks
1 2 3 4
1. Bid Guarantee Yes /No If yes please give details No, amount,
validity & date of issue.
2. Qualifying Data Yes /No
3. Commercial Deviation Yes /No
4. Technical Deviation Yes /No
5. Cost of withdrawn of
deviations
Yes /No
6. Bid validity Yes /No If yes state here the period.
7. Period of completion Yes/No
If, yes please state here the period of
completion.
8. Additional information offered
by bidder
State here briefly
N.B.:- The contents of this schedule will be read out during opening of Part-I Bid.
………………………
Signature of Bidder
Date & Seal:
Page 66 of 77
Page 2 of 2
N.B:-
1. The bid guarantee one original and one copy shall be furnished in two separate
sealed envelope appropriately superscribed thereon.
2. All Schedules pertaining to prices (originals) shall be furnished in a sealed
envelope duly superscribed thereon. Similarly one set of copies of such schedules
shall be given in a separate sealed envelope (these are not to be opened during
opening of Part –I ).
3. All other schedules, one set original and another copy shall be submitted in two
separate sealed envelope (these are to be opened during Part –I bid opening )
Date: (Signature) …………………..
Place: (Printed Name) ……………….
(Designation) …………………..
(Common Seal) ………………..
Page 67 of 77
ANNEXURE – XIII
Page 1 of 3
PROFORMA OF INDEMNITY BOND TO BE EXECUTED BY THE CONTRACTOR FOR THE
EQUIPMENT/MATERIAL HANDED OVER BY NESCO FOR PERFORMANCE OF ITS CONTRACT
(Entire Equipment consignment in one lot)
(On non-Judicial stamp paper of appropriate Value)
INDEMNITY BOND
THIS INDEMNITY BOND is made this ............. day of ...........20.............. by.................... a
Company registered under the Companies Act, 1956/ Partnership Firm / Proprietary
Concern having its Registered Office at .........................(hereinafter called as „Contractor‟ or
“Obligor” which expression shall include its successors and permitted assigns ) in favour of
North Eastern Electricity Supply Company of Orissa Ltd.(NESCO) ,Regd. Office: N 1/22, IRC
Village, Nayapalli, Bhubaneswar – 751015 registered under the Company Act 1956 (here in
after called “Owner”)”Which expression shall include its successors and assigns ) :
WHEREAS Owner has awarded to the Contractor a Contract for ............... vide its Letter of
Award / Contract No.................... dated.................... and its Amendment No. .................. and
Amendment No.................. (applicable when amendments have been issued) hereinafter
called the “Contract”) in terms of which Owner is required to handover various equipment to
the Contractor for execution of the Contract.
And WHERAS by virtue of Clause No............. of the said Contract, the Contractor is required
to executive an Indemnity Bond in favour of Owner for the Equipment/Material handed over
to it by Owner for the purpose of performance of the Contract / Erection portion of the
Contract (hereinafter called the “Equipment”)
NOW THEREFORE, This Indemnity Bond witnessth as follows:
1. That in consideration of various equipment as mentioned in the Contract, valued at Rs... ................
(Rupees .....................) handed over to the Contractor for the purpose of performance of the
Contract, the Contractor hereby undertakes to indemnify and shall keep Owner indemnified, for the
full value of the Equipment. The Contractor hereby acknowledges receipt of the Equipment as per
dispatch title documents handed over to the Contractor duly endorsed in their favour and detailed in
the Schedule appended hereto. It is expressly understood by the Contractor that handing over of the
dispatch title documents in respect of the said Equipment duly endorsed by Owner in favour of the
Contractor shall be construed as handing over of the Equipment purported to be covered by such title
documents and the Contractor shall hold such Equipment is trust as a Trustee for and on behalf of
Owner.
Page 68 of 77
2. That the Contractor is obliged and shall remain absolutely responsible for the safe transit / protection
and custody of the Equipment at Owner project Site against all risks, whatsoever, till the Equipment
are duly used / erected in accordance with the terms of the Contract and the Plant / Package duly
erected and commissioned in accordance with the terms of the Contract, is taken over by Owner.
The Contractor undertakes to keep Owner harmless against any loss or damage that may be caused
to the Equipment.
