NEW URGENT CARE CLINIC & EXTENSION SERVICE...
Transcript of NEW URGENT CARE CLINIC & EXTENSION SERVICE...
EMILY POOLE ARCHITECTURE, PLLC
HUMPHREYS COUNTY SHERRILL BUILDING RENOVATIONS:
NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICESHUMPHREYS COUNTY BOARD OF SUPERVISORSBELZONI, MISSISSIPPI
DRAWING INDEX
PROJECT LOCATION
PROJECT LOCATION
MECHANICAL
M1.0 MECHANICAL FLOOR PLAN
PLUMBING
P1.0 PLUMBING FLOOR PLANFP1.0 SPRINKLER SYSTEM RENOVATION
ELECTRICAL
E1.1 LIGHTING FLOOR PLANE1.2 ELECTRICAL FLOOR PLANE1.3 ELECTRICAL SERVICE ENTRANCE
FLOOR PLANE1.4 COMMUNICATION AND FIRE ALARM PLANE1.5 COMMUNICATIONS SERVICE ENTRANCE
CABLING PLAN
ARCHITECTURAL
A0.0 OVERALL SITE PLANA0.1 EXISTING BUILDING PLAN &
OVERALL PROPOSED BUILDING PLAN
EXTENSION SERVICES PLANS
A1.0 DEMOLITION PLANA1.1 FLOOR PLAN, FOUNDATION PLAN
PORCH SECTIONA1.2 FINISH SCHEDULE, DOOR SCHEDULE,
DOOR ELEVATIONSA1.3 REFLECTED CEILING PLANA1.4 INTERIOR ELEVATIONS, ADA TOILET
ELEVATIONS, GRAB BAR DETAILS
URGENT CARE CLINIC PLANS
A2.0 DEMOLITION PLANA2.1 FLOOR PLAN & WALL TYPESA2.2 FINISH SCHEDULE, DOOR SCHEDULE,
DOOR ELEVATIONS, WINDOW SCHEDULEA2.3 REFLECTED CEILING PLANA2.4 INTERIOR ELEVATIONS
CLASSROOM & FITNESS PLANS- ALTERNATE NO. 1
A3.1 FLOOR PLANA3.2 FINISH SCHEDULE, DOOR SCHEDULE,
DOOR ELEVATIONSA3.3 REFLECTED CEILING PLAN
WALKING TRACK PLANS- ALTERNATE NO. 2
A4.1 FLOOR PLAN & FINISH SCHEDULE
HUMPHREYS COUNTY BOARD OF SUPERVISORS
RICHARD "DICKIE" STEVENS, PRESIDENTJAMES BANKHEADWOODROW JOHNSONJERRY WOODROY BROOMFIELD
DESIGN TEAM
ARCHITECT ENGINEEREMILY POOLE ARCHITECTURE, PLLC GREY L. NEELY, JR., PE319 CALIFORNIA AVENUE 1136 ROSE CIRCLELELAND, MS 38756 CLARKSDALE, MS 38614(601) 597-2724 (662) 624-8452
PLAN DATE
APPLICABLE CODES
2006-ICC BUILDING CODE2006-ICC MECHANICAL CODE2006-ICC FUEL GAS CODE2006-ICC PLUMBING CODE2008-NEC ELECTRICAL CODE2006-ICC FIRE CODE2009-NFPA 101 LIFE SAFETY CODE
OCCUPANCY: B- BUSINESS
+/- 36'-9"
5' -
0"
REMOVE EXISTING CONCRETEFOR NEW 4" REINFORCEDCONC. SIDEWALK
5' -
0"
+/- 75'-0"NEW 4" REINFORCEDCONC. SIDEWALK
PROVIDE 6" SCH. 40 PVC BOOT @EA. DOWNSPOUT THRU SIDEWALK
NEW 4" REINFORCEDCONC. SIDEWALK
10' -
0"
8' - 2"
REPAIR GUTTER SYSTEMBEHIND PARRAPET WALL
REPAIR METAL WALL @ ENDOF GUTTER SYSTEM TO BEWATER TIGHT.
REPAIR ROOF LEAK INAPPROXIMATE LOCATION
EXISTING PARKINGTO BE RE-STRIPED
EXISTING PARKINGTO BE RE-STRIPED(FIRST 14 SPACES)
GEN.REMOVE EXISTINGRAMP
NEW COVERED PORCH
SLO
PE
SLOPESLOPE
CUT EXISTING SIDEWALK FORNEW RAMPS W/ 6" BACK CURB& NEW 4" REINFORCED CONC.SIDEWALK
6' - 6"6' - 6"
5' -
0"
SLO
PE
SLO
PE
6' -
6"6'
- 6"
5' -
0"
CUT EXISTING SIDEWALK FORNEW RAMPS W/ 6" BACK CURB& NEW 4" REINFORCED CONC.SIDEWALK
SLOPE
NEW HANDICAP PARKING SIGNTOP OF SIGN @ 60" ABOVEPARKING (PROVIDE 4)
EXISTING SIDEWALK EXISTING SIDEWALK
EX
ISTI
NG
SID
EW
ALK
TWO EXISTING TREES TO BEREMOVED BY THE COUNTY-CONTRACTOR TO SOD THISAREA ONLY
1:12
1:12
6" CURB
NEW H.C.PARKING SIGN
CUT EXISTINGSIDEWAL FOR NEWRAMP
NEW 4" REINFORCEDCONCRETE SIDEWALK
EXISTING SIDEWALK
1:12
AB
OV
E P
AR
KIN
G L
OT
SU
RFA
CE
5' -
0"
PARKING LOT SURFACE
TOP OF SIDEWALK
NEW 3,000 PSI 4"CONCRETE SIDEWALKW/ 6x6-10/10 W.W.M. @MID-DEPTH
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A0.0
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1" = 20'-0"1 OVERALL SITE PLAN
N
2 HANDICAP RAMP 1/2" = 1'-0"
3 NEW H.C. PARKING SIGN 1" = 1'-0"
4 SIDWALK SECTION
RE
F.
