Integrating Renewables into the European Power System
1
Dr. Susanne NiesCorporate Affairs Manager, ENTSO-E
EU-GCC Workshop: Electricity Interconnections and Trading for Growth and Efficiency
21 May, 2017
![Page 2: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/2.jpg)
ENTSO-E INSTRUMENTAL FOR THE CHANGE
2
300 000 km of
transmission lines
3300 TWh electricity
consumption
43 TSOs
36 countries
over 500 million
customers servedof the global
electricity
consumption
15%
![Page 3: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/3.jpg)
Network Codes facilitate EU policies
• 260 GW of RES connected
• 25 GW in 2016
• >10 GW of EU demand
side response
• NO multi-state interruptions recent years
• Up to 300 coordinated tasks/day in a RSC
• Hundreds trained employees in RSCs
programs and offices
• 23 states and 85% of European
consumption market coupled
• 10 million data files made available
yearly for 2500 daily users of
ENTSO-E transparency platform
Security of supply
Competitiveness & Social WelfareSustainability
Network codes
![Page 4: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/4.jpg)
THE ENERGY TRANSITION
Wind
Solar
Hydro
potential
Flow
North-south
Flow
North-East
South-West
Illustration of main RES potential across Europe towards 2030
27% RES policy goal means 45%of generation from renewables in the power transmission system
+30% energy
efficiency
-40% CO2
emissions
27%
Renewable
Energy
Sources
The EU’s 2030 goals
![Page 5: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/5.jpg)
EU TARGETS NEED ADEQUATE INFRASTRUCTURE
Regional differences & needs
must be considered
TSOs plan adequate
infrastructure investments
(TYNDPs)
Exchange of
flexibility
Geo-
political
Loop-flows
Physical
congestions
Market
integration
TYNDP 2016 investments at
€150bn
80% of TYNDP projects are due to
accommodate RES into the system
![Page 6: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/6.jpg)
6
BUILDING GRIDS AND CREATING VALUE (TYNDP 2016)
Consumers Society/Climate
Higher grid cost:
1,5 – 2 €/MWh
Lower wholesaleprices:
1,5 – 5 €/MWh
Emissions down by:
50 – 80%
Reduced spillage of renewable energy by:
30 – 90 TWh
Emissions
reduction
only due
to grid:
8%but…
![Page 7: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/7.jpg)
7
Aggregated PV feed-in from selected Continental Europe TSOs, 20
March 2015
22
GW
at
9.30a
m
35 GW
at
12.00
am
14 GW
at
10.00
am
The 2015 solar eclipse as a test for the future
challenges
• Successful preparation and cooperation avoiding disturbances
• Minimum cost: 4.2 M€ for additional reserves, cost of a black-out (~450-600 M€ / hour for
Germany)
• Increasing risks: expected RES ramping of 32GW/h after the eclipse in August 2027
(14GW/h in 2015)
Situation Solutions
1 Coordinated security analysis
> TSOs coordinated their assessment of the situation
2 Coordinated planning
> Anticipation of issues> Secured reserves and emergency plans
3 Real-time coordination between TSOs
> Real-time communication between TSOs during the eclipse
> Frequency quality was maintained
![Page 8: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/8.jpg)
8
The Flexibility challenge
A new role for our networks…
From asset……………………………………..
8
……to smart optimization of generation and load
56% wind power: End-consumers play an
increasingly important role
September 2016 in
Denmark, one week (source Energinet.dk)
![Page 9: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/9.jpg)
Pag
e 9
Flexibility
Service
Providers Flexibility
Bids
Single
Flexibility
Platform
Coordination
functions
3 Single (national) Flexibility Platform
Activations
TSO
Bid selection
for TCM and
Balancing
(specific)
DSO
Bid Selection
for DCM
EU Common
MOL
Bid selection
for
Balancing
(standard)
Data exchanges after Balancing Energy GCT
Activations Balancing
Bids with
Restrictions
Activation
Requests
Flexibility Bids
Limitations
Activation Information
Flexibility Bids
Limitations
Activation Information
Grid impact
analysis
Grid impact
analysis
![Page 10: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/10.jpg)
RES Integration is possible, when..
1
2
3
4
You set the right market framework
You build the grid for it
You establish active system management, with active
customers, smart meters, digitalisation
You have a ONE system approach!
![Page 11: New Integrating Renewables into the European Power System · 2017. 5. 23. · 7 Aggregated PV feed-in from selected Continental Europe TSOs, 20 March 2015 22 GW at 9.30a m 35 GW at](https://reader034.fdocuments.us/reader034/viewer/2022051911/60017bc90bad376bda4146eb/html5/thumbnails/11.jpg)
THANK YOUFOR YOUR ATTENTION