North American Power Group Western Mine-Mouth Coal-Fired Power Two Elk.
-
date post
22-Dec-2015 -
Category
Documents
-
view
219 -
download
0
Transcript of North American Power Group Western Mine-Mouth Coal-Fired Power Two Elk.
North American Power Group
Western Mine-Mouth Coal-Fired Power
Two Elk
North American Power Group
Western Mine-Mouth Coal-Fired Power
Two Elk
North American Power Group, Ltd.
NAPG
North American Power Group, Ltd.
NAPG 15 Year-Old Privately held Denver, CO based IPP Full member of WECC Owns and operates 7 power plants in California
4 Biomass (84 MW total)
2 Coal/Pet Coke (69 MW total)
1 Gas (48 MW total) Conceived and developed the Two Elk project in the Power River
Basin of Wyoming
Two Elk ProjectTwo Elk Project Central station plant anchoring transmission 2000-3000 MW Unit #1 at 325 MW under construction Ample water supply Ample coal supply by mine truck or overland conveyor
belt No additional infrastructure needed for subsequent units Potential for Clean Coal for reduced or “zero”emissions
Two Elk ProjectTwo Elk Project The plant is mine mouth, being a single mine truck haul from 20% of the nation’s coal
supply. The three mines abutting the project shipped approximately 196 million tons of coal in
2004 and can supply 250 million tons per year. Unit #1 has been designed and is being constructed by Bechtel to allow it to burn non-
commercial waste coal but run equally well on commercial coal. Unit #1 officially commenced construction in late May 2005. Wyoming ruled all permits
valid and in full force and effect in July 2005. The Two Elk project has permits and water rights for an 11 well field, providing more
than 3500 GPM. Two Elk Unit #1 has been designed with dry cooling to minimize water requirements.
An advantageous capital structure for Unit #1 based upon Tax Free Bonds provides most of Unit #1’s capital. Three hundred, twenty six million dollars ($326,000,000) in tax-exempt bonds have been sold to date.
Why Two Elk ?Why Two Elk ? Fuel Supply
3 mines adjacent to Two Elk – 2004 production 196 MM Tons– Mines Permitted for 250 MM Tons/year
The adjacent mines have coal reserves of more than 21.7 billion tonsNo risk of supply or additional permits required 4th mine scheduled to open by 2010
Why Two Elk ?Why Two Elk ?Fuel Transportation
Mine-Mouth location immediately adjacent to minesNo over the road trucking or railroad Delivery by 400 Ton Mine Truck or overland conveyor beltMine Plan and transportation rates agreed upon for 30 yearsAudit and adjustment rights to reflect actual costs to deliver
Why Two Elk ?Why Two Elk ?Air Permits
Construction underway on Unit #1Air Modeling completed for additional unitsAir Permit application can be filed in Q1 2006Developer experienced with WY DEQ
Why Two Elk ?Why Two Elk ?Water
11 well field permitted by State EngineerEach well permitted at 325 GPMUnit # 1 with dry cooling design consumes 275 GPMAdequate water to support additional generation
Why Two Elk ?Why Two Elk ? State Support
NAPG awarded $326 million in tax exempt bonds for Unit #1 (AA-/A-1+)Local and regional groups formed to support transmission
– Wyoming Infrastructure Authority– Governor Freudenthal– Wyoming Counties For Responsible Energy Development
(WyCFRED)
Wyoming Carbon Sequestration Committee formed to explore for CO2 capture and sequestrationWyoming Pipeline Authority exploring Enhanced Oil Recovery using CO2 flood
NAPG Coal DevelopmentNAPG Coal DevelopmentCharacteristic
Two Elk
Unit I
Two Elk
Unit II
Two Elk
Unit III
Two Elk
Unit IV
Two Elk
Unit V
Water275 gpm3575 gpm available
3000 gpm available To be permitted To be permitted To be permitted
Fuel SupplyPRB Waste– Mine truck/Conveyor belt
PRB Waste– Mine truck/Conveyor belt
PRB Waste– Mine truck/Conveyor belt
PRB Waste– Mine truck/Conveyor belt
PRB Waste– Mine truck/Conveyor belt
Electric
Transmission
PacifiCorpPacifiCorp, WAPA, Xcel, APS, TransElect, National Grid 500 kvDC Line Addition
PacifiCorp, WAPA, Xcel, APS, TransElect, National Grid 500 kvDC Line Addition
PacifiCorp, WAPA, Xcel, APS, TransElect, National Grid 500 kvDC Line Addition
PacifiCorp, WAPA, Xcel, APS, TransElect, National Grid 500 kvDC Line Addition
Land Owned Owned Owned Owned Owned
Rail Transport N/A N/A N/A N/A N/A
Competitive
Advantage
No fuel cost-transport only. Tax Exempt Debt Coal in gas market.
Identical need in Utility Resources (4 Utilities)Supply curve locationCoal in gas market.
Identical need in Utility Resources (4 Utilities)Supply curve locationCoal in gas mkt.
Identical need in Utility Resources (4 Utilities)Supply curve locationCoal in gas mkt.
Identical need in Utility Resources (4 Utilities)Supply curve locationCoal in gas mkt.
In-Service Date
2009 2010/2011 2010/2011 2010/2011 2010/2011
Why Two Elk ?Why Two Elk ? Transmission
Substantial studies completed for Two Elk to the desert SouthwestRight of Way from Two Elk to PacifiCorp securedInformation and previous work can accelerate process
– Environmental & site evaluation including GIS– Federal Agency contacts for lead and scoping– Corridor and route study information available
Why Two Elk ?Why Two Elk ? 760 acre site with expansion option allows for
additional units without added infrastructure expense. (600 MW IGCC => 80 Acre footprint)
Ash Ash storage and disposal site permitted and in place This is the only such permit in Wyoming
Two Elk can anchor transmission that will provide access to Wyoming’s Superb wind resources
Two Elk is 60 miles from prime CO2 flood enhance oil recovery fields and export pipelines
Why Now?Why Now? Unit 1 Currently Under Construction, COD 2009 NAPG is poised to permit subsequent coal units
(COD dates 2010-2012) Favorable State and Local support Unit #1 to anchor transmission build out as well
as subsequent expansion New Transmission with Two Elk as an Anchor
will enable Wyoming Wind Development
ConclusionConclusion The Two Elk Project will provide long-term, stable, lowest bus bar cost of
electric power. Unit #1 is under construction and has the support of local and regional
stakeholders. Two Elk will act as an anchor for your transmission additions. Future resource additions at Two Elk involve only an air permit. Project enhancements are possible via carbon capture and sequestration and
regional Enhanced Oil Recovery. With low fuel cost, no transportation, carbon capture and EOR, Two Elk has
the potential be the Palo Verde of Wyoming. NAPG already has completed significant work, reducing risk and
time to market.
PlanPlan The West has the Load The will exists to expand the transmission Funding is available All that is missing is the generation complex We have a head start with a project under
construction and room to grow We need partners that want to expand the site,
jointly own power projects or provide PPAs