Niger - Combined 2013-2017 Country Strategy Paper … 2013-2017 COUNTRY STRATEGY ... used in this...
Transcript of Niger - Combined 2013-2017 Country Strategy Paper … 2013-2017 COUNTRY STRATEGY ... used in this...
Translated Document
AFRICAN DEVELOPMENT BANK GROUP
ORWA DEPARTMENT
October 2013
NIGER
COMBINED 2013-2017 COUNTRY STRATEGY PAPER
AND PORTFOLIO REVIEW
TABLE OF CONTENTS
LIST OF ACRONYMS AND ABBREVIATIONS .................................................................................. ii
EXECUTIVE SUMMARY .................................................................................................................. IV
I. INTRODUCTION ....................................................................................................................... 1
II. COUNTRY CONTEXT AND PROSPECTS ............................................................................ 1
2.1 POLITICAL, ECONOMIC AND SOCIAL CONTEXT ............................................................................. 1
2.2 STRATEGIC OPTIONS ...................................................................................................................... 9
2.3 AID COORDINATION/HARMONIZATION AND BANK POSITIONING .............................................. 11
III. COUNTRY PORTFOLIO REVIEW ....................................................................................... 11
3.1 PORFOLIO OVERVIEW AND PERFORMANCE ................................................................................ 12
3.2 KEY LESSONS FROM THE PORTFOLIO REVIEW………………………………………………….13
IV. 2005-09 STRATEGY AND KEY LESSONS ........................................................................... 15
4.1 IMPLEMENTATION OF THE 2005-09 COUNTRY STRATEGY, EXTENDED TO 2012……………….14
4.2 KEY LESSONS……………………………………………………………………………………15
V. BANK COUNTRY STRATEGY 2013-17 IN NIGER ............................................................. 16
5.1 RATIONALE FOR BANK INVOLVEMENT AND PILLARS ................................................................ 16
5.2 OUTCOMES AND TARGETS .......................................................................................................... 17
5.3 STRATEGY IMPLEMENTATION INSTRUMENTS …………………………………………………..18
5.4 MONITORING/EVALUATION ......................................................................................................... 19
5.5 ISSUES COVERED BY COUNTRY DIALOGUE …………………………………………………….19
5.6 POTENTIAL RISKS AND MITIGATION MEASURES ........................................................................ 19
VI. CONCLUSION AND RECOMMENDATION ....................................................................... 20
6.1 CONCLUSION................................................................................................................................ 21
6.2 RECOMMENDATION ..................................................................................................................... 21
LIST OF GRAPHS Graph 1: Real GDP Growth Rate (%) ........................................................................................................... 2 Graph 2: Budget Balance (% of GDP) .......................................................................................................... 3 Graph 3: Country’s Strategic Option ........................................................................................................... 9 Graph 4: Breakdown by Sector of the Bank’s Active Portfolio in Niger..................................................... 11
LIST OF BOXES Box 1: Potential for the export of crude oil and refined products to enhance the external balance ..... 2 Box 2: High factor costs, an obstacle to the expansion of extractive industries .................................... 9 Box 3: Co-operation between the Bank and Niger ............................................................................... 11
The following conventions have been used in this combined 2013-17 Country Strategy Paper and Portfolio Review:
In the tables, a blank indicates that the corresponding item is "not applicable" in this case; (...) indicates that data are not
available; 0 or 0.0 indicates that the figure is equal to zero or that it is negligible. Given that some figures have been
rounded, the totals may not exactly match the sum of the components.
A dash (-) between years or months (for example, 2010-11 or March-September) indicates the period covered from the
first year or month to the last year or month indicated inclusive; a slash (/) between years (e.g., 2010/11) indicates a
fiscal (or financial) year.
Unless otherwise indicated, all amounts are expressed in CFAF. Where reference is made to the dollar, it is the United
States dollar.
i
LIST OF ANNEXES
Annex 1: Map of Niger ................................................................................................................................. Annex 2: Selected Macroeconomic Indicators ............................................................................................ Annex 3: Comparative Socio-economic Indicators ....................................................................................... Annex 4: Bank Portfolio in Niger at end-September 2013 ........................................................................... Annex 5: Portfolio Performance Improvement Action Plan ......................................................................... Annex 6: Indicative Grant/Loan Programme for the CSP 2013-17 .............................................................. Annex 7: Bank ‘s Fiduciary Strategy in Niger ............................................................................................... Annex 8: Challenges Related to the Environment, Climate Change and Green Growth .............................. Annex 9: Development Partners’ Areas of Intervention in Niger in 2013 .................................................... Annex 10 Implementation Status of the Kandadji Programme – Phase I (Agricultural Component) ........... Annex 11: CSP 2013-17 Indicative Results Framework .................................................................................
ii
FISCAL YEAR 1 January – 31 December
CURRENCY EQUIVALENTS (September 2013) UA 1 = EUR 1.1449 UA 1 = USD 1.51528 UA 1 = CFAF 751.00517
INDICATIVE SCHEDULE FOR THE PREPARATION OF NIGER CSP 2013-17 Key stages in the preparation of CSP 2013-17 Dates
Consideration of CSP Concept Note by Operations Committee (OpsCom) 9 May 2013
CSP Preparation Mission to Niger 13 to 25 May 2013
Review of CSP Draft Report by Peer Reviewers 24 to 30 June 2013
Review of CSP Draft Report by Niger Country Team and Readiness Review 16 to 22 July 2013
Review by Country Team 24 July 2013
Second virtual review of revised version of Report by Niger Country Team 4 September 2013
Dialogue Mission to Niger 23 September 2013
Review by Operations Committee (OpsCom) 3 October 2013
Board consideration 4 December 2013
LIST OF ACRONYMS AND ABBREVIATIONS
ADF : African Development Fund
AEO : African Economic Outlook
AFD : Agence Francaise de developpement (French Development Agency)
AfDB : African Development Bank
AWF : African Water Facility
BADEA : Arab Bank for Economic Development in Africa
BCEAO : Central Bank of West African States
BTP : Construction and Public Works
CAFER : Autonomous Road Maintenance Financing Fund
CC : Climate Change
CET : Common External Tariff
CFAF : Franc of the African Financial Community
CIF : Climate Investment Fund
CPI : Corruption Perception Index
CPIA : Country Policy and Institutional Assessment
CS : Sector Committee
CSP : Country Strategy Paper
CSRD : Supreme Council for the Restoration of Democracy
CTN : National Technical Council
DAC/OECD
:
Development Assistance Committee of the Organization for Economic Co-operation
and Development
DB : Doing Business
DTS : Trans-Saharan Backbone
EC : European Commission
ECOWAS : Economic Community of West African States
EPA : Economic Partnership Agreement
EU : European Union
FDI : Foreign Direct Investment
GDP : Gross Domestic Product
iii
GER : Gross Enrolment Rate
GWh : Gigawatt per hour
HALCIA : High Authority to Combat Corruption and Related Crimes
HDI : Human Development Index
I3N : “Nigeriens Feeding Nigeriens” Initiative
ICB : International Competitive Bidding
IDB : Islamic Development Bank
IMF : International Monetary Fund
KFAED : Kuwait Fund for Arab Economic Development
LPG : Liquefied Petroleum Gas
LSF : Legal Support Facility
M2 : Money and quasi-money
MDG : Millennium Development Goal
MISMA : International Support Mission for Mali
MUJAO : Movement for Oneness and Jihad in West Africa
NCB : National Competitive Bidding
NIGELEC : Niger Electricity Company
ODA : Official Development Assistance
OFID : OPEC Fund for International Development
PD : Paris Declaration on Aid Effectiveness
PDES : National Commission for Strategic Planning
PDES : Economic and Social Development Plan
PEFA : Public Expenditure and Financial Accountability /
PEMFAR : Public Expenditure Management and Financial Accountability Review
PIE : Independent Energy Producer
PNUD : United Nations Development Programme
PPCR : Climate Resilience Pilot Programme
PPP : Public-Private Partnership
PRGFP : Public Finance Management Reform Programme (PRGFP)
PRSF : Poverty Reduction Strategy Framework
RBCSP : Results-Based Country Strategy Paper
RIS : Regional Integration Strategy
RISP : Regional Integration Strategy Paper
RWSSI : Rural Water Supply and Sanitation Initiative
SCF : Strategic Climate Fund
SME : Small and Medium-Sized Enterprise
SMI : Small and Medium-Sized Industry
SP/PDES : PDES Permanent Secretariat
SRP : Sahel Resilience Programme
TFM : Migrant remittances (Transferts de fonds des migrants)
TFP : Technical and Financial Partners
TSH : Trans-Sahara Highway
U.S. : United States of America
UA : Unit of Account
WAEMU : West African Economic and Monetary Union
iv
SUMMARY
1. Introduction. This paper proposes a strategy for Bank Group intervention in Niger over
the period 2013-17, as well as areas where portfolio management could be enhanced.
2. Country Background. Niger is part of the Sahel region where efforts to promote inclusive
and green growth meet with greater specific structural challenges than elsewhere, resulting from a
combination of factors relating to the environment, climate change, lack of infrastructure, and high
poverty levels. These factors particularly increase the populations’ vulnerability to food insecurity,
and therefore Niger’s stakeholders have defined resilience to such food insecurity as a specific
objective. Moreover, the recent and future context marked by larger scale exploitation of mineral and
oil resources aids the funding of economic growth but also calls for greater focus on governance, in
order to enable the country participate fully in the exploitation of the underground resources and also
use the ensuing national income for its priority development actions. The country has other assets and
opportunities, including: (a) the agro-forestry and pastoral sector which can develop significantly;
and (b) untapped potential for the production of energy, especially renewable energy.
3. The Bank's portfolio in Niger comprises 18 operations (only one in the private sector),
totalling about UA 240 million, with an overall disbursement rate as at end April 2013 of about 24%,
an average age of three years and 27% of projects at risk. As at end November 2013, the overall
disbursement rate (excluding private sector window projects) increased to 31%. The 2.36 score for
the overall performance of the Bank's portfolio in Niger in 2013 (against 2.25 in 2010) is deemed
satisfactory. Despite this overall positive assessment, the portfolio is experiencing difficulties,
including hindrances observed in the implementation of Phase 1 of the Kandadji Project and the
Tibiri-Dakoro Road Project caused by the contractors recruited for the works. The implementation of
the proposed portfolio enhancement action plan should help to improve the quality at entry and
execution of future Bank operations.
4. Country Strategy for the 2013-17 Period. The Bank’s country strategy to help
Niger use its opportunities while addressing its major challenges and remaining selective, will
be based on two pillars: (i) strengthening resilience to food insecurity; and (ii) strengthening
governance, particularly of natural resources.
5. Pillar 1 aims, not only to create and enhance productive capacity in agriculture, but also to
increase market access capabilities by supporting the development of anchor infrastructure that could
contribute to this effort. Special attention will be paid to the areas of water control and management,
transport (to facilitate access to national and regional markets), and energy. The Bank’s experience
in Niger shows that it can effectively remain committed to these strategic infrastructure sectors,
considering its ability to mobilize other actors, especially in the implementation of major structuring
projects.
6. Pillar 2 is aimed at strengthening Niger’s governance framework to enable the country to
take full advantage of its natural resources, ensure sustainable exploitation of these resources,
promote and maintain macroeconomic stability and create an enabling environment for private
investment. These factors are essential to the robust, inclusive and green growth desired by the
country. The strategy will also support cross-cutting themes, with specific emphasis on
gender promotion, since the goal sought is to systematically integrate the dimensions of climate
change and the green economy, gender, capacity building and skills development as well as the
promotion of youth employment into Bank operations, in line with the priorities of the 2013-22 Ten-
year Strategy. Economic and sector-based surveys will also be undertaken to strengthen the Bank's
role as a knowledge institution.
v
7. With specific reference to gender promotion, which is a key issue within Niger’s context,
the Bank’s action will be at three levels. Furthermore, operations that will be prepared will
contribute directly to improving the status of women. In Niger, women are the most vulnerable in
terms of food insecurity – a problem that Pillar 1 of the strategy plans to directly solve. Concerning
Pillar 2, the strategy will seek to support national gender-sensitive budgeting efforts in the area of
governance and public finance management. Therefore, all operations prepared within the
strategy framework will incorporate this objective whose purpose is to promote gender, with precise
indicators to assess progress made. In addition, policy dialogue with Niger’s stakeholders on the
subject will be strengthened, particularly with the involvement of the Bank Group President’s
Special Gender Envoy. Lastly, the envisaged study on women’s status and child trafficking will
generate necessary knowledge to move forward the gender promotion agenda.
8. The strategy proposed above is consistent with government priorities as set out in the
2012-15 Economic and Social Development Plan (PDES). In addition, it will contribute to the
implementation of the Bank Group’s 2013-2022 Ten-Year Strategy, particularly the broad aspects
relating to infrastructure development, regional economic integration, private sector development and
promotion of good governance. The proposed Bank strategy will further contribute to the
implementation of the West Africa Regional Integration Strategy (RISP 2011-15), and the Bank’s
Sahel Initiative under preparation.
9. The strategy will be financed from the resources of the ADF-12 public sector window
for 2013, and those of ADF-13 and ADF-14 for 2017. These resources and those of the regional
envelope and private sector window will all serve as catalysts for mobilizing additional financing,
especially from other technical and financial partners. As part of the implementation of this strategy,
the Bank will pay special attention to the mobilization of resources for Niger. Accordingly, all Bank
Group sovereign and non-sovereign instruments, co-financing and/or guarantee arrangements, as well
as the resources of fiduciary funds or facilities will be used. Furthermore, and in accordance with the
Bank’s Ten-Year Strategy, public-private partnerships (PPP) will be sought, particularly to finance
major infrastructure projects. It is recommended that national procurement procedures be applied for
national competitive bidding (NCB) relating to Bank-financed operations.
1
I. INTRODUCTION
1.1 This report proposes a new strategy for Bank Group involvement in Niger over
the period 2013-2017 and areas where portfolio management needs to be
strengthened. Since 2011, the internal political climate in Niger has normalized and resulting
in the enhanced visibility and stability needed by the Bank Group to develop a country
strategy. In terms of economic development, Niger is facing significant challenges, including
recurrent food insecurity, an obvious vulnerability to climate change, partly due to the country's
location in the Sahel, a regional environment in search of stability and, finally, the need to
strengthen the governance of extractive industries. The government recently adopted an
Economic and Social Development Plan (PDES) as a response to these multiple challenges. All
these factors, as well as the recent adoption by the Bank of a 2013-2022 Ten-Year Strategy,
underpin the need to develop a new country strategy for Niger, covering the period 2013-
17. Beside this introduction, this CSP 2013-17 has six sections. Section II presents the country’s
political, economic and social context, and assesses medium-term prospects. It analyses the
challenges, opportunities and country strategic framework, aid coordination and harmonization,
and the Bank’s positioning in the country. Section III assesses portfolio performance. Section
IV is an overview of the implementation of the Bank’s previous strategy and draws key lessons
for CSP 2013-17. Section V presents the Bank's Niger strategy for the 2013-17 period and
highlights the strategic pillars, expected outcomes and targets, the issues covered by the country
dialogue, potential risks and mitigation measures. Section VI presents the conclusion and
recommendation addressed to the Board.
II. COUNTRY CONTEXT AND PROSPECTS
2.1 Political, Economic and Social Context
2.1.1 Political and Security Context
2.1.1.1 Continuing consolidation of the democratic process is a guarantee of stability,
peace, and the implementation of reforms. However, the interplay of political alliances
and regional threats poses risks for internal balance. A broad-based government was formed
in August 2013. The ruling coalition, the “Movement for the Revival of the Republic/Mouvance
pour la Renaissance de la République (MRN)" has a comfortable majority in the National
Assembly, although political alliances are being re-formed. The situation remains precarious at
the regional level, with potential or actual danger arising from the hybrid forces (identity-related
and religious conflict and trafficking of all kinds). The consequences of the Libyan crisis are
less alarming than a year ago, but the situation is far from being fully stabilized. The threat of
extremist groups like Boko Haram and MUJAO still looms, and the risk of negative impact on
Niger is real, even if it is contained. Finally, Niger has been affected by the crisis in Mali,
particularly through the security and humanitarian impact caused by the influx of refugees.
However, the recent progress achieved in the wake of the election of a new president in Mali
portends a relative stabilization of the situation. It appears that the natural expansionist tendency
of these threats is regional. In this context, any tentative solution can and should be considered
only at regional level.
2.1.2 Economic Context
Economic Growth Boosted by the start of oil production (see Box 1) and a good harvest,
real GDP growth in 2012 is estimated at over 13% (see Figure 1 below). Primary, secondary
and tertiary sector contribution is expected to stand at 6.9%, 4.0% and 2.5%, respectively.
2
2.1.2.1 Although some growth was recorded
in 2012 (16.5% against 3.7% in 2011), the
primary sector is has shown an erratic
performance, contributing somewhat to food
insecurity in rural and even urban areas of the
country. A long-term analysis shows that
agricultural production is often affected by
weather conditions. Niger was among the Sahel
countries that experienced the drought-related
acute food crises of 2005 and 2010, which
affected more than 10 million people in the
region, including 2 million in Niger. The country
therefore considers the search for greater food security a priority. To foster this objective, the
authorities, in April 2012, adopted the initiative dubbed “Nigeriens Feeding Nigeriens” (les
nigériens nourrissent les nigériens) or 3N, which aims to promote sustainable food security and
agricultural development.
