New Market Perspectives for large-scale PV Installations ...
Transcript of New Market Perspectives for large-scale PV Installations ...
Bundesverband Solarwirtschaft e.V. (BSW-Solar)
New Market Perspectives for large-scale
PV Installations in Germany
- regulatory framework, targets and changes -
German Solar Association
Feb. 13th, 2019
German Solar Association: Who we are
© BSW-Solar
2
TASK To represent the solar industry in Germany in the
thermal and photovoltaic and storage sector
VISION A sustainable global energy supply provided by solar
(renewable) energy
ACTIVITIES Lobbying, political advice, public relations, market
observation, standardization
EXPERIENCE Active in the solar energy sector for over 40 years
REPRESENTS More than 800 members along the complete value
chain active in the solar business
HEADQUARTERS Berlin, Germany
www.solarwirtschaft.de
Services on the German market
© BSW-Solar
3
Exploring solar markets worldwide
© BSW-Solar
4
Worldwide activities of the Association
© BSW-Solar
Cooperation with solar
organization Projects Projects/Cooperation with solar
organization
5
Agenda
© BSW-Solar
6
• Recent German PV market development
• Political background and discussion
• Regulatory changes for large-scale PV
installations
• Summary & Outlook
Recent Market Development (I)
• In 2018 German PV market was growing for the third time in a row
• Commercial segment has recently been the main market driver
• Installation of ground mounted PV is concentrated in eastern Germany
© BSW-Solar
7
160 MW
PV Market Segment Development in Germany Regional spread of ground mounted
PV projects since 2015
( 1.7 GW in total)
Recent Market Development (II) - Tender
© BSW-Solar
8
• Since first round in April 2015 average strike prices nearly cut in half
• Intensity of competition has been constantly high
• So far more than 90% of rewarded projects were realized in time
PV tender results and level of strike prices since April 2015
Political background – Extra tenders
• Coalition agreement of government demanded 4 GW extra capacity for
each PV and Wind until 2020
• Agreement required that the grid has to be prepared for higher RE
share
• The negotiations were difficult and took longer then expected
• Finally a revision of the German renewable energy act (EEG) was
adopted in late fall 2018
• The compromise included the agreed volumes of extra tenders for both
PV and Wind installations until 2021
• On the other side in order to improve grid stability and system
integration of RE innovation tenders were introduced
© BSW-Solar
9
Picture: BSW-Solar
What’s new in detail?
• Extra Tenders:
– Germany will put out additional 4 GW for tender until 2021
– The auctions will be conducted according to the existing rules for
PV tenders, like f.eg.:
• minimum Size of 750kW
• maximum Size of 10MW
• special requirements regarding the area of installation
• Innovation Tenders:
– Aim of innovation tenders is to examine new pricing and auctioning
mechanisms to increase competition and to proivde more grid
friendliness of RE installations
– In sum 1.15 GW are planed to be tendered that way until 2021
– Detailed requirements for the participation will be settled in a
special regulation this year
• New, reduced volumes for regular PV auctions
© BSW-Solar
10
Scheduled auction dates and volumes
© BSW-Solar
11
Extra Tenders - 4 GW extra PV capacity
• In order to increase the competition, extra tenders will grow from
1 GW in 2019, to 1.4 GW in 2020 up to 1.6 GW in 2021
• Compared to the 600 MW PV capacity which has so far been tendered
per year this is a significant increase
• German Solar Association estimates that this might correspond to an
additional sales potential between 3.5 to 4.5 billion EUR for companies
active in Germany
• The first extra-tender round is scheduled for March
© BSW-Solar
12
Dates and volumes Extra tenders in Germany
New Innovation-Tenders
• Innovation tenders were already included in the renewable energy act
of 2017, yet have never been implemented
• Now the new agreement includes even higher volumes
• Special regulation will determine the conditions
• The regulation might include:
– no compensation when market prices are negative
– incentives for hybrid installations (f.eg. PV-Wind combination)
– fixed market premium
– …
© BSW-Solar
13
Dates and volumes Extra tenders in Germany
Summary & Outlook
© BSW-Solar
14
• Germany introduced the tender support scheme for PV installations
above 750kW in 2015
• So far results demonstrate high competition and a significant price
decrease over the past years
• After a long debate German government decided to introduce extra
tender volumes, starting with 1 GW in 2019, 1.4 GW in 2020 and
finally 1.6 GW in 2021
• According to our estimations this will in sum induce additional
investments of about 3 to 4 billion Euros in the German PV market
• Ongoing high competition and low levels of average strike prices are
expected
Source: Solarmarkt
Thank you for your attention…
David Krehan Political Advisor
© BSW-Solar
15
Legal framework for tenders
Intersolar Europe Webinar, February 13, 2019
