Nguyễn Văn Tâm Bsc of Civil Engineering, 1997 (CTU, VN) Lecture notes: TU Delft, Holand...
-
Upload
marion-reeves -
Category
Documents
-
view
218 -
download
0
Transcript of Nguyễn Văn Tâm Bsc of Civil Engineering, 1997 (CTU, VN) Lecture notes: TU Delft, Holand...
Nguyễn Văn TâmBsc of Civil Engineering, 1997 (CTU, VN)
Lecture notes: TU Delft, Holand
Geotextile and Structural Experiment, 2000
Construction equipment & Method, 2004
MEng of Construction Engineering and Infrastructure Management
2009 (AIT, Thailand)
Claims (Delay and Cost Overrun) in Building Project in Public Sector: Case Study in Mekong Area, Vietnam
Building projects in Mekong Delta, Vietnam
Cantho AirportCantho Bridge
Introduction
An Giang supper market (D)
Aquiculture College, CTU (E)
Medicine and Pharmacy University (F) Bac Lieu Committee Building (C)
Can tho Sport Competition House (B)
College of Technology, CTU (A)
Six building projects of case study
Priv
ate
cont
ract
ors
Pub
lic c
ontr
acto
rs
Problem Statements
Claim status of construction projects
Construction Law of Vietnam and Tender Law are not precisely cover claims.
Unclear claim management and settlement: all claims are approved by owner or investor
(Clause 32 of DecreeDecree 16/2005/NĐ-CP)
Lack of claim knowledge: claim right (legal), Cooperate to mitigate claim and resolve claim events
Role of human resource: management competency, cooperation climate to deal claim issues in project.
Introduction
Research direction
Objective 1
Identification Claim Causes
Objective 2Claim settlement: Analysis
for additional costAnalysis for additional
time
Objective 3Study Claim attitude of
contractor and owner
Scope of study
VietnamMekong area
Public sectorBuilding Projects
Literature review Experts interviewing Case study: Multiple - Case (Yin, 2003) Claim causes? How they are settled? How the claim attitude affect on project?
Objectives
INP
UT
DA
TA
C
OLLEC
TIO
N,
AN
ALY
SIS
OU
TP
UT
Identification of Claims Causes, Settlement and Attitudes
SCOPE- Public Sector- Large Projects- Overrun Cost, Delays
SCOPE- Public Sector- Large Projects- Overrun Cost, Delays
STRATEGY- Literature: finding common claim sources- Project document: finding specific sources- Experts: Clarification, validity and finding new
sources
STRATEGY- Literature: finding common claim sources- Project document: finding specific sources- Experts: Clarification, validity and finding new
sources LITERATURELITERATURE EXPERTS
3 Experts, experience > 15 years (Academic, Govern., Consultant)
EXPERTS 3 Experts, experience > 15 years (Academic, Govern., Consultant)
Document data collection: Contracts, diaries, meeting record and schedules
Document data collection: Contracts, diaries, meeting record and schedules
List of Claims sources, Settlement
and Attitude
List of Claims sources, Settlement
and Attitude
PROJECT SELECTION- 3 Projects of public contr.- 3 projects of private contr.
PROJECT SELECTION- 3 Projects of public contr.- 3 projects of private contr.
Claim causesRelationships’ causesClaim causesRelationships’ causes
Claim causesClaim analysisClaim attitudes
Claim causesClaim analysisClaim attitudes
Ranking claim causesClaim attitudes
Ranking claim causesClaim attitudes
Expert DiscussionExpert Discussion
Interview 6 ParticipantsInterview 6 Participants
Observation
Observation
- 26 Claim causes- Relationships of claim causes- Claim analysis methods: Delay & Cost overrun- Claim attitudes- Claim climate assessment
- 26 Claim causes- Relationships of claim causes- Claim analysis methods: Delay & Cost overrun- Claim attitudes- Claim climate assessment
CONCLUSION- Claim causes- Claim management- Claim culture
CONCLUSION- Claim causes- Claim management- Claim culture
Methodology
Objective 1: Identification Claim CausesObjective
1Identificatio
n Claim Causes
Causes of Delay Time
Causes of Cost Overruns
Causes of Delay and/or Cost overruns
Ranking Causes and Seeking relationship of claim causes
Compare between the initial and final duration
0 200 400 600 800 1000 1200 1400 1600
A
B
C
D
E
F
Proj
ects
Days
Actual duration
Initial duration
Data Analysis
Private Contractor∑ Delay:46%
Public Contractor∑ Delay: 174%
Delay time Analysis
-Average total delay: 110% - Percentage of additional time on total delay: average: 41.57%
Mistakes during
construction, 31.21%
Low productivity,
17.31%
Defective works and reworks, 24.13%
Delay or Disruption,
27.35%
Contractor, 50.32%
Owner,15.34%
External,3.83% Designer &
consultant,30.51%
Data Analysis
Low awarded bid prices: 4.98%. This is strongly affect on delay time due to more number of contractors than building project and unit price to be lower than market price about 10% It is root of shortage of equipment, shortage materials, choosing incompetent subcontractors and suppliers.
-
10
20
30
40
50
60
A B C D E F
Projects
Am
ount
(Bill
ion
VND
)Cost estimate
Initial contract value
Delay time and delay factors of Contractor
Competence of Contractor is a serious problem: Main power, Equipment, and Finance.
