New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first...
Transcript of New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first...
![Page 1: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/1.jpg)
1
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
WSE 12.1_Bl23 rev 1, 2016-01-08
Mats Olsson Westinghouse SwedenSebastian Trappen KSB
New reactor Internal Pumpsin Olkiluoto 1 and 2
![Page 2: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/2.jpg)
2
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Introduction/background
Replacement of ReactorInternal Pumps inOlkiluoto 1 and 2
• Introduction/background• Project set-up, scope, schedule• Technical solutions• Challenges/risks• Lessons learned
![Page 3: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/3.jpg)
3
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Introduction/backgroundTVO need to replace existing reactor internal pumps inOlkiluoto 1 and 2 because of
- design life reached for the existing system and difficult toget spare parts
In addition, the technical solution should- be prepared for a future power uprate (+20% flow rate)- enable the drive system to be classified non-safety
![Page 4: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/4.jpg)
4
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Technical solutionsReactor internal pumps has less inertia compared withexternal pumps, and to maintain dryout margins, additionalinertia are installed in the drive systems
• Oskarshamn 1 Ringhals 11st generation Atom BWR, external pumps
• Forsmark 1,2 (Olkiluoto 1,2)3rd generation Atom BWR, internal pumps
• Oskarshamn 34th generation Atom BWR, internal pumps
![Page 5: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/5.jpg)
5
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Technical SolutionKSB PSR 570-FW pump
Wet-winding motor pump unitwith internal flywheel
New pump utilizing existing diffusorNo changes of RPV connections
Increased- pump length + 400 mm- weight + 1670 kg
![Page 6: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/6.jpg)
6
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Operating Temperature [°C] 274
Operating Pressure [kPa] 7400
Design Termperature [°C] 300
Design Pressure [kPa] 8500
Current UprateOperatingPoints
OP 1 OP 2 OP 1 OP 2
Q [m³/s] perpump
1,65 1,82 1,96 2,19
H [m] 23 28 33 41n [rpm] max = 1550
New Reactor Internal Pump design data
![Page 7: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/7.jpg)
7
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Project set-up, scope and schedule
![Page 8: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/8.jpg)
8
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Division of Responsibility (DOR) - Communication
Close communication between all partiesfacilitated by integrating KSB into the project team
Main contractorProject managementService equipmentInstallation
Design and delivery of12 + 4 reactor internalpumpsTesting
CommissioningTraining
Drive systemRPV loadsRPV verifications
![Page 9: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/9.jpg)
9
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
• Design/engineering, manufacturing, licensingand delivery of 12 + 4 reactor internal pumps
• Testing including• Hydraulic model test• Full load motor test (48 h on each motor)• Coast down test
• Service equipment• New hovercraft• Design and delivery of ~20 new tools and
adaptation of a few existing tools• Diffusor wearing tool
• Piping• Strength calculations• Pipe connections
• Installation• Commissioning• Training
Scope overview
KSB
WSE
KSB/WSE
![Page 10: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/10.jpg)
10
Westinghouse Proprietary Class 2 © 2014 Westinghouse Electric Sweden AB. All Rights Reserved.
Partial Deliveries• Three partial deliveries for installation at the outage each
year
![Page 11: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/11.jpg)
11
Westinghouse Proprietary Class 2 © 2014 Westinghouse Electric Sweden AB. All Rights Reserved.
Schedule overviewContract July 2014• Overall Project documentation Oct 2014• Manufacturing approval Dec 2014• Hydraulic model test Feb 2015• Manufacturing start of special tools Mar 2015FAT of 1st pump Feb 2016• FAT of special tools April 2016• Delivery to Olkiluoto of 1st RIP May 2016Completed installation of 1st RIP June 2016• FAT and delivery of RIPs for OL2 Feb 2017• Installation OL2 June 2017• Delivery of RIPs for OL1 Feb 2018Installation OL1 June 2018
![Page 12: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/12.jpg)
12
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Challenges
![Page 13: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/13.jpg)
13
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Challenges• Short lead time, less than 2 years(!) from contract signing
until finalized installation of the first pump
• New YVL guides applied for the first time in a project of thissize
• Interface towards a new drive system
• New pump utilizing existing diffusor
• Diffuser wear ring issue (old rings stuck)
![Page 14: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/14.jpg)
14
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Challenges• Several projects in the reactor pressure vessel on-going at
the same time with risk of interferences
• Installation, testing and commissioningof pumps within available outage window
• Limited space for installation- Downcumer
- Pumpdeck
- Transport path
![Page 15: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/15.jpg)
15
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Limited space for installation
Pump impeller/shaft need tobe transported horizontal inthe downcumer. Then slidingon the core shroud and thepump diffusor.
