NEW ERA INVESTMENT (PTY) LTD - NAMIBIA …ejustice.moj.na/High Court/Judgments/Civil/New Era... ·...
Transcript of NEW ERA INVESTMENT (PTY) LTD - NAMIBIA …ejustice.moj.na/High Court/Judgments/Civil/New Era... ·...
REPUBLIC OF NAMIBIA
HIGH COURT OF NAMIBIA MAIN DIVISION, WINDHOEK
JUDGMENT
Case no: HC-MD-CIV-MOT-GEN-2016/00342
In the matter between:
NEW ERA INVESTMENT (PTY) LTD APPLICANT
And
FERUSA CAPITAL FINANCING PARTNERS CC 1ST RESPONDENT
DESERT PAVING 2ND RESPONDENT
HOWARD & CHAMBERLAIN ARCHITECTS 3RD RESPONDENT
HENDRIK HERSELMAN QUANTITY SURVEYORS 4TH RESPONDENT
IMPACT PROPERTY MANAGEMENT & SERVICES 5TH RESPONDENT
Neutral citation: New Era Investment (PTY) LTD v Ferusa Capital Financing Partners cc & 4 Others (HC-MD-CIV-MOT-GEN-2016/00342) [2016] NAHCMD 380 (02 December 2016)
Coram: E ANGULA AJ
REPORTABLE
2
Heard: 10 November 2016
Delivered: 02 December 2016
Flynote: Mandament van spolie — Effective possession and control —
Suspension of building construction works — The applicant as contractor
engaged to build low cost housing placing security guards on site for the safety of
the property during suspension of works — Lack of evidence as to the nature and
extent of the applicant’s possession of property — Court holding that due to
scantiness of direct evidence that there was sufficient exercise of physical control
by the applicant of the property, there was no effectual possession — The
applicant must show that it exercised effective control over the property. —
Spoliation order refused.
Applications — Spoliation orders — Builder’s Liens — A lien is dependent on
possession — There must be physical control or occupation (detentio) and the
intention of holding and exercising possession (animus possidendi) —
Possession in order to exercise a builders lien is not sufficient — There must be
an intention to exercise a builders lien over the property — The intention must be
continuous and actual or effectual possession is a requisite.
Builder’s lien — Security — Builder’s lien is security for work done—contractual
lien limited to the terms of the contract — In a building contractual relationship a
party may exert a lien over the property for damages or losses arising due to the
suspension of works— A builder’s lien may be exercised over the building or
structures which the applicant has actually constructed.
Builder’s lien — Possession of entire property — The applicant claiming a
builder’s lien over the entire property— Court finding that from the papers it was
not clear which portion of the property applicant had occupied or exercised
control to the exclusion of the respondent— The applicant bears the onus to
3
prove on balance of probabilities that it was in possession of the entire property
— Court holding that the applicant did not discharged the onus.
Dispute resolution mechanism — Interdict pending the institution of proceeding
for specific performance — The dispute should be resolved as provided for in the
contract — Court cannot entertain the Interdict as the dispute has as yet not
been declared as provided for in the dispute resolution mechanism in terms of
the contract — The parties are required to exhaust such dispute resolution
mechanism before approaching court for an interdict.
Summary: The applicant and the respondent entered into a building
contract in terms of which the applicant was contracted to construct low cost
houses on the property in Swakopmund presumably belonging to the NHE or
Government. The applicant alleged that it had possession of the property to
construct the houses and in fact commenced construction when the first
respondent, due to cash flow problems was unable to meet its financial obligations
towards the applicant. As a result thereof, the works were suspended initially by
the applicant, and subsequently on instruction of NHE. During the period of
suspension applicant secured the property by guarding the premises. The
respondent paid the applicant some of the money owing to the Plaintiff but a
balance remained unpaid. The parties could not agree on the amount due to the
applicant. After the negotiation failed, the respondent contracted the second
respondent to complete the construction on the property. The applicant claimed
that it was exercising its builder’s lien over the property when it was spoliated from
the property by the first and second respondent who commenced construction on
the houses partially constructed by the applicant. This amongst others, prompted
the applicant to bring this application.
