NEXT-100 Pressure Vessel, Nov. 1, 2011

20
NEXT-100 Pressure Vessel, Nov. 1, 2011 D. Shuman, S. Carcel Lawrence Berkeley National Laboratory November 2, 2011 D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 1 / 20

Transcript of NEXT-100 Pressure Vessel, Nov. 1, 2011

Page 1: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel, Nov. 1, 2011

D. Shuman, S. Carcel

Lawrence Berkeley National Laboratory

November 2, 2011

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 1 / 20

Page 2: NEXT-100 Pressure Vessel, Nov. 1, 2011

Table of Contents1 NEXT-100 Pressure Vessel

Summary of Changes from CDRNEXT100 Pressure Vessel ParametersPressure VesselPressure Vessel Cross SectionCopper Shielding BarsField Cage InstalledPressure Vessel HeadsCarrier Plate Mounting DetailO-ring Leak Check PortDetector Overall Cross SectionMetal Gasket (Helicoflex) vs O-ringInterface Flange ConceptContracting Process, per ASMESpecial Conditions we add to UDRNext Steps

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 2 / 20

Page 3: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Summary of Changes from CDR

Vessel design simplified.3 parts instead of 4 - no service plateplain torispheric heads, both ends, PMTs inside

Vessel axis changed from vertical to horizontalreduces shielding heightgives room for axial expansion (cabling)cables and feedthroughs all above work platform

Vessel material changed to stainless steel, from titaniumNot confident radiopure Ti availableEven so, not confident vessel kept clean throughout mfr.High cost of Ti fab - limited mfrs, schedule riskStainless (304, 316) available in the few mBq/kg range, SO:

A copper liner (6 cm thk.) has been added to shield the higherbackground stainless steel

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 3 / 20

Page 4: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel NEXT100 Pressure Vessel Parameters

Parameter, (53 cm radius x 130 cm active vol.) qty unitsMaximum Operating Pressure (MOP) 15.0 bar (abs)Maximum Allowable Working pressure (MAWP) 16.4 bar (abs)Minimum Allowable Pressure (external 1.5 bar (abs)Inner diameter 124 cmOuter Diameter, Vessel 126 cmOuter Diameter, Flanges 134 cmLength, inside shielding 2.22 mLength, end to end, axial 2.85 mVessel and head wall thickness 10 mmFlange thickness, head to vessel (both) 3.0 cmBolt Diameter (Inconel 718), head to vessel flanges 14 mmBolt length, head to vessel flanges 9 cmNumber of Bolts, each head to vessel flange 120Mass, Vessel and both heads 1100 kgMass, Internal copper shielding (6 cm) 4700 kg

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 4 / 20

Page 5: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Pressure Vessel

Main Cylindrical VesselTorispheric Heads

Main Flanges

Shielding, External, Cu on Pb

Axial Nozzle

Aux. Nozzle

EL HV Port

EL Inspection Ports

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 5 / 20

Page 6: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Pressure Vessel Cross Section

Main Cylindrical VesselTorispheric Heads

Main Flanges

Axial Nozzle

Aux. Nozzle

EL HV Port

EL Inspection Ports

Internal Flanges ?

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 6 / 20

Page 7: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Copper Shielding Bars

Main Cylindrical Vessel

Cu Shield Bars, 40x 70 kg. ea.

Fastened at Internal FlangesSupported on Ends, low stress, no vessel contact

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 7 / 20

Page 8: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Copper Shielding Bars

Copper bars fastened to main cylindrical vessel internal flange

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 8 / 20

Page 9: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Field Cage Installed

Main Cylindrical Vessel

Shielding, External, Cu on Pb

EL HV F.T.

Cu Shield BarsF.C. Insulator

Field Cage RingsReflectors

EL mesh planesCathode

Buffer Field Cage Rings

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 9 / 20

Page 10: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Pressure Vessel Heads

Torispheric HeadsEnergy Plane, PMTs

Cu Shield

PMT FTs

Vac. Manifold

HV/Press. relief/Flow/Vac. PortsHV Cable

Shielding, External, Cu on Pb

Tracking Plane, SiPMCu Shield

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 10 / 20

Page 11: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Carrier Plate Mounting Detail

Shear LipVacuum O-ring

Pressure O-ringD. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 11 / 20

Page 12: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel O-ring Leak Check Port

Estimatedleakage <200 gm/year (butyl, nitrile O-rings) -recover in cold trap

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 12 / 20

Page 13: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Detector Overall Cross Section

Main Cylindrical VesselTorispheric Heads

Energy Plane, PMTsCu Shield

PMT FTs

Vac. Manifold

HV/Press. relief/Flow/Vac. PortsHV Cable Cu Shield Bars

F.C. InsulatorField Cage Rings

Reflectors

Shielding, External, Cu on Pb

EL mesh planes

EL HV F.T.Cathode Tracking Plane, SiPM

Cu Shield

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 13 / 20

Page 14: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Detector Overall Cross Section

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 14 / 20

Page 15: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Metal Gasket (Helicoflex) vs O-ring

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 15 / 20

Page 16: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Interface Flange Concept

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 16 / 20

Page 17: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Interface Flange Concept

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 17 / 20

Page 18: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Contracting Process, per ASME

We write: User Design Specification (UDS).Specifies our specific requirements, size, loads, operation, no.cycles, etc.Does not dictate thicknesses, etc. as mfr. is responsible forpressure integrityWe have a draft UDS written - needs drawings addedHowever - We also design vessel fully for our prior knowledge (nosurprises)

User Design Specification to be Certified (by Certifying Authority)Checks for completeness and correctness of UDSCertifying Authority must be ASME certifiedCertifying person must be Professional Engineer

Manufacturer writes: Manufacturer’s Design Report (MDR)has final dwgs., calculations, material and welder certs, testreports, etc

Manufacturer’s Deign Report to be Certified (by CertifyingAuthority)

Must be certified as correct by Professional Engineer- not same person as for UDR ( same firm OK)

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 18 / 20

Page 19: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Special Conditions we add to UDR

Full audit and inspection rights - in addition to official inspectorRadiopurity

Samples required for all material lots.Adequate time for testing - must coordinateWeld samples (from previously measured clean stock)Strict electrode and gun control - no thoriated allowed? ceriated, lanthanated, yttriated, zirconium OK?? Gas quality? (Ar), Electropolish?

Precision DimensionsFull solution anneal (1050-1120C) at various stages.Careful sequencing of fab steps to be subject to approval

Leak tightnessPlate stock for flanges to be leak checked , end samples, andas-cut ringsFull weld radiograph inspection (also minimizes req. thickness)Must pass vac. leak rate check after fab.

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 19 / 20

Page 20: NEXT-100 Pressure Vessel, Nov. 1, 2011

NEXT-100 Pressure Vessel Next Steps

Complete DRAFT UDS - update drawingsPass Draft to potential Manufacturers

Assess design details for manufacturabilityObtain a good cost and schedule estimate

Pass Draft to potential Certification AuthoritiesComplete our Design Analysis (supports, small flanges)Fine tune existing features

Size Nozzles for HVVerify or modify overall dimensions for Field Cage ?Nozzle and flanges design for Tracking Plane - CM or not?Internal mounting flange dimensions- mfr input

D. Shuman (LBNL) NEXT-100 Pressure Vessel, Nov. 1, 2011 November 2, 2011 20 / 20