2.1.2.2 The relative weight of the primary
sector in the economy stood at 46.2% of
GDP in 2012, compared with 45.4% in 2011
and 48% in 2010. The primary sector’s
volume expansion is mainly driven by
agriculture (+24.8%). This may be attributed to
rainy season cropping, an uptrend in irrigated
agricultural production resulting from
increased investment in agricultural
infrastructure and the supply of improved
seeds.
2.1.2.3 The secondary sector (15% of
GDP) experienced high volume growth of
37.7% in 2012, compared with 3% in
2011. The increased activity in this sector in
2012 (traditionally the lowest contribution to
GDP) may be attributed to “extractive
activities” which recorded a 152.5% growth
related to oil production. After declines in
2011, uranium and gold production rose by
13.2% and 11.9% respectively in 2012. After a 12.1% decline in 2011, refining operations, well
in excess of domestic demand, and improved power generation contributed to the 5.7% increase
in energy sector value added in 2012. Furthermore, the continued implementation of State
infrastructure projects helped to strengthen the construction industry, which recorded a 7.4%
growth rate in 2012, compared with a 3.3% decline in 2011. Rechanneling financing to non-
extractive sectors in order to diversify the economy would help avoid any likelihood of Dutch
disease.
2.1.2.4 The uptrend in the service sector, which accounts for 38.8% of GDP, continued.
After a 7.7% growth in volume in 2011, the pace of growth in the sector continued with a 6.6%
rate in 2012. This trend was due to increased activity in freight transport, including oil, which
rose by 8.5%.
2.1.2.5 Macroeconomic Management. Inflation increased to 3.9% in 2012, but could fall
to 1.8% in 2013. After rising to 2.9% in 2011 from 0.9% in 2010, following a poor crop season,
it climbed to 3.9% in 2012, due to the inflationary impact of the floods of July 2012. The
decision to temporarily place a cap on food prices, adopted in 2012 following the floods, should
-2
0
2
4
6
8
10
12
14
2004 2005 2006 2007 2008 2009 2010 2011 2012
Graph 1: Real GDP Growth (%)
Niger West Africa Africa
Box 1: Crude oil and refined products export potential to strengthen the external trade balance.
Niger officially joined the circle of African petroleum producing and exporting countries from November 2011. The inauguration of the Zinder refinery in 2011 enabled it to take a step towards consolidating its public finances. By providing the country with the means to produce and exchange crude oil and refined products, especially in the sub-region, the refinery made it possible for the country to strengthen its productive fabric and also reduce the structural deficit in its balance of payments. The Zinder refinery has a capacity of 20 000 barrels/day (or 1 million tonnes per year), and is able to produce the following derivatives:
Liquefied petroleum gas (LPG): 69 900 tonnes per year;
Super petrol: 306 200 tonnes per year;
Diesel: 505 400 tonnes per year
The Agadem deposits were estimated to be able to produce between 60 000 and 80 000 barrels of crude oil per day (3 to 4 million tonnes per year) for export. The route chosen will be the Chad-Cameroon oil pipeline (to the Kribi terminal). The current project consists in building a pipeline connecting the Agadem fields to the Doba pipeline (Chad-Kribi) running from Chad to Cameroon.
.
3
bring inflation down to 1.8% in 2013, which is below the community’s 3% threshold. The
downtrend should be accelerated by the BCEAO’s common monetary policy, which lays
emphasis on price stability.
2.1.2.6 The budget deficit is below 3% for 2012, reflecting a significant improvement on
2011, but could drop further to 2% in 2013. In spite of the expansionary fiscal policy adopted
in 2012, the overall budget deficit which had widened (see Figure 2), from 2.4% of GDP in
2010 to 6.8% in 2011, shrank to 2.8% in 2012. It is expected to 2% for 2013. This performance
is attributable to the huge revenue generated by the extractive industries. Moreover, the revenue
derived from the review of various tax rates, the expiry of certain exemptions and the continued
strengthening of the tax and customs services have also enhanced the performance1.
2.1.2.7 The current account balance is still
structurally in deficit although slightly
improved. In 2012, foreign trade witnessed 29%
growth in export volume related to the sale of
petroleum products and a 25% increase in import
volume. The structural deficit in the balance-of-
payments current account stabilized at 22.7% of
GDP in 2012 and 2011, compared with 20% in
2010. Imports of capital goods used in the
construction of the Zinder refinery and the
pipeline that will supply it with crude largely oil
account for this deficit. Foreign direct investment (FDI)2, notably Chinese and French, has
helped to make this deficit level sustainable.
2.1.2.8 Niger’s debt distress risk went from “low” to “moderate” in 2012. Debt ratios were
reduced substantially when the country became eligible for the Enhanced HIPC Initiative in
April 2004. At end-2010, the level of public debt was low, with the total public debt (internal
and external) accounting for about 19.8% of GDP. The release of a full internal debt inventory
and the signing in July 2010 of a bank loan repayment agreement with the BCEAO helped to
improve the State’s financial situation. However, the public debt has increased since 2011. The
stock of external debt rose from 16.8% of GDP in 2010 to 20.1% of GDP in 2012, as a result
of the provision of State guarantee of the non-concessional Chinese loan granted for the oil
refinery (SORAZ), a loan obtained to finance State participation in the Imouraren uranium
mine and a loan of CFAF 50 billion contracted with Congo. The debt sustainability analysis
thus revealed that the country’s debt distress risk had gone from “low” to “moderate”.
Governance
2.1.2.9 Natural Resource Management. The authorities are committed to strengthening
natural resource management and environmental governance. Although the recent increase
in mineral and oil exploitation is potentially an important source of income to support the
country’s economic and social progress, it also poses challenges for governance, particularly
environmental governance, which needs to be strengthened. The authorities are working on this
issue. Niger recently adopted a national charter on good governance and the management of
mineral resources and hydrocarbons. Moreover, in 2012 the country achieved the status of full
compliance with the Extractive Industries Transparency Initiative (EITI), implying that any
investor involved in the mining and hydrocarbons sector is required to carry out an
environmental and social impact assessment (ESIA) and have an Environmental and Social
Management Plan (ESMP). Furthermore, as part of the revision of the Mining Code and the
Investment Code, the Government plans to strengthen the environmental standards in line with
1 Despite the significant increase, (from 13.3% of GDP in 2010 to 14.4% in 2011), the tax burden rate is still low compared to the Community
target of 17%. 2 Representing 16.2% of GDP in 2011, compared with an average of 4% for Africa.
-10
0
10
20
30
40
50
2004 2005 2006 2007 2008 2009 2010 2011 2012
Graph 2: Fiscal Balance(% of GDP)
Niger West Africa Africa
4
international standards. Environmental management is moreover reflected in the 3N Initiative
through: (i) sustainable natural resource management; (ii) capacity building for stakeholders;
(iii) land tenure support; and (iv) the establishment of a participatory system of governance.
2.1.2.10 Quality of Policies and Institutions. Efforts are still needed despite the progress
recorded in some areas. Mo Ibrahim Foundation African Governance Indicators highlight the
urgent need for targeted reforms. Moreover, structural policy and social inclusion and equity
policy indicators have stagnated. The country has however made progress in the area of
transparency and the fight against corruption3, although the situation had initially
deteriorated. The overall assessment of policies and institutions conducted by the Bank over
the period 2010-11 shows that there has been a substantial improvement in the quality of
economic management and governance beyond the average for West Africa. This resulted in
an increase in Niger’s ADF-12 country allocation, by 14.4% and 4.5% in 2012 and 2013
respectively.
2.1.2.11 Public Finance Management. Unsatisfactory implementation of reforms despite
progress in transposing the WAEMU Directives. According to the latest PEFA report in the
process of validation by the Government, the implementation of the public finance Management
Reform Programme (PFMRP 2011-14) is unsatisfactory. Only five out of 31 PEFA
performance indicators were considered satisfactory, while 21 were awarded scores equal to or
lower than their 2008 levels (the year PEMFAR introduction leading of preparation of PFMRP
2011-14). Significant progress was recorded in public procurement and cash-flow
management. In addition, at Community level, all WAEMU Directives were transposed into
the national regulatory framework with the support of technical and financial partners,
including the Bank. The current challenge lies in the enactment of implementing
instruments. Weaknesses were observed, including the lack of commitment and procurement
plans. Significant challenges still have to be overcome in order to: (i) improve internal resource
mobilization to match the national economic potential; (ii) strengthen the national public
financial control and anti-corruption mechanism; and (iii) strengthen the capacity of economic
and financial services with a view to improving the efficiency of public services and better
inclusion of the gender dimension in the national budget.
Sector Governance
2.1.2.12 Energy sector. In the energy sector, the electricity sub-sector is characterized by
limited access to electricity (10%) and an aging transmission and distribution
network. Moreover, Niger imports about 86.6% of its electricity consumption from Nigeria,
under an agreement signed in 1972 and renegotiated in 2010. On-going reforms in the energy
sector in Nigeria could undermine the preferential tariffs on exports to Niger as practised
today. Indeed, the current rates in Niger date from 1994 and have not been substantially
amended since then4. The sector is therefore facing many challenges which, in the electrical
sector, relate in particular to the need to: (i) increase access and reduce disparities between rural
(1% access) and urban areas (50% access); (ii) modernize transport and distribution
infrastructure; (iii) develop appropriate information systems and master plans (National Master
Plan and National Rural Electrification Plan); (iv) provide capacity building for sector
stakeholders and conduct a study on electricity rates that will enable the framing of growth
assumptions; and (v) establish an independent regulatory body for the electricity sector,
considering that independent power producers are gradually moving in.
2.1.2.13 Transport Sector. Transport infrastructure is among PDES priority issues and in
this respect, Niger has opted to open up externally and internally. The Government has
updated the 2004-2010 National Transport Strategy (SNT) which concerned road transport
3 According to the Transparency International 2012 Report, the corruption perception index has improved. Niger ranks 113th in 2012, out
of 176 countries, against the 134th position in the 2011 ranking, that is, an increase of 21 places 4 These rates mask the actual margins realized by the Niger Electricity Company since the import price is about ¼ of the resale price charged
to the final consumer
5
only. It will be extended to other modes of transport (air, rail, sea and inland waterways). The
new 2011-2025 SNT being validated is presented as a set of transport policies for each mode
of transport and a costed action plan spanning 15 years. Beside Ordinance No. 2009-25 of 3
November 2009 setting out the fundamental principles governing the transport system, the
Government has issued the Ministerial Order of 27 February 2013 concerning types of traffic
control, road checkpoints and remedial mechanisms to minimize abuse in freight
transport. Other actions, decisions and instruments being considered include: (i) the imminent
adoption of a new highway code; (ii) the establishment of the Niger Road Safety Agency
(ANISER); (iii) which will be tabled before a parliamentary session in the days ahead. Lastly,
the new strategy being validated includes proposed institutional reforms in the sector such as
the transformation of the Autonomous Road Maintenance Financing Fund (CAFER) into a
second generation Road Maintenance Fund (FER2) and/or a road agency. The challenge is to
work within the framework of the Bank's strategy for these reforms to become effective.
2.1.2.14 ICT Sector. Inadequate infrastructure is an obstacle to the promotion and
development of innovative ICT applications and services. Niger mainly has only one
wireless network interconnecting seven regions, and two fibre optic links connecting the
country to underwater cables via Benin and Burkina Faso (itself landlocked) to ensure regional
and international connectivity. This inadequacy, coupled with the lack of a back-up direct
access to underwater cables (only via Benin for now) is a serious obstacle to the promotion and
development of innovative ICT applications and services requiring high bandwidth5. The
authorities prioritize ICT development as a remedy to this situation. Accordingly, in a bid to
supplement the national fibre optic backbone, the Government of Niger envisages the inclusion
a national and international connectivity component in the Trans-Sahara Highway (TSH)
Project linking Niger, Chad and Algeria. The project is under appraisal6.
2.1.2.15 The Private Sector and Business Climate. The Private Sector is marked by the
predominance of the informal sector. The growth of the formal private sector is limited
by low competitiveness, small size of the domestic market and limited access to
finance. The modern private sector, whose weight in the economy was estimated at 20% of
GDP in the 1990s, has steadily declined and represented less than 5% of GDP in 2012. It is
dominated by the informal sector, which accounts for about 70%. The formal sector consists of
SMEs/SMIs and its growth remains dependent on the improvement of the business
environment, a sound financial system and the removal of institutional and fiscal
constraints. Activities are highly concentrated in trade and services, to the detriment of more
processing-oriented industrial activities.
2.1.2.16 Business Climate. Niger has not undertaken any major reform in recent years to
improve the business climate. The country saw its ranking in the Doing Business Report drop
sharply from 173rd place in 2012 to 176th in 2013. Despite the measures taken and those being
implemented in 2013, there are still many challenges, related to the time it takes to set up a
business, which is still long and calls for the efficient implementation of land, real estate, tax
and legal reforms. Many consultation and reform frameworks overlap and are found to be
redundant in their missions and objectives. Greater synergy is needed in actions, particularly in
the operationalization of the single window and building the capacity of government
services. The legal framework also needs to be improved. Indeed, the country slipped back three
places compared with the 2012 ranking for this indicator in the Doing Business 2013 Report. An
improvement of the legal framework will usher in a climate of trust. Considering the high cost
5 The situation is such that the international cost of the bandwidth exceeds USD 5000 per megabit per month for these landlocked countries
(Chad, Niger, etc.) whereas the equivalent in volume and duration of the same international capacity in countries with access to submarine
cables is much cheaper. For example, one megabit costs USD 500 and USD 40 per month in South Africa and North Africa (especially
Tunisia) respectively. 6 Niger and Chad submitted a joint application for funding for the Trans-Sahara Backbone (DTS) to the Bank at the end of June 2013, as a
complement to the TSH project. It concerns a regional fiber optic interconnection project between Algeria, Niger, Nigeria and Chad. The
feasibility study of the project (separate from the TSH) will be conducted in 2013 in the context of an ICT investment project under ADF-13 and allow Niger to access additional resources through the Bank’s regional allocation.
6
of factors and the security risk in the Sahel strip, investors should be provided legal protection
to better stimulate the investment needed by Niger to bring about the structural transformation
of its economy. This requires the establishment of genuine commercial courts, among other
measures. The Government is already working on this issue, but Bank support could help to
speed up the process.
2.1.2.17 Financial Sector and Microfinance. The financial sector is relatively sound, but
lacks diversification and depth. Niger’s financial system comprises some ten banks and one
financial institution and, like that of WAEMU countries, remains highly concentrated. Four
major commercial banks owned 90% of the total assets amounting to CFAF 712.6 billion in
2011. The financial system remains relatively sound and was left unscathed by the recent
financial crisis, due to its poor integration into the international financial system as well as the
close supervision of the WAEMU Banking Commission. The depth of the financial sector as
measured by the ratio of broad money to GDP (M2/GDP) is also limited. It stood at 20.5% in
2010 and 20.3% in 2011, below the 41% level recorded in sub-Saharan Africa. Banking
facilities are little used in Niger (...); access to financing is very limited, as is the capacity to
mobilize medium- and long-term financing7. The microfinance system is in deep crisis. In spite
of a rehabilitation programme, it is characterized by weaknesses in governance and the
information system, notwithstanding the positive achievements recorded at end-December
2012. The breakdown of credit to the economy by sector shows that much remains to be done
to enhance financial sector support to the agricultural sector, given the importance of agriculture
for food security8.
2.1.2.18 Procurement System and Use of National Procedures. The evaluation carried out
by the Bank in 2010 concluded that Niger’s public procurement system is largely
consistent with international standards and Bank policy and procedures. This evaluation
recommended that national procedures should be applied for national competitive bidding
(NCB) with respect to Bank-financed operations. The next evaluation, taking the current
progress into account, will assess the performance of the national procurement system and its
robustness, with a view to making a recommendation on the use of national procedures for
international competitive bidding (ICB). To this end, urgent reforms should be initiated to align
the national system with Bank procedures and WAEMU standards (see Annex 7).
2.1.2.19 Regional Integration and Trade. Like most African countries, Niger faces a
number of economic and political challenges that transcend the national context and that
one country alone cannot solve (narrow national markets, inadequate functional
infrastructure, non-interconnection with the national infrastructure networks of
neighbouring countries, lack of commercial competitiveness due to a dysfunctional
infrastructure system, absence of policy and regulatory harmonisation, etc.). These problems
are exacerbated on Niger’s territory since the country does not have a seaboard, for which
reason it is largely dependent on other countries for commercial exchanges (import and
export). To remedy this situation, Niger has joined several multinational organisations
working towards trade promotion and economic integration, the free movement of persons
and goods, and trade facilitation. Thus, the country is a founding member of major sub-
regional West African institutions (Conseil de l’Entente, WAEMU, ECOWAS). It is also an
active member of several continental (CEN-SAD, the African Union, ECOWAS) and
international organisations (WTO, UN). Thanks to its geographic location that places it at
the crossroads of three regional economic communities (ECOWAS, ECCAS, AMU) and its
enormous natural resource reserves, especially uranium, gold, iron and crude oil, Niger will
undoubtedly draw enormous benefits from accelerated regional integration in the West
African zone and the interconnection of West Africa with Central and North Africa. Indeed,
7 The Bank Group supports the development of Niger’s financial sector, and recently granted SONIBANK a line of credit, accompanied by
a FAPA grant to strengthen the capacity of the institution. 8 In the light of this situation, the Government recently established an agricultural development bank, "BAGRI" whose objective is to support
the production and processing of agricultural products. The Bank Group could consider supporting these efforts.