Dr. Hartwig von Bredow
We offer comprehensive legal support for companies in the field of the production, storage and consumption of renewable energies
Conceptual and strategic advice
Drafting and reviewing of contracts
Representation in administrative proceedings, proceedings concerning
energy law and civil litigations
Expert analysis of legal inquiries, DD, legal opinions…
Our clients are plant operators, utilities, project developers, equipment manufacturers, energy traders, agricultural companies and financing banks.
Facts:
founded in 2012
highly specialized
10 Lawyers
Seated in Berlin
About us…
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 2
Dr. Hartwig von Bredow Attorney-at-law (Rechtsanwalt)
In the field of PV projects
...we advise manufacturers, project developers, operators and utility companies on all legal issues
concerning PV projects.
...we review and develop new business models together with our customers.
...we review, develop, draft and negotiate all relevant contracts (EPC Contracts, Operation & Maintenance
Contracts, Power Purchase and Trading Agreements, etc.).
...we help to ensure grid access and the financial support (feed-in tariffs & auctions)
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 3
Overview
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 4
General remarks Auctions Legal questions
Renewable Energy Sources Act (EEG 2017) grants
R Priority grid access and compensation in case of curtail of feed-in
R Feed-in tariffs / market premium for 20 years guaranteed
Mandatory market premium model since 2014
Tenders for all renewable energy sources since 2017
R Statutory feed-in tariffs only for small installations
R Pilot tenders for solar installations started in 2015
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 5
Financial support for PV in Germany
Obligation to report to Federal Grid Agency (Bundesnetzagentur)
Obligation to market the electricity directly for installations with more than 100 kW installed power
Technical requirements: devices that allow the grid system operator and the direct seller to
R call up the current level of feed-in
R reduce feed-in by remote control
Prohibition of self-supply
R Operators may not use the electricity generated in their installation for self-supply
R Does not apply, among others, to electricity consumed within the installation or when feed-in is reduced due to network congestion
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 6
Good to know…
Overview
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 7
General remarks Auctions Legal questions
Subject of the tender is the market premium (“value to be applied”)
R Remuneration for electricity fed into the grid
R Guaranteed for 20 years
The bid is submitted for a concrete project. However, award can be referred to other areas (premium reduced by 0.3 ct/kWh)
Pay-as-bid tender (no uniform pricing)
Maximum value: 8.91 ct/kWh, lowest bids will be awarded
Time limit for realisation: 18 months (after: reduced by 0.3 ct/kWh) or 24 months
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 8
Main aspects
Executing agency for all auctions: Federal Network Agency
Watch out: strictly formal procedure
R The forms published by the Federal Network Agency must be used
R It seems rather simple, but errors will lead to definite exclusion from tender
R Several court proceedings are pending
Formal requirement for the bids
R declaration of bidder that he owns the site or has the approval of the owner
R Copy of the decision on the establishment / amendment of the land-use plan, copy of the
disclosure decision, copy of the adopted land-use plan
R No copy of the cadastral exert required
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 9
Fromal Procedure
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 10
Overview of the auction procedure
First securityand fees
Second securityand fees
Announcementof the auction
Bid deadlines Awards
Commissioningand application
for paymentauthorisation
5 to 8 weeks Few days 10 days 18 months (max. 24 months)
Obligation to participate for all PV installations with an installed capacity of more than
750 kWp
R ground-mounted PV installations as well as for roof-top installations
R Minimum size of installation: 750 kWp
R Maximum size of installation: 10 MWp
Only certain places of installation (e.g. buildings, conversation areas, etc.) are eligible
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 11
Size and place of installation
Securities
R First security: 5 Euros per kW (to be paid upon bidding)
R Second security: 45 Euros per kW
to be paid at the latest on the tenth working day following the public announcement of the award
only 20 Euros per kW if a land-use plan has already been adopted or a planning approval decision exists
Instead of payment deposit of a security / bailment is also possible
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 12
Securities
Overview
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 13
General remarks Auctions Legal questions
Who am I, and if so how many?
