New gold bmo print version corporate presentation - february 2014
-
Upload
newgold2011 -
Category
Investor Relations
-
view
389 -
download
3
Embed Size (px)
description
Transcript of New gold bmo print version corporate presentation - february 2014

BMO Capital Markets
23rd Global Metals &
Mining ConferenceFebruary 2014

Cautionary statements
All monetary amounts in U.S. dollars unless otherwise stated
Total cash costs shown net of by-product sales unless otherwise stated
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS
Certain information contained in this presentation, including any information relating to New Gold’s future financial or operating performance are “forward looking”. All statements in this presentation, other than
statements of historical fact, which address events or developments that New Gold expects to occur are “forward-looking statements”. Forward-looking statements are statements that are not historical facts and
are generally, but not always, identified by the use of forward-looking terminology such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, “projects”,
“potential”, “believes” or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will be taken”, “occur” or “be achieved” or the
negative connotation of such terms. Forward-looking statements in this presentation include, among others, statements with respect to: guidance for production, cash costs and all-in sustaining costs (and its
components) and for growth capital expenditures, including the expected drivers of those figures and the nature and amount of particular expected expenditures; the expected throughput and recovery rates at New
Afton; planned modifications to the New Afton Mine and mill, the expected timeline, outcomes, cost and payback period of any such modifications; planed modifications to other operations; expected future mining
activities; planned exploration expenditures (and their accounting treatment) and drilling activities and costs; exploration potential and the goals and expected results of future exploration activities; the estimation of
mineral reserves and resources and the realization of such estimates; the results of the Rainy River and Blackwater feasibility studies, including the expected production, costs, stripping ratio, mining and
processing method and rate, stockpiling plan, recovery rates, mine life, infrastructure, NPV, IRR and payback period (and related sensitivities associated with each project; the potential annual production, cash
costs and capital costs, and the potential for a block cave, at the El Morro project; the timing of permitting activities and environmental asse ssment processes; and the timeline for development of Rainy River,
including targeted timing for commissioning and full production.
All forward-looking statements in this presentation are based on the opinions and estimates of management as of the date such statements are made and are subject to important risk factors and uncertainties,
many of which are beyond New Gold’s ability to control or predict. Certain material assumptions regarding our forward-looking statements are discussed in this presentation, New Gold’s MD&A, its Annual
Information Form and its Technical Reports filed at www.sedar.com. In addition to, and subject to, such assumptions discussed in more detail elsewhere, the forward-looking statements in this presentation are
also subject to the following assumptions: (1) there being no significant disruptions affecting New Gold’s operations; (2) political and legal developments in jurisdictions where New Gold operates, or may in the
future operate, being consistent with New Gold’s current expectations; (3) the accuracy of New Gold’s current mineral reserve and resource estimates; (4) the exchange rate between the Canadian dollar,
Australian dollar, Mexican Peso and U.S. dollar being approximately consistent with current levels; (5) prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with
current levels; (6) labour and material costs increasing on a basis consistent with New Gold’s current expectations; (7) permitting and arrangements with First Nations and other Aboriginal groups in respect of
Rainy River and Blackwater being consistent with New Gold’s current expectations; (8) all environmental approvals (including the environmental asse ssment process for the Blackwater and Rainy River projects),
required permits, licenses and authorizations being obtained from the relevant governments and other relevant stakeholders within the expected timelines; and (9) the results of the feasibility studies for the Rainy
River and Blackwater projectsbeing realized.
Forward-looking statements are necessarily based on estimates and assumptions that are inherently subject to known and unknown risks, uncertainties and other factors that may cause actual results, level of
activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. Such factors include, without limitation: significant capital requirements; price
volatility in the spot and forward markets for commodities; fluctuations in the international currency markets and in the rates of exchange of the currencies of Canada, the United States, Australia, Mexico and Chile;
discrepancies between actual and estimated production, between actual and estimated reserves and resources and between actual and estimated metallurgical recoveries; changes in national and local
government legislation in Canada, the United States, Australia, Mexico and Chile or any other country in which New Gold currently or may in the future carry on business; taxation; controls, regulations and political
or economic developments in the countries in which New Gold does or may carry on business; the speculative nature of mineral exploration and development, including the risks of obtaining and maintaining the
validity and enforceability of the necessary licenses and permits and complying with the permitting requirements of each jurisdiction in which New Gold operates, including, but not limited to: in Canada, obtaining
the necessary permits for the Blackwater and Rainy River projects; in Mexico, where Cerro San Pedro has a history of ongoing legal challenges related to our environmental authorization (EIS); and in Chile, where
the courts have temporarily suspended the approval of the environmental permit for El Morro; the lack of certainty with respect to foreign legal systems, which may not be immune from the influence of political
pressure, corruption or other factors that are inconsistent with the rule of law; the uncertainties inherent to current and future legal challenges New Gold is or may become a party to; diminishing quantities or
grades of reserves and resources; competition; loss of key employees; additional funding requirements; rising costs of labour, supplies, fuel and equipment; actual results of current exploration or reclamation
activities; uncertainties inherent to mining economic studies including the feasibility studies for Rainy River and Blackwater; changes in project parameters as plans continue to be refined; accidents; labour
disputes; defective title to mineral claims or property or contests over claims to mineral properties; unexpected delays and costs inherent to consulting and accommodating rights of First Nations and other
Aboriginal groups; uncertainties with respect to obtaining all necessary surface and other land use rights or tenure for Rainy River; risks, uncertainties and unanticipated delays associated with obtaining and
maintaining necessary licenses, permits and authorizations and complying with permitting requirements, including those associated with the environmental assessment processe s for Blackwater and Rainy River.
In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental events and hazards, industrial accidents, unusual or unexpected
formations, pressures, cave-ins, flooding and gold bullion losses (and the risk of inadequate insurance or inability to obtain insurance to cover these risks) a s well as “Risk Factors” included in New Gold’s
disclosure documents filed on and available at www.sedar.com.
Forward-looking statements are not guarantees of future performance, and actual results and future events could materially differ from those anticipated in such statements. All of the forward-looking statements
contained in this presentation are qualified by these cautionary statements. New Gold expressly disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new
information, eventsor otherwise, except in accordance with applicable securities laws.
The preliminary information provided for production, sales, total cash costs(1) and all-in sustaining costs(2) are approximate figures and may differ from the final results in the 2013 annual audited financial
statementsand management’sdiscussion and analysis. The footnotesto thispresentation contain important information, refer to appendicesand endnotesfound at the end of the presentation.

Portfolio of assets
in top-ratedjurisdictions
Invested and
experienced team
Amonglowest-cost
producers with established track record
Peer-leading growth pipeline
A history of value creation
New Gold investment thesis
3
18.5 Moz gold
reserves
~$90 million
investment by Board &
Management
Targeting
~$825/oz all-in sustaining
costs(1)
~900 Koz annual
production potential from
growth projects
+250% increase
in share price since March 2009
1. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.

Portfolio of assets in top-rated jurisdictions
Blackwater
New Afton
Rainy River
Mesquite
Cerro San Pedro
El Morro
Peak Mines
Mine Life: 17 years
Mine Life: 10 years
Mine Life: 14 years
Mine Life: 8+ years
Mine Life: 2+ years
Mine Life: 17 years
Mine Life: 6+ years
#2CANADA
#6UNITEDSTATES
#5MEXICO
#3CHILE
#1AUSTRALIA
OPERATING
DEVELOPMENT
4
Mining investment – country rankings(1)
1. Rankings based on 25 countries evaluated in 2013 Behre Dolbear Report – 2013 Ranking of Countries for Mining Investment: “Where Not to Invest”.