3. The Contractor undertakes that the Equipment shall be used exclusively for the performance /
execution of the Contract strictly in accordance with its terms and conditions and no part of the
equipment shall be utilized for any other work or purpose whatsoever. It is clearly understood by the
Contractor that non-observance of the obligations under this Indemnity Bond by the Contractor shall
inter-alia constitute a criminal breach of trust on the part of the Contractor for all intents and purpose
including legal / penal consequences .
4. That NESCO (as the case may be) is and shall remain the exclusive Owner of the Equipment free
from all encumbrances, charges or liens of any kind, whatsoever. The Equipment shall at all times
be open to inspection and checking by Engineer in Charge / Engineer or other employees/agents
authorized by him in this regard. Further, Owner shall always be free at all times to take possession
of the Equipment in whatever form the Equipment may be, if in its opinion the Equipment are likely
to be endangered, misutilised or converted to uses other than those specified in the Contract, by
any acts of omission or commission on the part of the Contractor binds himself and undertakes to
comply with the direction of demand of Owner to return the Equipment without any demur or
reservation.
5.
That this indemnity Bond is irrevocable. If at any time any loss or damage occurs to the Equipment
or the same or any part thereof is misutilised in any manner whatsoever, then the Contractor hereby
agrees that the decision of the Engineer-in-Charge/Engineer of Owner as to assessment of loss or
damage to the Equipment shall be final and binding on the Contractor. The Contractor binds itself
and undertakes to replace the lost and/or damaged Equipment at its own cost and/or shall pay the
amount of loss of Owner without demur, reservation or protest. This is without prejudice to any
other right or remedy that may be available to Owner against the Contractor under the Contract
and under this Indemnity Bond.
6. NOW THE CONDITION of this Bond is that if the Contractor shall duly and punctually comply with
terms and conditions of this Bond to the satisfaction of Owner, THEN, the above Bond shall be void,
but otherwise, it shall remain in full force and virtue.
IN WITNESS WHEREOF, the Contractor has hereunto set its hand through its authorized
representative under the common seal of the Company, the day, month and year first above
mentioned.
Page 69 of 77
SCHEDULE
Particulars of
the
Equipment
handed over
Quantity Particulars of Dispatch Title
Documents
Value of the
Equipment
Signature of
Attorney (authorised
representative as a
token of receipt RR / GR / No. /
Date of Bill of
Lading
Carrier
For an on behalf of M/s..............................................
WITNESS
1. 1. Signature ...................................... Signature .....................................
2. Name ........................................... Name ..........................................
3. Address........................................ Designation ................................
Authorised representative *
2. 1. Signature .....................................
2. Name ..........................................(Common Seal in case of Company)
3. Address .......................................
* Indemnity Bonds are to be executed by the authorised person and (i) in case of Contracting
Company under common seal of the Company or (ii) having the Power of Attorney issued
under common seal of the company with authority to execute Indemnity Bonds, (iii) In case of
(ii), the original Power of Attorney if it is specifically for this Contract or a Photostat copy of
the Power of Attorney if it is General Power of Attorney and such documents should be
attached to Indemnity Bond.
Page 70 of 77
ANNEXURE-XIV
SELF DECLARATION FORM
Name of the Purchaser: -------------------------
Tender Notice No: -----------------------------
Sir,
1. I / we, the undersigned do hereby declare that, I / we have never ever been
blacklisted and / or there were no debarring actions against us for any default in supply of
material / equipments or in the performance of the contract entrusted to us in any of the
Electricity Utilities of India.
2. In the event of any such information pertaining to the aforesaid matter found
at any given point of time either during the course of the contract or at the bidding stage, my
bid/contract shall be liable for truncation / cancellation / termination without any notice at the
sole discretion of the purchaser.
Yours faithfully,
Place-
Date-
Signature of the bidder
With seal
(This form shall be duly filled-up and signed by the bidder & submitted along with the original
copy of the Bid.)