The application is opposed by the first respondent who is the contract holder with
the National Housing Enterprise (NHE) to construct low cost houses in
Swakopmund. Second respondent is a company contracted by first respondent to
complete the construction works on the said property. First and second respondent
4
are alleged spoliators of the property from applicant.
The applicant seeks two separate but distinct reliefs in respect of the property. In
the first respect, applicant is seeking a spoliation order, and in the second respect,
an order interdicting the respondents from commencing or continuing with any
building construction works on the property.
Held that in order for the applicant to succeed in its application for mandament van
spolie it must adduce evidence that there was sufficient exercise of physical control
by the applicant on the property to constitute actual or effectual control. Held further
that when the property is too wide, the applicant is required to demonstrate how it
exercised control over the property.
Held that the applicant, on the conspectus of the common cause and the
undisputed facts, did not establish it was in possession of the site by having its
employees on the property. The employees were on site to guard the premises
for the primary purpose to secure the safety of the site from outside threats.
Held further that the applicant did not have exclusive possession of the property
as the respondent occupied a part of the property to complete the constructions
of the mass housing project
Held a builders’ lien is applicable over the buildings or structures which the
applicant has built and not over the entire property. The onus is upon the
applicant to prove that its lien extends over the entire property.
Held further that the applicant lost possession of the property already in October
2016, before the alleged spoliation took place.
Held further that clause 26 of the contract provides for adjudication and
arbitration of the dispute and that the applicant ought to engage the dispute
resolution mechanism first before approaching the court for an interdict under the
circumstances of this case.
5
ORDER
1. The applicant’s application is dismissed with costs.
JUDGMENT
E ANGULA, AJ
The applicant instituted mandament van spolie on an urgent basis, asking for
restoration of the property dispossessed by the respondent. The applicant also
sought an urgent interdict against the respondent for continuing or commencing
with the constructions on the property. The Court dismissed the application with
costs, with reasons to follow. These are the reasons.
Introduction
[1] The applicant approached the court on an urgent basis seeking an order
in the following terms:
‘1. That applicant’s non-compliance with the forms and service provided for
by the rules of this Honourable Court is condoned and that the matter is
heard as one of urgency as contemplated by Rule 73(3) of the Rules.
2. That first and second respondent immediately and forthwith restore
possession for the property fully described as Blocks 9C, 10A and 10B,
Swakopmund Mass Housing Project, Swakopmund, Namibia, (the
“property”) to applicant.
3. That an interim interdict be issued calling upon the respondents to show
cause, if any, on a date determined by this court, why the following Order
should not be made final:
6
4. That first and second respondent be interdicted from commencing or
continuing with any building construction work on the property pending
the outcome of an action or arbitration to be instituted by application
against first respondent for specific performance of the building contracts
entered into between applicant and first respondent in respect of the
property.’
[2] The application is opposed by the first respondent who was awarded a
contract by the National Housing Enterprise (NHE) to construct low cost houses
in Swakopmund. NHE is a state owned company enacted to primarily provide
housing solutions in order to alleviate the national housing needs to lower and
middle income nationals. Second respondent is a company contracted by first
respondent to complete the construction works on the property. First and second
respondent are the alleged spoliators of the property from applicant. Second
respondent did not oppose the relief sought by the applicant. I would simply refer
to the first respondent as the ‘respondent’ in this judgment.
[3] The applicant is seeking an order for the restoration of the ‘property’
described as Block 9C, 10A and 10B, Swakopmund Mass Housing Project,
Swakopmund. The applicant seeks two separate but distinct reliefs in respect of
the property. In the first relief the applicant seeks a spoliation order and in the
second relief, an order interdicting the respondents from commencing or
continuing with any building construction works on the property.
Background:
[4] On 22 August 2014, the applicant, a construction company, and the
respondent entered into a written building contract in terms of which the applicant
was contracted to build the low costs houses on behalf of the respondent for a
combined value of N$78 011 633.70. During August 2014, the applicant took
possession of Block 10B. In February 2015, the applicant took possession of
7
Block 9C and in April 2015 of Block 10A. The applicant commenced
constructions of the houses on the property.