RE
F.
REF. ICE
HUMAN SERVICES DEPARTMENT HEALTH DEPARTMENT
NO WORK TO BEDONE IN THIS AREA
ALTERNATE NO. 1-CLASSROOM & FITNESS
NEW EXTENSION SERVICE OFFICE
A1.01
NEW CLINIC
ALTERNATE NO. 2
A2.01
NO WORK TO BEDONE IN THIS AREA
A3.11
A1.11
HUMAN SERVICES DEPARTMENT HEALTH DEPARTMENT
NO WORK TO BEDONE IN THIS AREA
NEW CORRIDOR, WALLS &RELATED DOORS SHALL BEINCLUDED IN THE BASE BID
BUILDINGELECTRICAL
ROOM
CORRIDOR121
CORRIDOR122
122C
122B
122A
A2.12
A3.11
SPRINKLERRISER
HB
HBHB
SPRINKLER231 231A
122D
122E
122F
NEW WALLS & RELATEDDOORS SHALL BE INCLUDED INALTERNATE NO. 2
NEW WALLS & RELATEDDOORS SHALL BE INCLUDED INALTERNATE NO. 2
WALKING TRACK300
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A0.1
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/16" = 1'-0"1 EXISTING BUILDING PLAN
1/16" = 1'-0"2 OVERALL PROPOSED BUILDING PLAN
123
4
REMOVE EXISTING WALL
REMOVE EXISTINGDOOR & FRAME
REMOVE FLOORING, BASE, GYPSUMBOARD, CEILING, LIGHTS, MECH
REMOVE EXISTINGWINDOW
REMOVE EXISTINGWINDOW
NE
W P
ER
IME
TER
OF
PR
OJE
CT
REMOVE EXISTING ELECTRICAL, LIGHTS,MECH, ETC. SEE MEP DRAWINGS FOR DETAILS
REMOVE EXISTING METALPANEL FROM WALL
REMOVE EXISTINGDOOR & FRAME
REMOVE EXISTINGDOOR & FRAME
REMOVE FLOORING, BASE, GYPSUMBOARD, CEILING, LIGHTS, MECH
REMOVE FLOORING, BASE, GYPSUMBOARD, CEILING, LIGHTS, MECH
EXISTING TO BE REMOVED
EXISTING TO REMAIN
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A1.0
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"1 EXTENSION DEMOLITION PLAN
-2 EXTENSION SERVICE DEMO LEGEND
RE
F.
RE
F.
RECEPTIONIST101
DIRECTOR'SOFFICE
102
COPY/STORAGE103
CORRIDOR104
HVAC105
STORAGE106
MEETING ROOM107
JANITOR108
CONFERENCE109
OFFICE110
OFFICE111
CORRIDOR112
BREAK113
MEN114
WOMEN115
HVAC116
ELEC./COMM.117
OFFICE118
CORRIDOR120
OFFICE119
101A
104A
107A
105A
106A119A
118A
107B
108A
109A
116A
117A
115A
114A
111A110A
113A
CORRIDOR121
A1.32
A1.3
3
A1.41
A
2
B
A1.4 6
F
5 E
4
D
A1.4
3 C
A1.4 7
G
A1.48
H
9 I
A1.4 10
J
A1.4 10
J
A1.12
8' - 2"
A1.411
A1.14
A2.410
T
A2.411
U
A2.48
R
102A103A
122D
III
I
III
III
III
I
I
I
I
I
I I
I
14' -
0"
3A1.1
A1.14
NO. 4 DOWELL@ 16" O.C. W/SLEEVE
1' - 0"
1' -
0" 4"
1' -
6"
2' - 8"
1/2" EXPANSIONJOINT
SLOPE 1 "
6x6x-10/10W.W.M. FLATMATT
12"x12" TURN-DOWNFOOTING W/ (2) NO. 4REBAR CONT. W/ NO. 4TIES @ 24" O.C.
32"x24" SPOT FOOTING W/(3) NO. 4 REBAR EA. WAY
METAL WALL PANEL
2x4 WOOD STUD@ 16" O.C.
METAL WALL CAP
2x4 WOOD CLG.JOIST @ 24" O.C.
METAL CEILING PANEL
METAL WALL PANEL
2x12 FLITCH BEAM
2x10 FLITCH BEAM
2x4 WOOD FRAMING@ 24" O.C.
