New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first...

33
1 Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved. WSE 12.1_Bl23 rev 1, 2016-01-08 Mats Olsson Westinghouse Sweden Sebastian Trappen KSB New reactor Internal Pumps in Olkiluoto 1 and 2

Transcript of New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first...

Page 1: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

1

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

WSE 12.1_Bl23 rev 1, 2016-01-08

Mats Olsson Westinghouse SwedenSebastian Trappen KSB

New reactor Internal Pumpsin Olkiluoto 1 and 2

Page 2: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

2

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Introduction/background

Replacement of ReactorInternal Pumps inOlkiluoto 1 and 2

• Introduction/background• Project set-up, scope, schedule• Technical solutions• Challenges/risks• Lessons learned

Page 3: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

3

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Introduction/backgroundTVO need to replace existing reactor internal pumps inOlkiluoto 1 and 2 because of

- design life reached for the existing system and difficult toget spare parts

In addition, the technical solution should- be prepared for a future power uprate (+20% flow rate)- enable the drive system to be classified non-safety

Page 4: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

4

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Technical solutionsReactor internal pumps has less inertia compared withexternal pumps, and to maintain dryout margins, additionalinertia are installed in the drive systems

• Oskarshamn 1 Ringhals 11st generation Atom BWR, external pumps

• Forsmark 1,2 (Olkiluoto 1,2)3rd generation Atom BWR, internal pumps

• Oskarshamn 34th generation Atom BWR, internal pumps

Page 5: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

5

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Technical SolutionKSB PSR 570-FW pump

Wet-winding motor pump unitwith internal flywheel

New pump utilizing existing diffusorNo changes of RPV connections

Increased- pump length + 400 mm- weight + 1670 kg

Page 6: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

6

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Operating Temperature [°C] 274

Operating Pressure [kPa] 7400

Design Termperature [°C] 300

Design Pressure [kPa] 8500

Current UprateOperatingPoints

OP 1 OP 2 OP 1 OP 2

Q [m³/s] perpump

1,65 1,82 1,96 2,19

H [m] 23 28 33 41n [rpm] max = 1550

New Reactor Internal Pump design data

Page 7: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

7

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Project set-up, scope and schedule

Page 8: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

8

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Division of Responsibility (DOR) - Communication

Close communication between all partiesfacilitated by integrating KSB into the project team

Main contractorProject managementService equipmentInstallation

Design and delivery of12 + 4 reactor internalpumpsTesting

CommissioningTraining

Drive systemRPV loadsRPV verifications

Page 9: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

9

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

• Design/engineering, manufacturing, licensingand delivery of 12 + 4 reactor internal pumps

• Testing including• Hydraulic model test• Full load motor test (48 h on each motor)• Coast down test

• Service equipment• New hovercraft• Design and delivery of ~20 new tools and

adaptation of a few existing tools• Diffusor wearing tool

• Piping• Strength calculations• Pipe connections

• Installation• Commissioning• Training

Scope overview

KSB

WSE

KSB/WSE

Page 10: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

10

Westinghouse Proprietary Class 2 © 2014 Westinghouse Electric Sweden AB. All Rights Reserved.

Partial Deliveries• Three partial deliveries for installation at the outage each

year

Page 11: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

11

Westinghouse Proprietary Class 2 © 2014 Westinghouse Electric Sweden AB. All Rights Reserved.

Schedule overviewContract July 2014• Overall Project documentation Oct 2014• Manufacturing approval Dec 2014• Hydraulic model test Feb 2015• Manufacturing start of special tools Mar 2015FAT of 1st pump Feb 2016• FAT of special tools April 2016• Delivery to Olkiluoto of 1st RIP May 2016Completed installation of 1st RIP June 2016• FAT and delivery of RIPs for OL2 Feb 2017• Installation OL2 June 2017• Delivery of RIPs for OL1 Feb 2018Installation OL1 June 2018

Page 12: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

12

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Challenges

Page 13: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

13

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Challenges• Short lead time, less than 2 years(!) from contract signing

until finalized installation of the first pump

• New YVL guides applied for the first time in a project of thissize

• Interface towards a new drive system

• New pump utilizing existing diffusor

• Diffuser wear ring issue (old rings stuck)

Page 14: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

14

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Challenges• Several projects in the reactor pressure vessel on-going at

the same time with risk of interferences

• Installation, testing and commissioningof pumps within available outage window

• Limited space for installation- Downcumer

- Pumpdeck

- Transport path

Page 15: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

15

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Limited space for installation

Pump impeller/shaft need tobe transported horizontal inthe downcumer. Then slidingon the core shroud and thepump diffusor.