[5] From the papers it is unclear where on the property the applicant
commenced construction of the houses. It is also not clear if constructions took
place on all three blocks and to what extent.
[6] As at 31 March 2015, respondent owed N$7 560 145.20 to the applicant
for work done in terms of the contract. NHE, being the underlying employer of
the respondent, experienced shortage of funds resulting in the respondent not to
meet its financial obligations.
[7] On 16 April 2015, applicant suspended all works due to non-payment of its
accounts. In the letter suspending the works applicant states as follows:
‘The work team of Swakopmund housing project has been disbanded, but we still
keep a small construction group on site to complete all the possible work by
making use of the materials stocked on site. This will prevent further loss for
client and main contractor.
The safety for site is another issue for concern. Therefore we have arranged 5
safety guards on site to protect the materials and buildings. In the meantime,
any further action will be taken to protect the site whenever it is necessary’.
[8] On 10 June 2015, NHE instructed the respondent to suspend all works
with immediate effect. The Principal Agent communicated the suspension of the
works to the applicant in a letter as follows:
‘Our client, Ferusa Capital Partners, have been instructed by NHE to suspend
the works on the above project with immediate effect. This is an instruction that
8
originates directly from the Minister. As a result of this, you are hereby formally
instructed to suspend the works on your Blocks.
1 Based on clause 23 of the AGREEMENT AND SCHEDULE OF
CONDITIONS OF THE BUILDING CONTRACT:
1.1 Clause 23.1- The contractor shall with all reasonable dispatch remove
from the site all his goods, machinery and plant and give facility to his
subcontractors so also to do so;
1.2 Clause 23.2 - The contractor shall be paid by the Employer:
1.3 Clause 23.2.1 – The value of the Work commenced and executed but not
completed at the date of such determination as aforesaid, subject to Clause
10;
1.4 Clause 23.2.2 – The value of the Work commenced and executed but not
completed at the date of such determination, the value being ascertained
mutatis mutandis in accordance with the provisions of clause 10;
1.5 Clause 23.2.3 – The costs of materials and goods properly ordered and
delivered for the Works actually paid for by the Contractor, or of which he is
legally bound to accept delivery and on such costs being paid by the Employer
the same shall become his sold property;
1.6 Clause 23.2.4 – The reasonable costs of removal under clause 23.1;
1.7 Clause 23.3.4 – Any loss or damage caused to the Contractor owing to
such a determination as aforesaid;
Provided that, in addition to all other remedies, the contractor upon the said
determination, may take possession of and shall have a lien upon all unfixed
materials and/or goods intended for the Works, which may have become the
property of the employer under this contract, until payment of all monies due to
the contractor from the employer.’(My emphasis)
2 In addition to the above, we require that the following information be
issued:
2.1 Valuation
2.1.1 A valuation for Works executed up to and including today’s date.
2.2 Test Results
9
In order for payments to be affected (sic), the following test results must be
submitted to Impact Project Management …
We would like to take this opportunity to thank you for the manner in which your
Company has dealt with this rather unfortunate situation.’
[9] On 8 September 2015, the Principal Agent requested the applicant to
provide a schedule of materials stored off site in order to ensure payment to the
applicant. In response thereto, the applicant indicated that all materials were
stored at its several sites and warehouses in Walvis Bay and Windhoek. These
materials were ceded to the respondent who became the owner thereof.
[10] In applicant’s letter dated 8 September 2015 addressed to the principal
agent, therein contained the following extract which is of relevance:
‘As for the insurances, we can only provide the insurances for the three sites.
Imaging that the projects were not suspended and the construction team were on
site, all the materials were supposed to be delivered on site, and could be
covered by those insurances. The Building Contract can works as normal under
the natural and regular situation. But at this stage, Client cannot pay Main
Contractor for such a long time, and the construction is suspended by client,
therefore materials cannot and will not be delivered to site for safety
consideration. Main Contractor shall not bear the extra cost under this special
situation.’ (My emphasis)
[11] On 28 September 2015, applicant confirmed the suspension of the works
and informed the agent that it has arranged for 2 Chinese foremen, plus 7
security guards to be on site for security reasons. Applicant therein conceded that
the ‘site field’ was too large to secure.
