NFPA 241 Implementation
Presented by:Peter Harrod, P.E.Jeremy Souza
![Page 2: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/2.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Learning Objectives
• Scoping and Purpose
• At what project milestones is the property owner’s involvement necessary?
• Who is responsible for documentation and when/to whom is it submitted?
• FPPM, CPM, GC, and Subcontractor
• What are the Contents of the GC’s Project-Level NFPA 241 Plan?
• NFPA 241 Implementation and Inspections
• Common Challenges
62
![Page 3: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/3.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Who is Code Red Consultants?
▪ Fire Protection / Life Safety Code Consulting Firm▪ Building Code Consulting▪ Performance Based Design▪ Construction Site Safety Planning & Impairment Plans▪ Design of Tier 1 “make-safe” sprinkler/fire alarm▪ Special Inspection Services on Smoke Control and
Firestopping
▪ Independently owned and operated
▪ Currently 20 engineers with Masters Degree in FPE; 12 PE’s
▪ Code Blog at WWW.CRCFIRE.COM▪ REGISTER TO RECEIVE AUTOMATIC EMAILS
63
![Page 4: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/4.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Why do I need to Concern Myself?
64
![Page 5: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/5.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Why do I need to Concern Myself?
65
![Page 6: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/6.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Why do I need to Concern Myself?
66
![Page 7: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/7.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241, as referenced by 527CMR
67
![Page 8: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/8.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241, as referenced by 527CMR
68
![Page 9: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/9.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Why do I need to Concern Myself?
69
![Page 10: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/10.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241, as referenced by RI Fire Safety Code (Section 7)
70
![Page 11: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/11.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
71
• Maintain construction site fire safety
• Establish safe/adequate access for FD operations
• Outline manner in which FP/egress systems will be maintained/impaired during a renovation/alteration
• Protect abutting buildings or occupied areas during continued construction
Why its Required
![Page 12: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/12.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
How does this get implemented on site?
![Page 13: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/13.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• The Owner shall designate a person responsible for the fire prevention program and who shall ensure that it is carrier out to completion (NFPA 241, 7.2). Fire Prevention Program Manager
• New Construction• Ideally, Owner assigned, full time individual
• Often it’s GC’s FPPM
• In either case, on site full time
• Existing Building• Owners FPPM and/or Impairment Coordinator; and
• GC’s FPPM
• In either case, on site full time
How does this get implemented on site?
![Page 14: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/14.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• The Owner shall designate a person responsible for the fire prevention program and who shall ensure that it is carrier out to completion (NFPA 241, 7.2). Fire Prevention Program Manager
• New Construction• Ideally, Owner assigned, full time individual
• Often it’s GC’s FPPM
• In either case, on site full time
• Existing Building• Owners FPPM and/or Impairment Coordinator; and
• GC’s FPPM
• In either case, on site full time
How does this get implemented on site?
![Page 15: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/15.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• The Owner shall designate a person responsible for the fire prevention program and who shall ensure that it is carrier out to completion (NFPA 241, 7.2). Fire Prevention Program Manager
• New Construction• Ideally, Owner assigned, full time individual
• Often it’s GC’s FPPM
• In either case, on site full time
• Existing Building• Owners FPPM and/or Impairment Coordinator; and
• GC’s FPPM
• In either case, on site full time
How does this get implemented on site?
![Page 16: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/16.jpg)
• Impairment Plan (IP) does not equal an NFPA 241 Plan.• An NFPA 241 Plan is comprehensive to all fire safety
• No sprinkler/fire alarm alteration scope? Sorry, NFPA 241 Plan still req’d
• Rather, the IP is an appendix to the 241. Needed when:• Disabling of fire alarm systems or devices;
• Planned shutdowns of portions of fire protection systems
• Modifying means of egress or smoke control arrangement;
• No impairment work should commence until a permit is in hand.
Haven’t We Been Doing This For Years?
76
![Page 17: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/17.jpg)
Who Are The Stakeholders?