7
it is an established fact that regional integration is a catalyst for trade, investments, economic
growth and job creation. However, given that these benefits are underpinned by the existence
of functional infrastructure, Niger should develop its regional infrastructure network if it is
to take advantage of such benefits and develop its trade potential, including the considerable
trade (so far mostly informal) that it currently maintains with its large Nigerian neighbour.
Based on Vision 2020 and the ECOWAS Regional Infrastructure Programme, the Priority
Action Plan under the Programme for Infrastructure Development in Africa (PAP-PIDA),
the AfDB Regional Integration Strategy Paper (RISP) and the Sahel Initiative being
prepared, the Bank plans to contribute to financing the preparation and implementation of
high-impact transport infrastructure for regional integration and trade, thus opening up
Niger and facilitating the country’s access to the region’s sea ports.
2.1.2.20 Environment and Climate Change. Vulnerability exacerbated by climate change
(CC). The most anticipated climate scenario in Niger would be characterized by warmer and
more variable climate, resulting in unpredictability of the rainy season (onset and duration)9.
This single factor could exacerbate all the challenges already affecting the areas of water
resources, agriculture/livestock, fisheries and forestry. These challenges, in particular, urban
demand for firewood and charcoal, shifting cultivation, slash-and-burn cultivation and
overgrazing, all of which contribute to the worsening of desertification. Similarly, the expected
CC would be likely to increase poverty levels among a population segment that is already
vulnerable to the vagaries of climatic conditions, which compromise their food self-sufficiency
and raise their energy dependence, with consequences in terms of land clearing and
deforestation10. Moreover, the priority given to the exploitation of natural resources, especially
mining and hydrocarbons could escalate the related environmental hazards such as the use of
chemicals in mining (cyanides, etc.).
2.1.2.21 However, the natural environment in Niger is an asset for socioeconomic
activities, especially those carried out by the most impoverished rural populations. Niger’s
natural resources (land, water, soil and biomass) are prone to deep degradation, mainly due to
an imbalance between their exploitation and renewal rates11, coupled with marked climate
variability during the last decades. The major challenge faced mainly concerns natural resource
development and sustainable management. Indeed, agro-forestry and pastoral activities are the
main source of income and employment for nearly 80% of the population in rural areas.
Furthermore, these activities contributed to the country’s economy to the tune of between 45%
and 48% of GDP over the period 2010-2012. Optimal management of natural resources
underpinning the development of the rural sector is needed to boost the people’s resilience to
the adverse effects of climate change. This is important leverage for policy efficiency, in terms
inclusiveness. Otherwise, continuous degradation of the environment could lead to a substantial
decline in incomes earned by the poorest population segments from the supply of environmental
goods and services.
2.1.2.22 The government has adopted mitigation measures to address the adverse effects
of climate change. With regard to climate change resilience, Niger has been admitted to a Pilot
Programme for Climate Resilience (PPCR). This first programme of the Strategic Climate Fund
(SCF) is an instrument designed to reorient development towards low-density forms of carbon
that can withstand the effects of climate change12. To complement these resources, the
Government has established its own fund lodged with the BCEAO, which will be replenished
by proceeds from extractive industries and used to manage climate change-related crises such
as recurrent floods and droughts. This is a good example that should be emulated by other
countries.
9 Second National Communication for Sustainable Development (NCA), 2009 10 National Action Plan for Adaptation to Climate Change (NAPA). NCA, GEF, UNDP, 2006 11 Environmental Profile of Niger - Final Report, AGRIFOR Consult, April 2006. 12 Pilot Programme for Climate Resilience (PPCR - Niger), Joint Mission Fact Sheet, Niamey (28 June - 7 July 2010), IFC, World Bank and
African Development Bank.
8
2.1.3 Social Context
2.1.3.1 Demography. Niger’s rapid population growth is certainly one of the major
challenges that the country must overcome. The provisional findings of the general
population and housing census conducted in 2012 show that Niger has an annual
population growth rate of 3.9%, which is one of the highest in the continent, and comes
with many challenges. This very fast population growth is mainly due to a high fertility rate
of about 7.6 children per woman, resulting from very limited use of contraception methods. The
demographic expansion has been characterized by the rejuvenation of the population. Thus, two
Nigeriens out of three (66%) are less than 25 years old, making Niger one of the countries with
the highest proportion of young people in the world. This is equally true for the dependency
ratio. The job market integration remains a problem, in rural communities as well as in urban
areas where urban drift has become a constant phenomenon. This population dynamic poses
significant challenges in the areas of agriculture, environment, drinking water, health,
education, employment, housing, etc. There is an urgent need to address these challenges
proactively. Indeed, unemployed young people in this part of the Sahel may constitute a
breeding ground for religious or identity threats.
2.1.3.2 Given the link between the high birth rate and the status of women in Niger, there
is no denying the fact that population control – a key Government objective re-stated in the
PDES – will also demand efforts aimed at promoting gender parity. By contributing to
women’s economic advancement, the Bank strategy will also indirectly help Niger to attain
its population-related objectives.
2.1.3.3 Poverty situation and achievement of the MDGs. Progress towards improving the
living conditions of the populations has not yet resulted in a significant reduction in
poverty, and it is unlikely that Niger will achieve the MDGs by 2015. The gross enrolment
ratio (GER) increased from 57.8% to 66.3% between 2008 and 2010 and from 50.6% to 59.7%
for girls. The mortality rate of under-5 children remains high, despite a decline from 156 to 143
deaths per 1000 live births over the same period. Although Niger witnessed an improvement in
its Human Development Index (HDI) over the period 2009-2011, it is lagging, ranking 186th
out of 187 countries in 2011, with an HDI of 0.266. The household electrification rate at end-
2011 was approximately 10%, with a disparity between urban (50%) and rural (1%) areas. In
2013, two years before the expiry of the MDGs deadline, the poverty rate is estimated at 55%,
far from the target of 31.5% by 2015. In light of the poverty threshold of one dollar per day set
by the United Nations, an estimated 60% of Niger's population would be affected. The incidence
of poverty will be 85% if a threshold of two dollars per day is considered.
2.1.3.4 Gender Disparities. Gender disparities persist in education and the labour
market. However, women’s representation in politics is improving. Girls' enrolment in
primary education has doubled since 2000, but the absolute gap between girls and boys is
widening. The disparities are becoming more pronounced in secondary education, where girls
account for only 20% of total enrolment, compared with 50% at the primary level, due to socio-
cultural or religious factors that lead to their early withdrawal from the education system.
On the economic front, women are more active in the agricultural sector, especially in the
production and marketing of agricultural products. Yet, their full participation in these
productive activities is hampered by their limited access to fertile land, several land-tenure
difficulties and access to credit. Consequently, women are the most vulnerable to food
insecurity, especially in the rural area. Contribution to development is uneven between men
and women on the labour market. Women make up 50.1% of the population but only 26% and
21.7%13 of employees in the public and private sectors respectively.
13 Given the Law on Quotas that sets the minimum threshold of 25% for women in public sector senior jobs, the representation of women
will improve.
9
2.1.3.5 To overcome these constraints, the authorities hope that, during implementation of
the 3N Initiative, which the Bank could support within the framework of this strategy, part
of the irrigation schemes should be solely assigned to women’s agricultural cooperatives.
Furthermore, to promote access by agricultural entrepreneurs (including women) to credit,
the Bank could consider the possibility of extending a state-guaranteed line of credit to
Banque Agricole du Niger [Niger Agriculture Bank] (BAGRI). However, it is worth noting
that despite several economic challenges, women’s representation on the political scene has
improved 14.
2.1.4 Medium-Term Prospects
2.1.4.1 The macroeconomic prospects are bright, although subject to various risks.
Investments in the oil and mining sectors, as well as consolidation of the macroeconomic
framework are good omens for robust growth. After a meteoric rise to 13.1 % in 2012,
economic growth is expected to continue on a 5.5% trend from 2013. Exports of crude oil and
refined products will be on the increase. In addition, the new uranium mining project financed
by the French AREVA group would double uranium production between 2012 and 2016,
making Niger the world's second largest producer. Inflation is expected to remain low in 2013.
However, the fragile regional security situation and natural disasters (floods and droughts) are
significant risks that may influence these prospects. The challenge is to translate the growth
into effective poverty reduction.
2.2 Strategic Options
2.2.1 Country Strategic
Framework
2.2.1.1 The 2012-15 PDES is the
only Government reference
framework on development policies
and strategies. Founded on results-
based management principles, the
PDES is centred on five strategic
pillars (see Chart 3 opposite).
2.2.2 Weaknesses and Challenges
2.2.2.1 Reducing the vulnerability
of the economy to climate change
and enhancing food security:
Improving resilience to the impacts of
recurrent climatic shocks remains a
major challenge. In its structure,
Niger’s economy is still dominated by
the primary sector. This sector, which
accounted for over 45% of GDP between 2010 and 2012, determines both the performance and
stability of the macroeconomic framework and thus the populations’ well-being. However, the
primary sector, which employs the vast majority of rural inhabitants, remains heavily subject
to climate change and external shocks. The heavy dependence on rain-fed agriculture leaves
the country vulnerable to recurrent food crises. This vulnerability has increased since 2011,
14 In Government, it rose from 8.7% in 1999-2002 to 14.3% between 2002 and 2004 and more than 20% since then. In Parliament, women’s
representation increased from 1.2% in 1999 to 2004 to 12.4% from 2004 to 2009 and has been rising since then.
Graph 3: Country's Strategic Options
- Strong economic growth in 2012 and
favorable medium-term prospects,
driven by mining and hydrocarbons;
- Macroeconomic management deemed satisfactory by the IMF, but insignificant progress in terms of financial management, according to the 2012 PEFA study;
- Progress still necessary to align the
fiduciary framework with community
provisions;
- Deterioration of debt sustainability
indicators;
- Private sector dominated by informal
activities, a financial sector devoid of
diversification and depth, and an
agricultural sector that is under-
funded despite its weight in the
economy;
- - High population growth with
pressure on the labour market and
social infrastructure, but
characterized by lack of skilled
labour;
- Persistence of gender disparities in education and the labour market, but an improvement in women's representation in politics; and
- Recurrent extreme weather conditions.
- High vulnerability of the
economy to climate
change:
- Lack of basic
infrastructure (transport,
energy, ICT);
- Poor diversification of
the productive system;
- Poor mobilization of
domestic resources;
- A mining sector that
could become the
neucleus of industrial
activities:
- A hydrocarbon potential
(oil and gas); and
- An gro-forestry-pastoral
sector with growth
potential that could be
source of an agro-food
industry.
PDES 2012-15:
Pillar 1: Consolidation of the
credibility and efficiency of
public institutions;
Pillar 2: Creation of
sustainability conditions for
balanced and inclusive growth;
Pillar 3: Food security and
sustainable agricultural
development;
Axe 4 : Promotion of a
competitive and diversified
economy for accelerated and
inclusive growth; and
Axe 5 : Promotion of social
development .
Economic and Social Context Weaknesses and Challenges
Strengths and Opportunities
Country's Strategic Framework
10
following the crises that hit this region, also affecting budget allocations for a number of sectors
as well as migrant remittances15.
2.2.2.2 Inadequate infrastructure is an obstacle to the structural transformation of the
economy. Growth-supporting mainstay infrastructure (energy, transport, communication and
irrigation) is inadequate. This aggravates the country’s isolation, increases the cost of factors
of production, limits trade within the country and regional integration, and thus impedes the
development of a modern, diversified and competitive economy (see Box 2). In the area of
energy, needs are not met16, and this affects industrial activity. Analysis of transport
infrastructure shows: (i) a rapid deterioration of the road network17; (ii) the gradual silting up
of the Niger River, which greatly reduces its navigability; (iii) the dilapidated and poorly
equipped state of the three airports of Niamey, Zinder and Agadez; and (iv) lack of a rail
network.
2.2.2.3 Improving public finances governance and optimizing the mobilization of public
and private resources to finance growth. It appears, from the last PEMFAR for the period
2004-09, that there are still weaknesses in public finance management. These include: (i)
inadequate domestic resource mobilization18; (ii) poor management of public resources and
investment; and (iii) inadequate transparency in budget
execution.
2.2.3 Strengths and Opportunities
2.2.3.1 A mining sector which could become the
nucleus of industrial activities. The Bank will need to
provide assistance through its various financial
instruments and in terms of legal support and/or
financial and environmental governance tools. The
opening of the new mine at Imouraren by 2015 or 2016
will be a major turning point in uranium production in
Niger. This mine will reach its maximum capacity of
5,000 tonnes of uranates annually in 2017 for a 35-year
operating period. The country should thus rank among the
top three uranium producers, second after Kazakhstan. Gold mining, like other mining sectors,
should experience a period of expansion. In addition to uranium and gold, the country should
exploit its coal reserves that are estimated to exceed 80 million tonnes19. Niger also has more
than one billion tonnes of iron ore reserves. Its huge limestone reserves may also lead to the
development of new cement factories. Judicious tapping of the above resources, with various
forms of Bank support, may offer the opportunity to lay the groundwork for a diversified local
industry, create jobs and thus kick-start the structural transformation of Niger’s economy.
2.2.3.2 The same applies to the hydrocarbons sector. Niger’s oil and gas potential relates
to the two major sedimentary basins covering 90% of the territory. This potential is yet to be
confirmed through prospecting works, but available knowledge of Niger’s geological features
shows an array of positive elements. The petroleum cadaster currently consists of 34 blocks,
only four of which are under exploration or exploitation licenses. Of these four, three are held
by CNPC of China and one by SONATRACH of Algeria, and the remaining 30 blocks are open
to investors.
15 According to BCEAO, migrant remittances averaged 0.9% of GDP over the period 2000-2011, with a peak of 1.5% in 2004, 2005 and
2010. 16 In 2011, 3.4% of the estimated power consumption of 701.6 GWh was produced in Niger and the rest (86.6%) imported from Nigeria. 17 The road network is faced with a maintenance problem mainly because of the inadequacy of the resources allocated to the road fund
through the Autonomous Road Maintenance Financing Fund (CAFER). 18 At a level ranging between 13 and 14% of GDP, Niger's tax pressure rate is below the 17% threshold set by the WAEMU) 19 Demand is increasing due to Chinese and Indian energy needs. This is an indirect outcome of the moratorium on nuclear energy decided
in several Western States following the Fukushima disaster.
Box 2: The high factor, costs an impediment to the expansion of the mining sector.
The high cost of factors (energy and transport), the weak managerial capacity of the private sector and the country's landlocked position are major constraints that may impact the conveyance of not only the inputs and equipment, but the production as well.
To remedy this, the Government plans to develop an industrial policy and action plan, including the revision of the Investment Code, the rehabilitation of existing industrial areas and/or the creation of new ones, as well as and the establishment of a fund for the restructuring
and upgrading of enterprises
11
2.2.3.3 The food industry has potential that is yet to be fully tapped. It can become a
lever for growth and a source of economic diversification. The non-extractive industry
remains extremely marginal in Niger’s economy. Focused on food processing, its contribution
to GDP is less than 2%. The high cost of inputs such as electricity severely limits the
competitiveness of industrial products processed in Niger. The inappropriate legal and fiscal
framework contributes to the predominance of the informal sector. If the aforementioned
constraints were removed, the growth-enhancing agro-pastoral sectors identified in the Bank-
funded study of 2004 and in the export support project funded by the World Bank would offer
genuine opportunities for economic diversification.20
2.3 Aid Coordination/Harmonisation and Bank Positioning
2.3.1 Aid Coordination/Harmonisation
2.3.1.1 Official development assistance (ODA) is
coordinated by the Government. To that end, a
Permanent (Interministerial) Secretariat responsible for
implementing the Economic and Social Development
Plan (PDES) has been established. The Secretariat is also
responsible for mobilizing and monitoring resources for
the financing of DPES. To enhance the effectiveness of
the ODA, the authorities intend to continue the efforts
initiated under the Paris Declaration and the Accra
Agenda for Action. As part of the preparation and
monitoring of resource mobilization to finance the
PDES, a State/TFP Committee (OECD/DAC) has been
established. The Secretariat of the Committee, which
brings together all TFP present in Niger, is provided
jointly by UNDP and the World Bank.
2.3.1.2 Although the Bank currently has no field
office in Niger, it spares no effort in coordinating its assistance to the country. There are
regular contacts with all stakeholders. Thus, the Bank effectively plays its lead partner role
in implementing the first phase of the major Kandadji structuring programme. These
coordination efforts were intensified within the context of this strategy. The establishment of
the Bank’s presence in Niger will further contribute to the coordination effort and enhance
dialogue with stakeholders. Complementarity and synergy with other TFPs will also be
consolidated in areas of common interest (see Annex 9).
