A New Utility Scale Solar Inverter and Wiring Topology
Peter GerhardingerChief Technology OfficerNextronex Energy Systems4400 Moline Martin RdMillbury Ohio [email protected]
May 18, 2010
Roger King, Ph.D.Professor, Electrical EngineeringUniversity of Toledo M.S. 3082801 W. Bancroft St.Toledo Ohio [email protected]
![Page 2: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/2.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
• Nextronex Energy Systems, LLC
• Formed June 2008
• Initial Offering Closed November 2009
• 2nd Round currently Open
• Over $ 2 MM invested to date
• Inverter System received UL 1741 Certification June 2010
• First Installation May – July 2010 (399 kW, OANG Site)
• Two utility patents (and related foreign filings) pending
• Over 6 MW sold to date
![Page 3: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/3.jpg)
Solar Inverters – Technical Approaches
• (Insert Inverter Matrix Slide here)
![Page 4: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/4.jpg)
Nextronex Field
• (Photo of Nextronex Field Here)
![Page 5: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/5.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
• Nextronex has developed a unique kit of parts
containing everything needed from the string
wiring to the utility connection
• Low Profile 150 kW inverters
• Smart Controller
• Zone Boxes with Telemetry
• Power Strip(s)
• Load Center(s)
• All components UL listed for operation up to
1000 V dc
• Best-in-class 98 % + peak efficiency
• Distributed Architecture (M/S Switching)
![Page 6: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/6.jpg)
PV Plant Loss Factors (exclusive of panels)
1. DC Wiring Losses, 2 % nominal Could be as high
Defects as 15 %
2. Equipment Efficiency 2 % nominal 2 % nominal
and Reliability
3. Low Light Level 1 % - 3 % depending 1 % - 3 % depending
Energy Harvesting on climate on climate
4. Operation and – –
Maintenance Issues
% Improvement 5 % - 8 % Up to 20 %
% Improvement
from Model
% Improvement
from Actual Installations
![Page 7: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/7.jpg)
The DC Wiring Problem
• The DC collection system
represents a significant investment
in wire, connectors, and labor
• Problems are difficult to diagnose,
especially after commissioning
• Large variability if rows are long,
with many home runs (DC loss
increases with wire length)
• Commonly accepted 2% drop is
excessive for solar applications
![Page 8: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/8.jpg)
The DC Wiring Problem
This is what you want to avoid
![Page 9: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/9.jpg)
The DC Wiring Problem
• Installed Cost is proportional to Cu weight
• Operating Cost is proportional to CU loss
• Three Approaches:
- Constant area (CA) and constant V drop (CVD) have identical
power less, while proportional area has 25 % less loss.
- Proportional Area (PA) has the lowest power drop but the largest
variation in voltage drop.
Constant Area (CA) Proportional Area (PA) Constant V drop (CVD)
![Page 10: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/10.jpg)
The DC Wiring Problem
• Conclusions:
• Volume of Cu needed is proportional to the square of the total current,
and the square of the linear dimensions
• For all cases, total power loss and voltage drop are inversely
proportional to the conductor volume
• Tapping the collection bus in the center results in 4x less copper volume
than tapping at and end point
-
-
Constant Area (CA) Proportional Area (PA) Constant V drop (CVD)
![Page 11: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/11.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
Voltage Drop with Center Inverter Cluster
![Page 12: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/12.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
Voltage Drop with Perimeter Inverter
![Page 13: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/13.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
Voltage Drop with Perimeter InverterVoltage Drop with Center Inverter Cluster
![Page 14: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/14.jpg)
The Nextronex Solution
• Distributed Architecture
• 1000 V DC System (minimize IR Drop
and use 40 % fewer home runs)
• Low Profile Components for central
array placement
• DC Bus (Power Strip) with Integral
Zone boxes for very low loss, easy to
install and service DC collection
system
• Ungrounded DC operation for best
safety (with differential GFD)
Single Line System
![Page 15: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/15.jpg)
Inverter Switching / Sequencing
• Before sunrise, the controller
chooses the lead inverter for the
day (rotated, based on run time)
• The lead inverter manages the
MPPT for that day, and the
remaining inverters are brought on-
line in slave mode as needed
• Ramp rate, step size, timing have
been worked out to insure accurate
MPPT, and to quickly respond to
cloud transients
![Page 16: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/16.jpg)
Inverter & System Efficiency
• The Ray-Max Inverter has a peak
efficiency of 98 %
• Using the Nextronex Switching
Algorithm, a 1 MW system with 6
inverters reaches peak efficiency at
3% (30 kW) output, and will begin to
export power at 650 W
• The companion Load Center has a
peak efficiency greater than 98 %,
giving a system efficiency of 96 %
![Page 17: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/17.jpg)
MPPT Performance
Clear day performance Cloudy day performance
![Page 18: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/18.jpg)
The Importance of Information
• Without data, it is impossible to keep a
solar array in top condition
• Overall Power and Energy Output can
be assessed against weather data
• String level monitoring to quickly
address faults and keep your panel
mfgr honest
• Inverter and Transformer data for
predictive maintenance
• Advanced telemetry for timely updates
and remote monitoring
![Page 19: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/19.jpg)
Operation and Maintenance
• Distributed Architecture for Fault Tolerance
and Reliability
• Modular Inverter Design – Replace Core
Inverter in 30 Minutes without shutting
system down
• Smart Controller provides the centralized
control, data, and telemetry point to monitor
system performance and respond to faults
and alarms
• Zone level monitoring and switching to
isolate problem strings for servicing without
shutting system down
![Page 20: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/20.jpg)
The Smart Grid
• Utilities will need to control the output parameters of a solar
array if the promise of the “smart grid” is to be realized
• Curtailment to protect distribution and transmission lines
• VAR and Power Factor Correction
• Phase imbalance and brownout correction
• Shut-down verification for safety of line personnel
• The Nextronex Smart Controller provides the communication
point and our inverters are programmed to respond to
external commands
![Page 21: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/21.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
Questions?
![Page 22: Next105 Ases Power Point Presentation Internal Final](https://reader033.fdocuments.us/reader033/viewer/2022051616/557c9222d8b42a41498b47bb/html5/thumbnails/22.jpg)
A New Utility Scale Solar Inverter and Wiring Topology
Thank you