Ownership
GC(s)
3rd Party FPE
FD
Building Department
Subs
77
![Page 18: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/18.jpg)
WHEN DOES 241 DOCUMENTATION NEED TO BE FILED?
78
![Page 19: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/19.jpg)
• Whenever a building permit is secured.
• Whenever an impairment is needed.
• Whenever means of egress is altered.
• When requested by the AHJ.
In all cases, the level of detail depends on project complexity
WHEN DOES 241 DOCUMENTATION NEED TO BE FILED?
79
![Page 20: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/20.jpg)
• Whenever a building permit is secured.
• Whenever an impairment is needed.
• Whenever means of egress is altered.
• When requested by the AHJ.
In all cases, the level of detail depends on project complexity
WHEN DOES 241 DOCUMENTATION NEED TO BE FILED?
80
![Page 21: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/21.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Application to Campus Building/Renovation Campaign
Building Owner’s 241
Plan
GC#1 T.I. Project 241
F/A Sub Impairment Plan
Sprinkler Sub Impairment Plan
Means of Egress Impairment Plan
General Contractors Project 241 – New
Construction T
IME
OF
PE
RM
IT
AF
TE
R T
CO
81
![Page 22: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/22.jpg)
DOCUMENTATION ISSUANCE TIMELINESCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
82
![Page 23: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/23.jpg)
DOCUMENTATION ISSUANCE TIMELINESCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
83
![Page 24: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/24.jpg)
DOCUMENTATION ISSUANCE TIMELINESCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
84
![Page 25: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/25.jpg)
DOCUMENTATION ISSUANCE TIMELINESCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
85
![Page 26: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/26.jpg)
Documentation Issuance Timeline
SCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
CAMPUS MASTER NFPA 241 PROGRAM
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
86
![Page 27: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/27.jpg)
Documentation Issuance Timeline
SCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
CAMPUS MASTER NFPA 241 PROGRAM
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
87
![Page 28: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/28.jpg)
Documentation Issuance Timeline
SCHEDULE OF DOCUMENTATION ISSUANCE TO AHJ
CAMPUS MASTER NFPA 241 PROGRAM
MASTER BUILDING NFPA 241 PROGRAM
GC NFPA 241 PLAN
TENANT IMPROVEMENT BLD PERMIT APPLICATION
SUB IMPAIRMENT PLAN
F/A ALTERATION PERMIT
88
![Page 29: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/29.jpg)
• FPPM and/or 3rd party will develop a Master 241 Program
• Per building/address, develop a means to address FD’s concerns re: impairment coordination
• Serve as internal Permit Authorizing Individual (PAI)– Ensure FD permits in hand
– Authorize hot work and impairments in building, consistent with FD permits, based on other work conducted
• Liaise with GC to ensure that GC’s Project Level 241 Plan is created, references Master 241 Program, and letter of recognition is sent as cover.
ROLE OF THE OWNER’S FIRE PROTECTION PROGRAM MANAGER
89
![Page 30: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/30.jpg)
• GC’s PM/FPPM and/or 3rd party will develop the 241 Plan
• Submit 241 Plan to CPM and Building FPPM for review
• Identify FPPM to be available on site to ensure implementation– Daily inspections
– Hot work, fire watch, impairments, CO logs
– Make necessary updates to logistics/narrative
• Host FD/ISD/CPM for site visits and address concerns
• emergency
ROLE OF THE GC’S FIRE PROTECTION PLANMANAGER
90
![Page 31: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/31.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Pre-Incident Fire Plan
• Control of ignition sources and combustibles
• Roles and responsibilities of personnel
• Drawings depicting construction areas, temporary life safety measures, etc…
• Self Inspection Forms and Daily Logs
In all cases, the level of detail depends on project complexity
What's in the GC’s plan?