Page 71 of 77
ANNEXURE – XV (A)
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY
DEPOSIT
(ON NON-JUDICIAL STAMP PAPER OF Rs.100/-)
Ref Date Bank Guarantee No:
In accordance with invitation to Tender Notice No.--------- Dated ------------- of North Eastern
Electricity Supply Company of Orissa Ltd. [herein after referred to as the NESCO] for the execution
of ______________________________________________________________ (name of package)
M/s__________________________Address______________________________________________
_____________________________________________________wish/wished to participate in the
said tender and as the Bank Guarantee for the sum of Rs.______________
[Rupees________________________________________ Valid for a period of ………… days (in
words) is required to be submitted by the Bidder.
1.We the________________________________________________[Indicate the Name of the Bank]
[Hereinafter referred to as „the Bank‟] at the request of M/S
___________________________________________________________ [Herein after referred to as
supplier (s)] do hereby unequivocally and unconditionally guarantee and undertake to pay during the
above said period, on written request by NESCO an amount not exceeding Rs._________________to
the NESCO, without any reservation. The guarantee would remain valid up to 4.00 PM of
_________________ [date] and if any further extension to this is required, the same will be extended
on receiving instructions from M/s _______________________________________ on whose behalf
this guarantee has been issued.
2. We the _____________________________________ [Indicate the name of the bank] do hereby
further undertake to pay the amounts due and payable under this guarantee without any demur, merely
on a demand from the NESCO stating that the amount claimed is due by way of loss or damage caused
to or would be caused to or suffered by the NESCO by reason of any breach by the said supplier [s] of
any of the terms or conditions or failure to perform the said Bid. Any such demand made on the Bank
shall be conclusive as regards the amount due and payable by the Bank under this guarantee. However,
our liability under this guarantee shall be restricted to an amount not exceeding
Rs.______________________________ (in wards)
3. We, the _______________ Bank undertake to pay the NESCO any money so demanded not
withstanding any dispute or disputes so raised by the supplier [s] in any suit or proceeding
instituted/pending before any Court or Tribunal relating thereto, our liability under this agreement
being absolute and unequivocal. The payment so made by us under this bond shall be a valid
discharge of our liability for payment there under and the supplier(s) shall have no claim against
us for making such payment.
Page 72 of 77
4. We, the__________Bank [Indicate the name of the bank] or our local branch at Balasore further
agree that the guarantee herein contain shall remain in full force and effect during the aforesaid
period of -------------- days and it shall continue to be so enforceable till all the dues of the NESCO
under by virtue of the said Bid have been fully paid and its claims satisfied or discharged or till
NESCO certifies that the terms and conditions of the said Bid have been fully and properly carried
out by the said Supplier [s] and accordingly discharges this guarantee. Unless a demand or claim
under this guarantee is made on us in writing on or before the _________________ (date) we
shall be discharged from all liability under this guarantee thereafter.
5. We, the __________Bank [Indicate the name of the bank] or our local branch at Balasore further
agree that the NESCO shall have the fullest liberty without our consent and without affecting in
any manner our obligations here under to vary any of the terms and conditions of the said Bid or
to extend time of performance by the said Supplier [s] from time to time or to postpone for any
time or from time to time any of the powers exercisable by the NESCO against the said supplier
[s] and to forbear or enforce any of the terms and conditions relating to the said bid and we shall
not be relieved from our liability by reason of any such variation, postponement or extension
being granted to the said Supplier [s] or for any forbearance act or omission on the part of the
NESCO or any indulgence by the NESCO to the said Supplier[s] or by any such matter or thing
whatsoever which under the law relating to sureties would but for this provision, have effect of so
relieving us.
6. This guarantee will not be discharged due to the change in the name, style and constitution of
the Bank or the supplier [s].
7. We, the ____________Bank or our local branch at Balasore lastly undertake not revoke this
Guarantee during its currency except with the previous consent of the NESCO in writing.
8. We, the__________________________ Bank further agree that this guarantee shall also be
invokable at our place of business at Balasore [Indicate address & Branch code of local branch
at Balasore] in the State of Orissa.
Dated ________________________ Day of 2012.
Witness ((Signature, names & address) For_________ [Indicate the name of Bank]
1. Power of Attorney No.______
2 Date: _________
SEAL OF BANK
Note: The non-judicial stamp paper of worth Rs.100/- shall be purchased in the name of the
bank, which has issued the bank guarantee.