2.3.2 Bank Positioning
Cooperation between Niger and the Bank is dynamic and the Bank remains a leading
strategic partner (see Box 3). This cooperation will intensify over the next five years in
strategic and structural sectors of the economy (energy, agriculture, infrastructure and economic
governance). In this regard, Bank presence in Niger will be most useful in boosting the
institution's visibility. As part of the implementation of the CSP 2013-17, and to enhance
strategic dialogue with the Government and other donors, as well as ensure better monitoring
of its country portfolio, the Bank is exploring options for greater presence in Niger, within the
framework of its overall presence.
20 Indeed, better structuring of agro-pastoral sectors and valorization of their by-products (milk, meat, hides and skins for handicrafts), as
recommended by the study, may provide economic diversification and job creation opportunities.
Box 3: Cooperation between the Bank and Niger
The African Development Bank Group has been involved in Niger since 1970. To date, the Bank has allocated USD 861.5 million to the country. The Bank portfolio consists of 18 operations (grants and loans), totaling about USD 348.47 million.
The Bank will contribute to the financing of the
PDES and food security programme dubbed “3N
Initiative” to the tune of USD 530 million, thus
becoming the third largest contributor to Niger’s
development.
However, due to the absence of a Bank Office in
Niger, the Bank’s visibility remains very low. A
form of presence should be considered in the
near future, given the major structuring projects
planned for the period 2013-2017, with view to
making the Bank a genuine strategic partner of
Niger.
12
III. COUNTRY PORTFOLIO REVIEW
3.1 Overview of Portfolio
Performance
3.1.1 Portfolio Composition
3.1.1.1 The Bank’s active portfolio in
Niger at end-September 2013
comprised 18 public sector operations
and one private sector operation,
totalling about UA 230.04 million. The
focus areas of public sector operations
(see Chart 4 opposite) are agriculture for
106.5 million (48.7%), water and
sanitation - 33.3 million (15.2 %),
governance - 31.5 million (14.4%),
social sector - 22.5 million (11.6%) and
infrastructure - 22 million (10.1%). The
only private window operation concerns the line of credit of EUR 13 million granted to
SONIBANK, approved in January 2013.
3.1.1.2 This situation reflects the Government's priorities and the Bank's strategic
choices laid out in its country strategy for the period 2005-09 and extended to 2012, whose
two pillars were: (i) Support the development of rural areas through mobilization of water; and
(ii) Promote the reinforcement of infrastructure, including social infrastructure. In terms of
achievements, the Bank's interventions under Pillar 1 have improved agricultural infrastructure
and facilitated access to drinking water and sanitation, while its Pillar 2 initiatives have
contributed to the enhancement of transport infrastructure on the Mali-Chad backbone link, thus
facilitating the conveyance of agricultural produce from irrigated areas to the market.
Concerning the Dori-Tera Project, in addition to the spin-off benefits of the road, local residents
have been provided with health and education infrastructure.
3.1.2 Analysis of portfolio performance indicators
3.1.2.1 Absorption Level. Analysis of Bank portfolio performance during the review
period (April 2013) showed a disbursement rate of about 24%, for an overall average age
of approximately 3 years. The overall disbursement rate stood as follows: infrastructure
(68%), water and sanitation (28.68%), agriculture (13%), social (1%) and governance (0%).
The low rate of disbursement is partly due to the fact that seven operations approved less than
a year ago were still to be implemented (four in agriculture, two in governance and one in the
social sector). The recent establishment of the portfolio only partly explains the
underperformance observed. Indeed, there are also operations aged above two years for which
there has been no disbursement (water and sanitation and social sectors), and other operations
aged about five years with disbursement rates of around 15%. At end-September 2013, the
overall disbursement level stood at 27.46%, with the levels for the various sectors as follows:
infrastructure (77%), water and sanitation (29.46%), agriculture (18.58%), social (6.47%) and
governance (37%). As of end November 2013, the disbursement rate improved slightly to 31%,
compared with 24% in April of the same year during the portfolio review.
3.1.2.2 The low rate of disbursement for Bank projects in Niger is mainly due to the
following two factors: (i) long implementation periods (10 months on average); and (ii) long
periods taken in setting up project Management teams (about 1 year after approval). These two
factors combined inevitably delay the actual start-up of the project by a minimum period of
about two years.
Infrastructure
10,1%
Agriculture
48,7%
Water and
Sanitation
15.2%
Social 11,6%
Governance
14.4%
Graph 4: Distribution of AfDB Portfolio in Niger by
Sector
13
3.1.2.3 Project Age. The active portfolio currently contains no project aged more than
8 years. However, only one project (the Tibiri-Dakoro-Madaoua-Tahoua Road) will be eight
years old in December 201321. After three extensions, totalling 32 additional months, from a
normal project implementation period of 30 months, the project, which should have been
completed in September 2013, has a disbursement rate of 68%.
3.1.2.4 Projects at risk. At the time of the review, the portfolio had only three projects
at risk, or 27% overall, representing virtual stagnation, compared with 2010 when the
percentage of projects at risk stood at 26%, but an improvement over the 40% rate for 2008.
The review noted, however, that two of the three projects considered at risk could become
problem projects, given the obstacles hindering their implementation. These projects were the
Kandadji Programme and the Tibiri-Dakoro-Madaoua-Tahoua Road Project. In July 2013, the
Kandadji Programme did become a problem project (see Annex 10) following the suspension
of implementation. The Tibiri-Dakoro-Madaoua-Tahoua road was also closed end
September. This brings the number of risk projects to 2 (i.e. 18%).
3.1.2.5 Delays in fulfilling the effectiveness and start-up conditions. The 2013
review noted that the average project effectiveness timeframe (grants and loans) in Niger
is about 10 months, compared with the standard three months. Currently, four operations
approved over seven months ago are still not yet effective (two operations under the Water
Resource Mobilization and Development Project - PROMOVARE - and two under the Pilot
Programme for Climate Resilience - PPRC). Moreover, for projects in Niger, it takes one year
on average to put together a full implementation team, which delays the actual start-up of
project activities by an average of one and a half years to two years.
3.1.2.6 Cancellable Operations. At the time of the review, four projects were about to
be cancelled. These cancellations were due to two reasons: prolonged non-disbursement
periods and project completion. The first case concerns the resources of the loan component for
the Vocational and Technical Education Development Support Project approved in 2011,
amounting to UA 7.87 million, from which no disbursements have been made, and the Rural
Water Supply and Sanitation Project - Phase II, for which an RWSSI grant amounting to UA
3,300,956.45 was approved in 2011. The Bank will cancel the balances of two completed
operations (Tibiri - Dakoro Road, Invasive Aquatic Weeds) by end December 2013.
3.1.2.7 Audits and financial managements/disbursements . Audit report preparation
delays. It is worth noting that only two projects out of eight, or 25%, submitted timely audit
reports that were validated. The rest of the projects (75%), including one on-going project22 and
five projects23 completed several years ago are not up to date with audit report submission. This
situation could adversely impact the country portfolio performance. The authorities are
committed to taking appropriate remedial action. The audit report production status has
improved since the review and the establishment of a monitoring mechanism at the Ministry
of Planning. Out of 9 reports due, 7 have been produced, of which 4 validated, 3 not yet
validated and 2 not yet submitted. These efforts must be pursued.
3.1.2.8 Delays in justification of special accounts advances. Regarding disbursements, in
addition to the slow pace of replenishment of the revolving fund, there is an irregularity in the
justification of special account advances.
21 21 It should be noted that this project has faced obstacles; firstly during the first year from 2010 to 2011, in the Tibiri-Dakoro section. Then from January 2013,
along the Madaoua-Tahoua sections due to endorsements by the control mission exceeding the required threshold. 22 This refers to the RWSS project in three regions. 23 This refers to the Zinder Agricultural Development Project (2009 and 2010 reports), the Tahoua and Tillabéry Health Care Improvement Project (2009 and
2010 reports), the Gender Equity Strengthening Project (2010 report), the Decentralization Support Project (2010 report) and Emergency Humanitarian
Assistance to Drought Victims (2011 report).
14
3.2 Key Lessons from the Portfolio Review
3.2.1 Reminder concerning the 2010 Review and implementation of
recommendations. The 2010 review identified problems affecting portfolio performance
and adopted an improvement action plan. The problems identified in 2010 included: (i) delay
in putting together the project teams; (ii) inadequacy or poor quality of project baseline studies;
(iii) delay in the payment of counterpart funds; (iv) lapses in state structures' support to
programme; and (v) poor management of project extensions and completion. The portfolio
review noted the inadequate implementation of the 2010 Action Plan, partly for lack of an
effective portfolio performance monitoring mechanism (fulfilment of effectiveness conditions,
timely setting up of management teams, close monitoring of projects in difficulty, control of
the submission and quality of audit reports, urgent measures to be implemented in respect of
projects at risk, formal framework for the holding of periodic meetings to monitor the
implementation of review recommendations, etc.). However, the lessons from problems
encountered in the implementation of previous support programmes led to an improvement in
design support programmes, particularly in terms of institutional arrangement and human
resources.
3.2.2 Outcomes of the 2013 Review and analysis of the challenges and
constraints. The Action Plan of the 2010 Review was poorly implemented. The problems
identified remain and are negatively affecting the performance of projects in Niger. The
problems may be summed up as follows: (i) delay in putting together the project management
teams; (ii) poor quality of baseline studies; (iii) late payment of counterpart funds; (iv) non-
compliance with the established audit reporting timeframe and poor quality of reports; and (v)
lack of a portfolio monitoring mechanism. Recommendations to address these weaknesses were
agreed on with the authorities and are included in the portfolio improvement action plan set out
in Annex 5.
3.2.3 Projects requiring special monitoring. Two projects in the portfolio require
special attention because of the delays they have experienced and their importance in the
PDES implementation and the achievement of the Programme's objectives. These are, firstly,
the Kandadji Programme - Phase I (construction of the dam and development of irrigated areas),
along with Phase II of the Programme (establishment of the hydroelectric plant). Secondly, the
Tibiri-Dakoro Road Project, which has already received three extensions and was supposed to
have ended in September 2013, whereas three major structures (bridges) are still uncompleted.
The Bank decided end November 2013 to close the project. However, the Government
obtained West African Development Bank financing to complete the remaining works.
3.2.4 Next stages and monitoring mechanisms. Strengthening portfolio monitoring
and management mechanisms. Despite the overall portfolio performance score of 2.36 in
2013 (based on highly optimistic scores awarded sometimes by project officers), compared
with 2.25 in 2010, which is deemed satisfactory, it is noted that project implementation in Niger
continues to pose enormous challenges. The observations made jointly with Niger’s authorities
during the review highlighted the need for the Government to give greater attention to portfolio
issues. In this context it was agreed that the authorities establish a portfolio management
monitoring mechanism as soon as possible.
3.2.5 In line with the portfolio review recommendations, the Government appointed a
focal point in the Ministry of Planning in May 2013. The focal point is charged with: (i)
monitoring the coordination of Bank projects; (ii) monitoring the implementation of
recommendations and fulfilment of project conditions, the preparation of audit reports and
the justification of rolling funds; (iii) ensuring the mobilisation of the counterpart
contribution for project implementation; and (iv) holding periodic meetings (quarterly) to
assess the status of implementation of review recommendations. For its part, the Bank will,
during the first quarter of 2014, engage discussions with the Nigerien party to explore the
15
possibility of restructuring the portfolio, with a view to refocusing it on fewer operations,
taking into consideration the country’s capacity, realities and current priorities. The Bank’s
presence in Niger is the subject of a study within the overall presence framework. Such
presence would help to facilitate portfolio monitoring, while also giving more visibility to the
Bank’s action and facilitating coordination with the significant partner in the country.
IV. 2005-09 STRATEGY AND KEY LESSONS
4.1 Implementation of the 2005-09 Country Strategy, extended to 2012. The
preparation of this strategy was preceded by an evaluation of the previous one (2005-2009,
extended to 2012). Instead of issuing a separate report, the outcomes of that evaluation are
presented in this report.
4.1.1 Expected Outcomes. The 2005-09 RBCSP, extended to 2012, had two pillars: (i)
Rural development through water resource mobilization; and (ii) Infrastructure
development, including social infrastructure. Using a cross-cutting approach, the focus
has been on strengthening governance. Five outcomes were expected under the two major
pillars. Those envisaged under Pillar 1 are threefold: (i) increase agricultural production by
expanding irrigated areas; (ii) introduce decentralization; and (iii) improve the drinking water
supply of rural households. Under the second pillar, two outcomes were targeted: (i) strengthen
road infrastructure to aid the evacuation of agricultural and pastoral surpluses; and (ii)
increase access to quality technical education and vocational training. Under the governance
theme, there were three objectives: (i) finance budget deficits; (ii) consolidate the economic
and sector reform programme; and (iii) strengthen institutional capacity.
4.1.2 Outcomes obtained. Discussions with the Government and other stakeholders
(private sector and civil society) indicate that, at the strategic level, the two pillars of the 2005-
09 RBCSP extended to 2012 and the governance strengthening programme were well aligned
with the country's priorities. The consensus is that Bank strategy in Niger has effectively
responded to the Government’s concerns and efforts towards achieving some MDGs. The
implementation of the two pillars and the interventions of the State and other technical and
financial partners have helped to improve the living conditions of households in some parts of
the country.
4.1.3 Under the first pillar, the support provided by the Bank, in collaboration with other
development partners, has improved agricultural infrastructure, strengthened the
decentralization process and facilitated access to drinking water and sanitation. Under the
second pillar, the Bank’s intervention has strengthened transport infrastructure on the (Mali-
Chad) backbone road link, thereby also improving market access for agricultural products from
irrigated areas. In this regard, the road linking Dori to Tera on the Burkina Faso border is a
flagship project that has benefited all residents of the area, especially in terms of related
improved health infrastructure. The Bank also contributed to the improvement of health and
education facilities with positive impacts on human resource capacity building. Bank-funded
budget support (SAP-V) has helped to strengthen macroeconomic stability and speed up the
pace of economic reforms. The on-going implementation of PAMOGEF and PACIRSA,
respectively institutional support and budget support programmes adopted in 2012, will
enhance the capacity of government services and consolidate financial and sector-based reforms
related to the 3N Initiative.
16
4.2 Key Lessons
4.2.1 The completion report of CSP 2005-09, extended to 2012, the main conclusions and
recommendations of which were validated with the government and other stakeholders,
highlights the following recommendations aimed at improving future Bank operations in Niger
at both operational and strategic levels:
To the Bank Group
Strengthen strategic and operational dialogue with the Government, private
sector, civil society and technical and financial partners. Bank representation in
Niger, at least by a Country Economist or even a Programme Officer, is
necessary to ensure the quality of the country dialogue. In addition, the Bank's
strategic support for sector-based reforms, economic and financial governance,
and for the implementation of major projects in the areas of infrastructure, food
security and resilience to climate change is important for the structural
transformation of Niger’s economy. The effectiveness of this support is requires
constant and close interaction with stakeholders.
Conduct quality preliminary studies to ensure proper project design and
implementation. The implementation of both projects suffered from weaknesses
in the study phase, which resulted in the proposal of questionable or even
controversial project sites (Kandadji population displacement site).
Underestimation of the costs of certain project components and the
implementation of activities deemed irrelevant (decentralization support) were
also noted.
Develop major multi-phased structuring programmes/projects and support
efforts to foster resilience to the recurrent impacts of climate change.
Better appreciate the capacity building needs of entities selected to implement
projects/programmes at the preparatory stage and during the project cycle.
Programme support by State entities was the cause of delays in project
implementation in certain cases (DWSS, decentralization, equity and gender
support) due to the unavailability in these entities, in sufficient numbers and
quality, of key qualified staff required for implementing programmes in
accordance with Bank rules and procedures.
To the Government
Use of national procedures. It is recommended and agreed that national
procedures be applied to national competitive bidding (NCB) for Bank-financed
operations. Moreover, in preparation for a future appraisal of the national
procurement system to determine whether its robustness is such as to warrant the
use of national procedures for international competitive bidding, it is
recommended that the agreed reforms be implemented expeditiously.
Strengthen the process of ownership and internalization of projects by including
them in the national development process. Accordingly, it would be advisable,
in formulating the institutional and technical framework of projects, to pay
special attention to recurrent costs coverage and the financing of equipment
likely to impact on the viability and continuity of the service provided by the
project.
Pay greater attention to the selection of contractors for the implementation of
major structuring projects.
17
V. 2013-17 BANK COUNTRY STRATEGY IN NIGER
5.1 Rationale for Bank Involvement and Pillars
5.1.1 Rationale for Bank involvement: As indicated earlier in this strategy, Niger is part of
the Sahel region where efforts to promote inclusive and green growth are facing specific
structural challenges which are more daunting here than elsewhere, stemming from a
combination of factors related to the environment, climate change, lack of human capital, and
high levels of poverty. These factors highlight the extreme vulnerability to food insecurity,
which therefore makes resilience to this vulnerability a specific objective of Niger’s
stakeholders. The PDES has sized up this challenge and made it its third strategic pillar.