Significant increase in gold reserves per share
51. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 9. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical Information”. Measured and Indicated Resources are inclusive of Reserves.
7.8
18.5
YE 2012 YE 2013
GOLD RESERVES(1) (Moz)
21.4
27.5
YE 2012 YE 2013
GOLD M&I RESOURCES(1) (Moz)
+127%
per share
+22%
per share
• Gold reserves increased
by 10.7 million ounces during 2013
• Attributable to
establishing Blackwater reserves and accretive
acquisition of Rainy River
• Silver reserves increased by 58.8 million ounces and
copper reserves remained significant at 3.0 billion
pounds

Collectively ~$90 million invested in New Gold
6
BOARD OF DIRECTORS
David Emerson Former Canadian Cabinet Minister
James Estey Former Chairman, UBS Securities Canada
Robert Gallagher President & Chief Executive Officer
Vahan Kololian Founder, Terra Nova Partners
Martyn Konig Former Executive Chairman, European Goldfields
Pierre Lassonde Chairman, Franco-Nevada
Randall Oliphant Executive Chairman
Raymond Threlkeld Mining Consultant
EXECUTIVE MANAGEMENT TEAM
Randall Oliphant Executive Chairman
Robert Gallagher President & Chief Executive Officer
Brian Penny Executive Vice President & Chief Financial Officer
Ernie Mast Vice President Operations

Lowest costs in company’s history
7
FOURTH QUARTER AND FULL YEAR 2013
• Fourth quarter was the highest
production quarter of 2013
• Met full year production and cost
outlook
• 2013 lowest total cash costs(1) in
New Gold’s history
• Fourth quarter and full year total
cash costs(1) and all-in sustaining
costs(2) further establish
company’s low cost profile
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
107
398
Q4'13 FY 2013
$316$377
Q4'13 FY 2013
$883$899
Q4'13 FY 2013
GOLD PRODUCTION (Koz)
TOTAL CASH COSTS(1) ($/oz)
ALL-IN SUSTAINING COSTS(2) ($/oz)

2013 ACTUAL
398 Koz
2014 GUIDANCE
8
2014 consolidated guidance
1. Gold sales expected to be in the same range as production.
2. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”. All total cash cost estimates (excluding historical amounts) in this presentation assume commodity price assumptions of: Gold - $1,300 per ounce, Silver - $20.00 per ounce, Copper - $3.25 per pound, and CDN/USD - $1.11, AUD/USD - $1.14, MXN/USD - $13.00.
3. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”. All all-in sustaining cost estimates (excluding historical amounts) in this presentation assume commodity price assumptions of: Gold - $1,300 per ounce,
Silver - $20.00 per ounce, Copper - $3.25 per pound, and CDN/USD - $1.11, AUD/USD - $1.14, MXN/USD - $13.00.
380 –
420 Koz
$377/oz$320 –
$340/oz
$899/oz$815 –
$835/oz
Gold production(1)
Total cash costs(2)
All-in sustaining costs(3)
• Continued gold production
increases at New Afton offset
by lower production forecast
at Cerro San Pedro
• Copper production to increase
by approximately 12 percent
• Depreciation of Canadian and
Australian dollars benefits
New Gold costs
• Total cash costs(2) and all-in
sustaining costs(3) well below
industry average

Among lowest-cost producers, established track record
• 2014E all-in sustaining costs(2) to
decrease by over $70 per ounce versus 2013
• Costs benefiting from depreciating
Canadian and Australian dollar
• Generating over $200 per ounce
incremental margin versus average of peer-companies(3) that have provided 2014 guidance
New Gold2014 Reported Average (4)
~$825
9
Lower costs driving higher margins(1)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
3. Based on comparison with costs published by issuers listed in note 4. The manner in which costs are determined may vary from one issuer to another.
4. Average includes: Agnico-Eagle, Alamos, Aurico, Barrick, Detour, Eldorado, Goldcorp, IAMGOLD, Kinross and Newmont. The manner in which costs are determined may vary from one issuer to another.
~$825/oz~$825~$1,045/oz
2014E GUIDANCE –
ALL-IN SUSTAINING COSTS ($/OZ)(2)

Peer-leading growth pipeline
• Growth projects’ production
potential equivalent to over 2x
today’s production
• Blackwater and Rainy River
acquisitions increased shares
outstanding by 25% in total for
potential ~175% increase in
production
• Rainy River and Blackwater benefit
significantly from Canadian dollar
depreciation
• Rainy River $0.05 change in
exchange rate equivalent to
$141 million/2.8% change in
pre-tax NAV/IRR
• Blackwater $0.05 change in
exchange rate equivalent to
$270 million/1.9% change in
pre-tax NAV/IRR
Organic projects
+900 Koz(1) per year
Rainy River
2014E Gold Production
Future Organic Growth Potential
El Morro
10
Four current
operations
Blackwater
New Afton
Expansion
1. Based on ~325Koz annual production from Rainy River, ~485Koz annual production from Blackwater and ~90Koz annual production from El Morro as outlined in the feasibility studies for the projects.

New Afton – A special asset
11
87
102-112
First nine months of
2013 earnings from
mine operations
New Afton = +58%
Gold
(Koz)
72
78-84
Copper
(Mlbs)
2013 2014E
2013 2014E
NEW AFTON
UpsideContribution
Jurisdiction Production
Near-term mill expansion
Longer-term C-zone
potential
British Columbia, Canada
#2Country
Ranking(1)
1. Rankings based on 25 countries evaluated in 2013 Behre Dolbear Report – 2013 Ranking of Countries for Mining Investment: “Where Not to Invest”.
2015 to
benefit
further
from mill
expansion

9,262
11,055 11,967 12,460
Q1 2013 Q2 2013 Q3 2013 Q4 2013
12
1921 21
Q1 2013 Q2 2013 Q3 2013 Q4 2013
THROUGHPUT (tonnes per day)
New Afton moved successfully
beyond design capacity
• Gyratory crusher commissioned in
January 2013
• Completed construction of
32 drawbells in 2013
• Achieved increase to 12,000 tonnes
per day three months ahead of
schedule in September 2013
• Successfully evaluated potential for
further throughput increases going
forward
• 10-fold increase in C-zone Measured
and Indicated resources
12
New Afton – 2013 highlights
15
22
25 25
Q1 2013 Q2 2013 Q3 2013 Q4 2013
PRODUCTION (Koz)
PRODUCTION (Mlbs)
GOLD
COPPER
QUARTERLY AVERAGE THROUGHPUT
PRODUCTION (Koz)

Mill expansion capital estimates
13
Engineering, Construction and Equipment $26 million
Building and Site Works $12 million
Owner’s Costs $2 million
Contingency $5 million
ESTIMATED EXPANSION
CAPITAL
$45
MILLION
• Below is a summary of the key capital estimates for the expansion project
Target: 14,000 tonnes per day at higher metal recoveries
• $35 million of capital to be spent in 2014 with remainder in 2015

Value creation through mill expansion
14
IRR of +50% and payback period of less than two years
2014 TARGETED
AVERAGES
RUN RATE TARGETED AVERAGES
WITH MILL EXPANSION
Throughput
Gold recovery
Copper recovery
12,500 14,000
~85% ~87-88%
~86% ~88-89%
+12%
+2-3%
+2-3%

C-zone overview
15
C-zone
Main
A&B Zone
Isometric view looking NE YEAR-END 2013 C-ZONE(1)
Tonnes
(000’s)
Gold
(g/t)
Copper
(%)
Gold
(Koz)
Copper
(Mlbs)
Measured 618 0.75 0.91 15 12
Indicated 25,223 0.84 0.91 678 504
Total M&I 25,842 0.83 0.91 693 516
Inferred 11,288 0.63 0.64 227 159
1. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 2. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical Information”.

Rainy River
16
Gold Resource/UpsideSituated for Mine
Development
#2
Ontario, Canada
Jurisdiction
Country
Ranking(1)
+169 km2
Land Package
Multiple regional targets
RAINY RIVER
1. Rankings based on 25 countries evaluated in 2013 Behre Dolbear Report – 2013 Ranking of Countries for Mining Investment: “Where Not to Invest”.
2. Development capital assumes $1.11 CDN/USD exchange rate.
3. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
4. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
5. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 9. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical
Information”. Measured and Indicated Resources are inclusive of Reserves.
Flat terrain
Close to infrastructure
17km tie-in to power
+3.8 MozReserves(5)
+6.2 MozM&I Resources(5)
2014 Feasibility StudyFirst nine years:
$613/ozTotal Cash Costs(3)
$736/ozAll-in Sustaining Costs(4)
325 Koz (1.44 g/t)Annual Production
~$840 millionDevelopment Capital(2)

Blackwater
17
UPSIDEGOLD RESOURCE
British Columbia, Canada
BLACKWATER
Regional UpsideSignificant Gold Resource
Jurisdiction
#2Country
Ranking(1)
8.2 MozReserves(5)
9.5 Moz M&I Resources(5)
~1,100 km2
Land Package
Initial resource at
Capoose
Multiple newly
identified targets
1. Rankings based on 25 countries evaluated in 2013 Behre Dolbear Report – 2013 Ranking of Countries for Mining Investment: “Where Not to Invest”.
2. Development capital assumes $1.11 CDN/USD exchange rate.
3. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
4. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
5. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 9. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical
Information”. Measured and Indicated Resources are inclusive of Reserves.
17-yearMine Life
2013 Feasibility StudyFirst nine years:
$555/ozTotal Cash Costs(3)
$685/ozAll-in Sustaining Costs(4)
485 KozAnnual Production
~$1,760 millionDevelopment Capital(2)

El Morro
18
Chile
Higher Grade Block Cave Potential
EL MORRO
Unique Joint Venture
Structure
Gold/Copper Reserve (30%)
+ Upside
Jurisdiction 2011 Feasibility Study (30%)
#3Country
Ranking(1)
85 MlbsAnnual Copper Production
($700/oz)Total Cash Costs(2)
90 KozAnnual Gold Production
Goldcorp 70% partner
Funds 100% of capital
New Gold retains portion of
cash flow from mine start-up
2.7 Moz Gold Reserve(3)
2.0 BlbsCopper Reserve(3)
Life of mine:
1. Rankings based on 25 countries evaluated in 2013 Behre Dolbear Report – 2013 Ranking of Countries for Mining Investment: “Where Not to Invest”.
2. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
3. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 9. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical Information”. Measured and Indicated Resources are inclusive of Reserves.