91
![Page 32: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/32.jpg)
CONTENTS OF THE GC’S 241 PLAN• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
92
![Page 33: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/33.jpg)
CONTENTS OF THE GC’S 241 PLAN• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
93
![Page 34: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/34.jpg)
CONTENTS OF THE GC’S 241 PLAN• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
94
![Page 35: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/35.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
95
![Page 36: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/36.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
96
![Page 37: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/37.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
97
![Page 38: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/38.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
98
![Page 39: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/39.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
99
![Page 40: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/40.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
100
![Page 41: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/41.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
101
![Page 42: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/42.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
102
![Page 43: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/43.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
103
![Page 44: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/44.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
104
![Page 45: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/45.jpg)
• Signature Page
• Stacking Diagram/Executive Summary
• Hazardous Operations
• Features of Fire Protection
• Fire Department Turnout Information
• Logs and Inspection Forms
• Impairments
• Typical floor plan with horns and FE’s
CONTENTS OF THE GC’S 241 PLAN
105
![Page 46: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/46.jpg)
• Fire Alarm System permit applications
• Fire Suppression System permit applications
• Temporary heat detection
• Impairment process
NFPA 241 Coordination
106
![Page 47: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/47.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 IMPLEMENTATION – A LIVING, BREATHING DOCUMENT
113
![Page 48: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/48.jpg)
What to Identify on the Pre-Incident Plan
114
![Page 49: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/49.jpg)
What to Identify on the Pre-Incident Plan
115
![Page 50: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/50.jpg)
What to Identify on the Pre-Incident Plan
116
![Page 51: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/51.jpg)
What to Identify on the Pre-Incident Plan
117
![Page 52: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/52.jpg)
What to Identify on the Pre-Incident Plan
118
![Page 53: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/53.jpg)
What to Identify on the Pre-Incident Plan
119
![Page 54: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/54.jpg)
What to Identify on the Pre-Incident Plan
120
![Page 55: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/55.jpg)
What to Identify on the Pre-Incident Plan
121
![Page 56: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/56.jpg)
What to Identify on the Pre-Incident Plan
122
![Page 57: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/57.jpg)
What to Identify on the Pre-Incident Plan
123
![Page 58: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/58.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Knowledge Transfer to Subs• FD inspections are unannounced
• All workers should be able to at least answer the following:• Who is the project FPPM?
• Who is the owners FPPM?
• Where is the 241 plan kept?
• Where is the hot work white board?• Must be active and accurate
• Where are the impairment and hot work permits?• Must be active and accurate
124
![Page 59: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/59.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Field Offices
• Temporary trailers• Required separation distance from adjacent buildings and bldg. under
construction
• Stacked trailers may require sprinkler protection
• Shanties inside building• Local smoke detectors, FRT including door, extinguisher, no combustible
insulation or flammable liquid storage
• Daily inspections by FPPM requires keys to shanties
• No TCO generally permitted with shanties in building
125
![Page 60: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/60.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
126
![Page 61: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/61.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Stairs• Code compliant 7x11 stair must extend to not more than 1
floor below the cured deck (not turned over floor). this includes compliant landings. This is for emergency evacpurposes and right out of 241. The stair can be temporary as necessary.
• Signage must remain at each stair floor landing, even when painting; suggest tying/chaining to standpipe if necessary. Include floor number, exit signage, and evac maps that illustrate current exit arrangement.
• Fire extinguishers and air horns mounted at stairs.
127
![Page 62: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/62.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Stairs• Code compliant 7x11 stair must extend to not more than 1
floor below the cured deck (not turned over floor). this includes compliant landings. This is for emergency evacpurposes and right out of 241. The stair can be temporary as necessary.
• Signage must remain at each stair floor landing, even when painting; suggest tying/chaining to standpipe if necessary. Include floor number, exit signage, and evac maps that illustrate current exit arrangement.
• Fire extinguishers and air horns mounted at stairs.
128
![Page 63: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/63.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Stairs• Code compliant 7x11 stair must extend to not more than 1
floor below the cured deck (not turned over floor). this includes compliant landings. This is for emergency evacpurposes and right out of 241. The stair can be temporary as necessary.
• Signage must remain at each stair floor landing, even when painting; suggest tying/chaining to standpipe if necessary. Include floor number, exit signage, and evac maps that illustrate current exit arrangement.
