1 NORTH EAST LINE (NERL) UPGRADE Project Update Hume Corridor Passenger Rail Collaboration 11 October 2018 General Manager Asset Management Interstate, Brian Green General Manager Corporate Affairs, Bas Bolyn

Transcript of NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing...

Page 1: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

1

NORTH EAST LINE (NERL) UPGRADEProject Update – Hume Corridor Passenger Rail Collaboration

11 October 2018

General Manager Asset Management – Interstate, Brian Green

General Manager Corporate Affairs, Bas Bolyn

Page 2: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

2

1. Recap

2. Current Performance - NERL

3. Project Objectives & Scope

4. Works Program (delivery priorities)

5. Current Status

6. Monash Institute of Technology review

7. Stakeholder Engagement

8. Next Steps

AGENDA

Page 3: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

3

At the Group’s last meeting in May, ARTC:

• Explained that the Australian Government has allocated additional funding to upgrade the Victorian North East Rail Line (NERL), bringing the total investment to $235million

• Explained why the Government was making this investment, reflecting on performance and track condition

• Provided an indicative project timeframe

• Advised that ARTC and Victorian state agencies are working together to develop a scope of works for the NERL upgrade

• Committed to sharing the scope of works with the Group and getting on with the job of delivering.

• Today is about discussing the scope of works and next steps with the NERL upgrade project.

RECAP

Page 4: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

4

CURRENT PERFORMANCE

Transit Time Delay (mins/trip)

July 2018 to September 2018

Lease

Target

ARTC Performance

Target

Loco-hauled Passenger

115 km/h

XPT 130 km/h Super Freighter

115 km/h

Melbourne - Albury 30 20 5.2 7.3 11.7

16

14

18

19

18

12

1 2 5

6

5.2

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

Tim

e L

os

s (

min

ute

s)

Melbourne to Albury (East and West Track) Transit Time Delay Loco Hauled Passenger (P)

Time Loss KPI Target KPI Benchmark Average

Page 5: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

5

CAUSAL FACTORS: DELAYS

0

2

4

6

8

10

12

Min

ute

s d

ela

y p

er

se

rvic

e

Jan-Mar 2018 AverageDelay Per ServiceApr 2018 Average DelayPer ServiceMay 2018 Average DelayPer ServiceJun 2018 Average DelayPer Service

North East line project directly targets primary infrastructure factors contributing to delays

*Does not include cancelled passenger train services

Page 6: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

6

PROJECT SCOPE

• Deliver a Victorian ‘Class 2’ track performance standard - brings North East Line to the same standard as other long-haul passenger

regional rail lines in Victoria.

Wo

rk A

cti

vit

y

Mud hole removal Ballast undercutting and sledding.

Installation of crossovers Two new crossovers between Seymour and Benalla

Resurfacing Tamping and regulating.

Turnout upgrades Replacing bearers and steel components where required.

Signalling works Aerial removal and power supply backup improvements.

Drainage improvements Creating and reforming trackside drainage (cess drains).

Grinding Mainline grinder

Replacement of existing underbridgesConverting transom bridges to ballast-top, and replacing life expired and/or

substandard ballast-top bridges with new ballast-top bridge decks.

Recondition Existing BridgeCorrect tight gauge, Replace transoms, Reconditioning bridge ends U Upgrade

bridge ballast kerbs.

Ballast depth improvement Increasing depth of ballast under track.

Level crossing upgrades Complete renewal of level and pedestrian crossings

Page 7: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

7

NORTH EAST LINE WORKS

Page 8: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

8

• Early Project works continue to be progressed by ARTC:

• Bridge upgrade and track works were completed during the scheduled March 2018 possession

• A tender for the supply of turn-outs for the cross-over pairs, that are scheduled to be installed in track in March 2019,

has been released

• A construction plan for the track and civil aspects of the cross-over pairs, for delivery by ARTC staff, is being developed

• A tender is being finalised for a design and construction contract for signalling works associated with the cross-over

pairs

• The ARTC Signal Design Team continues to develop designs to remove aerial signal line wire and provide dedicated

power supplies. Given the ongoing theft of wire which is disruption network operations additional external design

support is also being contracted to accelerate this work

• A construction tender for the replacement of aerial line wire is also developed by ARTC

• A tender for the main track and civil upgrade construction activities is being developed

PROJECT UPDATE

Page 9: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

9

MONASH INSTITUTE EXTERNAL REVIEW

• Based on stakeholder feedback, ARTC engaged the Institute of Railway Technology (IRT) at Monash University to undertake an independent review of the proposed NERL upgrade plan against the following principal criteria:

• Ability to deliver V/Line Passenger Class 2 track geometry at the completion of the upgrade program, taking into consideration: Punctuality, ride quality and resilience

• Included extensive data review, analysis and assessment of scope methodology

• A site inspection was conducted between Seymour and Benalla. Based on this visual assessment, the focus on mud hole removal, ballast addition in conjunction with tamping and lining together with transom deck bridge replacement was reinforced.