19
Organic pipeline
• Rainy River development (2015/2016)
• New Afton expansion (mid-2015)
• Mesquite return to run rate (2015+)
• CSP to residual leaching (2016)
Existing low cost production base to be further enhanced by our
lower cost development projects(1)
• Sequence Blackwater development
• El Morro advanced
2014(2) 2017(3) Future Potential(4)
GO
LD
PR
OD
UC
TIO
N
1. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”. Rainy River and Blackwater life-of-mine all-in sustaining costs are estimated to be $736/oz and $685/oz based on their respective Feasibility Studies.
2. Based on mid-point of 2014 guidance.
3. Based on expected annual production from current operations, including positive production impact of New Afton’s mill expansion targeted for mid-2015, Mesquite’s mine plan moving into grades more in line with reserve grade, which is partially offset by Cerro San Pedro ceasing active mining and moving into residual leaching, and includes the first year of full production from Rainy River.
4. Based on ~325Koz annual production from Rainy River, ~485Koz annual production from Blackwater and ~90Koz annual production from El Morro as outlined in their Feasibility Studies for the projects and production contribution from New Afton, Mesquite and the Peak Mines and is dependent on the timely development of Blackwater and El Morro.

Near-term catalysts
20
2014 costs declining versus 2013
New Afton production and cash flow continues to increase
New Afton C-zone exploration
Rainy River regional exploration
Blackwater regional exploration
Rainy River permitting
Blackwater permitting
New Afton mill expansion

A history of value creation
Performance since March 2009 New Gold/Western Goldfields merger announcement
21
S&P/TSX Global Gold Index(1)
Gold Price
New Gold (NYSE)
1. S&P/TSX Global Gold Index includes 37 gold companies in various stages of development/producti on.
256%
44%
(7%)

Portfolio of assets
in top-ratedjurisdictions
Invested and
experienced team
Amonglowest-cost
producers with established track record
Peer-leading growth pipeline
A history of value creation
New Gold investment thesis
22
18.5 Moz gold
reserves
~$90 million
investment by Board &
Management
Targeting
~$825/oz all-in sustaining
costs(1)
~900 Koz annual
production potential from
growth projects
+250% increase
in share price since March 2009
1. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
Establishing the leading
intermediate gold company

Appendices
23
Appendices
Page
1. Financial information 24
2. Consolidated operating performance 29
3. New Afton 36
4. Mesquite, Peak Mines, Cerro San Pedro 42
5. Rainy River 45
6. Blackwater 47
7. El Morro 48
8. Exploration 51
9. Reserves and Resources notes 55
10. Commodity price/foreign exchange assumptions 64

$414 mm
$106 mm
Liquidity
Position$520 mm
Cash and
Equivalents(1)
Undrawn Credit
Facility(2)
Strong balance sheet
24
1. Cash and equivalents as at December 31, 2013.
2. $44 million of total $150 million at December 31, 2013 used for Letters of Credit.
3. See Appendix 1 – Summary of debt for detailed breakdown of components of debt.
• Face value $878 million in
long-term debt(3)
• Face value $300 million, 7.00% notes due in 2020
• Face value $500 million, 6.25% notes due in 2022
• $78 million in carried El Morro loan, payable out of El Morro project cash flow
Appendix 1

Summary of debt
25
Undrawn Credit
Facility
Senior Unsecured Notes
(April 2012)
Senior Unsecured Notes
(November 2012)
El Morro Funding
Loan
Face Value $150 million(1) $300 million $500 million $78 million
Maturity 1 year with annual
extensions permitted
April 15, 2020 November 15, 2022 n/a
Interest Rate See ‘Key features’ 7.00% 6.25% 4.58%
Payable Revolving credit Semi-annually Semi-annually Upon start of
production
Conversion price n/a n/a n/a n/a
Current trading value n/a ~103 ~96 n/a
Key features • Normal financial
covenants
Interest Rate
• 3.00-4.25% over
LIBOR based on
ratios
• Standby fee of 0.75-
1.06%
• Senior unsecured
• Redeemable after April 15,
2016 at 103.5% down to
100% of face after 2018
• Unlimited dividends if
leverage ratio below 2:1
• Senior unsecured
• Redeemable after
November 15, 2017 at par
plus half coupon, declining
ratably to par
• Unlimited dividends if
leverage ratio below 2:1
New Gold to repay
Goldcorp out of
80% of its 30%
share of cash flow
once El Morro
starts production
1. $44 million of total $150 million at December 31, 2013 used for Letters of Credit.
Appendix 1

26
2014 capital expenditures by category
New
Afton
~$340
million
Sustaining Capital: ~$145 million Growth Capital: ~$195 million
Mesquite
Peak
Mines
Cerro San
Pedro
Rainy
River
New Afton
Cerro San
Pedro
Blackwater
Total Capital
Appendix 1

27
Growth capital
• Set out below is a breakdown of expected 2014 capital expenditures at each site divided into two
categories – sustaining capital and growth capital (future production growth and mine life extension)
New Afton - $115 million
Rainy River - $105 million
Mesquite - $40 million
Sustaining capital
48%52%
100%
100%
• $60 million – ~2,500 metre development, two new trucks, dam raise and
surface ventilation upgrade
• $35 million – mill expansion
• $20 million – C-zone scoping level engineering and capitalized exploration
• $60 million – property, plant and equipment
• $35 million – detailed engineering, studies, environmental monitoring and permitting
• $10 million – capitalized exploration
• $28 million – four new trucks and leach pad expansion
• $12 million – major components/building and tank construction
2014 capital expenditures by category
Appendix 1

28
Peak Mines - $40 million
Cerro San Pedro - $28 million
100%
71%
• $20 million – two haul trucks and site maintenance
• $20 million – capitalized development and capitalized exploration
• $20 million – capitalized stripping
• $8 million – leach pad expansion
2014 capital expenditures by category
Growth capital Sustaining capital
New Gold’s 30% share of estimated 2014 El Morro capital costs of
$6 million fully carried by Goldcorp Inc.
Blackwater - $15 million
100%• $10 million – permitting
• $5 million – engineering studies
29%
Appendix 1

291. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
2013 consolidated operational results
GOLD PRODUCTION (Koz) COPPER PRODUCTION (Mlbs)SILVER PRODUCTION (Moz)
ALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
398
$377 $899
1.6 85
• High end of outlook
• New Afton and Peak
Mines met guidance
• In line with outlook • High end of guidance
• In line with outlook • In line with outlook
Appendix 2

2013 fourth quarter mine-by-mine operating results
30
2013 FOURTH QUARTER
Gold production
(Koz)
Total cash costs(1)
($/oz)
All-in sustaining costs(2)
($/oz)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
New Afton 25 ($1,428) $12
Mesquite 35 $841 $988
Peak Mines 24 $778 $1,106
Cerro San Pedro 22 $911 $1,076
107 $316 $883
New Afton co-product cash costs(1)
Gold ($/oz) $391
Copper ($/lb) $1.08
2013 FOURTH QUARTER
• New Afton continues to
perform well
• Mesquite had strongest
quarter of 2013 as planned
with higher grades
• Peak Mines all-in sustaining
costs(2) decreased by over
$200 per ounce from third
quarter of 2013
• Cerro San Pedro achieved
higher recoveries in each
consecutive month during
the quarter
Appendix 2