Moreover, while the recent and future context marked by a larger-scale exploitation of mineral
and oil resources affords the country access to the resources required to finance economic
growth, the situation will also call for greater focus on governance to ensure that the country
participates fully in the exploitation of these underground resources and that the national
income derived from these resources actually contributes to the financing of priority
development projects.
5.1.2 Strategic Pillars. The landscape of international aid to Niger, characterized by the
effective involvement of the United Nations, regional actors and the international community
in the quest for greater regional stability, offers the Bank an opportunity to focus on such
structural issues as agricultural development and food security, resilience to climate change and
governance. Therefore, the Bank's strategy for promoting inclusive and green growth in Niger
over the period 2013-2017 will be based on two pillars: (i) strengthening resilience to food
insecurity and (ii) strengthening governance, particularly of natural resources. Besides
contributing to PDES objectives, these strategic choices also take into account the Bank’s
experience in the countries where it is already involved in these issues, opportunities for
synergies with other stakeholders, the Bank’s Ten-Year Strategy for 2013-2022, and the
regional integration strategy.
Pillar 1: Strengthening resilience to food insecurity
5.1.3 To enhance resilience to food insecurity, efforts will need to be made, not only to
create and develop productive capacities in the agricultural field, but also to increase market
access capacities. Achieving these two objectives calls, above all, for the continuation of efforts
to develop basic infrastructure capable of contributing to their furtherance, especially in the
areas of water harnessing and management, transport (to facilitate access to national and
regional markets), and energy. The Bank’s experience in Niger shows that it can remain fully
engaged in these strategic infrastructure sectors, given its ability to mobilize other players,
especially for the implementation of major projects. As a matter of fact, the Bank is, for
instance, the leader of a group of donors supporting the implementation of the first phase - or
the agricultural component - of the major Kandadji Programme. In addition, the Government
of Niger and the Heads of State of member countries of the Rail Loop Project (Projet de la
Boucle ferroviaire) - Côte d'Ivoire, Burkina Faso, Niger and Benin requested the Bank to
assume a leadership role in that project involving other technical and financial partners, as well
as partners from the private sector.
5.1.4 Furthermore, since Nigerien women are the lead actors in the agricultural chain
(albeit constituting the most vulnerable segment of the population in terms of food
insecurity), the Bank’s support under this pillar will contribute directly to improving their
status and promoting gender.
18
Pillar 2: Strengthening governance, particularly of natural resources
5.1.5 Niger needs to strengthen its governance frameworks in order to derive full benefit
from its natural resources, ensure sustainable exploitation of these resources, promote and
maintain macroeconomic stability and create a favourable climate for private investment. These
factors are indispensable for the robust, inclusive and green growth for which the country is
striving. The Bank will therefore continue its support, through various instruments, including
the faster-disbursing operations, institutional support, the African Legal Support Facility, and
knowledge products, to enable Niger to make progress in these areas.
Cross-cutting issues: strengthen resilience to climatic hazards, ensure the
transition to a green economy and contribute to the Knowledge Bank
5.1.6 The objective will also be to mainstream into Bank operations measures
contributing to such important cross-cutting themes as environmental resilience to
climate change, promotion of the green economy and youth employment. In these areas,
the Bank will also intervene through capacity building and skill development programmes, as
well as economic and sector-based studies (see Annex 6).
5.1.7 Resources available for strategy implementation
The strategy is financed from ADF-12 resources for 2013 and those of ADF-13 and ADF-
14 for 2017. The allocation available under ADF-12 amounts to UA 54.49 million. Assuming
that the ADF-13 and ADF-14 resources will match those of ADF-12, and that the sustainable
lending level (SLL) will remain the same as for ADF-12, public and private window resources
available for the strategy, excluding regional allocations24, could total UA 247.01 million for
the period 2013-17. In addition, regional allocations and private window resources will serve
as a catalyst for mobilizing additional financing. Public-private partnerships (PPP), co-
financing or guarantee mechanisms and the resources of fiduciary funds or facilities will also
help to fund the strategy.25 Moreover, the NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF) has budgeted USD 2 000 000 under its 2013-2015 financing programme for
additional studies and PPP structuring dedicated to the construction of the Côte d’Ivoire-
Burkina-Faso-Niger-Benin rail loop, as well as USD 3 000 000 (through the ECOWAS
Smart Transport Corridor Programme) for studies on the missing links along the Niamey -
Dakar ECOWAS trans-sahelian road corridor and the Niger Border - Lagos link.
5.2 Outcomes and Targets
5.2.1 To achieve the objectives discussed above, the Bank's strategy will aim to deliver
the following outcomes:
Pillar 1 (Outcome 1). Strengthening the basic infrastructure for the development
of agricultural supply: On the strength of its experience in the country, the Bank
will continue its support to the Government for the development of agricultural
and energy potential in the Kandadji region. To that end, it will support the
development of water-harnessing infrastructure as part of the first phase of the
Kandadji Programme. The Bank will also provide specific support towards the
implementation of the 3N Initiative (a national food security initiative in which
the authorities have given an important place to women). Moreover, given the
crucial role of energy in the development of agricultural potential and resilience
to food insecurity, the Bank will participate in the development of the country’s
energy potential under the second phase of the Kandadji Programme (see Annex
6). Despite the challenges facing the first phase of this operation, the Bank and
24 Regional budget resources are allocated in accordance with the regional operations selection and prioritization framework. 25 The Green Fund, the Migration and Development Fund, the African Water Facility (AWF), the Legal Support Facility (LSF), the Sahel
Resilience Programme (SRP).
19
stakeholders remain committed to this important programme and will draw
lessons from the experience to move the programme forward.
Pillar 1 (Outcome 2). Increasing market access to boost resilience to food
insecurity. The Bank will also contribute to the development of infrastructure to
improve market access. Indeed, such infrastructure will not only promote access
to food, but also stimulate agricultural supply by creating sustainable demand.
In this context, the Bank will support the infrastructure connecting regions with
high economic potential in Niger with markets within the country, and with the
sub-regional economic area, such as the Trans-Sahara Highway (TSH) linking
Chad, Niger and Algeria, and the development of the related regional optical
fibre network as part of the trans-Saharan backbone to contribute to
improving the market information system. The Bank’s action will also focus
on: (i) implementation of the above-mentioned Rail Loop; (ii) facilitation of
intercommunity exchange (integrated management of border control posts);
and (iii) development of the missing links along the West African trans-
Sahelian road (Niamey – Dakar and Niger Border – Lagos links).
Pillar 2 (Outcome 1). Strengthening economic and financial governance:
Through this support, the Bank will assist the implementation of the Public
Financial Management Reform Programme (PRGFP 2011-14). The focus will
primarily be on supporting Niger in the process of implementing WAEMU
guidelines. Indeed, beyond the gains of transposing community instruments into
Niger’s legislation, the establishment of an effective operating system
compatible with those instruments remains a fundamental challenge. The Bank’s
support will also be aimed at assisting Niger in its efforts to improve domestic
resource mobilization by supporting the tax and customs reforms necessary for
this purpose. In an effort to enhance transparency in public resource
management, the Bank will support capacity building for entities in charge of
procurement and assist in the decentralization of DGPCOR. Special attention
will be given to the reforms envisaged by Niger for streamlining the existing
oversight and anti-corruption framework, as well as the strengthening of the
analysis and advocacy capacities of Parliament and civil society. The Bank will
also support reforms aimed at improving the business climate and putting in
place an investment-friendly institutional and legal framework, including an
enabling framework for public-private partnerships (PPP). Furthermore, to
reduce persisting gender disparities, the Bank will support Niger in preparing
and implementing a national gender promotion strategy. In this regard, the
integration of the gender dimension during the preparation of sector MTEFs
must be systematized with a view to the gradual introduction of gender-
sensitive budgeting.
Pillar 2 (Outcome 2). Strengthening sector governance and supporting
economic diversification: Bank support will contribute to the development and
implementation of sector-based plans for improving governance and
strengthening technical and human capacities both at the central and
decentralized levels. In view of the rural sector development challenges facing
Niger and the importance of the extractive sector in the economy, special
emphasis will be placed on actions aimed at building capacity and improving
governance in the agro-sylvo-pastoral sector with a view to supporting the
implementation of the 3N Initiative, on the one hand, and on strengthening
transparency in the extractive industries by supporting the Extractive Industries
Transparency Initiative (EITI), on the other hand. The Bank will also support
studies for the establishment of a national capacity building programme in Niger
20
and the introduction of new training courses tailored to the needs of the economy
in general and the 3N Initiative, in particular. To support the diversification of
the economy, the Bank will back Government effort to introduce reforms aimed
at boosting revenue mobilization in extractive sectors and ensuring the optimal
use of such revenue in structuring investments, particularly in the energy and
transport sectors. The Bank will support Niger’s private sector by making lines
of credit available to banks
5.3 Strategy Implementation Instruments
The Bank will use its sovereign and non-sovereign operational tools to support the CSP
implementation. General budget, or even sector-based, support will be used to underpin the
economic and financial sector reforms. Special emphasis will be placed on mobilizing co-
financing and other non-sovereign instruments. The Partial Credit Guarantee (PCG)26,
which will be provided under ADF-13, will also play a central role in mobilizing private
investment flows into the country and the sectors deemed very risky. To contribute more to
the objectives of this strategy while supporting private sector development, the Bank will
consider the possibility of granting a line of credit to Banque Agricole du Niger [Niger
Agriculture Bank] (BAGRI).
5.4 Monitoring/Evaluation
Monitoring and evaluation of the implementation of the strategy will be based on a system that
operates at three levels: first, at the level of the PDES. Since the objectives, projects and programmes
supported by the strategy are aligned with the PDES, the reports prepared by PDES monitoring
mechanisms, which consist of (i) the PDES Guidance Board; (ii) the PDES National Strategic Planning
Commission (CNPS/PDES); (iii) the of PDES Implementation Standing Secretariat (SP/PDES); (iv) the
National Technical Committee (CTN); (v) Sector Committees (CS), and (vi) the OECD/DAC
Committee, will provide the basic material that the Bank will use to monitor the PDES and CSP
implementation. Secondly, a matrix of strategy outcomes, attached in Annex 11, will also enable the
Bank to monitor and evaluate the implementation of this strategy. Lastly, each project will also include
a logical framework aimed at achieving the objectives of this strategy. These project logical
frameworks will also include indicators to measure progress on gender issues. To implement
this monitoring mechanism, the Bank plans to strengthen its presence in Niger, as part of the
comprehensive approach, in order to better monitor the CSP implementation. A mid-term review of the
strategy will be conducted in 2015. The half-yearly portfolio reviews will contribute to the operational
monitoring of the strategy implementation.
5.5 Issues Covered by Country Dialogue
Dialogue with the country for CSP implementation will focus on five themes: (i)
mobilization of water resources for irrigated agriculture and food security; (ii) economic
diversification and youth employment through increased value chains of the agro-forestry-
pastoral sector; (iii) governance of extractive resources, public finance and improvement of
the business climate; (iv) country portfolio management; and (v) gender promotion.
5.6 Potential Risks and Mitigation Measures
5.6.1 There are four major internal and external risks associated with the Bank’s strategy.
Internally, these comprise: (i) a breakdown in political consensus within the ruling coalition and,
consequently, failure to stay the course of political and institutional reforms; and (ii) weak project
implementation capacity. Externally, the risks relate to: (i) the collateral effects of regional political
and security crises; and (ii) exogenous shocks affecting the economic, climate or food sectors. These
risks will be mitigated by Government efforts and support from partners.
26 The GPC will be used to partially guarantee the debt service of the country and eligible public enterprises and help to extend debt maturities,
improve access to capital markets for public sector investment projects, particularly in the area of infrastructure, as well as to effectively reduce borrowing costs, and mobilize resources to support long-term international and domestic capital markets.
21
5.6.2 To cope with these internal and external risks, mitigation measures have been
taken. Internally, the ruling coalition is working to strengthen political consensus through
closer dialogue with the opposition on major decisions. The democratic institutions provided
for by the Constitution are being gradually established. Externally, it is worth noting that the
authorities are involved in the ECOWAS efforts to find a lasting solution to the crisis in Mali.
Strengthening the management of public finances, the natural resource management
framework, and the decision adopted under the PDES to plough back revenue from extractive
sectors into mainstay infrastructure, especially in agricultural irrigation and social sectors, will
help mitigate the aforementioned risks. The same is true of investments under the 3N Initiative
which should ensure food and nutrition security and limit the adverse impacts of climate change
which may exacerbate the populations.
VI. CONCLUSION AND RECOMMENDATION
6.1 Conclusion
6.1.1 Since the return to constitutional order in 2011, the socio-political situation has
improved substantially despite the political crisis in some neighbouring countries and regional
security threats, particularly in the Sahel strip. The medium-term prospects are promising,
driven by the rebound in extractive activities (mining and oil) with a growth path of 5.5% from
2013. The adoption of the 2012-15 PDES marks a return to a medium- and long-term planning
system. The strategy proposed by the Bank for the period 2013-17 is consistent with the PDES
and the guidelines of the Bank’s Ten-Year Strategy for the period 2013-22. The strategy takes
into account the major needs of the country in terms of resilience to food insecurity, in view of
climate change, and the need to open up the country both internally and externally. It also takes
account of the reforms that should be initiated concerning the business environment, as well as
economic, financial, sector-based and institutional governance. It highlights the need to
enhance natural resource governance as a stepping stone to achieve a more inclusive growth for
a nation whose population growth rate is one of the highest of the African continent. The
strategy focuses on a selective approach, based on national and regional operations that could
leverage funding by other partners and maximize the impacts.
6.2 Recommendation
6.2.1 The Boards of Directors are requested to consider and approve the Bank’s
Country Strategy in Niger for the period 2013-17, proposed in this paper.
Annex 2 Page 1/1
Indicators Unit 2000 2008 2009 2010 2011 2012 2013 (e)
National Accounts
GNI at Current Prices Million US $ 1 966 4 769 5 091 5 584 5 785 ... ...
GNI per Capita US$ 180 330 340 360 360 ... ...
GDP at Current Prices Million US $ 1 672 5 397 5 373 5 665 6 355 6 661 7 466
GDP at 2000 Constant prices Million US $ 1 672 2 582 2 564 2 774 2 832 3 203 3 379
Real GDP Growth Rate % -2,6 9,6 -0,7 8,2 2,1 13,1 5,5
Real per Capita GDP Growth Rate % -5,8 5,8 -4,1 4,5 -1,4 9,2 1,9
Gross Domestic Investment % GDP 13,9 32,1 33,2 35,9 32,1 33,3 33,9
Public Investment % GDP 4,3 6,7 5,1 -0,4 2,4 3,8 4,3
Private Investment % GDP 9,6 25,4 28,1 36,3 29,7 29,5 29,6
Gross National Savings % GDP 5,7 19,3 7,9 17,7 10,9 15,1 14,7
Prices and Money
Inflation (CPI) % 2,9 11,3 1,1 0,9 2,9 3,9 1,8
Exchange Rate (Annual Average) local currency/US$ 712,0 447,8 472,2 495,3 471,9 510,5 ...
Monetary Growth (M2) % 12,4 11,9 18,7 21,6 6,0 ... ...
Money and Quasi Money as % of GDP % 8,7 16,5 18,6 20,5 20,3 ... ...
Government Finance
Total Revenue and Grants % GDP 14,2 25,0 18,7 18,4 18,8 21,4 21,9
Total Expenditure and Net Lending % GDP 18,0 23,6 24,1 20,8 25,6 24,1 23,9
Overall Deficit (-) / Surplus (+) % GDP -3,8 1,4 -5,3 -2,4 -6,8 -2,8 -2,0
External Sector
Exports Volume Growth (Goods) % 27,4 6,3 13,6 0,0 9,6 29,0 13,7
Imports Volume Growth (Goods) % 6,7 40,2 35,3 -10,5 12,6 25,0 -5,0
Terms of Trade Growth % -17,7 22,5 -1,8 -5,6 0,2 4,6 -15,4
Current Account Balance Million US $ -111 -699 -1 080 -1 133 -1 445 -1 509 -1 607
Current Account Balance % GDP -6,7 -13,0 -20,1 -20,0 -22,7 -22,7 -21,5
External Reserves months of imports 2,1 4,3 3,1 3,0 2,5 3,0 ...
Debt and Financial Flows
Debt Service % exports 73,4 1,8 1,7 1,3 3,5 1,4 2,2
External Debt % GDP 88,8 14,0 19,7 16,8 15,8 20,1 22,0
Net Total Financial Flows Million US $ 184 581 473 680 600 ... ...
Net Official Development Assistance Million US $ 209 612 469 745 649 ... ...
Net Foreign Direct Investment Million US $ 8 340 791 940 1 014 ... ...
Source : AfDB Statistics Department; IMF: World Economic Outlook, October 2012 and International Financial Statistics, October 2012;
AfDB Statistics Department: Development Data Portal Database, March 2013. United Nations: OECD, Reporting System Division.