[12] It is common cause between the parties that the security arrangement was
too expensive for the respondent to maintain. The respondent was particularly
10
concerned about the costs of the 2 Chinese foremen. Eventually, the parties
agreed to pay for only one Chinese foreman to secure the site during the period
of suspension. The applicant maintained that security costs are claimable under
‘site security’ listed under preliminary and generals (P&Gs) in the contract.
[13] In terms of clause 12 of the contract, any unfixed materials and goods, the
value of which has been included in a certificate for payment, shall upon payment
thereof become the Employer’s property. It is a further term of the contract that
the applicant shall protect such materials and goods against damage.
[14] It is noteworthy that in an email addressed by the applicant’s manager,
dated 29 September 2015, the following appears:
‘The ownership of materials already belongs to Client after the signing of cession
of rights. We suggest & claim 7 security guards and 2 Chinese is just hope to
protect the whole suspended area/houses/materials (10A 10B & 9C) for our
Client (My emphasis).
We have two proposals if Client cannot pay high cost on Security:
1. Withdraw two security guards on site; but the security risk will be much
higher than before and New Era cannot promise the safe of the whole big area.
2. If Client insist to not to pay the 25000N$/month for the Chinese, we can
withdraw the Chinese from site, but Client must take the risk of secure on site
and bear the loss if any accident happened after that. As we all know, most of
the stealing cases on Construction sites are premeditated by Security Guards.
No matter which proposal Client choose, The two Chinese must be paid as per
the Claim dated on June 30th. (June 10th to August 20th: 2 Chinese: August 21st
to now: 1 Chinese).
As you can see from our Security Claim, we haven’t take any profit on the
security, those are just cost prices. What we always considering is the safety of
the suspended site!’ (My emphasis)
11
[15] On 7 March 2016, applicant maintained that as a direct result of the
suspension of works it has complied with its obligations to secure and protect the
works. The applicant also ensured that materials were kept off site for security
reasons in order to avoid same being stolen.
[16] By September 2016, the parties were in disagreement about amount owed
to applicant. It is common cause that by this time a substantial amount was
already paid to the applicant, whilst the remaining balance is disputed. The
remaining balance was to be determined by the Principal Agent. The Principal
Agent determined the amount due to the applicant at N$6 554 829.61. The
applicant however did not agree with the determined amount and asserted that it
was entitled to N$13 114 217.51. It is common cause that the parties agreed to
renegotiate and conclude new agreements in respect of each block after the
NHE terminated the underlying contract.
[17] On 26 September 2016, the respondent notified the applicant that it
terminates the negotiations in respect of the new construction agreements for
completing the works on blocks 10A,10B and 9C. The next day, the applicant
threatened to employ clause 26 of the contract which provides for dispute
resolution mechanism. Furthermore, no agreement could be reached between
the parties on the amount due to the applicant.
[18] After NHE cancelled its agreement with the respondent, a new agreement
was concluded between the respondent and the Government of the Republic of
Namibia (‘the Government’). The agreement gave the respondent a new
mandate to complete the mass housing project. On this basis, the respondent
contended that the cancellation of its agreement with NHE automatically
terminates its agreement with the applicant. This was in fact communicated to
applicant on 7 October 2016.
[19] On 10 October 2016, the applicant asserted for the first time that it was in
possession of the site and is entitled to exercise its lien until such time when ‘all
12
monies’ due is paid. The applicant thereupon demanded to know from the
respondent whether it was responsible for the removal of approximately 500
bricks from the site. The respondent disputed that the applicant was exercising a
lien and in turn accused the applicant of attempting to obstruct construction of the
works which began two weeks earlier.