METAL ROOF PANELSLOPE 1/4":12"
METAL FLASHING TOEXISTING ROOFSYSTEM
2' - 0" 4"
1' -
4"
8x8x8 SPLIT FACEDCORNER BLOCK
8x16x8 SPLIT FACEDCORNER BLOCK
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A1.1
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"1 EXTENSION SERVICE FLOOR PLAN
1/4" = 1'-0"2 FOUNDATION PLAN
1/2" = 1'-0"3 Section 1
1/2" = 1'-0"4 COLUMN DETAIL
I
NEW IT-451 ALUMINUMSTOREFRONT BY US ALLUMINUM
OR APPROVED EQUAL
III
NEW PRE-FINISHED SOLIDCORE WOOD DOOR WITH
WOOD FRAME BY JELDWYN ORAPPROVED EQUAL
3' - 0"
7' -
0"
VI
NEW PRE-FINISHED SOLID COREWOOD DOOR WITH WOOD FRAME BY
JELDWYN OR APPROVED EQUAL
2' -
9"4'
- 6"
2' - 0"6' - 0"
7' -
0"
3' - 0"
7' -
0"
VII
NEW HOLLOW METALINSULATED DOOR BY REPUBLIC
OR APPROVED EQUAL
VIII
NEW PRE-FINISHED SOLID COREWOOD DOOR WITH WOOD FRAME
BY JELDWYN OR APPROVEDEQUAL
4' - 0"
7' -
0"
NEW 2x4 WOOD STUD WALL
BLOCKING @ MID-POINT
5/8" GYPSUM BOARD TYPE "X"EITHER SIDE
9' -
0"
2x2 SUSPENDED CEILING
R-30 BATT INSULATION
1' -
0"
TYPE I
BLOCKING @ MID-POINT
5/8" GYPSUM BOARD TYPE "X"EITHER SIDE
9' -
0"
2x2 SUSPENDED CEILING
R-30 BATT INSULATION
TYPE III
1 HR. RATED WALL- FIRESTOPPING & CAULKING AS
REQUIRED
6" RUBBER BASE 6" RUBBER BASE
NEW 2x4 WOOD STUD WALLOR METAL STUD
TO R
OO
F A
SS
EM
BLY
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A1.2
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
EXTENSION SERVICE FINISH SCHEULE
AREA FLOORS BASE WALLS CEILING PAINTING
NUMBER NAME PO
RC
ELA
IN T
ILE
VCT
TILE
PAIN
TED
CO
NC
RET
E
6" R
UB
BER
POR
CEL
AIN
FRONT REAR RIGHT LEFT
5/8"
GYP
. BD
. TY
PE "
X" S
USP
. CEI
LIN
G
2'x2
' SU
SPEN
DED
CEI
LIN
G
CLG
. HT.
FRONT REAR RIGHT LEFT CEILING TRIM
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
5/8"
GYP
BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X E
NA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL(1
) CT.
PR
IMER
& (2
) CTS
. SEM
I-GLO
SS O
IL B
ASE
D E
NA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS C
EILI
NG
FLA
T W
HIT
E
NO
NE
(1) C
T. P
RIM
ER &
(2) C
TS S
EMI-G
LOSS
OIL
-BA
SED
EN
AM
EL
101 RECEPTIONIST X X X X X X X 9'-0" X X X X X X102 DIRECTOR'S OFFICE X X X X X X X 9'-0" X X X X X X103 COPY/STORAGE X X X X X X X 9'-0" X X X X X X104 CORRIDOR X X X X X X X 9'-0" X X X X X X105 HVAC X X X X X106 STORAGE X X X X X X X 9'-0" X X X X X X107 MEETING ROOM X X X X X X X 9'-0" X X X X X X108 JANITOR X X X X X X X 9'-0" X X X X X X109 CONFERENCE X X X X X X X 9'-0" X X X X X X110 OFFICE X X X X X X X 9'-0" X X X X X X111 OFFICE X X X X X X X 9'-0" X X X X X X112 CORRIDOR X X X X X X X 9'-0" X X X X X X113 BREAK X X X X X X X 9'-0" X X X X X X114 MEN X X X X X X X 9'-0" X X X X X X115 WOMEN X X X X X X X 9'-0" X X X X X X116 HVAC X X X X X117 ELEC./COMM. X X X X X X X 9'-0" X X X X X X118 OFFICE X X X X X X X 9'-0" X X X X X X119 OFFICE X X X X X X X 9'-0" X X X X X X120 CORRIDOR X X X X X X X 9'-0" X X X X X X121 CORRIDOR X X X X X X X 9'-0" X X X X X X122 CORRIDOR X X X X X X X 9'-0" X X X X X X
EXTENSION SERVICE DOOR SCHEDULE
Mark Width Height Thickness MATERIAL TYPE Frame Material Comments
101A 6' - 0" 7' - 0" 0' - 1 3/4" ALUMINUM I ALUMINUM NEW ALUMINUM STOREFRONT102A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR103A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR103B 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR104A 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR105A 2' - 0" 4' - 6" 0' - 1 3/4" S.C. WOOD VI WOOD SOLID CORE WOOD DOOR106A 4' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD VIII WOOD SOLID CORE WOOD DOUBLE DOOR107A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR107B 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR108A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR109A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR110A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR111A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR113A 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR114A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR115A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR116A 2' - 0" 4' - 6" 0' - 1 3/4" S.C. WOOD VI WOOD SOLID CORE WOOD DOOR117A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR118A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR119A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR122A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR122B 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR122C 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III WOOD SOLID CORE WOOD DOOR122D 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR122E 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR122F 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR
