New Tools for Project Management and Control · 2019. 9. 12. · •Research at MIT CEE 1995-1999...
Transcript of New Tools for Project Management and Control · 2019. 9. 12. · •Research at MIT CEE 1995-1999...
New Tools for New Tools for Project Management and Project Management and
ControlControlDr. Sarah SlaughterMIT 1.040/1.401JMarch 12, 2007
Project Management and Project Management and ControlControl
1. Evaluate Different Options1. Cost2. Schedule3. Resources4. Quality5. Safety6. Environment
2. Select Best Option(s) and Establish Project Plan3. Monitor and Control Progress4. Establish Baseline for Operations and Later
Renovation
Cash Flow Over Life Cycle of Cash Flow Over Life Cycle of Built FacilitiesBuilt Facilities
CashFlow
Time
+
_Design
Construction
Operation5-50 yrs
Renovation
Impact of Alternatives on Impact of Alternatives on Cash FlowCash Flow
Time
+
_Design
Construction
Operation5-50 yrs
Renovation
CashFlow
Capital ProgrammingCapital Programming
ClientClient
ProjProj Mgt Mgt With New With New ToolsTools
Provide Program Descriptions
Create preliminary baseline(s)
Analyze scope, phasing alternatives
Provide baseline budgets with achievable completion dates
Analyze combinations of projects for total budget and revenue studies
Model potential project sequences and traffic flow, etc.
Set Annual Expenditure Target
Need
Determination
Budget Development
Prioritization and Planning
Set Priorities with Strategic Objectives
Planning/DesignPlanning/Design
Provide Design/ Engineering Documents
Manage Project Scope and Budget
Create preliminary baseline(s)
Analyze scope, phasing, design and construction alternatives
Analyze additional design/construction alternatives
Prepare final baseline(s)
Support contractor selection
Update baseline(s) to reflect means & methods
Provide resource-loaded schedule as benchmark
Provide benchmark schedule of values
Select Designer, Contractor
Select best alternatives
Planning
Detailed Design Contractor Selection
Means and Methods
ClientClient
ProjProj Mgt Mgt With New With New ToolsTools
Establish basic performance parameters, benchmarks
ConstructionConstructionProgress monitoring
Change Order Analysis
Closeout
Provide Design/ Engineering Documents
Monitor Progress
Audit Construction Progress
Analyze Schedule Deviations
Review Requests for Payment
Analyze cost/schedule impact of change orders
Analyze Recovery or Acceleration Options
Create equipment and material database
Provide performance parameter report
Approve Selected Changes and Options
Update Performance Benchmarks
ClientClient
ProjProj Mgt Mgt With New With New ToolsTools
OperationsOperationsConditionmonitoring
Maint, Upgrade
Decomm, Re-Use
Monitor facility performance
Adjust systems to achieve performance quality
Monitor Progress
Maintain systems
Select system, finish upgrades
Monitor project performance
Identify use basis-current, potential re-use
Decommission facility –system, component, material disposition
Establish re-use basis
ClientClient
ProjProj Mgt Mgt With New With New ToolsTools
Audit Progress
Analyze Deviations
Establish cost/schedule
Provide performance parameter report
Transfer equipment and material database
Provide new baseline
New Tools for Project New Tools for Project Management and ControlManagement and Control
• Construction Micro-Simulation• Computational Flow Dynamics Simulation• 4D CAD Visualization• GPS• Radio-frequency Identifiers
New Tools: Construction New Tools: Construction MicroMicro--SimulationSimulation
• Automatically Integrate Cost, Schedule, Resource and Safety
• Rapidly Assess the Impacts of Multiple Options Under Different Scenarios
• Create Definitive and Reusable Baselines for Each Scenario
• Incorporate Interactions Between Trades Throughout Construction for Construction Planning, Monitoring and Control
• Re-Use Baselines for Similar Facilities
MOCABuildMOCABuild™™ Simulation SystemSimulation System•Research at MIT CEE 1995-1999•MOCA Systems, Inc. founded June 1999, started operations April 2000•Current selected clients – US Air Force, Real Estate Developers, Hospitals
Time-Motion Studies Material Takeoff
Means and Methods Staffing Levels
MOCABuildMOCABuild: Detailed Cost : Detailed Cost Estimates with Verifiable QuantitiesEstimates with Verifiable Quantities
MOCA Cost Estimate - Level 2 (Dallas)
Level 1 Item # ate Descr
Cost Code Description Quantity Unit
Dallas Material
Unit Cost
DallasTotal Material
CostDallas Labor
Unit Cost
DallasTotal Labor
CostDallas
Total Cost23 HVAC Labor -Sheetmetal Workers 773 hrs $0.00 $0.00 $19.14 $14,793.32 $14,793.3223 Labor -Steamfitters 478 hrs $0.00 $0.00 $15.71 $7,506.76 $7,506.7623 15107 Fittings(included in pipe) 599 each $0.00 $0.00 $0.00 $0.00 $0.0023 Hangers(included in pipe) 171 each $0.00 $0.00 $0.00 $0.00 $0.0023 Pipe Copper - 1 720 lnft $3.11 $2,239.20 $0.00 $0.00 $2,239.2023 Pipe Copper - 1.5 990 lnft $4.89 $4,841.10 $0.00 $0.00 $4,841.1023 Valves(included in pipe) 30 each $0.00 $0.00 $0.00 $0.00 $0.0023 15810 Hangers(included in duct) 2,556 each $0.00 $0.00 $0.00 $0.00 $0.0023 HVAC Ducting 36,492 lbs $3.13 $114,221.40 $0.00 $0.00 $114,221.4023 15850 Diffusers - 18x18 61 each $136.85 $8,347.85 $0.00 $0.00 $8,347.8523 Large VAV 2 each $225.00 $450.00 $0.00 $0.00 $450.0023 Medium VAV 6 each $180.00 $1,080.00 $0.00 $0.00 $1,080.0023 Return Air Registers - 22x22 36 each $71.30 $2,566.80 $0.00 $0.00 $2,566.8023 Small VAV 16 each $175.00 $2,800.00 $0.00 $0.00 $2,800.00
Source: www.mocasystems.com
MOCABuildMOCABuild: Automatic : Automatic ResourceResource--Loaded ScheduleLoaded Schedule
Source: www.mocasystems.comCourtesy of MOCA Systems. Used with permission.