Sect. 3 n° 1
“installation” shall mean every facility to generate electricity from renewable energy sources or from mine gas; whereas
in case of solar power installations each module is considered a separate installation; ....”
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 14
The definition of an installation
Sec. 24 RESA 2017
(1) Several installations shall …. be regarded as one installation if
1. they are located … in the immediate vicinity, …
4. they have commenced operations within twelve consecutive calendar months.
… In derogation of sentence 1, ground-mounted installations shall not be counted together with solar installations in or on buildings and noise protection walls.
(2) Without prejudice to subsection 1 sentence 1, several ground-mounted installations shall … be deemed equivalent to one installation if they
1. have been constructed within the same municipality ….and
2. have been commissioned within twenty-four consecutive calendar months, spaced up to a linear distance of two kilometres apart measured from the outside edge of the respective installation.
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 15
Several installations (1/3)
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 16
Several installations (2/3)
749,99 kWp 500 kWp
Installation N° 1 = statutory feed-in tariff (without tender)
Installation N° 2 =- no statutory feed-in tariff (as its installed capacity is considered to be more than 750 kWp)- no tender (as tenders are open only to installation with more than 750 kWp) à no financial support at all
Immediate vicinity / same municipalityand 2 km
Commissioningwithin 12 / 24 months
Dr. Hartwig von Bredow – Intersolar Europe Webinar - 13 February 2019 17
Several installations (3/3)
749,99 kWp
1.000 kWp
Installation N° 1 = statutory feed-in tariff (without tender)
Installation N° 2 =- no statutory feed-in tariff (as its installed capacity is considered to be more than 750 kWp)- Admissable for tender
Immediate vicinity / same municipalityand 2 km
Commissioningwithin 12 / 24 months
Littenstraße 10510179 Berlin
T: +49-30-8092482-20F: +49-30-8092482-30
[email protected] www.vonbredow-valentin-herz.de
www.twitter.com/EE_Recht
Dr. Hartwig von Bredow
••
Large-scale PV-installations
eligible areas, aspects of construction law
•
Overview
I. Areas eligible for financial support
II. Area-related restrictions for installations without financial support
III. Large scale PV-installations and construction law
IV. Some practical advice
13.02.2019 Large-scale PV-installations 2Margarete von Oppen, [email protected] www.asd-law.com
•
I. Areas eligible for financial support
The realization of large scale pv-installations under the EEG support schemes
requires construction on specific sites.
1. Background
2. Categorization
3. Examples of areas
4. Specific land area categories in case of tender
3Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.1. Background
Land use conflicts between renewable energy installations and environmental
protection
Prioritization of PV-installations on rooftops as already sealed areas (unlike wind
turbines)
Concentration of ground-mounted PV-installations on areas of “inferior
environmental” quality
4Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.2. Categorization
The areas deemed of “inferior environmental quality” were determined in a political process (7
for installations up to 750 kWp; 10 for pv installations with compulsory tendering process). So
it´s not about logic.