Page 73 of 77
ANNEXURE- XV (B)
FORM OF EXTENSION OF BANK GUARANTEE
(ON NON-JUDICIAL STAMP PAPER OF Rs.100/-)
Ref. No.________________
Dated: __________
NESCO Ltd.,
Regd. Office: N1/22, IRC Village, Nayapalli
Bhubaneswar - 751015
Dear Sirs,
Sub: Extension of Bank Guarantee No.__________for Rs._____________favouring yourselves
expiring ______________ on account of M/s. ______________ in respect of contract
No.______________ dated _____________ (hereinafter called original bank guarantee).
At the request of M/s. _____________we ____________ bank Branch office at ________ having its
head office at _____________ do hereby extend our liability under the above mentioned guarantee
No. ___________ Dated__________ for a further period of _______ Years/months from ________to
expire on __________ except as provided above, all other terms and conditions of the original bank
guarantee No.__________dated __________ shall remain unaltered and binding.
Please treat this as an integral part of the original guarantee to which it would be attached.
Yours faithfully,
For ____________
Manager/Agent/Accountant
Power of Attorney No.______
Date: _________
SEAL OF BANK
Note: The non-judicial stamp paper of worth Rs.100/- shall be purchased in the name of the bank,
which has issued the bank guarantee.
Page 74 of 77
RATE QUOTATION
(Single Phase Meter)
S.L
NO ITEM UNIT
Cost of Erection Per
Unit including
service Tax
Cost of
Erection Per
Unit including
service Tax
(In Word)
01
For both Replacement and
Shifting of 1 phase meter from
inside to outside of the house.
No
02
For replacement of defective or
electro mechanical meter
without shifting the
meter location.
No
03 For replacement of damaged
service connection. No
RATE QUOTATION
(Three Phase Meter)
S.L
NO ITEM UNIT
Cost of Erection Per
Unit including
service Tax
Cost of
Erection Per
Unit including
service Tax
(In Word)
01
For consumer metering,
installation of 3-Ph
WC/HTTV meter.
No
02
For DTR metering, installation of
LTCT meter with supply and
erection of required materials
(as per drawing).
No
Signature of Contractor
Page 75 of 77
DRAWING FOR DTR METERING (CT RATIO 200/5 A) UNDER CAPEX
75CM
35CM
WELDED JOINT
6CM
3CM
8 NOS 5MM φ HOLES AT 3 CM
SPACING LT CABLE FROM TRANSFORMER
50X8 MM GI FLAT
METER BOX
67CM
15φX25 MM SLOT HOLE 130CM
LT CABLE TO DISTRIBUTION BOX
CT BOX
WELDED JOINT
10CM PEDDING
41CM
75X40X6 MM GI CHANNEL
50CM SAND & COMPRESSED EARTH
FILLING
G.L.
10CM PCC(1:2:3)
BILLS OF MATERIALS
SL NO. MATERIAL UNIT QUANTITY
1
(75X40X6)MM
X1.8MTR. GI
CHANNEL NO 2
2
(50X8)MM
X82CM GI
FLAT NO 2
3
GI
NUTS,BOLTS &
WASHER KG 0.5
4
CEMENT,SAND
& AGRIGATE - LUMPSUM
Page 76 of 77
DRAWING FOR DTR METERING (CT RATIO 800/5 & 400/5 A) UNDER CAPEX
75CM
35CM
WELDED JOINT
6CM
3CM
8 NOS 5MM φ
HOLES AT 3 CM SPACING LT CABLE FROM
TRANSFORMER
50X8 MM GI FLAT
METER BOX
72CM
15φX25 MM SLOT HOLE 130CM
LT CABLE TO DISTRIBUTION BOX
CT BOX
WELDED JOINT
10CM PEDDING
41CM
75X40X6 MM GI CHANNEL
50CM SAND & COMPRESSED EARTH
FILLING
G.L.
10CM PCC(1:2:3)
BILLS OF MATERIALS
SL NO. MATERIAL
UNI
T QUANTITY
1
(75X40X6)MM
X1.8MTR. GI
CHANNEL NO 2
2
(50X8)MM
X82CM GI
FLAT NO 2
3
GI
NUTS,BOLTS
& WASHER KG 0.5
4
CEMENT,SAN
D &
AGRIGATE - LUMPSUM
Page 77 of 77