2013 full year mine-by-mine operating results
31
2013 FULL YEAR
Gold production
(Koz)
Total cash costs(1)
($/oz)
All-in sustaining costs(2)
($/oz)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
New Afton 87 ($1,196) ($133)
Mesquite 107 $907 $1,108
Peak Mines 101 $850 $1,331
Cerro San Pedro 103 $676 $766
398 $377 $899
New Afton co-product cash costs(1)
Gold ($/oz) $486
Copper ($/lb) $1.19
2013 FULL YEAR
• New Afton throughput higher
in each consecutive quarter
during the year
• 5% increase in gold
production at Peak Mines
versus previous year
• Lowest total cash costs(1) in
company’s history
Appendix 2

$465
$418 $446
$421
$377
$478
$557
$643
$738
$782
32
Among lowest cost producers in industry
Industry
New Gold
2013
Incremental
Benefit to NGD Shareholder
2009
(2)
New Gold versus Industry Average Total Cash Costs(1)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”. New Gold total cash costs as at year-end 2013.
2. Industry data per GFMS reports calculated net of by-product credits for the nine months ended September 2013.
Appendix 2

33
Detailed operating results and assumptions
Appendix 2
2013A 2013A 2013A 2013A
Tonnes processed (000 tonnes) 14,297 13,000 - 13,300 13,463 13,400 - 13,800 814 830 - 850 4,087 4,500 - 4,700
Tonnes mined (000 tonnes) 48,206 56,000 - 58,000 31,018 33,000 - 35,000 1,100 1,300 - 1,320 4,226 4,600 - 4,800
Strip ratio 2.37 3.31 - 3.36 1.30 1.46 - 1.54 -- -- - -- -- -- - --
Gold grade (g/t) 0.37 0.40 - 0.44 0.47 0.35 - 0.40 4.14 3.9 - 4.1 0.78 0.81 - 0.85
Silver grade (g/t) -- -- - -- 20.91 15.0 - 17.0 -- -- - -- -- -- - --
Copper grade (%) -- -- - -- -- -- - -- 0.85% 0.86% - 0.90% 0.93% 0.93% - 0.95%
Gold recovery (%) 63.0% 51.0% 92.9% 91.0% - 93.0% 85.1% 85.0% - 87.0%
Silver recovery (%) -- -- - -- 15.0% -- -- - -- -- -- - --
Copper recovery (%) -- -- - -- -- -- - -- 88.0% 91.0% - 93.0% 85.9% 86.0% - 88.0%
Production
Gold production (Koz) 107.0 113.0 - 123.0 102.8 70.0 - 80.0 100.7 95.0 - 105.0 87.2 102.0 - 112.0
Silver production (Koz) -- -- - -- 1,300.6 1,100.0 - 1,300.0 -- -- - -- -- -- - --
Copper production (Mlbs) -- -- - -- -- -- - -- 13.4 14.0 - 16.0 72.0 78.0 - 84.0
Reserve grade
Gold grade (g/t)
Silver grade (g/t)
Copper grade (%)
3.52
7.1
1.22%
0.56
2.2
0.84%
0.60
--
--
0.46
18.1
--
Mesquite
2014E2014E
New AftonCerro San Pedro
2014E
Peak Mines
2014E
~50%
~15%
~65%

341. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
2014 consolidated guidance
GOLD PRODUCTION (Koz) COPPER PRODUCTION (Mlbs)SILVER PRODUCTION (Moz)
ALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
380 – 420
$320 – $340 $815 – $835
1.35 – 1.75 92 – 100
• Increased production at high
margin New Afton offset by lower
production at Cerro San Pedro
• Consistent with 2013 • 12% increase with both New
Afton and Peak Mines higher
• Decrease driven by higher copper
production and depreciation of
Canadian and Australian dollars
• ~$75 per ounce decrease driven
by lower total cash costs(1) and
lower sustaining capital
Appendix 2

35
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. General and administrative includes stock-based compensation and asset retirement obligation.
3. Sustaining capital based on New Gold’s total 2014 estimated capital expenditures excluding expenditures related to growth-related initiatives.
4. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
2014 estimated all-in sustaining costs
Total cash costs(1) ~$330/oz
General and administrative(2) ~$90/oz
Exploration expense ~$35/oz
Sustaining capital(3) ~$370/oz
ALL-IN SUSTAINING COSTS(4) ~$825/oz
Appendix 2

36
New Afton – 2014 guidance
GOLD PRODUCTION (Koz) COPPER PRODUCTION (Mlbs)
ALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
102 – 112 78 – 84
($1,260) –
($1,240)
($620) –
($600)
TOTAL CASH COSTS(1)
$440 –
$460
$1.10 –
$1.20
Co-Product Gold ($/oz) Co-Product Copper ($/lb)
• Copper price - $3.25 per pound
(2013A - $3.23 per pound)
• Canadian dollar: U.S. dollar exchange –
$1.11
• $0.25 per pound change in copper
equals ~$200 per ounce change in New
Afton total cash costs
• $0.01 change in Canadian dollar equals
~$15 per ounce change in New Afton
total cash costs
• Gold and copper production expected to
increase due to:
• Increase in average annual
throughput rate
• Increase in gold grades
• Costs benefit from targeted increase in
copper production, depreciating
Canadian dollar and decrease in
sustaining capital costs
OVERVIEW
KEY ASSUMPTIONS AND SENSITIVITIES
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
Appendix 3

New Afton – Expansion evaluation
37
• Ran operation at 14,000 to 15,500 tonnes per day over multi-day periods in August and
December 2013
• Mill was able to process higher throughput, however a decrease in recovery was seen
• Began evaluating low capital cost alternatives to increase recoveries at higher throughput
• Identified that tertiary grinding and increased flotation capacity would be required to maintain
recoveries
• Worked with third party engineering firm on the capital cost estimate
Process of evaluating further throughput increase
Appendix 3

New Afton – Mill schematic
38
New Facilities
To Tailings
Surface Stockpile
Appendix 3

New Afton – Expansion timeline
39
• EPCM contract award
• Geotechnical and detailed
engineering
• Early works
• Buried services relocation
• Reagent tank relocation
H1’15
• Excavation
• Foundations
• Building construction
• Building services
• Vertimill delivery
• Piping/electrical
• Instrumentation
• Commissioning
H2’14H1’14
Appendix 3

New Afton – C-zone resource expansion
40
• C-zone originally identified through
limited deep holes drilled from
surface
• Drilling from underground
commenced in second half of 2012
• During 2013 completed 41 holes
totaling 26,800 metres
• Increased tonnes and grade of
Measured and Indicated resource
resulting in 10-fold increase in
contained gold and copper
• Incremental increase to Inferred
resource
Tonnes
(000’s)
Gold
(g/t)
Copper
(%)
Gold
(Koz)
Copper
(Mlbs)
Measured 618 0.75 0.91 15 12
Indicated 25,223 0.84 0.91 678 504
Total M&I 25,842 0.83 0.91 693 516
Inferred 11,288 0.63 0.64 227 159
YEAR-END 2012 C-ZONE(1)
YEAR-END 2013 C-ZONE(2)
Tonnes
(000’s)
Gold
(g/t)
Copper
(%)
Gold
(Koz)
Copper
(Mlbs)
Measured 400 0.60 0.73 8 6
Indicated 2,900 0.63 0.68 58 43
Total M&I 3,300 0.62 0.68 66 49
Inferred 13,600 0.70 0.76 307 228
1. 2012 information per Annual Information Form dated March 27, 2013.
2. For a detailed breakdown of Mineral Resources and Reserves by category, refer to Appendix 2. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of Mineral Reserves and Mineral Resources” and “Technical Information”.
Appendix 3

New Afton – 2014 C-zone program
41
• Convert Inferred resource to Measured and Indicated
• Expand resource laterally to east and west as well as vertically
• Underground delineation and infill – 30,000 to 35,000 metres
Appendix 3

42
• Diesel comprises ~25% of Mesquite’s
total costs
• Rack diesel price most correlated to
Brent oil price
• Diesel price - $3.25 per gallon
• Every $0.25 per gallon change in diesel
price has ~$15 per ounce impact on
total cash costs
• Production increase driven by planned
mining of higher grades versus 2013
• Increase in costs attributable to
increase in total tonnes mined
• Peak year for sustaining capital at
Mesquite
Mesquite – 2014 guidance
GOLD PRODUCTION (Koz) OVERVIEW
KEY ASSUMPTIONS AND SENSITIVITIESALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
113 – 123
$930 –
$950
$1,310 –
$1,330
Appendix 4