• Fire extinguishers and air horns mounted at stairs.
129
![Page 64: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/64.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Stairs• Code compliant 7x11 stair must extend to not more than 1
floor below the cured deck (not turned over floor). this includes compliant landings. This is for emergency evacpurposes and right out of 241. The stair can be temporary as necessary.
• Signage must remain at each stair floor landing, even when painting; suggest tying/chaining to standpipe if necessary. Include floor number, exit signage, and evac maps that illustrate current exit arrangement.
• Fire extinguishers and air horns mounted at stairs.
130
![Page 65: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/65.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Stairs• Code compliant 7x11 stair must extend to not more than 1
floor below the cured deck (not turned over floor). this includes compliant landings. This is for emergency evacpurposes and right out of 241. The stair can be temporary as necessary.
• Signage must remain at each stair floor landing, even when painting; suggest tying/chaining to standpipe if necessary. Include floor number, exit signage, and evac maps that illustrate current exit arrangement.
• Fire extinguishers and air horns mounted at stairs.
131
![Page 66: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/66.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
132
![Page 67: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/67.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
133
![Page 68: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/68.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
134
![Page 69: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/69.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
135
![Page 70: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/70.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
136
![Page 71: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/71.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
137
![Page 72: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/72.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
138
![Page 73: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/73.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Construction Standpipes
• Temporary standpipe should be available when floor level of cured (or walkable) working deck is 30-feet above lowest FD access.
• Standpipe should climb to 1 floor below the cured (or walkable) deck (not to be confused with the lowest “turned over floor”).
• Make sure signage is provided at FDC, with required pumping pressure indicated on the sign.
• Free and unobstructed access to FDC
139
![Page 74: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/74.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Construction Operations• Waste Removal
• Dumpster permit/Trash Chute
• Combustible materials removed from site daily, should not be more than 1 days worth of debris at any point
• FPPM and staff monitors regularly, daily review of egress paths
• Dumpster location required to be outside the building unless you get special permission
140
![Page 75: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/75.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
General Storage for Fuel• Flammable Gas Storage
• Need for Fuel Storage Permit – check with AHJ• Include material such as:
• O2, Acetylene, gas/diesel, propane
• Fuel for temp heat
• Fuel for equipment stored inside the building
• Preincident site plan with accurate primary/secondary location
• 1-hour stalls or inside storage requires special permission and letter from an FPE
141
![Page 76: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/76.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
General Storage for Fuel• Flammable Gas Storage
• Need for Fuel Storage Permit – check with AHJ• Include material such as:
• O2, Acetylene, gas/diesel, propane
• Fuel for temp heat
• Fuel for equipment stored inside the building
• Preincident site plan with accurate primary/secondary location
• 1-hour stalls or inside storage requires special permission and letter from an FPE
142
![Page 77: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/77.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
General Storage for Fuel• Flammable Gas Storage
• Need for Fuel Storage Permit – check with AHJ• Include material such as:
• O2, Acetylene, gas/diesel, propane
• Fuel for temp heat
• Fuel for equipment stored inside the building
• Preincident site plan with accurate primary/secondary location
• 1-hour stalls or inside storage requires special permission and letter from an FPE
143
![Page 78: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/78.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Documenting Hot Work
144
![Page 79: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/79.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Documenting Hot Work• White board / logs updated daily prior to work• Records to be kept on site
• FPPM reviews and files the paperwork• Can be in 241 binder at approved location or in a separate binder in the field
office if outlined in 241 plan• Person performing hot work submits paperwork to FPPM at the end of
the shift
• Dedicated fire watch must remain present at hotwork site for 30 min after completion (even at lunch/break; provide relief as necessary).
• If sparks impact adjacent buildings, FD detail likely required to protect that property owner. District chief should be made aware of hazard for review.