1/2" = 1'-0"EXTENSION SERVICE DOOR ELEVATIONS
1/2" = 1'-0"EXTENSION SERVICE WALL TYPES
S
S
S
S
S
S
S
S
3A1.1
10' -
8"
MA
TCH
EX
ISTI
NG
FR
ON
T P
OR
CH
WA
LL
5' -
10"
NEW SPLIT FACEDCMU COLUMNS
EXISTING RAKE TRIM
EXISTING METALWALL PANEL -PAINT THIS WALLFROM CORNER TOCORNER
NEW ENTRY PORCH
101A
RELOCATE EXISTINGEXTENSION SERVICE SIGN
NEW ENTRY PORCHREPAIR EXISTING DOWNSPOUT
EXISTING GUTTER
EXISTING METALWALL PANEL
EXISTING WINDOWS
NEW SPLIT FACEDCMU COLUMNS
V1 V1
CA
V1
V1
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A1.3
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"2 NEW FRONT
1/4" = 1'-0"3 NEW SIDE
1/4" = 1'-0"1 EXTENSION SERVICE REFLECTED CEILING PLAN
2' - 0" 2' - 0" 2' - 0" 2' - 0"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
4' -
6"2'
- 6"
7' -
0"
5' - 0"
4' - 0"
1' -
3"1'
- 3"
1' -
3"1'
- 3"
2' -
0"
7' -
0"
2' - 6" 2' - 6" 2' - 0"
7' - 0"
3' -
0"2'
- 9"
1' -
3"
7' -
0"
2' - 6" 3' - 2" 1' - 6" 1' - 0"
8' - 2"
1' -
3"2'
- 9"
3' -
0"
7' -
0"
2' - 0" 7" 3' - 0" 7" 2' - 0"
8' - 2"
3' -
0"
3' -
0"2'
- 9"
1' -
3"
7' -
0"
2' - 0" 1' - 9" 2' - 6" 1' - 9"
8' - 0"
VENT HOOD
STAINLESSBACKSPLASH@ RANGE
4' -
0"
6' -
0"
FRP WALL PANELON (3) SIDES
WOOD SHELF
2' - 6" 2' - 0" 2' - 6" 2' - 0"
9' - 0"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
2' - 6" 2' - 0" 2' - 6" 2' - 0"
1' -
3"2'
- 9"
3' -
0"
7' -
0"
3' - 0"2' - 0"
5' - 0"
2' - 0" 3' - 0"
MIRRORSEE SECTION 10100
PROVIDE TRAP WRAPSEE PLUMBING
3' -
4"
2' -
10"
5'-0" CLEAR
1' - 6"
A1.4 10
J
18"
36" 6" MAX.
36"
36"
42"
18"
12" MAX.
FRONT VIEW SIDE VIEW
BACK WALL SIDE WALL
42"36"2x6 SOLID WOODBLOCKING
36"
36"
DISPENSERLOCATION
MIN
.
1' -
3"M
AX
.
4' -
0"
O.C.
9"
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A1.4
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
3/8" = 1'-0"1 A
3/8" = 1'-0"2 B
3/8" = 1'-0"3 C
3/8" = 1'-0"4 D
3/8" = 1'-0"5 E
3/8" = 1'-0"6 F
3/8" = 1'-0"7 G 3/8" = 1'-0"
8 H
3/8" = 1'-0"9 I
3/8" = 1'-0"10 J
3/8" = 1'-0"11 ADA TOILET PLAN
1/2" = 1'-0"12 GRAB BAR DETAILS
8
9
9
9
9
9
9
9
9
9
9
5
5
5
5
5
55
5
5
5
5
5
5
5
5
1010
9
9
9
11
9
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 71, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7 1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1, 2, 3, 4, 6, 7
1. REMOVE EXISTING FLOORING TO CONCRETE.2. REMOVE EXISTING GYPSUM BOARD-
METAL STUD WALLS TO REMAIN.3. REMOVE EXISTING SUSPENDED CEILING,
GRID & INSULATION.4. REMOVE EXISTING MECHANICAL, ELECTRICAL
& PLUMBING- SEE SHEETS M, E & P.5. REMOVE EXISTING DOORS & HARDWARE.6. REMOVE EXISTING WINDOW TREATMENTS.7. REMOVE EXISTING BASE.8. CUT & REMOVE APPROX. 28' OF EXISTING
CONCRETE SIDEWALK.9. REMOVE EXISTING WALLS.10. REMOVED EXISTING WINDOWS.11. REMOVED EXISTING CASEWORK.
EXISTING TO BE REMOVED
EXISTING TO REMAIN
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A2.0
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"1 CLINIC DEMOLITION PLAN
-2 CLINIC DEMOLITION NOTES
-3 CLINC DEMO LEGEND
REF.ICE
14' -
7 5
/8"
9' -
0 1/
2"10
' - 6
"8'
- 1
7/8"
9' -
2"11' -
6 3
/4"
7' -
9 1/
4"7'
- 9
7/8"
8' -
8"7'
- 8
1/8"
10' -
3 3
/8"
10' -
4 7
/8"
9' -
9"9'
- 7"
7' - 7 7/8" 13' - 10 1/2" 15' - 2 1/2"
WAITING201
CHECK-IN202
VITALS203
X-RAY204
EXAM205
TEL/DATA206
EXAM207
EXAM208
EXAM209
CORRIDOR210
TOILET211
TOILET212
LAB213
CLEAN STORAGE214
OFFICE215
BREAK216
SOILED STORAGE217
WORKROOM218
HVAC219
HVAC220
201A219A
201B
206A
205A
204A
202A
209A
210A
211A 212A
213A
214A
220A217A
215A 216A
210B
A2.4
1 K
A2.4
1 K
A2.4
1 K
A2.4
2 L
A2.4
3 M
A2.4
4 N
5
O
A2.4
6P
A2.4
9 SA2.410
T
A2.411
U
A1.410
J
A1.4 10
J
3' - 2 3/8"
4' -
2 3/
8"
9' -
7"
207A
208A
8' -
5 1/
2"5'
- 2
3/8"
5' -
4 3/
8"3'
- 4
1/2"
5' -
2 3/
8"
1' -
0"
4' - 2 3/8"
7' -
6 7/
8"24
' - 5
1/4
"
STORAGE221 221A
4' - 2 1/2"
4' -
10 1
/4"
3' - 6
3/4
"
145.