Nonetheless, it´s possible to classify the areas according to certain characteristics.
a. Constructions other than buildings (no formal planning, e.g. zoning plan)
b. Only formal planning
Zoning plan prior to September 2003
Zoning plan prior to January 2010 for commercial or industrial purposes
Area subject of a plan approval procedure (= complex administrative procedure)
c. Zoning plan + soil of minor quality
Conversion area (economic, military, residential construction, traffic construction)
Areas along a highway or a railway
Sealed
5Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.3. Examples of areas - 1
Constructions other than buildings (e.g. landfill site, gravel pits)
6Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.3. Examples of areas - 2
Zoning-plan for business parks and industrial estates
(GE/GI)
7Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.3. Examples of areas - 3
Area in a corridor of 110 m along a motorway or railway track
8Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.4. Specific land area categories in case of tender (1)
Larger variety of eligible areas in case of tender; zoning plan + specific area
Areas owned by the Federal Republic or the Federal Authority for Real Property
Administration (Bundesanstalt für Immobilienaufgaben = BIMA), which have
been managed by BIMA after 31.12.2013 and have been published on the
BIMA-Website for solar purposes (https://www.bundesimmobilien.de)
Plots of land in less-favoured areas according to European agricultural law,
under the following conditions
The land was grassland at the time the development of the zoning plan was
approved by the competent community or
The land was farmland at the time the development of the zoning plan was
approved by the competent community and
The respective federal state adopted a regulation according to that the federal
state opens tenders for the aforementioned areas
9Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
I.4. Specific land area categories in case of tender (2)
10Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
II. Area-related restrictions for installations without financial support
The existence of a support scheme does not exclude the installation of pv-plants
without support.
High spot market prices for electricity and low tender outcomes have fuelled
a hyped discussion in Germany right now.
In principle free choice of area for construction.
Nevertheless legal limitations come from building – and environmental law.
See III
11Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III. Large-scale installations and building law
1. Concept of plant permit in Germany
2. Area with zoning plan
3. Area without zoning plan
4. Development of a zoning plan
5. Duration of the procedures
12Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III.1. Concept of plant permit in Germany
Principle. Construction of a Large scale pv-installations requires a building permit (unlike
roof-top installations)
Conditions for authorization. A building permit has to be granted if there is no conflict with
the applicable public law.
Relevant public law provisions are mainly
o Planning regulations
o Environmental law
o Conservation law
13Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III.2. Area with zoning plan
1. Specific zoning plan for solar installations: The permit has to be granted
2. Unspecific zoning plan, e.g. zoning plan for business parks or industrial estates.
Depends on the stipulations of the plan. Often, it’s necessary to ask for exemptions.
14Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III.3. Area without zoning plan
1.Premise. Large scale pv-installations are to built in exterior areas in the sense of the
German Building Code, not in the cities
2.Theory. There are stipulations in the German Building Code that allow under certain
conditions constructions in exterior areas (e.g. must not be in conflict with the landscape)
3.Practice. Large scale pv-installations are in general too big. Therefore most communities or
districts see a so called “planning requirement” independent of a support scheme.
15Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III.4. Development of a zoning plan
1. Convince the competent authority (municipality/municipal council)
2. Municipal council approves the development of a zoning plan
3. Regional planning has to be observed (sometimes relevant restrictions)
4. Two phases of participation of the public
5. Two phases of participation of the relevant public authorities
6. Administration prepares the zoning plan and tries to balance the different
interests
7. Municipal council approves the zoning plan
16Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
III.5. Duration of the procedures
1. Zoning plan. Quick: under 6 month; long: up to 18 months
2. Permit. Regularly under 3 months; often quicker, sometimes longer
17Margarete von Oppen, [email protected] www.asd-law.com
13.02.2019 Large-scale PV-installations
•
Thank you for your attention!
Margarete von Oppen [email protected]
1813.02.2019 Large-scale PV-installations
•