145
![Page 80: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/80.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Documenting Hot Work• White board / logs updated daily prior to work• Records to be kept on site
• FPPM reviews and files the paperwork• Can be in 241 binder at approved location or in a separate binder in the field
office if outlined in 241 plan• Person performing hot work submits paperwork to FPPM at the end of
the shift
• Dedicated fire watch must remain present at hotwork site for 30 min after completion (even at lunch/break; provide relief as necessary).
• If sparks impact adjacent buildings, FD detail likely required to protect that property owner. District chief should be made aware of hazard for review.
146
![Page 81: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/81.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
241 Implementation- Sample Fire Watch and Hot Work Logs
147
![Page 82: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/82.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Sample Inspection Form
148
![Page 83: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/83.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Accepted Fire protection, alarm, smoke control systems• Once FD accepts these, they must remain active or an
impairment permit must be sought.
• Disabling/bagging of SD’s after FD f/a acceptance requires bagging permit; note number of floors needed prior to occupancy
• Fire pumps must remain on once accepted.
149
![Page 84: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/84.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Accepted Fire protection, alarm, smoke control systems• Once FD accepts these, they must remain active or an
impairment permit must be sought.
• Disabling/bagging of SD’s after FD f/a acceptance requires bagging permit; note number of floors needed prior to occupancy
• Fire pumps must remain on once accepted.
150
![Page 85: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/85.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Accepted Fire protection, alarm, smoke control systems• Once FD accepts these, they must remain active or an
impairment permit must be sought.
• Disabling/bagging of SD’s after FD f/a acceptance requires bagging permit; note number of floors needed prior to occupancy
• Fire pumps must remain on once accepted.
151
![Page 86: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/86.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
NFPA 241 Lessons Learned over Past 12 Months
• Accepted Fire protection, alarm, smoke control systems• Once FD accepts these, they must remain active or an
impairment permit must be sought.
• Disabling/bagging of SD’s after FD f/a acceptance requires bagging permit; note number of floors needed prior to occupancy
• Fire pumps must remain on once accepted.
152
![Page 87: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/87.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
153
![Page 88: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/88.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
154
![Page 89: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/89.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Sprinklers• Impairment permit needed
• New impairment submittals coordinated with 241 plan via letter of joint acknowledgment
• Upturned heads or tiles replaced at the end of the shift
• Impairments longer than 8 hours need heat detection in space that is impaired• Temp heat detection requires alteration permit
• Prolonged impairments without sprinkler or fire alarm separated from occupied building with 1 hour separation
241 Implementation- Fire Protection During Construction
155
![Page 90: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/90.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Sprinklers• Impairment permit needed
• New impairment submittals coordinated with 241 plan via letter of joint acknowledgment
• Upturned heads or tiles replaced at the end of the shift
• Impairments longer than 8 hours need heat detection in space that is impaired• Temp heat detection requires alteration permit
• Prolonged impairments without sprinkler or fire alarm separated from occupied building with 1 hour separation
241 Implementation- Fire Protection During Construction
156
![Page 91: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/91.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Sprinklers• Impairment permit needed
• New impairment submittals coordinated with 241 plan via letter of joint acknowledgment
• Upturned heads or tiles replaced at the end of the shift
• Impairments longer than 8 hours need heat detection in space that is impaired• Temp heat detection requires alteration permit
• Prolonged impairments without sprinkler or fire alarm separated from occupied building with 1 hour separation
241 Implementation- Fire Protection During Construction
157
![Page 92: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/92.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENT
Code compliant in
reflected ceiling
Existing Condition
158
![Page 93: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/93.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENT
Code compliant without
reflected ceiling (within 12” in
pendant position)
Ceilings removed during
construction
159
![Page 94: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/94.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENT
Non-code compliant (not within
12” of ceiling). Compliant
alternative required
Ceilings removed during
construction
160
> 12”
![Page 95: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/95.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENT
Code compliant without
reflected ceiling (within 12” in
upright position)
Ceilings removed during
construction
161
![Page 96: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/96.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENT
Sprinkler system removed with
temporary heat detection and
1-hour wall installed
Ceilings removed during
construction
162
![Page 97: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/97.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENTCeilings installed for finished
condition
Code compliant without
reflected ceiling (within 12” in
upright position)
163
![Page 98: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/98.jpg)
REMOVAL OF CEILINGS WITHOUT SPRINKLER IMPAIRMENTCeilings installed for finished
condition
Sprinklers downturned into
reflected ceiling (>12”) with
temporary heat detection
installed
164
![Page 99: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/99.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Required for FP Impairments > 8 hours
• Need to determine early on if temporary detection is required• Work with institution to potentially award this work early under
separate F/A permit.