00°
TV
TV
218A
A
A2.4
7 Q
A2.48
R
B
B
IIII
II
II
I
I
I
I
III
I
I
I
I
I
I
I
I
EXISTING OR NEW METALSTUD WALL- 20GA. MIN.
BLOCKING @ MID-POINT
5/8" GYPSUM BOARD TYPE "X"EITHER SIDE
9' -
0"
2x2 SUSPENDED CEILING
R-30 BATT INSULATION
1' -
0"
TYPE I
EXISTING OR NEW METALSTUD WALL- 20 GA. MIN.
BLOCKING @ MID-POINT
5/8" GYPSUM BOARD TYPE "X"EITHER SIDE
9' -
0"
2x2 SUSPENDED CEILING
R-30 BATT INSULATION
1' -
0"
TYPE II
6" RUBBER BASE 6" RUBBER BASE
5/8" GYPSUM BOARD W/1/16" LEAD SHIELDING 7'
- 0"
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A2.1
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17 1/4" = 1'-0"2 CLINIC FLOOR PLAN
1/2" = 1'-0"CLINIC WALL TYPES
I
EXISTING ALUMINUMSTOREFRONT TO REMAIN
II
NEW PRE-FINISHED SOLID COREWOOD DOOR BY GRAHAM OR
APPROVED EQUAL
3' - 6"
7' -
0"
III
NEW PRE-FINISHED SOLID COREWOOD DOOR BY GRAHAM OR
APPROVED EQUAL
3' - 0"
7' -
0"
3' - 6"
7' -
0"
IV
NEW PRE-FINISHED SOLID CORE WOODDOOR BY GRAHAM OR APPROVED EQUALW/ 1/16" LEAD SHIELDING AS REQUIRED
V
NEW STEEL DOOR W/ FULLSAFETY GLASS & SIDELIGHT BY
REPUBLIC OR APPROVED EQUAL
VI
NEW PRE-FINISHED SOLID COREWOOD DOOR BY GRAHAM OR
APPROVED EQUAL
2' -
6"4'
- 6"
2' - 0"3' - 0"
7' -
0"
1' - 0"
VII
NEW HOLLOW METALINSULATED DOOR BY REPUBLIC
OR APPROVED EQUAL
3' - 0"
7' -
0"
1. OVERLAY EXISTING WALLS WITH 5/8" GYPSUM BOARDWITH 1/16" LEAD SHIELDING TO 7'-0" A.F.F. WITHAPPLICABLE LEAD ACCESSORIES AS REQUIREDTO COMPLETE SHIELDING SYSTEM (BLOCK WINDOWOPENING AS REQUIRED).
2. STRIP EXISTING WINDOWS WITH 2x4 STUD AND "INFILL"WITH 5/8" GYPSUM BOARD AS REQUIRED FOR SMOOTHNEW WALL SURFACE.
SPECIAL WINDOW FINISH NOTE:
ALL WINDOWS THAT ARE TO BE "INFILLED" SHALLRECIEVE A NEW WINDOW TREATMENT LEFT IN THE CLOSEDPOSITION PRIOR TO BE COVERED.
2' - 0"
2' -
0"4'
- 0"
6' -
0"
A
LEAD SHIELDED FIXEDVIEW WINDOW
4' -
0"3'
- 0"
7' -
0"
3' - 0"
B
METAL FRAMEDSAFETY GLASS VIEW
WINDOW
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A2.2
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
CLINIC FINISH SCHEULE
AREA FLOORS BASE WALLS CEILING PAINTING
NUMBER NAME PO
RC
ELA
IN
VCT
TILE
POR
CEL
AIN
6" R
UB
BER
BA
SE
FRONT REAR RIGHT LEFT
2'x2
' SU
SPEN
DED
CEI
LIN
G
CLG
. HT.
FRONT REAR RIGHT LEFT CEILING TRIM
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
5/8"
GYP
BD
.