The review has found that the upgrade will meet Victorian Class 2 standard and is supportive of the approach with the NERL scope of works.

• “Given the overall condition of the NERL in terms of ballast quality and fouling, proposed plan targets the key criteria outlined and will provide a much-improved and more maintainable permanent way at the completion of the works within the current funding commitment of $235M.”

Page 10: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

10

EXTENSIVE DATA VALIDATION & SCOPE REVIEW

Page 11: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

11

• ARTC is committed to ongoing engagement and information sharing

throughout the delivery of the project

• will include things such as: a dedicated project website, fact sheets,

website, stakeholder briefings, presence at stations/community pop-ups,

progress update letters to stakeholders.

• ARTC partnering with Federal and Victorian State agencies on

engagement activity: PTV, TfV, V/Line and DIRD&C.

• www.artc.com.au/projects/northeast

• Community ‘pop-ups’ including at train stations and local community

events: Seymour, Euroa, Benalla, Wangaratta, Wodonga, Albury. • Commence end-October

• Engagement will be reviewed, coordinated and aligned with the Inland Rail

project and Victorian agencies so as to minimise ‘engagement fatigue’ on

communities/ stakeholders – noting the high number of projects in Victoria

currently.

• Will transition to ‘disruption’ focused information in early New Year

STAKEHOLDER ENGAGEMENT

Page 12: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

12

• Infrastructure Australia (IA) Business Case being finalised, review by IA expected in December 2018

• Steps leading up to construction include:

• engaging contractors and procuring material (early 2019)

• finalising design (Q1 2019)

• before major works can start in early 2019 (by end Q2).

• Works to be undertaken during Q1 2019 include signalling. ARTC will go to tender for this package of work shortly.

• Major works will be fully underway mid- 2019 and finalised by mid-2021.

• ARTC will keep the Group and community informed throughout the delivery of the NERL upgrade

• Engagement activity (ongoing)

NEXT STEPS

Page 13: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

13

QUESTIONS?

Page 14: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

14

APPENDICES

Page 15: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

15

IRT Review commentary - Upgrade Plan

The principal components of the upgrade plan include:

• Identification and removal of all existing mud holes

• Currently 234 locations on the East track and 137 locations on the West track

• Where formation issues also need to be addressed, these will be actioned during the upgrade

• Small regions for ballast cleaning have been identified

• Addition of new ballast across the majority of the network (between 50mm and 200mm)

to facilitate improved geometry retention

• Ballast additions will be supported by tamping and lining across the network

• Drainage will also be upgraded across the network

• Replacement of a significant number of short transom deck bridges to ballast top

• To facilitate improved geometry

• Rail grinding (minimum single pass) across the entire network

Page 16: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

16

Information to Support Proposed Upgrade Plan

ARTC provided high quality information in

support of the proposed upgrade plan.

This demonstrated that significant effort had

been placed on ensuring a detailed

understanding of the network existed.

Key data included:

• An excel based worksheet summarising the

current condition of the asset and proposed

upgrade activities within each section

• NERL maintenance records covering the period

2003 to 2018

• Detailed plots showing asset condition

Page 17: NORTH EAST LINE (NERL) UPGRADE...NORTH EAST LINE (NERL) UPGRADE Project Update ... Given the ongoing theft of wire which is disruption network operations additional external design

17

Appendix 2 Criteria to Assess Track Condition

Various criteria have been used to

assess the track condition

• TMS, VQI, VTI hits and IRV ride comfort

• Pros and cons associated with each of

these indices

• Generally all point to the same locations

as being poor

The emphasis on mud holes and

high TMS locations is appropriate to

ensure that the track reaches the

required V/Line standard

Approximately 150km of track sits

below this requirement the V/Line

VQI requirement