![Page 16: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/16.jpg)
16
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
![Page 17: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/17.jpg)
17
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Tools overview
• The tools are divided in to threegroups– The new hovercraft– Adoption of the design of existing
tools– Redesign of existing tool for
replacement of diffuser wear ring forthe test in 2015
• Special tools for mounting and dismounting the pumps areincluded in the scope of supply
![Page 18: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/18.jpg)
18
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Limited space for pump handling
![Page 19: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/19.jpg)
19
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Factory testing and verifications
![Page 20: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/20.jpg)
20
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Functional Testings and VerificationsKSB workshop in Frankenthal
February 2015• Hydraulic model test
Autumn 2015 (first assembly)• Functional testing in the test loop• Verification of special tools together
with the first pump
February 2016• Factory Acceptance Test (FAT)• Full load motor test (48 hours)
June 2016• Site test/verifications first RIP
November 2016• Coast Down Test (all pumps in test loop)
![Page 21: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/21.jpg)
21
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Functional Testing (hydraulic model test)Approval of testing organizationaccording to YVL 1.3
![Page 22: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/22.jpg)
22
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Factory Acceptance Test incl. 48 hours test• Original drive system used• 10 starts and stops• 48 h endurance test• Different load points
load pump
test rig
motor to be testedmotor cooler
drive system
test loop
![Page 23: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/23.jpg)
23
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Coast Down Curve measured vs. calculatedCoast Down Time• Measured in OL 1 (blue)• Cold reactor, all six RIPs tripped together• Test results are showing excellent correspondence with
calculated curve
Calculated
Measured
![Page 24: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/24.jpg)
24
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Coast Down Test (November 2016)• To verify coast down time of the RIP• New test loop developed and
installed• Complete loop optimized via. CFD
(similar flow conditions as in theRPV)
pipe elbow RIP motor
New test loop
![Page 25: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/25.jpg)
25
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Outage Planning and Pump Installation 2016
![Page 26: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/26.jpg)
26
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Installation of Reactor Internal PumpsThe installation of the new RIP were very similarto an ordinary maintenance outage when pumpsare replaced for maintenance.
The main differences were:• The number of pumps to be changed• Two sets of special tools are needed• Rerouting and welding of cooling and
drainage pipes• Installation of new power cables• Installation of new diffusor wear rings
![Page 27: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/27.jpg)
27
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Installation of Reactor Internal Pump 2016
WSE TVO (FECO)
R S
R S
S R
S R
- R
S R
- R
DORGrid
Installation
Commissioning
openreactor
closedreacor
Insulation measurementPhase rotational checkRotation check
12 days
Commissioningcertificate
PTR PTO certificate
30 daysS= SupportR=Responsible
Overview of site sequence
![Page 28: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/28.jpg)
28
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Installation of Reactor Internal Pump 2016• In general installation went very well
– Pump installed according to plan incl diffusor wear ring• CI* pump April 21• Delivery to site (pump and tools) May 6• Approved receipt inspection May 10• Disassembly of pump for inspection (pump/tools) May 17• CI piping material May 21• CI cooling piping installation May 26• CI small bore piping installation May 28• Construction inspection complete installation June 1
• Very good co-operation Westinghouse/KSB/TVO/STUK on site* CI=Construction Inspection
![Page 29: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/29.jpg)
29
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Lessons learned / Risk process
![Page 30: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/30.jpg)
30
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Iterative Risk processRisks identified and handled atregularly- Weekly meetings (WSE/KSB)
- Monthly Project meetingsWSE/TVO/KSB
- Regular joint STECO-meetings
Example of major mitigated risks:- Short schedule- New design– short delivery time- Handling tools – new pump, new
tools design- Installation schedule- Diffuser wear ring issue (old rings
stuck)
![Page 31: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/31.jpg)
31
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Lessons Learned / Summary
![Page 32: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/32.jpg)
32
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Lessons Learned / Summary• Short lead time – full time committed project team• Mixed project team - less interfaces• Successful iterative risk process (TVO/W/KSB)• Licensing documentation - early involvement of STUK• The pre-installation of one pump gave many very valuable
experiences for the coming installations.• Engineering team (W/KSB) on site resulted in that
questions/issues could quickly be resolved
• Next year – Target to keep as many from installationteam as possible. Less engineering support but LeadEngineer and Piping supervisor will still be needed onsite
![Page 33: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools](https://reader034.fdocuments.us/reader034/viewer/2022042102/5e7fda1f9d779141bf3fafea/html5/thumbnails/33.jpg)
33
Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.
Thank you !