MOCABuildMOCABuild: Actual vs.Expected : Actual vs.Expected ProgressProgress
Concrete In-Place by Day
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270
Workday
Cum
ulat
ive
CY
1. Beacon-Skanska Schedule
2. MOCA run with Beacon-Skanska column (1,000 sf), wall (7,000 sf), & slab (32,000 sf) form constraints
4. MOCA run with 50% more slab formwork (48,000 sf). Column (9,000 sf)and wall (21,000 sf) forms set by MOCA.
Source: www.mocasystems.com
MOCABuildMOCABuild: Analysis of : Analysis of AlternativesAlternatives
Workdays % Increase $ % IncreaseCase A: Standard Design 240 - $6,421,911 -Case B: Standard Design w/ Natural Light Enhancements
241 0% $6,540,849 2%
Case C: Green Design (Dimella Shaffer Design)
243 1% $6,904,885 8%
Case C: Green Design w/ IAQ Requirements
256 7% $6,924,385 8%
Construction DurationSimulation Description Project Cost
Source: www.mocasystems.com
New Tools: Computational New Tools: Computational Flow DynamicsFlow Dynamics
• Analyze performance during operation of complex interdependent systems– Air flow through a building– Air pollution in an urban area– Water flow through a terrain
• Track transport of pollutants and biological agents
• Monitor and control air/water flow to improve performance
New Tools: Computational New Tools: Computational Flow DynamicsFlow Dynamics
• Research– Penn State, course “CFD in Building Design”
(www.arche.psu.edu)
– National Research Council Canada
• Examples of use in buildings:– Southwest Research Institute – large scale
engineered and natural systems (www.swri.org)– Vipac – CFD for interior and exterior building
performance (www.vipac.com.au)• Resources:
– www.cfd-online.com
New Tools: 4D CAD New Tools: 4D CAD Construction AnimationConstruction Animation
• Provide Visualization of Facility to Client
• Check Clearances for Placement of Equipment, Large Component, and Equipment
• Check Construction Sequence– Reach of Hoisting Equipment– Relative Progress for Each System
and Location• Communicate Construction
Schedule
New Tools: 4D CAD New Tools: 4D CAD Construction AnimationConstruction Animation
• Research– Stanford University (www.stanford.edu)– Bauhaus-Universitat Weimar (www.uni-
weimar.de)– Yonsei University
(archmedia.yonsei.ac.kr)• Examples of use:
– Motorway and Highway Development (www.polyimage.co.uk)
– Building modeling (www.xscad.com)– Equipment movement
(www.cadjapan.com)
New Tools: GPS for New Tools: GPS for Monitoring and ControlMonitoring and Control
• Plan Exact Location of Equipment for Optimum Performance
• Provide Real Time Feedback and Control During Construction– Earth Moving– Equipment Location– Large Component Location
• Monitor Over Long Term– Movement Under Normal Load
Conditions– Movement Under Extreme Load
Conditions
New Tools: GPS for New Tools: GPS for Monitoring and ControlMonitoring and Control
• Research– Field conditions (www.ars.usda.gov)– Indiana University (www.indiana.edu)
• Examples of use– Pipeline mapping (State of California,
osfm.fire.ca.gov)– Surveying (www.forerunnercorp.com)
New Tools: Radio Frequency New Tools: Radio Frequency IdentifiersIdentifiers
• Tag Components, Material or Equipment Tied to Computer-aided Design and Manufacturing
• Track Throughout Fabrication and Shipping
• Improve Speed and Accuracy of Inventory On-site
• Reduce Theft and Loss• Monitor Performance In-situ
New Tools: Radio Frequency New Tools: Radio Frequency IdentifiersIdentifiers
• Research– In-situ sensors (Carnegie-Mellon
University, www.ce.cmu.edu)• Examples of use
– Construction inventory control (www.zebra.com)
• Resources– ENR, “Researchers are getting
serious about electronic tracking tags” (12/13/04)
– RFID Centre (www.rfidc.com)
Key Issues in Project Key Issues in Project Management and ControlManagement and Control
• Data Quality• Speed of Analysis• Speed of Decision Making*• Clear Communications• Accurate Tracking and Recording
New Tools Can Address Most (but Not All*) Key Issues in Project Management