[20] On 24 October 2016, the respondent accused the applicant of disrupting
and causing work stoppage at the respondent’s site. The site is referred to as
block 9C and 10A. The applicant could not respond to the aforesaid allegations
which it considered as vague and unspecified. The applicant reiterated that it
was exercising its builder’s lien on the sites because its employees were
permanently staying on the site, in addition to the security guards employed to
safeguard the site.
[21] On 2nd November 2016, applicant instructed its legal practitioner to bring
an urgent court interdict against the respondents.
[22] The applicant averred that ‘shortly thereafter’ it erected 40 site boards as
depicted in the photographs’. It is unclear what is meant by ‘shortly thereafter’
however it apparent that the applicant was replying to the respondent’s legal
practitioner’s letter dated 14th of October 2016.
[23] The applicant alleged that on 1 November 2016, 13 people allegedly from
second respondent came to the site and removed all 40 sign boards and left
them lying in a pile. The boards were re-erected and the site was enclosed with
chevron security tape. On 4 November 2016, it is alleged that the second
respondent’s employees removed the chevron security tape. On unspecified
date the applicant alleges that the employees of the second respondent started
working on the site. On the same day, a letter addressed to the second
respondent, from which the following is extracted:
‘It is our instructions that you have entered (ostensibly on the instructions of
Ferusa Capital) a portion of portions of the sites where our client is exercising a
13
builder’s lien, to wit blocks 10A, 10B and 9C, Swakopmund mass housing project
on the 01st of November 2016 in order to commence with construction work. (My
Emphasis)
We record that you have also made an illegal water connection to our client’s
water installations and will hold you liable for any damages suffered and payment
for the water so used as well as for the signs / notices erected around the sites
indicating that our client is exercising its builder’s lien which you removed and / or
attempted to remove.’
[24] The applicant’s legal practitioner thereupon, addressed a letter to the
respondent’s legal practitioner demanding the second respondent not enter or
remain on the site, whereupon the applicant was exercising its builder’s lien.
[25] The application was brought on the 7 th of November 2016 and heard on
the 10th of November 2016.
Submissions on behalf of the applicant
[26] Mr Heathcote representing the applicant submitted that the applicant had
a contractual lien over the site. This lien was exercised by the applicant’s
employees on site and the applicant was in possession of the site since 2014.
Since the respondent admitted owing the applicant an amount of N$6 554
829.61, the law confers on the applicant as security for payment by the employer,
a lien (a right of retention). In terms of the contract between the parties, the lien
extends to all unfixed materials and goods which have become the property of
the employer.1
[27] Mr Heathcote quoted an extract from Quail on the building contract,2 which
read as follows:
1 Quail on the building contract, second edition, revised and enlarged by Eyvind Finsen, at 133.2 Quail supra at 187.
14
‘As was pointed out in the discussion of clause 25, the contractor has a lien on the
site of the contract works until he has been paid in full. Such lien, or right of retention, is
automatic and does not require prior agreement… (My emphasis)
[28] Although clause 23 of the contract provides, as security for payment by
the employer, a lien on all unfixed materials and goods which have become the
property of the employer, the employer is also required to compensate the
contractor for any loss or damage which he has suffered because of giving notice
of determination. The claim for compensation can arise outside the provision of
clause 23. A lien for contract works is available in terms of clause 25 and it is in
addition to the contractual lien provided for in clause 23 of the agreement. A
claim for compensation may include a debt or damages arising as a result of
suspension of the work
[29] Mr Heathcote further submitted that in view of the provisions of clause 23
and 25 of the building contract, the applicant was entitled to a lien in terms of
clause 23 and to such other remedies as may be available for compensation for
damages caused as a result of the suspension and subsequent termination of
the contract, as provided for in clause 25. In this respect, the applicant’s claim for
specific performance is well established. The applicant has made out a case for
an interim interdict in protection of its claim for specific performance. Mr
Heathcote referred this court to various authorities dealing with the requirements
of an interdict.