• Also consider including any a/v or sd devices that want to be demo’d during construction.
Temporary Heat Detection
165
![Page 100: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/100.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
• Required for FP Impairments > 8 hours
• Need to determine early on if temporary detection is required• Work with institution to potentially award this work early under
separate F/A permit.
• Also consider including any a/v or sd devices that want to be demo’d during construction.
Temporary Heat Detection
166
![Page 101: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/101.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
167
![Page 102: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/102.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
168
![Page 103: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/103.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIRSMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
169
![Page 104: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/104.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIRSMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
170
![Page 105: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/105.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
171
![Page 106: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/106.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
172
![Page 107: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/107.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
173
![Page 108: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/108.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
174
![Page 109: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/109.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
175
![Page 110: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/110.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
176
![Page 111: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/111.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
177
![Page 112: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/112.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
178
![Page 113: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/113.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
179
![Page 114: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/114.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
180
![Page 115: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/115.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
181
![Page 116: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/116.jpg)
• REMOVAL OF CEILINGS W/OUT SPRINKLER IMPAIRMENT
• BAGGING OF ELEV LOBBY OR STAIR SMOKE DETECTORS
• FIRE EXTINGUISHERS ON STANDS
• IMPEDIMENTS TO EGRESS PATHWAYS
• PEGGING OF DOORS
• HOT WORKS OCCURING WITHOUT FIRE WATCH
• MAINTANING STANDPIPE UNOBSTRUCTED WITH SIGNAGE AND IN GOOD CONDITION
• HOUSEKEEPING
COMMON CHALLENGES
182
![Page 117: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/117.jpg)
• Flex heads not properly secured
• Debris removal – dedicated manpower and infrastructure access
• Updated 241 plans required
– Expected at each new sprinkler fire alarm permit application
• Implementation and site audits
• Maintenance of FD access, including roads and adjacent building FDC’s
NFPA 241 LESSONS LEARNED OVER PAST 12 MONTHS
183
![Page 118: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/118.jpg)
• Flex heads not properly secured
• Debris removal – dedicated manpower and infrastructure access
• Updated 241 plans required
– Expected at each new sprinkler fire alarm permit application
• Implementation and site audits
• Maintenance of FD access, including roads and adjacent building FDC’s
NFPA 241 LESSONS LEARNED OVER PAST 12 MONTHS
184
![Page 119: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/119.jpg)
• Flex heads not properly secured
• Debris removal – dedicated manpower and infrastructure access
• Updated 241 plans required
– Expected at each new sprinkler fire alarm permit application
• Implementation and site audits
• Maintenance of FD access, including roads and adjacent building FDC’s
NFPA 241 LESSONS LEARNED OVER PAST 12 MONTHS
185
![Page 120: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/120.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Questions?
Peter Harrod, P.E.
Code Red Consultants, LLC
186
![Page 121: NFPA 241 Implementation - buildingsaferinri.orgbuildingsaferinri.org/wp-content/uploads/2019/06/NFPA241CodeRed-1.pdf · 85. Documentation Issuance Timeline SCHEDULE OF DOCUMENTATION](https://reader030.fdocuments.us/reader030/viewer/2022040821/5e6aa7988f246b35fa5183f1/html5/thumbnails/121.jpg)
©2019 Code Red Consultants, LLC. All Rights Reserved
Copyright Materials
This presentation is protected by US and International copyright laws. Reproduction, distribution, display
and use of the presentation without written permission of the speakers is prohibited.
© Code Red Consultants, LLC 2019