Notes: … Data Not Available ( e ) Estimations Last Update: May 2013
NigerSelected Macroeconomic Indicators
-4,0
-2,0
0,0
2,0
4,0
6,0
8,0
10,0
12,0
14,0
200
0
200
1
200
2
200
3
200
4
200
5
200
6
200
7
200
8
200
9
201
0
201
1
201
2
201
3
%
Real GDP Growth Rate, 2000-2013
-4
-2
0
2
4
6
8
10
12
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
Inflation (CPI),
2000-2013
-25,0
-20,0
-15,0
-10,0
-5,0
0,0
2 000
2 001
2 002
2 003
2 004
2 005
2 006
2 007
2 008
2 009
2 010
2 011
2 012
2 013
Current Account Balance as % of GDP,
2000-2013
Annex 3 Page 1/1
Year Niger Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2011 1 267 30 323 98 458 35 811Total Population (millions) 2012 16,6 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 17,4 40,8 46,0 75,7Population Density (per Km²) 2012 12,7 34,5 70,0 23,4GNI per Capita (US $) 2011 360 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 32,0 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 31,2 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,308 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 186 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2011 43,6 40,0 22,4 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2012 3,5 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 4,4 3,4 2,3 0,7Population < 15 y ears (%) 2012 48,9 40,0 28,5 16,6Population >= 65 y ears (%) 2012 2,3 3,6 6,0 16,5Dependency Ratio (%) 2012 104,8 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 101,3 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 21,6 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 55,1 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 55,6 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 47,9 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 12,3 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 86,5 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 145,1 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 7,0 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 590,0 417,8 230,0 13,7Women Using Contraception (%) 2012 13,7 31,6 62,4 71,4
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2004-2010 1,9 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 13,7 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2006-2010 17,7 53,7 65,4 ...Access to Safe Water (% of Population) 2010 49,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 30,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 9,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 0,8 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 108,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 61,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 76,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2006-2011 39,9 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 489 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 5,2 5,9 2,9 8,2
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2010-2012 70,8 101,9 103,1 106,6 Primary School - Female 2010-2012 64,3 98,4 105,1 102,8 Secondary School - Total 2010-2012 14,4 42,3 66,3 101,5 Secondary School - Female 2010-2012 11,3 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 45,2 43,2 58,6 80,0Adult literacy Rate - Total (%) 2005-2010 28,7 67,0 80,8 98,3Adult literacy Rate - Male (%) 2005-2010 42,9 75,8 86,4 98,7Adult literacy Rate - Female (%) 2005-2010 15,1 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 4,5 5,3 3,9 5,2
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2011 11,8 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 3,7 0,6 0,4 -0,2Forest (As % of Land Area) 2011 0,9 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,1 1,2 3,1 11,4
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available.
COMPARATIVE SOCIO-ECONOMIC INDICATORS
May 2013
0
20
40
60
80
100
120
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Infant Mortality Rate( Per 1000 )
Niger Africa
0
200
400
600
800
1000
1200
1400
1600
1800
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
GNI Per Capita US $
Niger Africa
0,0
0,5
1,0
1,5
2,0
2,5
3,0
3,5
4,0
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Population Growth Rate (%)
Niger Africa
1
11
21
31
41
51
61
71
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
Life Expectancy at Birth (years)
Niger Africa
Annex 4 Page 1/1
Bank Portfolio in Niger at end-September 2013 (Amount in UA)
Project Approval
Date
Completion
Date
Loan/Grant
Amount
Disburse
ment
Rate
Implemen
tation
Progress
Develop
ment
Objectiv
e
Risk Status
Tibiri-Dakoro and Madaoua
Bouza Roads Project
19/12/2005 30/09/2013 22,000,000.00 77.00 2.14 2.75 NON PP/PPP
Sub-Total Infrastructure - OITC
(10.1%)
22,000,000.00 77.00
Niger- PPCR Pilot Programme 24/09/2012 01/06/2014 6,170,353.72 0.00 0,00 0.00 NO
SUPERVISION
Niger- PPCR Pilot Programme 24/09/2012 01/06/2014 2,272,288,21 0.00 0.00 0.00 NO
SUPERVISION
PPCR-Niger PROMOVARE
Project
25/09/2012 31/12/2018 8,118,886.48 0.00 0.00 0.00 NO
SUPERVISION
PPCR-Niger PROMOVARE
Project
25/09/2012 31/12/2018 6,170,353.72 0.00 0.00 0.00 NO
SUPERVISION
Mobilization Project in Maradi,
Tahoua and Zinder
20/09/2011 31/12/2016 9,340,000.00 6.66 2.86 3.00 NON PP/PPP
Mobilization Project in Maradi,
Tahoua and Zinder
20/09/2011 31/12/2016 21,433,860.30 0.68 2.86 3.00 NON PP/PPP
Water Mobilization Project in the
Tillabéry, Diffa regions
05/10/2006 30/11/2013 13,000,000.00 95.59 2.36 2.76 NON PP/NON
PPP
KANDADJI Programme Phase I 29/10/2008 31/12/2015 20,000,000.00 15.84 1.57 2.00 NON PP/PPP
KANDADJI Programme Phase I 29/10/2008 31/12/2015 20,000,000.00 17.13 1.57 2.00 NON PP/PPP
Sub-Total Agriculture - OSAN
(48.7%)
106,506,742.4
3
18.58
DWSS Project in 3 regions 21/02/2007 31/12/2013 10,351,947.98 68.51 1.93 2 NON PP/PPP
DWSS Project in 3 regions 21/02/2007 31/12/2013 3,000,000.00 82.24 1.93 2 NON PP/PPP
RWSS Project Phase II 20/09/2011 31/12/2015 16 000, 000.00 1.61 2.23 3 NO
SUPERVISION RWSS Project Phase II 20/09/2011 31/12/2015 3,300,956.45 0 2.23 3 NO
SUPERVISION Sub-Total Water and Sanitation –
OWAS (15.2%)
33,320,617.69 29.46
Support for the Development of
Education and Vocational
Training – PADEFPT
15/12/2012 31/12/2016 17,630,000.00 9.32 2.43 3 NON PP/NON
PPP
Support for the Development of
Education and Vocational
Training - PADEFPT
15/12/2012 31/12/2016 7,870,000.00 0 NON PP/NON
PPP
Sub-Total Social - OSHD
(11.6%)
25,500,000.00 6.44
PAMOGEF- Domestic Resource
Mobilization Support Project
26/01/2012 31/12/2016 10,000, 000 1.24 NON PP/NON
PPP
PACIRSA – Project to Support
Inclusive Growth and Food
Security Enhancement
14/11/2012 31/12/2014 21,560,000.00 53.62 NON PP/NON
PPP
Sub-Total Governance (14.4%) 31,560, 000 37.0
Total (18) operations
representing 11 projects)
% PPP = 27%
% PP = 0%
218,000,000 27.46 2.18 2.55
PP = Problem Project
Non PP = Non Problem Project
PPP = Potential Problem Project
Non PPP = Non Potential Problem Project
Annex 5 Page 1/1
Portfolio Performance Improvement Action Plan Problems Identified Actions Required /Recommendations Responsibility Schedule Output Monitoring Indicators
I. Problems at entry
1.1 Delay in the establishment of project
teams Include, in the project appraisal documents, the list, profile of vacancies and
precise and detailed Terms of Reference of staff to be recruited;
Absolutely select the coordinator and at least one other key person at the latest
during the negotiation phase of the project (condition precedent to
negotiations) so that the key project management staff are involved in the
negotiations;
Submit the appraisal report at least two weeks prior to negotiations;
Establish the full project team prior to effectiveness (condition precedent to
effectiveness).
AfDB Project
Officers/MP/MF/
Sector Ministries
Starting from
new ADF
operations
- The ToR of project management
staff are included in appraisal reports;
-Project coordinators are designated
prior to negotiations;
- Appraisal reports are transmitted no
later than 2 weeks prior to
negotiations;
- The entire project team is recruited
prior to effectiveness.
1.2 Inadequacy or poor quality of
baseline studies of projects Take the required time and provide the necessary resources (financial and
human) for the conduct of comprehensive and quality studies prior to
finalizing project appraisal reports.
Ensure broad-based consensus on the outcomes of studies and validate them
in conjunction with all relevant authorities and supervisory authorities of
projects and possibly with the affected populations or beneficiaries.
ADB Project
Officers/MP/MF/
Sector Ministries
Starting from
new ADF
operations
- Exhaustive and comprehensive
baseline studies are conducted prior
to project appraisal;
- The outcomes of studies are
validated by the relevant structures.
II. Problems at implementation
2.1 Limited knowledge of Bank rules Ensure, on a periodic basis (every year), the training of project staff on Bank
procedures (procurements, financial management and disbursements);
FFCO.3 and
ORPF- AfDB
End-2013 Training courses are organized every
year;
2.2 Very frequent change of project staff Work out a mechanism for avoiding frequent changes of coordinators for
programme support.
Line ministries of
projects
End-2013 - Project staff maintain their positions
throughout project implementation
except in cases of proven poor
performance.
III. Problems at closing 3.1 Failure to submit audit reports The funding mechanism of the previous audit should be clarified by the Bank
and preferably specified in the Loan Agreement (Bank or Government
counterpart contribution).
AfDB (FFCO,
ORPF).
ADB Project
Officers/MP/MF
/Sector
Ministries
End-2013
The previous audits are fully
funded and produced at most six
months after closure and in all
cases prior to the production of
the completion report.
3.2 Failure to justify the use of the last
working capital Make arrangements to justify all working capital received at project
completion.
Management
organs and
supervisory
ministries of
closed
projects/Ministrie
s of Plan and
Finance and
/FFCO at AfDB.
End-2013 All working capital is justified by
project completion at the latest
Small teams are maintained after
closing to ensure proper closure
of the project.
Annex 6 Page 1/1
Indicative Grant/Loan Programme for the Period 2013-17
(Amount in UA million)
Sectors/Projects Approval Date Indicative
Amount
Financing
Pillar 1 – Strengthening Resilience to Food Insecurity
National Public Projects – ADF Window
RURAL DEVELOPMENT
(in close coordination with the World Bank)
3N Initiative Support Project 2014 40 ADF 13
Climate Resilience Programme Support Project 2014-2017 To be
determined
ADF 14
ENERGY
(in close coordination with the World Bank, AFD and other co-financiers of the Kandadji Project – Phase
II)
Kandadji Project Phase II – Hydroelectricity Component 2014 40 ADF 13
National Private Sector Projects – Private Sector Window (PSW)
PRIVATE SECTOR
Project to Grant a Line of Credit to BAGRI 2014-17 To be
determined
ADB/
PSW*
Project to Build a 20 MW Solar Power Plant 2014-17 To be
determined
ADB/
PSW*
Multinational Projects – Regional Envelop (RE)
TRANSPORT
(in close coordination with the World Bank, WAEMU, BOAD (WADB), EU, AFD and private partners)
Multinational Trans-Saharan Road Project (TSR)
Niger – Chad Corridor
2013
22.50 ADF 12/ RE
56.57 ADF 12
Côte d’Ivoire-Burkina Faso-Niger-Benin Rail Loop
Project
2014-17 USD 2 000 000 NEPAD-
IPPF
Trans-Sahelian Corridor (Niamey – Dakar and Niger
Border - Lagos)
2014-2017 USD 3 000 000 NEPAD-
IPPF
ICT
Regional Trans-Saharan Backbone Project (TSB) 2014-17 26.6 To be
determined
Pillar 2 – Strengthening Governance, Particularly of Natural Resources
REFORM SUPPORT AND INSTITUTIONAL DEVELOPMENT
(in close coordination with the IMF, World Bank, EU, AFD, UNDP and French Cooperation)
General Budget Support Programme 2014-17 20 ADF 13
Institutional Support Project for Building State Capacity
and Effectiveness
2015-17 10 ADF 13
Economic and Sector Work
(in close collaboration with other technical and financial partners)
1. Preparation of a Transport Sector Policy Action Plan
2. Energy Sector Policy and Strategy
3. Study on the Status of Women and Child Trafficking in Niger
4.
________________________ (*) PSW = Private Sector Window
RA = Regional Allocation
Annex 7
Page 1/3
Bank’s Fiduciary Strategy in Niger A- BANK’S PROCUREMENT STRATEGY
1. Niger’s procurement system was established in 2002. It was amended in 2008 by Decree No. 2008-
120/PRN/ME/F of 9 May 2008 on the organization and duties of the General Directorate for Public
Procurement Control (DGPCOR) to ensure compliance with WAEMU directives. The procurement code was
amended by Law No. 2011-37 of 28 October 2011 on the general principles, control and regulation of public
procurement and public service delegations in Niger. The current public procurement regulation is governed
by Decree No. 2011-686/PRN/PM of 29 December 2011 on Public Procurement Code and public service
delegations, by Decree No. 2011-687 PRN/PM of 29 December 2011 on the duties, composition, organization
and operating procedures of the Public Procurement Regulatory Agency and by Decree No. 2011-688 PRN/PM
of 29 December 2011 on the code of ethics for public procurement and public service delegations.
2. The Bank’s appraisal of 2010 concluded that Niger’s public procurement system is for the most part
consistent with international standards and Bank procedures and policy. Accordingly, it is recommended at
this stage that national procedures be applicable to national competitive bidding (NCB) in respect of Bank-
financed operations. The next appraisal, which will take account of current progress, will assess the
performance of the national procurement system and its robustness with a view to making a recommendation
on the use of national procedures for International Competitive Bidding (ICB).
3. In this regard, as part of the implementation of the CSP 2013-2017, particularly its Pillar 2, aimed at
“strengthening governance and developing the private and financial sector” of the Bank's intervention strategy
in Niger, urgent reform actions should be undertaken by the Government to enhance the national system’s
compliance with Bank procedures and community standards. These actions include: (i) developing a
programme of gradual decentralization with the establishment of DGPCOR branches in the regions and
districts of the country; (ii) establishing a procurement capacity building strategy; (iii) establishing the
Integrated Public Procurement Management System (SIGMAP) which should allow DGPCOR, in the short
term, to develop reliable statistical data on public procurement, including the share of contracts awarded by
direct negotiation; (iv) continuing the measures taken by the DGPCOR to process only the procurement
documents of structures whose Procurement Plan has been approved and published in the Public Procurement
Journal; (v) establishing a physical and/or electronic filing system for documents with the allocation of
appropriate premises and equipment; (vi) conducting procurement audits for 2011 and 2012, under year 2013,
and regular annual audits starting 2013 to allow a complete and comprehensive assessment of public
procurement in Niger; (vii) taking a decision on the full collection of regulatory fees; (viii) operationalizing
the special line established for the reporting of procurement fraud; and (ix) improving access to public
procurement in the private sector, especially SMEs which should be the subject of dialogue with the
Government for actions to be undertaken under the Bank's strategy
B- BANK'S FINANCIAL MANAGEMENT STRATEGY
4. The successful implementation of the Bank's strategy for the period 2013-2017 in Niger will depend,
to a large extent, on the capacity of its administration to implement the operations that will be retained for
financing by the Bank, and to manage the public funds and resources to be allocated on the basis of its own
systems and institutions.
Annex 7 Page 2/3
5. Hence, in accordance with the provisions of the Paris Declaration and the Accra Forum on Aid
Effectiveness, the Bank will continue to support the Public Finance Management Reform Programme (PRGFP)
and reforms aimed at strengthening the public financial management, procurement and audit systems.
6. However, while it is acknowledged that the use of national systems contributes to their improvement,
it will not be possible, during the period 2013-2017, to use their components, given the outcomes of the
assessment of systems, processes and public finance management institutions in 2012 in accordance with
PEFA methodology. Overall, these results confirm that the expected progress of the Public Finance
Management Reform Programme (PRGFP) covering the period 2011-2014 were not significant and highlight
the persistent weaknesses of the PFM system in Niger described in the table of risks in the annex.
7. Therefore, the Bank will, as part of its operations for the current CSP period of 2013-2017, ensure
the use, as much as possible, of components of the public finance management system that are of satisfactory
or proven quality.
8. To boost the strengthening and improvement of other components and hence the use of national
systems over the period 2013-2017, the Bank’s fiduciary strategy will be based on the following three pillars:
First: The use of country systems (public finance management systems and national
implementation structures: ministries, agencies or services) will be the default option for all
activity programmes or public investment projects to be implemented under the current CSP;
Second: The use of parallel project implementation units will be the exception and should be
systematically justified. When it is established that the use of country systems is not feasible,
safeguard mechanisms should be designed for the ultimate purpose of consolidating weak
national systems and procedures; and
Third: budget support programmes will use national systems in their entirety. They will need
to have objectives and conditionalities focused on the Public Finance Management Reform
Programme (PRGFP) emanating from the conclusions of PEFA 2012 and other diagnostics of
the public finance system that may be conducted in the course of this CSP period.
A. Fiduciary Risk Assessment based on the 2012 PEFA
PFM System
Component Fiduciary Risk Rating
1- Budget
Process
Resource projections are still of limited quality, mainly based on rudimentary methods.
Information on international aid is inadequate. The strategic allocation of resources by
ministry is still not clearly justified. The timely release, to directors, of appropriations
necessary for the implementation of their programmes is still a challenge. The use of the
payment procedure without prior authorization persists. The distribution of funds
determined by the initial finance law continues to be greatly modified by the Government
during budget implementation.