43
• Copper price - $3.25 per pound
(2013A - $3.29 per pound)
• Australian dollar: U.S. dollar
exchange – $1.14
• $0.25 per pound change in copper
equals ~$40 per ounce change in Peak
Mines total cash costs
• $0.01 change in Australian dollar equals
~$10 per ounce change in Peak Mines
total cash costs
• Gold production in line with 2013
• Increase in copper production a result of
increased copper grade and recovery
• Decrease in total cash costs a result of
increased copper by-product revenue,
depreciating Australian dollar and
increased productivity through lower
turnover
Peak Mines – 2014 guidance
GOLD PRODUCTION (Koz) COPPER PRODUCTION (Mlbs) OVERVIEW
KEY ASSUMPTIONS AND SENSITIVITIESALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
95 – 105 14 – 16
$630 –
$650
$1,065 –
$1,085
Appendix 4

44
• Silver price - $20.00 per ounce
(2013A – $23.61 per ounce)
• Mexican peso: U.S. dollar exchange –
$13.00
• $1.00 per ounce change in silver equals
~$15 per ounce change in Cerro San
Pedro total cash costs
• $1.00 change in Mexican peso equals
~$50 per ounce change in Cerro San
Pedro total cash costs
• Decrease in production reflects the
increased strip ratio for Phase 5
pushback and mining of lower grade ore
• Increase in costs primarily driven by
lower gold production, lower silver by-
product revenue and increased volume
of processing reagents
Cerro San Pedro – 2014 guidance
GOLD PRODUCTION (Koz) SILVER PRODUCTION (Moz) OVERVIEW
KEY ASSUMPTIONS AND SENSITIVITIESALL-IN SUSTAINING COSTS(2) ($/oz)TOTAL CASH COSTS(1) ($/oz)
1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.
70 – 80 1.1 – 1.3
$1,030 –
$1,050
$1,125 –
$1,145
Appendix 4

45
• 21,000 tonne per day process plan with
conventional crushing, grinding, leaching and carbon-in-pulp technology
• Targeted commissioning in 2016 with first
year of full production in 2017
• 14-year mine life with direct processing of
open pit and underground ore for first nine years and processing of a combination of stockpile and underground ore thereafter
• Development capital of $885 million inclusive of $70 million contingency (at
$1.05 CDN/USD)
• ~$840 million at $1.11 CDN/USD
• Life-of-mine gold and silver recoveries of
91% and 64%
• Open pit mining schedule incorporates an
elevated cut-off grade strategy during first nine years
Rainy River – Project overview
Appendix 5
Pre-tax Economics
Gold Price ($/oz) 1,150 1,300 1,300 1,450 1,600
US$/C$ exchange 0.93 0.95 0.90 0.97 1.00
5% NPV ($mm) 138 438 579 738 1,009
IRR (%) 7.8 13.1 15.9 17.6 21.1
Payback (years) 6.8 5.4 4.7 4.3 3.6
After-tax Economics
Gold Price ($/oz) 1,150 1,300 1,300 1,450 1,600
US$/C$ exchange 0.93 0.95 0.90 0.97 1.00
5% NPV ($mm) 100 314 416 520 706
IRR (%) 7.1 11.3 13.7 14.9 17.8
Payback (years) 6.8 5.5 4.8 4.4 3.8

Rainy River – Indicative timeline
461. Indicative timeline is dependent on permit approvals and other variables. There is no assurance this timeline will be achieved or that the deposit will ever reach the production stage.
Final construction during commissioning
Ongoing consultation
Project Schedule
Feasibility Study
First Nations & Public Consultation
Engineering/Procurement
Environmental Assessment
Permitting
Construction
Production
2014 2015 2016 2017
Appendix 5

47
• Conventional truck and shovel open pit mine
with 60,000 tonne per day processing plant
• Simple, conventional flowsheet using whole ore leach process
• Low grade stockpiling strategy
• Development capital of $1,865 million
inclusive of $190 million contingency (at $1.05 CDN/USD)
• ~$1,760 million at $1.11 CDN/USD
• Life-of-mine operational strip ratio of 1.88 to 1
• Life-of-mine gold and silver recoveries of
87% and 49%
• Conventional waste rock and Tailings Storage Facility
• Power supply from the hydroelectric power grid, via 140-kilometre transmission line
• Minimal off-site infrastructure required
• Good existing access road; water supply within 15 kilometres
• Low environmental risk and facility designed for closure
Blackwater – Project overview
Appendix 6
Pre-tax Economics
Gold Price ($/oz) 1,150 1,300 1,300 1,450 1,600
US$/C$ exchange 0.93 0.95 0.90 0.97 1.00
5% NPV ($mm) 402 991 1,263 1,582 2,120
IRR (%) 7.8 11.3 13.3 14.4 16.8
Payback (years) 7.5 6.2 5.5 5.1 4.5

481. Capital estimates based on December 2011 Feasibility Study.
El Morro (30%) – Funding structure
Funded by
$1.2 billioninterest at 4.58%
~ $2.7 billion 70%
20% 80%
• New Gold’s 30% share of development capital 100% carried
• Interest fixed at 4.58%
30% 70%
30%
Total Capital100%
~ $3.9 billion(1)
100% Average annual
cash flow
Carried funding repayment
Appendix 7

49
2012 open pit Proven and
Probable reserves and Measured and Indicated resources
Underground Inferred
resource with block cave potential
500 metres
La Fortuna deposit
Appendix 7
Reserve Grade
Gold: 0.46 g/t
Copper: 0.49%
Inferred Grade
Gold: 0.97 g/t
Copper: 0.78%

501. All reserve information taken from Goldcorp’s December 31, 2013 year-end resource statements.
2. Gold equivalent calculated based on the following commodity prices: Gold - $1,300/oz; Silver - $22.00/oz; Copper - $3.00/lb; Lead - $0.90/lb; Zinc - $0.90/lb.
El Morro relative positioning(1)
EL MORRO WITHIN GOLDCORP PORTFOLIO
Asset Gold Reserves (Moz) Asset Gold Equivalent(2) (Moz)
Penasquito 11.6 Penasquito 30.6
Los Filos 8.0 El Morro 18.0
El Morro 6.7 Los Filos 8.9
Pueblo Viejo 6.5 Pueblo Viejo 7.5
Cerro Negro 5.7 Cerro Negro 6.6
Appendix 7

51
New Gold’s estimated exploration budget for 2014 is $50 million
• Capitalized: $30 million (included in sustaining capital total shown previously)
• Expensed: $20 million (approximately 70% related to current operations)
New Afton
30,000-35,000
metres
Peak Mines
45,000
metres
Blackwater
10,000-15,000
metres
2014 exploration program overview
Rainy River
35,000-40,000
metres
1. Circle proportions are representative of both capitalized and expensed exploration for each respective asset.
Appendix 8

Rainy River exploration
52
• Intrepid resource drilled off and incorporated into Feasibility Study
• Condemnation drilling program approximately 40% complete by year end
• Improved ability to predict prospective ore horizons beneath surface cover
2013 ACHIEVEMENTS
2014 PROGRAM
Targeting resource expansion in near-mine environment
• Complete condemnation drilling program
• Test potential to expand open pit resource to west
• Explore prospective trends south of main mine area and extending
from Intrepid Zone
Intrepid Zone
Appendix 8

Blackwater exploration
53
2013 Achievement
• Expanded exploration targeting coverage to ~50% of claim block
• 14 prospective target areas identified to date
• Seven new targets drill tested with favorable geology intercepted on six
and gold mineralization intercepted on three
• Acquired Key property immediately south of Blackwater deposit area
2014 Program
• Follow up favorable results at Van Tine, Fawn and earlier stage prospects
• Initiate exploration at Key
Appendix 8

Peak Mines exploration
54
• Near-mine exploration and resource conversion partially offset mine depletion
• Advanced earlier stage targets along regional Rookery fault trend
2013 ACHIEVEMENTS
2014 PROGRAM
Focus on reserves replacement in near-mine environment
• Convert Measured and Indicated resources to reserves to extend mine life
• Test newly emerging targets along mine corridor
• Continue to advance earlier stage regional targets
Appendix 8

551. 2012 information per Annual Information Form dated March 27, 2013.
Reserves and resources summary
Appendix 9
Gold
Koz
Silver
Koz
Copper
Mlbs
Gold
Koz
Silver
Koz
Copper
Mlbs
Proven and Probable Reserves 18,538 90,080 2,953 7,752 31,256 3,282
Measured and Indicated Resources (inclusive of Reserves) 27,505 124,499 4,353 21,403 131,847 4,061
Inferred Resources 4,161 30,360 1,821 4,383 84,620 1,114
M&I Resources (inclusive of Reserves)
New Afton 2,297 7,786 1,988 1,979 6,830 1,818
Mesquite 4,904 - - 5,684 - -
Peak Mines 810 1,380 158 880 1,350 146
Cerro San Pedro 397 15,948 - 1,703 57,980 -
Rainy River 6,236 14,635 - n/a n/a n/a
Blackwater 9,500 70,130 - 8,070 56,190 -
Capoose 320 14,620 - 196 9,497 -
El Morro 3,041 - 2,207 2,891 - 2,097
Total M&I 27,505 124,499 4,353 21,403 131,847 4,061
Mineral Reserves and Resources Summary
As at December 31, 2013 As at December 31, 2012(1)