Causes of delay of 6 cases (Based on document record, smaller than total delay time)
Delay CausesCaused by
GroupTotal delay
time (days)Percent
Design changes by mistakes Designer 686 21.92%Mistakes during construction Contractor 485 15.50%Additional works by owner Owner 480 15.34%Delay or Disruption Contractor 425 13.58%Defective works and reworks Contractor 375 11.98%Low productivity Contractor 290 9.27%Inspection of completed works Consultant 269 8.59%Unforeseen site conditions External 65 2.08%Price fluctuations External 55 1.76%
Data Analysis
Delay causes of Parties
Contractors have mistakes: foundation tasks as producing and driving pile foundation.
Designers have been small or middle businesses. Foundation structure must be changed due to lack survey soil properties.
Owners have unclear scope, difficult financial and adding works. There are many people can give ideas to change architect and material. (3D model should be used for architect designs- show a clear view for owner)
Roles of owners can motivate or force contractors, consultants and designers to improve all aspects in order to achieve effective and efficient building projects. But they cannot do as contract.
Data Analysis
Cost estimate, initial contract value, claim paid and actual value.
Percentage of decreasing bidding price (average: 4.98%)
Percentage of claim paid (average: 21.55%)
Data Analysis
Cost Overrun
-10
0
10
20
30
40
50
60
A B C D E F
Projects
Am
ou
nt
(Bill
ion
VN
D)
Initial contract value
Claim paid
Comparison between initial contract values and claims paid by the client.
Causes of cost overruns Causes of cost overrun of 6 cases (Based on document)
Design changes by mistakes,
30.03%
Price fluctuations, 23.57%
Additional works by owner, 22.04%
Unforeseen site conditions,
16.67%
Inaccurate estimates, 7.70%
Adding cost factor Groups Claim Amount (VND)Percentage of Claims
Design changes by mistakesDesigner 9,437,909,000 30.03%Price fluctuations External 7,408,428,000 23.57%Additional works by owner Owner 6,926,039,000 22.04%Unforeseen site conditions External 5,239,300,000 16.67%
Inaccurate estimates Designer 2,420,273,000 7.70%
Causes of Cost overrun: Competence of Designer, small scale consultant firmsOwner has many personnel who have high power to change
Data Analysis
26 factors of Delay and/or Additional Cost Relationship Network (from expert interview and literature review)
Design changes by mistakes
Inaccurate estimates
Owners’ site clearance difficulties
Incompetent subcontractors
Low awarded bid prices
Financial difficulties of owner
Lack of capable project managers
Delay and/or
Additional Cost
Mistakes during construction
Additional works/ reworks by
owner
Defective works and reworks
Delay or Disruption
Unforeseen site conditions
Shortages of materials
Financial difficulties of contractor
Slow payment of completed
worksPrice fluctuations
Designers’ inadequate
experience and capability
Shortage of equipment
Low productivity
Inappropriate construction
methods
Bad weatherUnclear contractual
conditions
Obstacles from government Inspection of
completed works
Shortages of skilled workers
Lack of capable site supervisors
Compensation from owner
No Compensation
from owner
Data Analysis
Objective 1
Identification Claim Causes
Objective 2Claim settlement:
Analysis for additional cost
Analysis for additional time
Objective 2: Claim Analysis
Extension of time analysis
Delay time due to owner
Delay time due to contractor
Method analysis: As-planned versus As-built, Global claim
Additional cost analysis
Direct cost
Indirect cost
Data Analysis
Delay analysis issues
In six building projects, there are not data actual resource usage and monthly update.
Float ownership: “Who owns float?”
Concurrent delay
Logic change (Hard VS Soft logic)
Resource allocation due to delay or logic changes
Data Analysis
Additional cost analysis
Direct cost: cost of additional works out side contract Material, equipment and labor cost Unit price is applied as unit price in contract or update due to price
fluctuation Quantity is noticed and submitted during construction stage and
approved by the engineers of owner.
Indirect cost: do not estimate through 6 cases Overhead cost (site and office overhead cost) Financial cost However: they are not compensated by owner.
Data Analysis
Bad Strategy of Contractor to deal with indirect cost
Construction law VS Tender law about definition of main contractor and subcontractor obligation. Thus:
Change subcontractors which were not written in bidding document.
Cannot manage delay, quality and cost.
Subcontractors are small and local contractors with old equipment, unskilled labors (farmers) and lack managers or engineers to decrease indirect cost when the project is delayed too long.
Just in time to delivery material and equipment. No warehouse cost.
Site office
Local labors
Local equipment
Data Analysis
Some issues of claim analysis are found through six building projects.
Tools to monitor and control delay and cost overrun are not used: CPM: use & update Earn value concept Assessment of cost control systems (Chotchai Charoenngam, 2001)
Construction Law, Tender Law Some clauses are contradiction together Contract is not managed effectively. Unclear claim procedure (specially, delay analysis method) Contracts are not strong constraints. Owners cannot force contractor to use
equipment and labors which have good quality as bidding document.
Human resource Lack project managers. Cooperation is not used to allocate risk and mitigate claim: passive to deal
claim events, extend time to approve claim procedures.
Data Analysis
Thank you!
5/2010
Nguyen Van Tam