Risk relating to the credibility of project/programme resource allocations.
High
Annex 7
Page 3/3
2-Cash
flow
manage
ment
The cash plan continues to be developed without any real consultation with the Directorate
General of the Budget and sector ministries. Hence, its relevance and robustness are
limited. With respect to the expenditure component, the cash-flow plan is not yet
adequately based on 'the overall commitment plan. The value of the plan itself is
undermined by the lack of robustness of procurement and commitment plans and sector
ministries’ sector expenditure commitment plans. The use of such tools for programming
the pace of expenditure is still very haphazard in most sector ministries.
Risk of uncertainty as to the availability of financial resources allocated to projects/
programmes and their use for the intended purposes, and the Treasury's capacity to
perform complex financial transactions.
Substantial
3-
Accounti
ng and
financial
reports.
Recent progress has been achieved in the production of annual financial statements (2007,
2008 and 2009). The draft 2010 Budget Review Law and the 2010 management accounts
are being prepared. However, there are still major weaknesses. Periodic accounting
statements are not produced during the year. Accounting data are available only after the
preparation of management accounts. Some accounts show balances carried over for
several years, especially for expenses paid in advance without available credit. The data
presented in reports available on the execution of budget expenditures are neither
comprehensive nor totally reliable. These data do not include the status of ministries’
expenditure or that of external financing. The quality levels and timeliness of annual
financial statements are below expectation. The information systems do not cover the full
range of public finance items and are not adequately integrated and accessible to all users.
Regional entities have only very little access to existing information systems and do not
have direct access to central databases enabling real-time information sharing. Such
information sharing is conducted periodically through magnetic media.
Risks of lengthy production timeframes and unreliability of financial and accounting
reports.
Substantial
4- Internal
controls
and
internal
audit
Internal control, which should be based on the principle that the authorizing officer and
the accounting officer should be separate, is still heavily flawed and contributes very little
to the anti-corruption effort. Its alignment with international standards and its
administrative control or efficiency audit activity are still very unsatisfactory.
Risks of weak internal control
Substantial
4.1-
Procure
ment
System.
5-
External
audit
The Court of Auditors has been established and its resources increased. However, external
control still covers a limited part of its scope as defined. Given that the Ministry of Finance
belatedly forwards to the Court accounts to be audited and the draft Budget Review Law
on which it is required to report, the said Court is not able to audit the financial statements
within the required timeframes.
Risk of failure to prepare timely audit reports for public entities.
Moderate
Opportun
ities
Existence of a new reform plan: the Public Finance Management Reform Programme
(PRGFP3) whose overall objective is to introduce an effective, efficient and transparent
public finance management system enabling the entity to consolidate its core functions
and improve the credibility of the PDES (National Economic and Social Development
Plan) in Niger.
Overall fiduciary risk assessment Substantial
Annex 8
Page 1/2
Challenges Related to the Environment, Climate Change and Green Growth 1- An environment affected by to natural resource degradation: Niger's natural resources (land,
water, soil and biomass) are exposed to profound degradation, mainly due to an imbalance between the rate of
their use and their rate of replacement, aggravated by h pronounced climate variability in recent decades. This
situation is compounded by rapid population growth which translates, in rural areas, into a precarious
equilibrium between energy and food needs and the use of forests. The key environmental issues relate to the: (i) protection of farmland from sand encroachment and loss of fertility; (ii) sustainable water management and
containment of siltation of water bodies; and (iii) improved use of biomass. Hence, the major challenge pertains
mainly to the development and sustainable management of the country's natural resources.
2- Environmental preservation is a source of economic growth: Despite these constraints, the natural
environment remains crucial for all socio-economic activities of the country as well as for the rural populations.
Indeed, the rural sector employs about 80% of the population, while its contribution to Niger’s economy is
estimated at approximately 42% of GDP (2003), of which 28% from agriculture, 10% from livestock
production and 4% from fishing/fish farming. Considering, therefore, the additional cost which environmental
degradation entails for the State budget, environmental protection is a source of economic growth. Given that
the poorest segments of the rural population are the most dependent on environmental goods and services and
are thus extremely vulnerable to climate change (CC), they will be the most affected.
3- A climate scenario characterized by disruption in the rainy season: Over the past decades, the
climate of Niger has become warmer and the rainfall more variable. By 2025 and 2050, it is expected that the
climate scenario in Niger will be a continuation of these trends, with a warmer climate characterized by greater
aridity. This would result in greater variation in rainfall, reflected in the late onset of the rainy season and its
decreasing duration.
4- Prospects of mitigating GHG emissions: Land Use, Land-Use Change and Forestry (UTCATF)
account for about 55.62% of total GHG emissions in Niger, whereas the agricultural/livestock sector accounts
for 34.60%. These activities which are vital to the country's economy are synergistic with issues related to
urban demand for firewood and charcoal, shifting agriculture, slash-and-burn agriculture and overgrazing.
They are all at the same time:
Environmental: reduction in GHG sequestration capacity and increased risk of desertification
in places, especially in the north of the country;
Energy-related: reduced supply of biomass energy; and
Social: risk of increased poverty in rural areas and consequently decreased resilience to
weather conditions for the rural populations most vulnerable to climate change.
Climate change will likely worsen the situation of food security, already compromised in recent decades: The agricultural productivity surplus of the early 1970s gave way, in the 1980s, to a 14% shortfall in food
needs coverage. This is due largely to extreme weather events that occurred in the region, particularly the
drought that afflicted the Sahel in the 1970s. In addition, climate change had visible impacts on grazing lands,
reflected in a sharp drop in livestock numbers, deteriorated animal health and reduced access to fodder. This
decline in agricultural production and livestock numbers, coupled with extreme poverty among the
populations, substantially reduces resilience to climate hazards.
Annex 8 Page 2/2
At the macroeconomic level, CC will likely exacerbate the structural food deficit in Niger, already seriously
undermined by climate hazards in recent decades.
5- Bank assistance to Niger to support these populations with low resilience to climate hazards.
The Bank intervenes in Niger in particular through the Pilot Programme for Climate Resilience (PPCR). It is
a programme which aims to combat climate change by improving the resilience of the most vulnerable
segments of the rural population. It comprises four priority projects, two of which will be implemented by the
Bank, namely:
Water Resource Mobilization and Development Project (PROMARE); and
Climate Information Development and Forecast Project (PDIPC).
6- Integrated approach to cope with CC through the National Environmental Plan for
Sustainable Development (PNEDD): This provides the baseline framework for environmental policy, with
the objective of ensuring energy security and integrated management of various national resources. Moreover,
the PNEDD comprises six programmes affecting the food sector, poverty, mitigation of GHG emissions and
climate variability. The climate change-related programme is based on a national strategy and action plan
whose implementation has resulted in the National Adaptation Programme of Action (NAPA) on Climate
Change, designed in 2006. This programme was launched under the Poverty Reduction Strategy (PRS) for the
socioeconomic development of the country.
Project/programme Recommendations:
7- Guidelines: On the basis of this analysis and prospects for integrating environmental/CC dimensions
in the CSP for Niger, as well as concerns related to green growth, the following guidelines are proposed:
Pay special attention to the two major ecological issues namely: (i) reversing the current
environmental degradation trend; and (ii) managing biomass energy in synergy with
agroforestry needs as a source of economic growth;
Pay special attention to agriculture, livestock and agro-forestry as sectors that are vulnerable
to CC, while at the same time displaying an interesting potential for mitigating GHG
emissions;
Approach the energy sector with a policy vision that is inclusive of the rural populations, by
showing special interest in the issue of management/substitution of biomass energy (the most
widely used form of energy in Niger); and
Consider an environment/CC capacity building programme aimed at identifying key issues
and better integrating them into sector-based policies and programmes.
Annex 9 Page 1/2
Development Partners’ Areas of Intervention in Niger in 2013
Matrix of Donors in
Niger
2013
1.
Str
ate
gic
D
ev
elo
pm
en
t
Pla
nn
ing
2 R
eg
ion
al.
In
teg
ra
tio
n
3.
Tra
de –
Priv
ate
secto
r
4.
Min
es
5.
Cu
ltu
re
6.
Decen
tra
liza
tio
n
7.
Co
mm
un
ity
Dev
elo
pm
en
t
8. R
ura
l D
ev
elo
pm
en
t /S
DR
9.
Fo
od
Secu
rit
y
10
. F
orest
s/en
vir
on
men
t
11
. W
ate
r
an
d s
an
ita
tio
n
12
. E
nerg
y
13
. T
ra
nsp
ort
14
. E
du
ca
tio
n
15
. V
oca
tio
na
l a
nd
tech
nic
al
tra
inin
g
16
. H
ealt
h
17
. H
IV/A
IDS
18
. G
end
er
19
. P
op
ula
tio
n
20
. M
acro
Sta
bil
iza
tio
n
21
. P
ub
lic F
ina
nce
22
. G
ov
ern
an
ce
23
. J
ust
ice
24
. O
thers
Area
s b
y
acti
ve
pa
rtn
er
European Union
EC ** ** LP ** ** LP LP ** ** LP ** ** LP ** ** 15
Germany ** ** ** ** ** ** ** ** ** 9
Belgium ** ** ** ** ** ** ** ** LP 9
Denmark ** ** ** ** ** ** 6
Spain ** ** ** LP ** 5
France-AFD ** ** ** ** ** ** LP ** ** ** ** ** 12
France-SCAC ** ** ** LP ** ** ** ** ** ** LP 11
Italy ** ** ** ** ** ** ** 7
Luxemburg ** ** ** ** ** ** ** 7
United Kingdom
Other Bilateral
Partners
Canada ** ** ** ** ** 5
United States
Japan ** ** ** ** ** 5
Switzerland ** ** ** ** ** ** ** ** 8
Multilateral
Partners
IAEA ** ** ** ** ** ** ** 7
AfDB ** ** ** ** ** ** ** ** ** ** ** ** ** 13
BADEA ** ** ** ** ** ** 6
** = Active Technical and Financial Partner (TFP) LP = Lead TFP
Annex 9 Page 2/2
Development Partners’ Areas of Intervention in Niger in 2013 (cont’d).
Matrix of Donors in
Niger
2013
1.
Str
ate
gic
D
ev
elo
pm
en
t
Pla
nn
ing
2.
Reg
ion
al.
In
teg
ra
tio
n
3.
Tra
de –
Priv
ate
secto
r
4.
Min
es
5.
Cu
ltu
re
6.
Decen
tra
liza
tio
n
7 C
om
mu
nit
y D
ev
elo
pm
en
t
8 R
ura
l D
ev
elo
pm
en
t /S
DR
9.
Fo
od
Secu
rit
y
10
. F
orest
s/E
nv
iro
nm
en
t
11
. W
ate
r
an
d s
an
ita
tio
n
12
. E
nerg
y
13
. T
ra
nsp
ort
14
. E
du
ca
tio
n
15
. V
oca
tio
na
l a
nd
te
ch
nic
al
tra
inin
g
16
. H
ealt
h
17
. H
IV/A
IDS
18
. G
end
er
19
. P
op
ula
tio
n
20
. M
acro
Sta
bil
iza
tio
n
21
. P
ub
lic F
ina
nce
22
. G
ov
ern
an
ce
23
. J
ust
ice
24
.
Oth
ers
No
. o
f i
nte
rv
en
tio
n a
rea
s p
er
acti
ve
TF
P
World Bank ** ** ** ** ** ** ** ** ** ** LP ** ** ** ** ** ** 17
IDB ** ** ** ** ** ** 6
BOAD ** ** ** ** ** ** 6
ECA ** ** ** ** ** ** ** ** ** ** 10
FAO ** ** ** ** 4
UNCDF ** ** ** ** ** ** ** ** ** 9
IFAD ** ** ** ** ** ** ** ** ** ** 10
KFAED ** ** ** ** ** ** 6
IMF LP ** 2
UNFPA LP ** 2
OCHA/CERF ** ** ** ** 4
OFID ** ** ** ** ** ** 6
WHO ** 1
UNAIDS LP 1
WFP ** 1
UNDP ** ** ** ** ** LP ** ** ** ** ** ** ** ** ** LP 16
UNESCO ** 1
UNICEF ** ** ** ** LP ** ** ** ** ** 10
UNIFEM * ** ** 3
Active TFP 10 9 9 5 2 10 8 24 21 9 18 10 10 14 14 13 7 11 3 6 8 8 3 9
Source: Provisional Mapping Report /Labour Division
** = Active Technical and Financial Partner (TFP) LP = Lead TFP
Annex 10
Page 1/2
Implementation Status of the Kandadji Programme
Phase I – (Agricultural Component)
The “Kandadji” Ecosystem Regeneration and Niger Valley Development Programme (P-KRESMIN)
is a support programme for the Accelerated Development and Poverty Reduction Strategy (DPRS) in
Niger. This program was designed in three phases: i) Phase I- major investment for the construction
of the Kandadji dam and implementation of socio-economic and environmental plans; ii) Phase II-
consolidation of investments through the construction of the hydroelectric plant and power lines; and
iii) Phase III- agriculture and farmland development.
The first phase, for a total amount of UA 186 Million, is funded by the State of Niger and several
other donors (AfDB, IDB, BOAD, BADEA EBID, OPEC, KFAED, SFD, and ABU DHABI F.).
AfDB contributes to the project through two ADF financings, namely a grant of UA 20 million and
a loan of UA 20 million. The project started in 2008 and the last disbursement is scheduled for
December 2015.
The main component of the project, namely the construction of the Kandadji Dam, was entrusted to
the Russian company “Zarubezhvodstroy” for an amount of CFAF 84,791,891,535.10. The contract
was notified on 25 May 2011 for a works implementation lead time of 57 months.
The various progress reports on the programme and aide memoires of supervision missions have
reported significant delays in the works implementation and the poor technical and financial capacity
of the company tasked with the works implementation. Indeed, 26 months after the start-up of works,
the rate of progress is only 6%, compared with a contract forecast of more than 30%, and 35% into
the contract period set.
The Bank, as lead donor of the Kandadji Programme, organized several joint missions with other
donors and a multidisciplinary technical mission with the participation of ORPF, GECL, OSAN and
AFSL experts which enabled an analysis of contract terms and assessment of identified weaknesses.
In the wake of their missions, all donors unanimously expressed concern about the future of the
programme and the risks involved in the use of funds allocated to Niger.
In the face of this extremely negative situation, the project owner wrote the company three letters of
formal notice which met with no response. This prompted the Government of Niger, after
consultation with the donors, to terminate the contract with the Russian company
“ZARUBEZHVODSTROY”, on 18 July 2013, and to initiate the appropriate process, under
the circumstances, to ensure implementation of programme objectives.
Annex 10
Page 2/2
As a practical measure for managing the post-termination phase, all the donors, in coordination with
the Government of Niger, agreed on the need to organize a technical and financial audit to analyze
the current status of the physical and financial performance of the contract, assess the consequences
as well as the social and environmental impacts of the termination, and make fresh proposals on the
general programme organization and allotment.
This audit was conducted last August and the report was forwarded to the donors, in the week of 16
September 2013.
The outcomes of this audit are being considered by the Government of Niger and the donors. At the
Bank, the audit report was sent to the various relevant departments for opinions and remarks, and a
meeting of the country team is planned for the first week of October 2013 to help coordinate the
Bank’s position.
NEXT STAGES:
Based on the findings of this audit, the next steps for the implementation of programme activities are
as follows:
1- Internal coordination at the Bank, to analyse the proposals of the technical and
financial audit and harmonize the Bank's position on the technical, legal and
procurement aspects;
2- Cooperation with the Government of Niger and other donors to agree on the new
general organization of the programme, the preparation of new procurement
documents and support for the ZVS contract termination process (October 2013);
3- Define the potential financing gap and liaise with the Government of Niger to seek the
additional financing required to fill the gap (October/November 2013);
4- Speed up the procedures for initiating a second international competitive bidding
(ICB) process, with the pre-qualification of contractors for the selection of a new
company for the dam construction; and
5- Design an overall plan for the implementation of all phases of the programme.
