NMCB Ops Officer Perspective Iraq/Kuwait Deployment
Brief to: SAME Mid-Atlantic Regional Conference10 OCT 07
Overview
• Deployment Overview– Deployment Timeline– Mission– Organization– Locations
• Deployment Highlights
Deployment Summary:• Advanced Party Deploys: 26 Jul 05
• Iraq MEF Support: 15 Aug 05 to 25 Nov 05
• CFLCC Support: 18 Nov 05 to 28 Feb 06
• Delayed Party Re-deploys: 28 Feb 06
206162195217173195151184206
Feb-06Jan-06Dec-05Nov-05Oct-05Sep-05Aug-05Jul-05Jun-05
Timeline for Deployment
CSE Training Iraq MEF Support CFLCC Support
Mission
– On 26 July 05, NMCB THREE will deploy a responsive, flexible general engineering / construction force with Convoy Security Element (CSE) capabilities.
– Provide general engineering support to II MEF (FWD), ARCENT CFLCC, and JTF HOA.
COMMAND MASTER CHIEF STAFF
Safety Officer Military Advisor
CMAA
OPSLCDR Stasick
SUPPLYADMIN TRAINING COMM
OPS STAFF
S3C–
Ops Chief–S3E Engineering OffS3QC -
–Quality Control
S3A
–
Asst Ops
SPECIAL STAFFX1 - ChaplainX2 - DentalX3 - LegalX4 - Medical
CO
XO
CHARLIE COMPANY
INTEL / WEAPONSMLO
Organization
BRAVO COMPANYALFA COMPANYHQ COMPANY DETAILS MOBILITY COMPANY
Deployment Locations
Det PAPA
Gulfport
Det GTMO
Det Andros
Det Rota Det Souda Bay Kosovo IA Iraq Mainbody
CFLCC-Camp Arifjan (MB)-Camp Buehring-Camp Virginia-Ali Al Saleem-Kuwait Naval Base-K-Crossing-Navistar-Camp Victory-Ash Shuaybah
Det Bahrain
ABO/KAAOT OILPLAT
Qatar IA
Det Seychelles
Det Horn of Africa-Camp Lemonier, Djibouti-Adangalina, Djibouti-Tadjura, Djibouti-Nairobi, Kenya-Manda Bay Kenya-Harer, Ethiopia-Hurso, Ethiopia-Gode, Ethiopia
3
3
33
3 3
33
33
3
3
Iraq Deployment Highlights
• Camp Fallujah– MHG Camp Maintenance– Pump House O & M– Election Support
• Ramadi \ Taquaddum– Hardened Galley’s– SWA Hut Construction– Iraqi Security Force Camp– Timber Tower– Camp Maintenance
• Kalsu– Electrical Upgrades– Dust Abatement Motor– Force Protection Improvements– Super SWA Huts in the RDF– MHG Camp Maintenance
• Al Asad– Hardened Galley (CG)– Runway Joint Repair– ISF Camp Support– Coalition Forces FOB Construction
CENTCOM Laydown
3U n ite d S ta te s F lee t F o rc e sU n ite d S ta te s F lee t F o rc e s O p e ra tio n a l R ea d in e ss E ffe c tiv e n es s P rim a cyO p e ra tio n a l R ea d in e ss E ffe c tiv e n es s P rim a cy
Al AsadNMCB 3 DETNMCB 22
Al Taqaddum30 NCR DETNMCB 4 DET
NMCB 22 DET
Al Fallujah30 NCRNMCB 3 NMCB 22 DET
Korean VillageNMCB 22 DET
HOA (Djibouti)
NMCB 3 DET BahrainNMCB 3 DET
Ar RamadiNMCB 3 DETNMCB 22 DET
Al QaimNMCB 22 DET
RawahNMCB 3 DET
NMCB 22 DET
CorregidorNMCB 3 DET
II MEF
CJSOTFCJSOTF
HOA HOA
NAVCENTNAVCENT
30 NCR DETNMCB 3 DET
NMCB 21 DET
HadithaNMCB 22 DET
Command Element
Kuwait22NCR FWD
NMCB 3NMCB 21 DET
HOA (Ethiopia)
NMCB 3 DET
HOA (Kenya)NMCB 3 DET
KalsuNMCB 3 DET
Drainage Improvements
Water Well, Camp Rawah
MEF Construction
Electrical UpgradesRunway Repairs, Al Asad
Bridge Repair, Habbiniyah
Timber Tower, Ar Ramadi
SWAHut, TQ Comm Tower, Al Asad
Mission in Kuwait
• Setup Mainbody Site at Camp Arifjan
• Setup two Detail Camps– Camp Virginia– Camp Buehring
• Completed 58 projects and over 22,596 mandays of construction at 11 different locations
• 19 Projects partially completed and turned over to NMCB SEVEN
• Active/Reserve integration
• Joint operations
Camp Virginia-Manholes For Fiber Optic Cables-Construct Base Roads-PEB Sunshades
KCIA / APOD-Bus and Convoy Route Upgrade
Ali Al Salem/Camp Moreell/Army LSA-ECP Sun Shade-USO Tent Improvements-ATOC Briefing Room
Arifjan-POL Fuel Transfer Yard PEB-Concrete Loading Ramp-Drainage Improvements-Construct Secure Room-TNOSC Pad Expansion
Camp Victory-PX Construction
SPOD-Construct Height Check Arch-Redeployment Yard ICODE Prep
Navistar-Southbound Lane Improvements-South Immigration Lot Improvements
Camp Buehring-ASP Site Prep-ASR Dallas Improvements-Erect 4 LAMS-Erect 5 Sunshade PEBs
KNB-Staging Yard improvements-Concrete Loading Ramp
K Crossing
UNCLASSIFIED
UNCLASSIFIED
Udairi Range-South Road Repairs-Road Maintenance
Kuwait Project Locations
K-Crossing
• 2KM long border crossing• Over 3,000 manday project• 70,000 metric tons of asphalt• 1,800 cubic meters of concrete• Completed 38% of project
Det HOA
• Completed over 8,200 mandays of work at 8 different det sites stretched across three countries
• Drilled three water wells and repaired another
• Rapid response to Nairobi building collapse
• Completed a design/build boat ramp in Kenya
Ea r t hwor k 14 %
FOB S uppor t2 %M i nor P r oj e c t s
8 %For c e P r ot e c t i on
2 %
Ca mp S e t - up15 %
Ca mp M a i nt e na nc e
17 %
P l umbi ng3 %
Wa t e r We l l s3 %
I nt e r i or Fi ni sh7 %
El e c t r i c a l1%
Fa br i c S t r uc t ur e s1%
M a sonr y S t r uc t ur e s
5 %
Conc r e t e & P a v i ng
5 %
Wood S t r uc t ur e s12 %
M e t a l S t r uc t ur e s5 %
Work Breakdown
Deployment Summary
• 112 Projects Completed• 64,218 MD’s Completed• Personnel Deployed to Iraq and Kuwait
– 570 Personnel in Iraq– 877 Personnel in Kuwait (NMCB 21 and 63rd CSE) – 6 CSEs completing over 26,000 miles and 200
missions in Iraq