56
Reserves and resources summary (cont’d)
Appendix 9
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
New Afton
Proven - - - - - - - - - - - - - -
Probable 48,821 0.56 2.2 0.84 879 3,500 904 52,500 0.65 2.3 0.93 1,100 3,880 1,080
Total New Afton P&P 48,821 0.56 2.2 0.84 879 3,500 904 52,500 0.65 2.3 0.93 1,100 3,880 1,080
Mesquite
Proven 3,809 0.70 - - 86 - - 13,140 0.68 - - 287 - -
Probable 112,094 0.60 - - 2,152 - - 114,409 0.56 - - 2,055 - -
Total Mesquite P&P 115,903 0.60 - - 2,237 - - 127,549 0.57 - - 2,342 - -
Peak Mines
Proven 1,820 4.35 6.7 1.16 255 390 47 2,109 5.89 7.5 1.08 399 510 50
Probable 1,820 2.69 7.4 1.27 157 430 51 2,118 3.82 6.8 1.18 260 466 55
Total Peak Mines P&P 3,640 3.52 7.1 1.22 412 820 98 4,227 4.85 7.2 1.13 659 976 105
Cerro San Pedro
Proven 12,982 0.47 17.5 - 197 7,311 - 21,100 0.52 17.1 - 353 11,600 -
Probable 13,714 0.44 18.7 - 195 8,239 - 26,400 0.48 17.4 - 407 14,800 -
Total CSP P&P 26,696 0.46 18.1 - 392 15,550 - 47,500 0.50 17.3 - 760 26,400 -
Mineral Reserves statement as at December 31, 2013
Contained metalMetal grade Metal grade Contained metal
Mineral Reserves statement as at December 31, 2012
1. 2012 information per Annual Information Form dated March 27, 2013.

57
Reserves and resources summary (cont’d)
Appendix 9
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Rainy River
Direct processing material
Open Pit
Proven 15,839 1.47 2.0 - 746 1,038 -
Probable 46,866 1.26 3.1 - 1,896 4,594 -
Open Pit P&P (direct processing) 62,705 1.31 2.8 - 2,642 5,632 -
Underground
Proven - - - - - - -
Probable 4,187 4.96 10.3 - 668 1,388 -
Underground P&P (direct processing) 4,187 4.96 10.3 - 668 1,388 -
Stockpile material
Open Pit
Proven 6,843 0.38 1.5 - 84 332 -
Probable 30,541 0.39 2.1 - 378 2,058 -
Open Pit P&P (stockpile) 37,384 0.38 2.0 - 462 2,390 -
Total P&P
Proven 22,681 1.14 1.9 - 830 1,370 -
Probable 81,594 1.12 3.1 - 2,943 8,040 -
Total Rainy River P&P 104,275 1.13 2.8 - 3,773 9,410 -
Blackwater
Direct processing material
Proven 124,500 0.95 5.5 - 3,790 22,100 -
Probable 169,700 0.68 4.1 - 3,730 22,300 -
P&P (direct processing) 294,300 0.79 4.7 - 7,510 44,400 -
Stockpile material
Proven 20,100 0.50 3.6 - 330 2,300 -
Probable 30,100 0.34 14.6 - 330 14,100 -
P&P (stockpile) 50,200 0.40 10.2 - 650 16,400 -
Total Blackwater P&P 344,400 0.74 5.5 - 8,170 60,800 -
El Morro 30% Basis
Proven 321,814 0.56 - 0.55 1,746 - 1,163 307,949 0.57 - 0.56 1,705 - 1,135
Probable 277,240 0.35 - 0.43 929 - 788 335,152 0.37 - 0.44 1,186 - 962
Total El Morro P&P 599,054 0.46 - 0.49 2,675 - 1,951 643,101 0.47 - 0.49 2,891 - 2,097
Total P&P 18,538 90,080 2,953 7,752 31,256 3,282
100% Basis 30% Basis 100% Basis
Mineral Reserves statement as at December 31, 2013
Contained metalMetal grade Metal grade Contained metal
Mineral Reserves statement as at December 31, 2012
1. 2012 information per Annual Information Form dated March 27, 2013.

58
Reserves and resources summary (cont’d)
Appendix 9
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
New Afton
A&B Zones
Measured 41,059 0.79 2.7 1.09 1,041 3,624 984 33,500 0.86 2.9 1.18 929 3,160 873
Indicated 26,966 0.44 2.1 0.65 384 1,777 384 45,900 0.67 2.4 0.89 984 3,530 896
A&B Zone M&I 68,025 0.65 2.5 0.91 1,425 5,401 1,368 79,400 0.75 2.6 1.01 1,913 6,690 1,769
C-Zone
Measured 618 0.75 1.5 0.91 15 30 12 400 0.60 1.3 0.73 8 20 6
Indicated 25,223 0.84 2.0 0.91 678 1,589 504 2,900 0.63 1.3 0.68 58 120 43
C-Zone M&I 25,842 0.83 2.0 0.91 693 1,620 516 3,300 0.62 1.3 0.68 66 140 49
HW Lens
Measured - - - - - - - - - - - - - -
Indicated 11,035 0.50 2.2 0.43 179 763 104 - - - - - - -
HW Lens M&I 11,035 0.50 2.2 0.43 179 763 104 - - - - - - -
Total New Afton M&I 104,901 0.68 2.3 0.86 2,297 7,786 1,988 82,700 0.74 2.6 1.00 1,979 6,830 1,818
Mesquite
Measured 9,070 0.66 - - 191 - - 24,000 0.61 - - 452 - -
Indicated 304,081 0.48 - - 4,713 - - 370,100 0.45 - - 5,232 - -
Total Mesquite M&I 313,151 0.49 - - 4,904 - - 394,100 0.45 - - 5,684 - -
Peak Mines
Measured 3,000 4.69 6.7 1.06 450 650 70 2,700 5.74 7.5 1.05 494 647 62
Indicated 3,400 3.29 6.7 1.18 360 730 88 3,200 3.75 6.8 1.19 386 703 84
Peak Mines M&I 6,400 3.95 6.7 1.12 810 1,380 158 5,900 4.66 7.1 1.13 880 1,350 146
Cerro San Pedro
Measured 13,387 0.46 17.3 - 199 7,459 - 42,300 0.40 14.4 - 532 18,900 -
Indicated 14,311 0.43 18.4 - 198 8,489 - 109,400 0.34 11.5 - 1,171 39,080 -
Total CSP M&I 27,698 0.45 17.9 - 397 15,948 - 151,700 0.35 11.9 - 1,703 57,980 -
M easured and Indicated mineral R eso urce statement ( inclusive o f R eserves) as at D ecember 31, 2012
Metal grade Contained metal
M easured and Indicated mineral R eso urce statement ( inclusive o f R eserves) as at D ecember 31, 2013
Contained metalMetal grade
1. 2012 information per Annual Information Form dated March 27, 2013.