5/8"
GYP
. BD
. TYP
E "X
"
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
(1) C
T. P
RIM
ER &
(2) C
TS. E
GG
SHEL
L LA
TEX
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. E
GG
SHEL
L LA
TEX
ENA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. E
GG
SHEL
L LA
TEX
ENA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. E
GG
SHEL
L LA
TEX
ENA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS C
EILI
NG
FLA
T W
HIT
E
(1) C
T. P
RIM
ER &
(2) C
TS S
EMI-G
LOSS
OIL
-BA
SED
EN
AM
EL
201 WAITING X X X X X X X 9'-0" X X X X X202 CHECK-IN X X X X X X X 9'-0" X X X X X203 VITALS X X X X X X X 9'-0" X X X X X204 X-RAY X X 1 1 1 1 X 9'-0" X X X X X205 EXAM X X X X X X X 9'-0" X X X X X206 TEL/DATA X X X X 2 X X 9'-0" X X X X X207 EXAM X X X X X X X 9'-0" X X X X X208 EXAM X X X X X X X 9'-0" X X X X X209 EXAM X X X X X X X 9'-0" X X X X X210 CORRIDOR X X X X X X X 9'-0" X X X X X211 TOILET X X X X X X X 9'-0" X X X X X212 TOILET X X X X X X X 9'-0" X X X X X213 LAB X X X X X X X 9'-0" X X X X X214 CLEAN STORAGE X X X X X X X 9'-0" X X X X X215 OFFICE X X 2 X X X X 9'-0" X X X X X216 BREAK X X 2 X X X X 9'-0" X X X X X217 SOILED STORAGE X X X X X X X 9'-0" X X X X X218 WORKROOM X X X X X X X 9'-0" X X X X X219 HVAC X X X X X X X X X X220 HVAC X X X X X X X X X X221 STORAGE X X X X X X X 9'-0" X X X X X
1/2" = 1'-0"CLINIC DOOR ELEVATIONS
CLINIC DOOR SCHEDULE
Mark Width Height Thickness MATERIAL TYPE Frame Material Comments
201A 6' - 0" 7' - 0" 0' - 1 3/4" ALUMINUM I ALUMINUM EXISTING DOORS TO REMAIN201B 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR202A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR204A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD IV METAL SOLID CORE WOOD DOOR W/ LEAD SHIELDING205A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR206A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR207A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR208A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR209A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR210A 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR210B 3' - 0" 7' - 0" 0' - 1 3/4" METAL V METAL METAL DOOR W/ FULL SAFETY GLASS211A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR212A 3' - 6" 7' - 0" 0' - 1 3/4" S.C. WOOD II METAL SOLID CORE WOOD DOOR213A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR214A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR215A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR216A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR217A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR218A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR219A 2' - 0" 4' - 6" 0' - 1 3/4" S.C. WOOD VI METAL SOLID CORE WOOD DOOR220A 2' - 0" 4' - 6" 0' - 1 3/4" S.C. WOOD VI METAL SOLID CORE WOOD DOOR221A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR
-1 FINISH SCHEDULE NOTES
1/2" = 1'-0"WINDOW ELEVATIONS
S
S
S
S
S
S
S
S
S
S
S
S
V1 V1
CA
CA
CACA
V1
V1
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A2.3
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"1 URGENT CARE CLINIC REFLECTED CEILING PLAN
KNEE SPACE
2' -
10"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
2' - 0"2' - 0"3' - 0"
FIXED SHELVING
LAMINATED CASEWORK
LAMINATED COUNTERTOP
7' - 0"
1"
KNEE SPACE
FIXED SHELVING
LAMINATED CASEWORK
LAMINATED COUNTERTOP
3' - 0"2' - 0"2' - 0"
7' - 0"
2' -
6"1'
- 6"
3' -
0"
7' -
0"
2' -
10"
1"
3' - 0" 1' - 0"
6' - 0"
2' -
10"
KNEE SPACE
LAMINATEDCASEWORK
LAMINATEDCOUNTERTOP
2' - 0"
7' -
0"
1' -
8"2'
- 6"
1"
LOCKABLE MEDICINECABINET W/ ADJUSTABLESHELVES
2' -
10"
2' - 1"
15' - 0"
1' - 0"1' - 0"4' - 8"1' - 6"3' - 9"1' - 0" 2' - 0" 3' - 0"
5' - 0"
2' -
10"
202A
1"
2' -
6"1'
- 8"
1' - 6"3' - 4"1' - 0"3' - 4"1' - 0"3' - 4"1' - 6"
15' - 0"
2' -
10"
2' - 6" 2' - 6"
2' -
6"4'
- 6"
7' -
0"
2' - 8" 1' - 3" 2' - 0"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
3' - 0" 1' - 9" 2' - 0" 1' - 3" 1' - 0"
2' -
6"1'
- 6"
3' -
0"
7' -
0"
2' - 7" 2' - 9" 2' - 0"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
2' - 7" 2' - 9" 2' - 0"
7' - 4"
2' - 5" 1' - 6" 1' - 6" 2' - 0"
3' -
0"1'
- 6"
2' -
6"
7' -
0"
2' - 5" 3' - 0" 2' - 0"
7' - 5"
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A2.4
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
3/8" = 1'-0"1 K
3/8" = 1'-0"2 L
3/8" = 1'-0"3 M
3/8" = 1'-0"4 N
3/8" = 1'-0"5 O
3/8" = 1'-0"6 P
3/8" = 1'-0"7 Q
3/8" = 1'-0"8 R
3/8" = 1'-0"9 S
3/8" = 1'-0"10 T
3/8" = 1'-0"11 U
LOBBY222
FITNESS224
CLASSROOM225
WOMEN227
MEN228
STORAGE230
HVAC223
HVAC226
CORRIDOR229
TV TV
225B225C
122C
226A
122B
206A
225A
224B
230A
230B 224A
223A
222A
TEL/DATA206
CORRIDOR122
CORRIDOR121
122A
210A
231A
122F
122E
122D
III
III
IIIIII
III
III
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A3.1
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17 1/4" = 1'-0"
1
CLASSROOM & FITNESS FLOOR PLAN-ALTERNATE NO. 1
III
NEW PRE-FINISHED SOLID COREWOOD DOOR BY GRAHAM OR
APPROVED EQUAL
3' - 0"
7' -
0"
VII
EXISTING HOLLOW METALINSULATED DOOR TO
REMAIN
3' - 0"
7' -
0"
3' - 0"
7' -
0"
IX
EXISTING ALUMINUMSTOREFRONT TO REMAIN
X
EXISTING HOLLOW METALINSULATED DOOR TO REMAIN
2' -
6"4'
- 6"
7' -
0"
5' - 0"6' - 0"
7' -
0"
III
NEW PRE-FINISHED SOLID COREWOOD DOOR BY GRAHAM OR
APPROVED EQUAL
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A3.2
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
CLASSROOM & FITNESS FINISH SCHEULE
AREA FLOORS BASE WALLS CEILING PAINTING
NUMBER NAME VC
T TI
LE
PAIN
TED
CO
NC
RET
E
6" R
UB
BER
FRONT REAR RIGHT LEFT
5/8"
GYP
. BD
. TY
PE "
X" S
USP
. CEI
LIN
G
2'x2
' SU
SPEN
DED
CEI
LIN
G
CLG
. HT.
