NM Department of Transportation ( NMDOT) All Roads Network of Linear Referenced Data (ARNOLD)
description
Transcript of NM Department of Transportation ( NMDOT) All Roads Network of Linear Referenced Data (ARNOLD)
NM DEPARTMENT OF TRANSPORTATION (NMDOT)
ALL ROADS NETWORK OF LINEAR REFERENCED DATA
(ARNOLD)
Executive Sponsor: Tom Church, Cabinet Secretary
Business Owners: Yolanda Duran, NMDOT Data Management BureauMel Herrera, GIS/Geospatial Team - Supervisor
Jack Yates, Roadway Inventory ProgramGenevieve Grant Business Support IT Project Manager
Project Certification for InitiationSeptember 8, 2014
Project Goals and Deadline
1. Full Integration and implementation of the Environmental Systems Research Institute (ESRI) Roads and Highways module of ARCGIS. Migration of data from the Transportation Information Management System (TIMS) into NMDOT’s Roads and Highways Database.
2. Data Linkage with Asset data requirements such as Pavement, Bridge, Crash, Traffic Monitoring Data, Roadway Inventory Assets, Maintenance Management System, Fiscal Management Information System (FMIS), and the Highway Safety Improvement Program (HSIP). This Linear Reference System needs to meet the Federal Highway Administration (FHWA) data requirements for the federal “Moving Ahead for Progress in the 21st Century” (MAP-21) act, and meet NMDOT’s performance measures.
NMDOT Data Management needs to comply with the All Roads Network of Linear Referenced Data (ARNOLD) deadline of June 15,
2015.
Business Problems Current system:
…is cumbersome and not Windows-intuitive, requiring an 18-month learning curve to proficiently utilize the system.
…is relative inaccessible to NMDOT’s staff supporting Geographic Information Systems (GIS) and the Rural Infrastructure Program (RIP). Requests for data exports, summary tabulation must go through NMDOT’s IT Division.
…does not link to other department databases such as pavement and bridge.
Business Problems Cont’d Current system:
… requires a complicated process to upload bulk data files.
…must use ArcMap 9.3., a number of versions behind current ArcMap technology and associated functions and analytical tools.
…requires use of Internet Explorer 8 for tabular data editing.
Desired Outcomes
A Linear Referencing System (LRS) that meets the MAP 21 ARNOLD requirements
Data Linkage with Asset data requirements such as Pavement, Bridge, Crash, Traffic Monitoring Data, Roadway Inventory Assets, Maintenance Management System, FMIS, and HSIP
A more user-friendly design for database data import, query and reporting
Ability to readily transform GPS coordinates to linear reference system mile points and vice-versa.
Business Opportunity Meet Map 21 Highway Performance Monitoring System
(HPMS) and Highway Safety Improvement Program (HSIP) Requirements
Provide an easy means to validate NM-certified mileage
Meet the expanded MAP 21 LRS requirement “to cover all public roads including representation of dual carriageways on divided highways” and related highway facilities (e.g., ramps).
Opportunity to implement the expanded requirements, based on best practices identified by other State DOTs.
Cost Savings
Reduced staff time due to increased efficiency and productivity by utilizing a single, state-wide, well implemented linear reference system
Lower government service costs due to more efficient work flows and more accurate business process tracking, data entry, auditing, and reporting of information
Utilization of a much more familiar, user-friendly software interface will greatly reduce staff training time and costs.
Risk of Keeping the Status Quo
Loss of federal funds due to inadequate reporting
Further degradation of the data quality due to inability to stay current with necessary updates
Current system does not meet the Federal Highway Performance Monitoring System (HPMS) nor their Model Inventory of Roadway Elements (MIRE) data requirements, and it uses outdated technology
Many manual processes needed to produce reports required by FHWA
Maintaining multiple LRS systems and databases.
Project Phases and Deliverables
Project Phase Due Date Deliverable
Enterprise LRS and Road Inventory Discovery Workshop and Implementation Planning
10/31/2014
Project team, Implementation methodology, Overview of Project Tasks and Deliverables, Project Plan and Data Review Document
Aggregation and conflation of City, County and Municipal “All-Road” geodatabases to one master road network geodatabase.
6/1/2015 Data Cleansing and Migration Methodology and Materials, Review Data Cleansing and migration test database
Migration of data from TIMS into Roads and Highways Database. Data Linkage with Asset data requirements such as Pavement, Bridge, Crash, Traffic Monitoring Data, Roadway Inventory Assets, Maintenance Management System, FMIS, and HSIP.
4/1/2016 Publication and Reporting, Review of Mapping, Reporting, Asset Management System Integration, and Asset Management System Integration components
System Delivery, performance testing, user acceptance testing, user training/documentation.
6/1/2016 Final fully functional system, roll-out support, training documents and user manuals.
Total Cost of Ownership
Description FY15 FY16
Consulting Services
System Implementation
$900,000.00 $500,000.00
Software Licenses Included in existing
Enterprise License
Agreement (ELA)
Included in existing ELA Agreement
TOTAL $900,000.00 $500,000.00