59
Reserves and resources summary (cont’d)
Appendix 9
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Rainy River
Direct processing material
Open Pit
Measured 20,282 1.45 1.9 - 947 1,261 -
Indicated 80,411 1.35 2.6 - 3,486 6,584 -
Open Pit M&I (direct processing) 100,693 1.37 2.4 - 4,433 7,846 -
Underground
Measured 89 4.95 2.8 - 14 8 -
Indicated 5,469 4.53 11.3 - 796 1,994 -
Underground M&I (direct processing) 5,558 4.53 11.2 - 810 2,002 -
Stockpile material
Open Pit
Measured 6,294 0.37 1.3 - 74 262 -
Indicated 64,816 0.44 2.2 - 919 4,526 -
Open Pit M&I (stockpile) 71,110 0.43 2.1 - 993 4,788 -
Total M&I
Measured 26,665 1.21 1.8 - 1,035 1,531 -
Indicated 150,696 1.07 2.7 - 5,202 13,104 -
Total Rainy River M&I 177,361 1.09 2.6 - 6,236 14,635 -
Blackwater
Direct processing material
Measured 116,955 1.04 5.6 - 3,900 21,060 -
Indicated 189,044 0.78 6.0 - 4,730 36,470 -
M&I (direct processing) 305,999 0.88 5.8 - 8,620 57,520 -
Stockpile material
Measured 26,521 0.30 4.1 - 260 3,500 -
Indicated 64,382 0.30 4.4 - 620 9,110 -
M&I (stockpile) 90,904 0.30 4.3 - 870 12,600 -
Total Blackwater M&I 396,903 0.74 5.5 - 9,500 70,130 - 296,146 0.85 5.9 - 8,070 56,190 -
Capoose
Indicated 20,280 0.50 22.4 - 320 14,620 - 14,200 0.43 20.8 - 196 9,497 -
El Morro
Measured 341,604 0.56 - 0.54 1,848 - 1,230 307,949 0.57 - 0.56 1,705 - 1,135
Indicated 349,803 0.35 - 0.42 1,193 - 977 335,152 0.37 - 0.44 1,186 - 962
Total El Morro M&I 691,407 0.46 - 0.48 3,041 - 2,207 643,101 0.47 - 0.49 2,891 - 2,097
Total M&I 27,505 124,499 4,353 21,403 131,847 4,061
M easured and Indicated mineral R eso urce statement ( inclusive o f R eserves) as at D ecember 31, 2012
Metal grade Contained metal
100% Basis 30% Basis
M easured and Indicated mineral R eso urce statement ( inclusive o f R eserves) as at D ecember 31, 2013
Contained metal
100% Basis 30% Basis
Metal grade
1. 2012 information per Annual Information Form dated March 27, 2013.

60
Reserves and resources summary (cont’d)
Appendix 9
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
Tonnes
000's
Gold
g/t
Silver
g/t
Copper
%
Gold
Koz
Silver
Koz
Copper
Mlbs
New Afton
A&B-Zone 5,607 0.32 1.5 0.38 59 272 46 14,900 0.45 2.0 0.65 216 940 212
C-Zone 11,288 0.63 1.7 0.64 227 602 159 13,600 0.70 1.5 0.76 307 670 228
HW Lens 818 0.56 1.3 0.42 15 33 7 - - - - - - -
New Afton Inferred 17,713 0.53 1.6 0.54 301 907 212 28,400 0.57 1.8 0.70 523 1,610 440
Mesquite 17,550 0.42 - - 238 - - 50,900 0.40 - - 651 - -
Peak Mines 2,000 2.34 4.7 1.17 150 300 51 1,700 2.64 4.8 1.13 144 261 42
CSP 1,174 0.34 11.6 - 13 436 - 103,900 0.25 8.8 - 850 29,200 -
Rainy River
Direct processing
Open Pit 9,388 0.97 2.3 - 292 687 -
Underground 2,641 4.46 8.3 - 379 707 -
Total Direct Processing 12,029 1.74 3.6 - 671 1,394 -
Stockpile
Open Pit 8,626 0.37 1.2 - 102 323 -
Rainy River Inferred 20,655 1.16 2.6 - 773 1,717 -
Blackwater
Direct processing 13,815 0.76 4.1 - 340 1,820 -
Stockpile 3,785 0.31 3.6 - 40 440 -
Blackwater Inferred 17,600 0.66 4.0 - 380 2,260 - 16,585 0.58 10.8 - 310 5,760 -
Capoose 29,263 0.39 26.3 - 370 24,740 - 64,070 0.29 23.2 - 595 47,789 -
El Morro - Open Pit 564,217 0.16 - 0.26 871 - 970 137,555 0.99 - 0.70 1,310 - 632
El Morro - Underground 113,840 0.97 - 0.78 1,065 - 587
Total Inferred 4,161 30,360 1,821 4,383 84,620 1,114
100% Basis 30% Basis30% Basis100% Basis
Inferred Resource statement as at December 31, 2013
Contained metalMetal grade
Inferred Resource statement as at December 31, 2012
Metal grade Contained metal
1. 2012 information per Annual Information Form dated March 27, 2013.

61
New Gold reports its Measured and Indicated mineral resources inclusive of its mineral reserves. Measured and Indicated mineral resources that are not mineral reserves do not have
demonstrated economic viability. Inferred mineral resources have a greater amount of uncertainty as to their existence and ec onomic and legal feasibility, do not have demonstrated economic
viability, and are exclusive of mineral reserves. Mineral reserves have been estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) definition
standards and National Instrument 43-101 (“NI 43-101”).
1) Mineral Reserves for the company’s mineral properties have been estimated based on the follow ing metal prices and low er cut-off criteria:
Mineral Property Gold
(US$/oz)
Silver
(US$/oz)
Copper
(US$/lb)
Lower Cut-off
New Afton $1,300 $22.00 $3.00 US$21.00/t NSR
Mesquite $1,300 - - 0.21 g/t Au – Oxide and transition reserves
0.41 g/t Au – Non-oxide reserves
Peak Mines $1,300 $22.00 $3.00 A$88 – 134/t NSR
Cerro San Pedro $1,300 $22.00 - US$3.00/t
Rainy River $800
$1,300
$25.00
$22.00
- Open Pit: 0.3 – 0.7 g/t Au
Underground: 3.5 g/t Au
Blackw ater $1,300 $22.00 - Direct processing: 0.26 – 0.38 g/t AuEq
Stockpile: 0.32 g/t AuEq
El Morro $1,300 - $3.00 0.20% Cu
Reserves and resources notes
Appendix 9

62
2) Mineral Resources for the company’s mineral properties have been estimated based on the follow ing metal prices and low er cut-off criteria:
3) Mineral resources are classif ied as Measured, Indicated and Inferred resources and are reported based on technical and economic parameters consistent w ith the methods most suitable
for their potential commercial exploitation. Where different mining and/or processing methods might be applied to different portions of a mineral resource, the designators ‘open pit’ and
‘underground’ have been applied to indicate envisioned mining method. Likew ise the designators ‘oxide’, ‘non-oxide’ and ‘sulphide’ have been applied to indicate the type of mineralization
as it relates to appropriate mineral processing method and expected payable metal recoveries. Additional details regarding mineral resource estimation, classif ication, reporting parameters, key assumptions and associated risks for each of New Gold’s mineral properties, other than Rainy River, are provided in the respective NI 43-101 Technical Reports w hich are available at
www.sedar.com. Refer to the supplementary information below regarding the mineral reserve and mineral resource estimates for Rainy River.
Mineral Property Gold
(US$/oz)
Silver
(US$/oz)
Copper
(US$/lb)
Lower Cut-off
New Afton $1,400 $24.00 $3.25 0.40% CuEq
Mesquite $1,400 - - 0.11 g/t Au – Oxide and transition resources
0.22 g/t Au – Non-oxide resources
Peak Mines $1,400 $24.00 $3.25 A$92 - 125/t NSR
Cerro San Pedro $1,400 $24.00 - 0.10 g/t AuEq – Open pit oxide resources
0.30 g/t AuEq – Open pit sulphide resources
Rainy River $1,400 $24.00 - Open Pit: 0.3 – 0.45 g/t Au
Underground: 2.5 g/t Au
Blackw ater $1,400 $24.00 - Direct processing: 0.40 g/t AuEq
Stockpile: 0.30 – 0.40 g/t AuEq
Capoose $1,400 $24.00 - 0.40 g/t AuEq
El Morro $1,300 - $3.00 0.20% Cu
Reserves and resources notes (cont’d)
Appendix 9