FRONT REAR RIGHT LEFT CEILING TRIM
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
5/8"
GYP
BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X E
NA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS C
EILI
NG
FLA
T W
HIT
E
NO
NE
(1) C
T. P
RIM
ER &
(2) C
TS S
EMI-G
LOSS
OIL
-BA
SED
EN
AM
EL
222 LOBBY X X X 9'-0" X X X X X X223 HVAC X 9'-0" X X X X X X224 FITNESS X X X 9'-0" X X X X X X225 CLASSROOM X X X 9'-0" X X X X X X226 HVAC X 9'-0" X X X X X X227 WOMEN X X X 9'-0" X X X X X X228 MEN X X X 9'-0" X X X X X X229 CORRIDOR X X X X 9'-0" X X X X X X230 STORAGE X X X X 9'-0" X X X X X X231 SPRINKLER X X X X X X 9'-0" X X X X X X
CLASSROOM & FITNESS DOOR SCHEDULE
Mark Width Height Thickness MATERIAL TYPE Frame Material Comments
222A 3' - 0" 7' - 0" 0' - 1 3/4" ALUMINUM IX ALUMINUM EXISTING DOORS TO REMAIN223A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR224A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR224B 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR225A 3' - 0" 7' - 0" 0' - 1 3/4" S.C. WOOD III METAL SOLID CORE WOOD DOOR225B 6' - 0" 7' - 0" 0' - 1 3/4" H.M.I. X METAL EXISTING DOORS TO REMAIN225C 6' - 0" 7' - 0" 0' - 1 3/4" H.M.I. X METAL EXISTING DOORS TO REMAIN226A 5' - 0" 4' - 6" 0' - 1 3/4" S.C. WOOD XI METAL SOLID CORE WOOD DOUBLE DOOR230A 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL EXISTING DOORS TO REMAIN230B 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL EXISTING DOORS TO REMAIN231A 3' - 0" 7' - 0" 0' - 1 3/4" H.M.I. VII METAL HOLLOW METAL INSULATED DOOR
1/2" = 1'-0"CLASSROOM DOOR ELEVATIONS
S
S
S
S
V1
CA
V1
V1
V1
CA
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A3.3
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/4" = 1'-0"1
CLASSROOM & FITNESS REFLECTED CEILINGPLAN
NEW CORRIDOR, WALLS& RELATED DOORSSHALL BE INCLUDED INTHE BASE BID
CORRIDOR122
122C
122B
122A
SPRINKLERRISER
SPRINKLER231 231A
122D
122E
122F
NEW WALLS & RELATEDDOORS SHALL BE INCLUDEDIN ALTERNATE NO. 2
NEW WALLS & RELATEDDOORS SHALL BE INCLUDEDIN ALTERNATE NO. 2
WALKING TRACK300
EXISTING EXIT
EXISTING COLUMNS TO BEPAINTED
APPROXIMATELY 115'-0"
R 15' - 0" R 15' -
0"
R 15' - 0"
R 15' -
0"R
20'
- 0"
R 20' - 0"
R 20' - 0"R 20' - 0"
5' -
0"5'
- 0"
63' -
0 1
/8"
5' - 0" 70' - 0" 5' - 0"
WALKING TRACK TO BE PAINTED
START1' LETTERING ANDBAND TO BE PAINTEDON TRACK
GENERAL INFORMATION:1 MILE IS EQUAL TOAPPROXIMATELY 22 LAPS.
III
III
III
III
OF SHEETS
DRAWN
DATE
CHECKED
REVISED
SHEET NUMBER
PROJ. NO.