Annex 11 Page 1/7
CSP 2013-17 Indicative Results Framework
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
CSP 2013-17 Pillar 1 – Strengthening resilience to food insecurity
Thrust 3: Food security
and sustainable
agricultural development.
i) Output 1.1 : Strengthening anchor infrastructure for the development of agricultural supply
- Inadequate national energy production
and transportation
infrastructure ;
- Significant
predominance of thermal
electricity production source;
- Low rate of
household access to electricity;
- 130 MW hydroelectric power plant built in 2017;
- 80 MW thermal power plant
at Gourou Banda;
- 200 MW Coal power plant
at Salkadamna
- 190 km-long 132 kV
transmission line built in
2017; - Two 132/33 kV stations
built in 2017;
- Extension of the distribution
network and household
connections;
- 600 GW/h of hydroelectric power (green energy) produced annually
in the country in 2017;
- 40% of renewable energy in the
energy mix in 2017;
- Reduction of 790 K tons of
greenhouse gas emissions (CO2);
- Rate of access to electricity stands
at 20% in 2017;
- One hydroelectric power plant of an
installed capacity
of 130 MW under
construction;
- 190 km-long 132 kV
transmission line
under construction;
- Two 132/33 kV stations under
construction;
- Extension of the
distribution
network and
household
connections;
Rate of access to electricity stands at 15%;
New projects - Kandadji
Hydroelectric Power Plant
Construction project;
- Recurrent food
crises due to drought
- Degradation of
natural resources in the Niger
River Basin
- Construction of 5 mini-dams
and 20 weirs;
- CES works over 10,000 ha; - Development of 2,000 ha for
small-scale irrigation;
- Development of xxx for
small-scale irrigation;
- Planting of 2,000 ha of trees;
- Development of 5 grazing
areas of an area of 100,000 ha
- 100,000 ml of California
grid are laid;
- 1,000 motor pumps
provided to farmers;
- Construction of
socioeconomic
infrastructure;
- 10,000 sustainable jobs in the
agro-pastoral sector;
- Additional production of 5,000 t/year in the rainy season;
- Additional production of 50,000
t/year in the dry season (Off
season);
- Ensuring food security for an
additional 50,000 Tropical
Livestock Unit (TLU)/year; - Increased income from agro-
sylvo-pastoral activities;
- Construction of 10
sills;
- CES works over 2,500 ha ;
- Development of 1000
ha for irrigation;
- Planting of 500 ha of
trees;
- 50,000 ml of
California grid are laid;
- 50 motor pumps
provided to
farmers;
- Construction of
socio-economic
infrastructure;
- 3,000 sustainable jobs in
the agro-pastoral sector;
- Additional production of 500 t/year in the dry
season;
- Additional production of
15,000 t/year in the dry
season (Off season);
- Increased income from agro-forestry-pastoral
activities;
- Project to Support the
3N Initiative;
- Climate Resilience Programme Support Project in
Niger;
- Integrated
Development and climate change
adaptation Programme PIDACC/BN
(multinational);
ii) Output 1.2: Increase market access to contribute to resilience to food insecurity
Annex 11 Page 2/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
- Inadequacy of
Niger's international
access (via Benin
only through direct
access to the
international
underwater
cables);
- Limiting access by the populations,
governments and
businesses to
quality ICT
services;
- ICT service access
rates too high;
- Installation of
1,715 km-long fibre optic connections along the main roads
connecting Niger to its
immediate neighbours (Algeria,
Nigeria and Chad);
- Extension of the
National Backbone throughout
the communities crossed by the
DTS;
- Two additional links for
direct access to the international underwater cables (via Algeria and
Nigeria);
- Indirect access through
Chad to underwater cables with cable-
landing points in Cameroon;
- 50% combined
penetration rate for fixed and mobile
cables in 2017;
- On-going
installation of DTS fibre optic
connections;
- Connection of
certain secondary
cities of the country
to broadband
Internet;
- At least one additional
international access; - 35% combined penetration
rate for mobile and fixed
cables;
- Algeria/Niger/Nigeria/Chad
Trans-Saharan Regional Backbone Project;
- The performance of the major
international road
corridors
(Ouagadougou-
Dori-Tera-Niamey
and Trans-Sahara
Highway) is
reduced by the persistence of
physical and non-
physical barriers
and the costs
involved are high;
- The exploitation of
mineral deposits in
the region in general and Niger
in particular, is
subject to the
completion of the
Niger’s section of
the Abidjan-
Ouagadougou-Cotonou-Niamey
rail loop;
- Cross-border trade
with Nigeria is
hampered by the
- 223 km-long road between Arlit and Assamaka on the
Trans-Sahara Highway will
be built by 2018;
- 2 Juxtaposed Checkpoints
(JCPs) constructed,
equipped and commissioned
at the Algeria/Niger and
Niger/Chad borders; - 543 metre-long bridge with
3 km-long access roads will
be built at Farié on the
Ouagadougou-Dori-Tera-
Niamey corridor by 2015;
- At least 100 km of railway
track on the Nigerien section
of the Abidjan-Ouagadougou- Niamey-
Cotonou rail loop will be
built by 2017;
- 200 km of cross-border
roads with Nigeria will be
built by 2017;
- The total traffic at the Niger/Algeria land border will
increase from 62 vehicles/day in
2013 to 116 vehicles/day in 2018;
- The total traffic at the Niger/Chad
land border will increase from 18
vehicles/day in 2013 to 76
vehicles/day in 2018;
- The travel time of a heavy truck (HV) on the Arlit-Assamaka
section which is currently 2 days
(2013) will be reduced to 3.5
hours in 2018;
- The average vehicle operating cost
(VOC) for heavy vehicles in Niger
will be reduced from CFAF
945/km (in 2013) to CFAF 494 / km (in 2018;
- The average time for the
conveyance of goods from
Southern European ports will be
reduced by 40 days (in 2013) to 18
days (2018);
- Length of daily uptime for facilities for crossing the River
Niger at Farié between Dori and
Tera will be reduced by 50% (from 24 hours in 2013 to 12 hours
in 2018);
- - - Niger-Chad Corridor Trans-Sahara Highway (TSH)
Multinational Project;
- Cross-border roads Project
with Nigeria;
- Abidjan-Ouagadougou-
Niamey-Cotonou Rail Loop
Multinational Project;
Annex 11 Page 3/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
poor state of trans-
border roads;
- Freight traffic between Niger and
Nigeria will increase;
CSP 2013-17 Pillar 2 – Strengthening governance, particularly of natural resources
Thrust 1: Strengthening
the credibility and
effectiveness of public
institutions
i) Output 2.1: Strengthening economic and financial governance
Implementation of WAEMU
directives is not effective;
Poor mobilization of internal
resources;
Inadequate alignment of the
budget with the PDES;
Low efficiency of budget
execution internal oversight ;
- Delay in the
adoption of final
audited accounts.
- Weak human and
technical capacity
of the government
services;
- Effective implementation
of the 6 directives of the
harmonized public
finance framework within
WAEMU;
- The tax revenue
optimization action plan
is implemented;
- Taxpayer education on
the new General Tax Code is effective and
sustained;
- Review and adoption of a
customs code consistent
with Community
provisions and taking into
account the provisions of the Kyoto Convention;
- All ministries have a
MTEF and programme
budgets aligned with the
PDES;
- The decentralization of
financial controllers and
DGCMP services realized
for eight regions;
- PEFA PI-19 indicator is
rated "A" in 2015;
- The public finance management
system is consistent with
WAEMU directives, results-based
and efficient;
- At least 10 PEFA indicators are rated "B" as compared to the
current 5;
- PI-13, PI-14 and PI-15 are rated at
least "B";
Tax burden (tax revenue as% of GDP) is at least 19%;
- The credibility and relevance of
the budget is strengthened. PEFA
PI-1, PI-2, PI-3 and PI-4 are rated
at least "B" PI-11 is rated at least
"B" and PI-12 rated "A";
- Annual rate of execution of the investment budget is at least 80%
- Internal budget oversight is more
effective;
- Competitive bidding, optimal use
of resources and public
procurement control are effective;
- Budget execution transparency
and monitoring are strengthened. -
PI-28 is at least "B";
- At least 3 of the 6
WAEMU directives
are effectively
implemented in
public finance management;
- The tax revenue
optimization plan is
adopted;
- The new General Tax Code is
published and
widely
disseminated;
- 50% of ministries
have MTEF and
budget
programmes consistent with the
objectives of the
national
development
strategy;
- The
decentralization of
financial controllers
and DGCMP
services is effective
- The public finance
management system
is at least 50%
compliant with
WAEMU directives;
- Rate of tax burden
(tax revenue as% of
GDP) is at least 17%;
- The credibility and
relevance of the
budget are gradually
improved;
- Annual rate of
execution of the
investment budget has gradually
improved;
- The internal budget
control system is
strengthened;
- Competitive bidding,
optimal use of
resources and public procurement control
- Support Project for the
Mobilization of Domestic
Resources and the
Improvement of Economic
and Financial Governance (PAMOGEF) – on-going
project; - Support Programme for
Inclusive Growth and the
Strengthening of Food
Security (PACIRSA) – on-
going budget support
programme; - Economic and Financial
Reform Support Programme
- new budget support
operation to be approved
between 2014 and 2015; - Institutional Capacity
Building and Reform Programme - new
institutional support to be
approved between 2014
and 2015;
- Support Project for the
Mobilization of Domestic
Annex 11 Page 4/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
- Lack of
appropriate policies and
sector strategies that are
consistent with the PDES;
- Final audited accounts
are prepared and adopted
in a timely manner;
- The national strategy for
building the capacity of
government services and
modernizing the State and
its action plan are
implemented; - Public officials are trained
under relevant and
harmonized training plans;
- Sector strategies consistent
with the 3N Initiative of all
sub-sectors of the rural sector are adopted and
implemented;
- The mining sector has a
sector policy and regulatory
framework aligned with
PDES objectives. Action
plans are implemented;
- The energy sector has a sector policy and framework
aligned with PDES
objectives. Action plans are
implemented;
- The transport sector has a
sector policy and regulatory
framework in line with PDES objectives. Action
plans are implemented;
- A programme for
strengthening the human,
technical and material
capacity of the rural, energy,
mining and transport sectors
is implemented;
- Public service performances have
improved. CPIA rating: Quality
of Government Services is at least
“5”;
- The implementation of the 3N
Programme is satisfactory;
- CPIA indicators related to
structural policies and social
inclusion and equity policies are
rated at least "4";
for at least 5
regions;
- PEFA PI-19
indicator is rated
"A" in 2015;
- Delays encountered
are gradually
resolved;
- The national
strategy to build the
capacity of
institutions and the
Public Service as well as its Action
Plan, are adopted by
the Government;
- Public officials are
trained under
relevant, consistent
and harmonized
training plans;
- Sector strategies
consistent with the
3NI of all sub-
sectors of the rural
sector are adopted;
- The mining sector
has a sector policy and regulatory
framework aligned
with PDES
objectives;
- The energy sector
has a sector policy
and regulatory framework aligned
with PDES
objectives.
- The transport
sector has a sector
policy and
regulatory
framework aligned
are gradually
improved;
- Transparency and
budget execution
monitoring are
gradually improved;
- Public service
performances have
improved. CPIA
rating: Quality of
Government Services
is at least “5”;
- Technical capacity
building programmes;
- The implementation
of the 3N Programme is satisfactory;
- CPIA indicators
related to structural
policies and social
inclusion and equity
policies are rated at least “4”;
Resources and the
Improvement of Economic
and Financial Governance
(PAMOGEF) -on-going
project;
- Programme to Support Inclusive Growth and Food
Security Enhancement
(PACIRSA) – on-going
budget support Programme;
- Programme to support
economic, financial and
institutional reforms - new budget support operation to
be approved between 2014
and 2017.
Annex 11 Page 5/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
with PDES
objectives.
- A programme for
strengthening the
human, technical
and material capacity of the rural,
energy, mining and
transport sectors
was adopted by the
Government.
Thrust 4: Promoting a
competitive and diversified
economy for accelerated
and inclusive growth.
ii) Output 2.2: Strengthening sector-based governance and supporting economic diversification
- Business
climate not conducive to the
promotion of investment,
employment, youth entrepreneurship and creation
of value added;
- Lack of transport and communication
infrastructure;
- Lack of non-
agriculture production sectors such as manufacturing,
construction and mining;
- Support the
programme to promote and secure
private investment;
- Support the
programme for the development of road and railway infrastructure,
digital applications and content of
communication;
- Support the
National Industrial Development Strategy (SNDI) and improved
productivity in the mining sector;
- The Investment Code was
revised and adopted;
- The procedures for starting or
establishing a business are streamlined and consistent with
OHADA;
- The Mining Code is revised;
- The Labour Code is revised;
- The Public-Private Partnership
Framework for the regulation of
transport, energy and water resources is operational;
- International roads to
neighbouring countries are
developed and paved;
- The road maintenance system is
strengthened and CAFER is
transformed into a second-
generation road fund; - The national transport strategy is
finalized and updated and axle-
load regulations are
implemented;
- Digital content and applications
are developed and digital
terrestrial television
infrastructure is deployed; - The legal and institutional
framework is appropriate and
The programme to promote
and secure private
investment is
adopted and implemented;
- The programme for the development of
road and railway
infrastructure,
digital applications
and content of
communication is
adopted and
implemented;
Improved business climate and
Niger's improved score in the
World Bank's “Doing Business”
report, compared with2012;
- The quality of
international roads to
neighbouring countries has improved
significantly, compared
with previous years;
- Road maintenance is
enhanced and the national
transport strategy is known
and implemented;
- Communication infrastructure has
improved, the legal and
institutional framework is
appropriate and the quality
of human resources in the
sector has increased
substantially;
Annex 11 Page 6/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
- Poor financial
intermediation to support Niger's economy;
- Support the
Development Programme for the banking and financial and
insurance sector.
universal access to ICT services
is ensured;
- The human and institutional
capacity of the sector is
strengthened;
- A coherent and appropriate
industrial policy is developed and
adopted; - A national innovation, industrial
property and quality policy is
implemented;
- New industrial zones are created
and energy production and
produce delivery infrastructure
are built;
- Production costs are reduced and local products are more
competitive;
- Industrial processing units for
agro- pastoral produce are
operational;
- Mining activities are better known and diversified;
- The mining code is drawn up;
- The Fund for artisanal mining
companies is established and
operational;
- The institutional framework is
improved and the mining sector
better managed; - The share capital of all banks is
increased to a minimum of CFAF
5 billion and that of financial
institutions to CFAF 1 billion by
the end of PDES;
- All banks and financial
institutions comply with prudential management ratios;
- The implementation of the new
legal framework for
decentralized financial systems is
effective;
- Studies and operational
recommendations on the
- The National
Industrial Development
Strategy (NSDI) and
mining policy are
adopted and
implemented;
- The Development
Programme for the
banking and financial and
insurance
institutions sector is adopted and
implemented.
- An industrial policy is
formulated and known; - Niger’s industrial sector is
significantly improved,
compared with previous
years;
- Production costs in
industrial units are
significantly reduced,
compared with previous years;
- Local produce processing
units exist and are
operational;
- The Fund for artisanal
mining companies is
established;
- The mining code exists;
- The share of mining
activities in Niger's
economic growth has
increased significantly,
compared with previous
years. - Most banks and financial
institutions comply with
the decided share capital
level;
- All banks and financial
institutions comply with
the prudential
management ratios of the WAEMU region;
- A new legal framework for
decentralized financial
systems is implemented;
- The conclusions and
recommendations of
studies on the financing of SMEs and the agricultural
sector are available;
- The volume of medium-
and long-term credit
granted to SMEs/SMIs has
increased by 30%;
- At least 10% of public
procurement and 20% of
- Line of Credit at
SONIBANK to finance SMEs/SMIs.
Annex 11 Page 7/7
PDES Strategic Objectives
Problems Impeding the
Achievement of PDES
Objectives
Final Outcomes Final Outputs Mid-Term Outcomes Mid-Term Outputs Indicative programme of new
operations during period (2013-17)
of the CSP and on-going projects (expected at the end of the strategy in 2017) (expected for 2015)
financing of SMEs and the
agricultural sector are made; - Financing for SMEs/SMIs with
long-term resources is
established and the ability of
SMEs/SMIs to meet their
medium- and long-term credit
needs has improved;
- The volume of contracts won and
executed by SMEs/SMIs has increased significantly.
private procurement
contracts are outsourced to SMEs/SMIs.
CSP 2013-17 Cross-cutting issues – Development of indigenous knowledge and capacity building for climate resilience and green economy
i) Output 1: Strengthening indigenous knowledge for better implementation of the Bank's strategy
- Inadequate
knowledge
- Economic and
sector studies: Formulation of the
sector policy and the transport
sector action plan (gender will be
mainstreamed in this study) - Economic and
sector studies: Formulation of the
sector policy and action plan of
the Energy sector (gender will be
mainstreamed in this study)
- Economic and
Sector Studies: Study on the
status of women and child
trafficking in Niger
- Improved performance of the
transport sector
- Improved performance of the
energy sector
- Better targeting by the poverty reduction and women
empowerment strategy
the
ii) Output 2: Capacity building in the area of green economy and climate change
- Inadequate
integration of climate
information into the
management of agro-sylvo-
pastoral activities.
- Dissemination of
climate information to 150,000
farmers in the 235 communes of
Niger;
- Dissemination
multi-risk information from the
Early Warning System (EWS) in the 235 communes.
- At least 120 communes in Niger
have incorporated climate
information in their commune
development plans (PDC);
- 200,000 Nigerien farmers
routinely use climate
information in the management of their activities;
- Flood, drought, sandstorm, and
extreme temperature alerts are
disseminated in the communes.
- Dissemination of
climate
information to
150,000 farmers in
the 235 communes
of Niger;
- Dissemination of information from
the EWS multi-risk
early warning
system in the 235
communes.
- At least 60 communes in
Niger have incorporated
climate information in
their PDC;
- 50,000 farmers in Niger
routinely use climate information in the
management of their
activities;
- Floods, droughts,
sandstorms, and extreme
temperature are covered by the EWS.
- Climate Resilience
Programme Support Project in Niger