63
Rainy River Mineral Reserves:
1. Open pit mineral reserves have been estimated using an optimized pit shell based on metal prices of $800 per ounce gold and $25 per ounce silver, a foreign exchange rate of C$1.05 to
US$1.00, gold recovery of 89.9% (non-CAP Zone) and 74.3% (CAP Zone) and a silver recovery of 67.1% (non-CAP Zone) and 69.5% (CAP Zone). The cut-off grade is based on a gold
price of $1,200. Underground reserves have been estimated from mining shapes generated using a cut-off grade of 3.5 g/t gold-equivalent. Development material from stope access drives
above a cut-off grade of 1.5 g/t gold-equivalent is also assumed to be sent to the mill for processing. Underground breakeven cut-off grade is calculated at 2.75 g/t gold-equivalent based on metal prices of $1,300 per ounce gold and $22 per ounce silver, a foreign exchange rate of CAD $1.05 to USD $1.00, gold recov ery of 95% and a silver recovery of 75%.
2. Open pit reserves have been estimated using a dilution of 4% at 0.21 g/t Au and 1.19 g/t Ag, and underground reserves have been estimated using an overall dilution of 8.3%, inclusive of
both rock and backfill dilution. Open pit and underground reserves have been estimated using a mining recovery of 95% and 96.5%, respectively.
3. Open pit direct processing material is defined as mineralization likely to be mined and processed directly and above a var iable cut-off grade ranging from 0.3-0.7 Au g/t.
4. Stockpile material includes all material w ithin designed open pit betw een variable cut-offs described above in Note 3, as w ell as material w ithin the CAP Zone (code 500) that is suitable for stockpiling and future processing.
5. Mineral Reserves for the open pit are derived from the resource model effective November 2, 2013. Models for the underground reserves were derived from the August 2013 and
September 2013 models for the main ODM zone and Intrepid Zone, respectively. Models w ere prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole, P.Geo. (APGO
#1416), of SRK, both independent “Qualif ied Persons" as that term is defined in National Instrument 43-101. Rainy River’s exploration program in Richardson Tow nship is being supervised
by Mark A. Petersen, (AIPG Certif ied Professional Geologist #10563), Vice President, Exploration for New Gold and a “Qualif ied Person” as defined in National Instrument 43-101. New Gold continues to implement a rigorous QA/QC program to ensure best practices in drill core sampling, analysis and data management.
6. Qualif ied persons - The open pit portion of the mineral reserve statement w as prepared under the supervision of Patrice Live (OIQ #38991) of BBA, and the underground portion of the
mineral reserve statement w as prepared by Colm Keogh, P.Eng. (APEGBC #37433) of AMC Mining Consultants (Canada) Ltd., both independent “Qualif ied Persons" as that term is defined
in National Instrument 43-101.
7. The mineral reserve estimate may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, and other relevant issues.
Rainy River Mineral Resources:
1. Mineral resources are reported in relation to conceptual pit shells and are inclusive of the Intrepid zone. Vertical limit of -150m msl.
2. Open pit mineral resources are reported at a cut-off grade of 0.30 gpt gold, underground mineral resources are reported at a cut-off grade of 2.5 gpt gold based on a gold price of $1,400
per ounce, a silver price of $24.00 per ounce, a foreign exchange rate of C$1.10 to US$1.00, gold recovery of 88% for open pit resources and 90% for underground resources with silver recovery at 75%.
3. Direct processing material is defined as mineralization above a cut-off of 0.45 g/t gold and likely to be mined and processed directly.
4. Stockpile material includes all material w ithin conceptual pit shells in the gold grade range 0.30 – 0.45 gpt as w ell as all material w ithin the CAP zone that is suitable for stockpiling and
future processing based on average metallurgical recoveries of 88% gold and 75% silver.
5. Qualif ied Persons – The mineral resource statement w as prepared by Dorota El-Rassi, P. Eng. (APEO #100012348) and Glen Cole (APGO #1416) from SRK, both independent "Qualif ied Persons" as that term is defined in National Instrument 43-101.
6. Mineral resources are inclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
7. The mineral resource estimate may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing and other relevant issues.
4) Qualif ied Person: The preparation of New Gold's mineral reserve and mineral resource statements has been done by Qualif ied Persons as defined under National Instrument 43-101 under the supervision of Mark A. Petersen, a Qualif ied Person under National Instrument 43-101 and an off icer of New Gold.
Reserves and resources notes (cont’d)
Appendix 9

64
Guidance assumptions
Spot:
2014
Gold price ($/oz) 1,300
Silver price ($/oz) 20.00
Copper price ($/oz) 3.25
AUD/USD 1.14
CDN/USD 1.11
MXN/USD 13.00
Spot
Gold price ($/oz) 1,325
Silver price ($/oz) 21.85
Copper price ($/oz) 3.25
AUD/USD 1.12
CDN/USD 1.11
MXN/USD 13.31
Commodity price/foreign exchange assumptions
Appendix 10

Endnotes
65
CAUTIONARY NOTE TO U.S. READERS CONCERNING ESTIMATES OF MINERAL RESERVES AND MINERAL RESOURCES
Information concerning the properties and operations of New Gold has been prepared in accordance with Canadian standards unde r applicable Canadian securities laws, and may not be comparable to
similar information for United States companies. The terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Minera l Resource” and “Inferred Mineral Resource” used in this Report are
Canadian mining terms as defined in the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Definition Standards f or Mineral Resources and Mineral Reserves adopted by CIM Council on
November 27, 2010 and incorporated by reference in National Instrument 43-101 (“NI 43-101”). While the terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Mineral Resource” and
“Inferred Mineral Resource” are recognized and required by Canadian securities regulations, they are not defined terms under standards of the United States Securities and Exchange Commission. As such,
certain information contained in this Report concerning descriptions of mineralization and resources under Canadian standards isnot comparable to similar information made public by United States
companies subject to the reporting and disclosure requirements of the United States Securities and Exchange Commission.
An “Inferred Mineral Resource” has a greater amount of uncertainty as to its existence and as to its economic and legal feasi bility. Under Canadian rules, estimates of Inferred Mineral Resources may not
form the basis of feasibility of pre-feasibility studies. It cannot be assumed that all or any part of an “Inferred Mineral Resource” wil l ever be upgraded to a higher confidence category. Readers are
cautioned not to assume that all or any part of an “Inferred Mineral Resource” exists or is economically or legally mineable.
Under United States standards, mineralization may not be classified as a “Reserve” unless the determination has been made tha t the mineralization could be economically and legally produced or extracted
at the time the Reserve estimation is made. Readers are cautioned not to assume that all or any part of the Measured or Indicated Mineral Resources that are not Mineral Reserves will ever be converted
into Mineral Reserves. In addition, the definitions of “Proven Mineral Reserves” and “Probable Mineral Reserves” under CIM st andards differ in certain respects from the standards of the United States
Securities and Exchange Commission.
TECHNICAL INFORMATION
The scientific and technical information in this presentation has been reviewed and approved by Mark A. Petersen, Vice President, Exploration of New Gold. Mr. Petersen is an AIPG Certified Professional
Geologist and a “qualified person” under National Instrument 43 -101.
NON-GAAP MEASURES
(1) TOTAL CASH COSTS
“Total cash costs” per ounce figures are non-GAAP measures which are calculated in accordance with a standard developed by The Gold Institute, a worldwide association of suppliers of gold and gold
products that ceased operations in 2002. Adoption of the standard is voluntary and the cost measures presented may not be com parable to other similarly titled measures of other companies. New Gold
reports total cash costs on a sales basis. Total cash costs include mine site operating costs such as mining, processing, adm inistration, royalties and production taxes, but are exclusive of amortization,
reclamation, capital and exploration costs. Total cash costs are reduced by any by-product revenue and then divided by ounces of gold sold to arrive at a per ounce figure. Co-product cash costs are
calculated based on total cash costs, prior to any reduction for by-product revenue, being apportioned to each metal produced on a percentage of revenue basis and subsequently divided by ounces of gold
or silver sold or pounds of copper sold to arrive at per ounce or per pound figures. These measures, along with sales, are co nsidered to be a key indicator of a company’s ability to generate operating
earnings and cash flow from its mining operations. This data is furnished to provide additional information and is a non -GAAP measure. Total cash costs and co-product cash costs presented do not have a
standardized meaning under GAAP and may not be comparable to similar measures presented by other mining companies. It should not be considered in isolation or as a substitute for measures of
performance prepared in accordance with GAAP and is not necessarily indicative of operating costs presented under GAAP. Furth er details regarding our non-GAAP measures and a reconciliation to the
nearest GAAP measures are provided in our MD&A’s accompanying our financial statements fi led from time to time on www.sedar.com.
(2) ALL-IN SUSTAINING COSTS
Consistent with guidance announced in 2013 by the World Gold Council, an association of various gold mining companies from around the world of which New Gold is a member, New Gold defines “all -in
sustaining costs” per ounce as the sum of total cash costs, sustaining capital expenditures, corporate general and administra tive costs, capitalized and expensed exploration that is sustaining in nature and
environmental reclamation costs, all divided by the ounces of gold sold to arrive at a per ounce figure. New Gold believes th is non-GAAP measure provides further transparency into costs associated with
producing gold and will assist analysts, investors and other stakeholders of the company in assessing the company’s expected operating performance, ability to generate free cash flow and its overall value.
This data is furnished to provide additional information and is a non-GAAP measure. All -in sustaining costs presented do not have a standardized meaning under GAAP and may not be comparable to similar
measures presented by other mining companies. It should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP and is not necessarily indicative
of operating costs presented under GAAP. Further details regarding our non-GAAP measures and a reconciliation to the nearest GAAP measures are provided in our MD&A’s accompanying our financial
statements fi led from time to time on www.sedar.com.

Contact information
66
Investor Relations
Hannes PortmannVice President, Corporate Development
416-324-6014