NGN Connections Update Mar 2009

8
NGN Connections Update Mar 2009 Delivering Utility Solutions

description

Delivering Utility Solutions. NGN Connections Update Mar 2009. Customer. GSOS- last 3 months. Complaints February 2009. Scheduling. Work Basket. - PowerPoint PPT Presentation

Transcript of NGN Connections Update Mar 2009

Page 1: NGN Connections Update Mar 2009

NGN Connections Update Mar 2009

Delivering Utility Solutions

Page 2: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

CustomerGSOS- last 3 months

GSOS 9/10 YTD

84.00%

86.00%

88.00%

90.00%

92.00%

94.00%

96.00%

98.00%

100.00%

Nov Dec J an Feb Mar

Month

%

GSOS9

GSOS10

GSOS 11

75.00%

80.00%

85.00%

90.00%

95.00%

100.00%

Nov Dec Jan Feb

Month

%

GSOS 11 Overall

<=£1000

<=£4000

<=£20000

<=£50000

Page 3: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

Complaints February 2009

Reason BBUS NGN UUN Total

Missed Appointment 9     9

Lack of Communication 7 1 8

Quality of Service Provided – Scheduling 5   5

Quality of Service Provided – Operations 2   2

Compensation – Liquidated Damages Claim 1   1

Dispute with Contract Terms   1   1

Dispute with Quotation Price   1   1

Failed Site Visit 1   1

General   1 1

Quality of Service Provided   1 1

Reinstatement Delays 1     1

Grand Total 26 2 3 31

Page 4: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

SchedulingJob Acceptances Received 2008 vs 2009

Week 2009 2008 Downturn

w.c. 5.1.09 99 140 29%

w.c. 12.1.09 99 159 38%

w.c. 19.1.09 126 181 30%

w.c. 26.1.09 101 145 30%

w.c. 2.2.09 106 163 35%

w.c. 9.2.09 117 132 11%

w.c. 16.2.09 118 153 23%

w.c. 23.2.09 80 132 39%

w.c. 2.3.09 127 121 -5%

w.c. 9.3.09 105 144 27%

w.c. 16.3.09 142 195 27%

w.c. 23.3.09 93 131 29%

Work BasketJob Acceptances Received 2008 vs 2009

0

50

100

150

200

250

Week

No.

-10%

-5%

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

%

2009

2008

% Downturn in Workload

Page 5: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

Work Basket Available to Plan

0

100

200

300

400

500

600

700

800

900

Week

No.

-120%

-100%

-80%

-60%

-40%

-20%

0%

20%

40%

60%

80%

%

Work Basket Available to Plan2009

Work Basket Available to Plan2008

Work Basket Available to Plan% Downturn in Workload

Work Basket Available to Plan

Week2009

2008

% Downturn in Workload

w.c. 5.1.09 242 398 39%

w.c. 12.1.09 178 438 59%

w.c. 19.1.09 242 455 47%

w.c. 26.1.09 272 303 10%

w.c. 2.2.09 365 309 -15%

w.c. 9.2.09 314 282 -11%

w.c. 16.2.09 327 348 6%

w.c.23.2.09 325 325 0%

w.c. 2.3.09 462 452 -1%

w.c. 9.3.09 293 475 38%

w.c. 16.3.09 584 367 -59%

w.c. 23.3.09 828 404 -105%

Page 6: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

Leadtimes

BBUS North- 4 weeks BBUS South- 5 weeksEnterprise West- 6 weeks

Scheduling Targets

BBUS North- 2.2 jobs per day/£7700 per week BBUS South- 1.5 jobs per day/£5250

Current Team NumbersWest- 4 teamsSouth- 14 teamsNorth- 8 teams

Page 7: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

Lifetime of Excavation

Page 8: NGN Connections Update Mar 2009

Delivering Utility Solutions

Oct 2007 Version 1.0

Streetworks

FPN’s received January- 0

Defects Outstanding- BBUS North East- 15, BBUS Cumbria- 87, BBUS South- 6, Morgan Est-5, Enterprise- 62