319
CA
LIF
OR
NIA
AV
EN
UE
L
EL
AN
D, M
ISSI
SSIP
PI
3875
6em
ily-p
oole
@ho
tmai
l.com
6
01-5
97-2
724
ARCH
ITEC
TURE
, PLL
CE
MIL
Y
PO
OL
E
BELZONI, MISSISSIPPI
HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS:
EWP
EWP
-
-
04/20/2016
A4.1
NE
W U
RG
EN
T C
AR
E C
LIN
IC &
EX
TEN
SIO
N S
ER
VIC
E O
FFIC
ES
HU
MP
HR
EY
S C
O. B
D. O
F S
UP
ER
VIS
OR
S
17
1/8" = 1'-0"1 WALKING TRACK- ALTNERNATE NO. 2
WALKING TRACK FINISH SCHEDULE
AREA FLOORS BASE WALLS CEILING PAINTING
NUMBER NAME VC
T TI
LE
PAIN
TED
CO
NC
RET
E
6" R
UB
BER
FRONT REAR RIGHT LEFT
5/8"
GYP
. BD
. TY
PE "
X" S
USP
. CEI
LIN
G
2'x2
' SU
SPEN
DED
CEI
LIN
G
CLG
. HT.
FRONT REAR RIGHT LEFT CEILING TRIM
5/8"
GYP
. BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
5/8"
GYP
BD
.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U5/
8" G
YP. B
D.
5/8"
GYP
. BD
. TYP
E "X
"
CM
U
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X E
NA
MEL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
ATI
N L
ATE
X EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS. S
EMI-G
LOSS
OIL
BA
SED
EN
AM
EL
(1) C
T. P
RIM
ER &
(2) C
TS C
EILI
NG
FLA
T W
HIT
E
NO
NE
(1) C
T. P
RIM
ER &
(2) C
TS S
EMI-G
LOSS
OIL
-BA
SED
EN
AM
EL
300 WALKING TRACK X X X X X X OPEN X X X X X X
NO WORK TO BEDONE IN THIS AREA
NO WORK TO BEDONE IN THIS AREA
RECEPTIONIST
COPY/STOR.
ELECTRICALROOM
BUILDINGDIRECTOR
CORRIDOR
CORRIDOR
SPRINKLERRISER
NO WORK TO BEDONE IN THIS AREA
CONFERENCE
WOMEN
MEN
Room
LARGE MEETING
OFFICE
JAN.
OFFICE BREAK
FITNESS
HVAC
CLASSROOM
STORAGE
CLEAN STORAGE
STORAGE
SOILED STORAGE
OFFICE
ELEC.
OFFICE
TOILET
HVAC
CORRIDOR
LAB
TOILET
EXAM
EXAM
EXAM
LOBBY
TEL/DATA
HVAC
VITALS
EXAM
OFFICE
BREAK
WORKROOM
WAITING
CHECK-IN
X-RAY
HVAC
NO WORK TO BEDONE IN THIS AREA
SPRINKLERRISER
NO WORK TO BEDONE IN THIS AREA
CONFERENCE
OFFICE OFFICE BREAK
ELEC.
JAN.
OFFICE
OFFICE
LARGE MEETING
RECEPTIONISTDIRECTOR
COPY/STOR.
230STORAGE
LOBBY222
HVAC223
FITNESS224
206TEL/DATA
EXAM 205
204X-RAY
EXAM207
203VITALS
208EXAM
CHECK-IN202
209EXAM
CORRIDOR210
WAITING201
HVAC219
212TOILET
211TOILET
LAB213
CLEAN STORAGE214
HVAC220
SOILED STORAGE217
STORAGE221
CLASSROOM225
MEN228
WOMEN227
226HVACCORRIDOR
122
CORRIDOR121
229Room
BUILDINGELECTRICAL
ROOM
SPRINKLERRISER
WORKROOM218
BREAK216
215OFFICE
RECEPTIONIST
COPY/STOR.
ELECTRICALROOM
BUILDINGDIRECTOR
122
121
CORRIDOR
CORRIDOR
SPRINKLERRISER
NO WORK TO BEDONE IN THIS AREA
CONFERENCE
227WOMEN
228MEN
Room229
LARGE MEETING
OFFICE
JAN.
OFFICE BREAK
FITNESS
HVAC226
225CLASSROOM
224
STORAGE230
CLEAN STORAGE
STORAGE
SOILED STORAGE
OFFICE
ELEC.
OFFICE
217
221
211
214
TOILET
HVAC220
CORRIDOR
212
213LAB
TOILET
210
206
EXAM208
EXAM209
207EXAM
LOBBY222
TEL/DATA205
219HVAC
VITALS203
EXAM
OFFICE215
BREAK216
218WORKROOM
201WAITING
CHECK-IN202
204X-RAY
HVAC223
NO WORK TO BEDONE IN THIS AREA
CONFERENCE
OFFICE OFFICEBREAK
ELEC.
JAN.
OFFICE
OFFICE
LARGE MEETING
RECEPTIONIST
DIRECTOR
COPY/STOR.
STORAGE
LOBBY
HVAC
FITNESS
TEL/DATA EXAM
X-RAY
EXAM
VITALS
EXAM
CHECK-IN
EXAM
CORRIDOR
WAITING
HVAC
TOILETTOILET
LAB
CLEAN STORAGE
HVAC
SOILED STORAGE
STORAGE
CLASSROOM
MEN
WOMEN
HVACCORRIDOR
CORRIDOR
Room
BUILDINGELECTRICAL
ROOM
SPRINKLERRISER
WORKROOM
BREAK
OFFICE
HUMAN SERVICES DEPARTMENT HEALTH DEPARTMENT
SPRINKLERRISER
NO WORK TO BEDONE IN THIS AREA