Page 16: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

16

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Page 17: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

17

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Tools overview

• The tools are divided in to threegroups– The new hovercraft– Adoption of the design of existing

tools– Redesign of existing tool for

replacement of diffuser wear ring forthe test in 2015

• Special tools for mounting and dismounting the pumps areincluded in the scope of supply

Page 18: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

18

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Limited space for pump handling

Page 19: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

19

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Factory testing and verifications

Page 20: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

20

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Functional Testings and VerificationsKSB workshop in Frankenthal

February 2015• Hydraulic model test

Autumn 2015 (first assembly)• Functional testing in the test loop• Verification of special tools together

with the first pump

February 2016• Factory Acceptance Test (FAT)• Full load motor test (48 hours)

June 2016• Site test/verifications first RIP

November 2016• Coast Down Test (all pumps in test loop)

Page 21: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

21

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Functional Testing (hydraulic model test)Approval of testing organizationaccording to YVL 1.3

Page 22: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

22

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Factory Acceptance Test incl. 48 hours test• Original drive system used• 10 starts and stops• 48 h endurance test• Different load points

load pump

test rig

motor to be testedmotor cooler

drive system

test loop

Page 23: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

23

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Coast Down Curve measured vs. calculatedCoast Down Time• Measured in OL 1 (blue)• Cold reactor, all six RIPs tripped together• Test results are showing excellent correspondence with

calculated curve

Calculated

Measured

Page 24: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

24

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Coast Down Test (November 2016)• To verify coast down time of the RIP• New test loop developed and

installed• Complete loop optimized via. CFD

(similar flow conditions as in theRPV)

pipe elbow RIP motor

New test loop

Page 25: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

25

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Outage Planning and Pump Installation 2016

Page 26: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

26

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Installation of Reactor Internal PumpsThe installation of the new RIP were very similarto an ordinary maintenance outage when pumpsare replaced for maintenance.

The main differences were:• The number of pumps to be changed• Two sets of special tools are needed• Rerouting and welding of cooling and

drainage pipes• Installation of new power cables• Installation of new diffusor wear rings

Page 27: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

27

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Installation of Reactor Internal Pump 2016

WSE TVO (FECO)

R S

R S

S R

S R

- R

S R

- R

DORGrid

Installation

Commissioning

openreactor

closedreacor

Insulation measurementPhase rotational checkRotation check

12 days

Commissioningcertificate

PTR PTO certificate

30 daysS= SupportR=Responsible

Overview of site sequence

Page 28: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

28

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Installation of Reactor Internal Pump 2016• In general installation went very well

– Pump installed according to plan incl diffusor wear ring• CI* pump April 21• Delivery to site (pump and tools) May 6• Approved receipt inspection May 10• Disassembly of pump for inspection (pump/tools) May 17• CI piping material May 21• CI cooling piping installation May 26• CI small bore piping installation May 28• Construction inspection complete installation June 1

• Very good co-operation Westinghouse/KSB/TVO/STUK on site* CI=Construction Inspection

Page 29: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

29

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Lessons learned / Risk process

Page 30: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

30

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Iterative Risk processRisks identified and handled atregularly- Weekly meetings (WSE/KSB)

- Monthly Project meetingsWSE/TVO/KSB

- Regular joint STECO-meetings

Example of major mitigated risks:- Short schedule- New design– short delivery time- Handling tools – new pump, new

tools design- Installation schedule- Diffuser wear ring issue (old rings

stuck)

Page 31: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

31

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Lessons Learned / Summary

Page 32: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

32

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Lessons Learned / Summary• Short lead time – full time committed project team• Mixed project team - less interfaces• Successful iterative risk process (TVO/W/KSB)• Licensing documentation - early involvement of STUK• The pre-installation of one pump gave many very valuable

experiences for the coming installations.• Engineering team (W/KSB) on site resulted in that

questions/issues could quickly be resolved

• Next year – Target to keep as many from installationteam as possible. Less engineering support but LeadEngineer and Piping supervisor will still be needed onsite

Page 33: New reactor Internal Pumps in Olkiluoto 1 and 2 · • Hydraulic model test Autumn 2015 (first assembly) • Functional testing in the test loop • Verification of special tools

33

Westinghouse Proprietary Class 3 © 2016 Westinghouse Electric Sweden AB. All Rights Reserved.

Thank you !