[30] It was argued on behalf of the applicant that the facts show that the
applicant was in peaceful and undisturbed possession of the property and that
the respondent had unlawfully deprived the applicant of its peaceful and
undisturbed possession of the property. ‘The happening of the events leading to
the bringing of this application’ threatened the applicant’s possession can be
summarised as follows:
15
1. On 1 November 2016 the employees of second defendant removed all 40 lien
sign boards belonging to applicant and left them lying in a pile, which were re-
erected immediately after they left by Mr Huang Ding Wei (site foreman);
2. On 1 November 2016 the employees of second respondent started with
construction works at the site possessed and on the houses built by applicant; and
3. On 2 November 2016 Mr Uys (second respondent) informed Mr Albert Nicanor
(applicant) that he would cease the construction works but would re-commence
therewith on Monday 7 November 2016.
[31] In respect of non-joinder of the government and NHE, Mr Heathcote
submitted these parties do not have direct interests in the issues for
determination before court. A spoliation remedy can be brought against a
spoliator and as such, the government and NHE do not have an interest in the
outcome of the proceedings. In any event, so it was argued, the government and
NHE may be served with the application and be joined as parties after the rule
nisi was issued.
[32] In respect of urgency, Mr Heathcote submitted that a mandament van
spolie is regarded as an urgent remedy. In this case, it was brought as soon as
possible given the fact that spoliation took place on 1 November 2016. The court
has a discretion which must be exercised judiciously and each case must be
determined on its own facts. The applicant acted expeditiously and it cannot be
said that the applicant was in ‘culpable remissness’ as contended by the
respondent.
Submission on behalf of respondent
[33] It was argued on behalf of the respondent that the contract entered
between it and the government requires of it to comply with its obligations. The
applicant did not have ‘exclusive possession’ of the site. Furthermore, the
applicant did not have a builder’s lien over site except the contractual lien
provided for in the contract between the parties which is restricted to the
16
provisions of clause 23 of the contract. The contractual liens provided for in
clause 23, is for the applicant ‘to take possession of and shall have a lien upon
all unfixed materials and/or goods intended for the works.’ On this basis, the
respondent cannot be deprived of its access and possession on the basis of the
applicant’s builder’s lien.
[34] Mr Muhongo representing the respondent submitted that the applicant did
not provide sufficient details as to what is included in the alleged builder’s lien.
He submitted that if the applicant has a builder’s lien, it does not extend to the
entire site. Mr Muhongo made an observation from the google maps of the site
provided by applicant, that constructions works are noticeable on block 10B, and
to a limited extent, on block 9C. He noted that no construction works took place
on block 10A.
[35] Mr Muhongo argued that the photographs in the founding affidavit should
be rejected as evidence because the identity of the photographer is unknown and
no confirmatory affidavit of the photographer is attached to the papers.
[36] It was further argued on behalf of the respondent, that applicant was not in
peaceful and undisturbed possession of the property because of the alleged theft
that took place on site. On the version of the applicant, on 7 October 2016,
possession of the site was disturbed based on the alleged theft of bricks and of
the illegal water and electricity connections. This is aggravated by the fact that
the applicant does not know who stole the bricks or made the unlawful water and
electricity connections. As a result of the aforesaid, so it was argued, the
applicant’s possession was not peaceful nor was it undisturbed.
[37] In terms of the agreement between the respondent and the Government
there are more pressing public interest issues that should take precedent over
the applicant’s alleged interdict. As a result, the balance of convenience does
not favour the granting of an interdict in favour of the applicant who can be
afforded substantial redress in due course. The commercial interest of the
17
applicant should not outweigh the public interests for housing. In any event, it
was contended that the application was not urgent as the applicant created the
urgency through its own remissness.
[38] Mr Muhongo argued that the non-joinder of the Government and NHE who
have direct and substantial interests in outcome of the case involving the mass
housing project is fatal to the applicant’s case. The Government had contracted
the respondents to complete the construction of the mass housing project, and
as such, the respondent is enjoined in the obligations of the Government to
provide housing
The issues on spoliation
[39] The issues to be decided are:
a) Whether applicant had, enjoyed undisturbed and peaceful
possession since 2014 by having the applicant’s employees on
site?
b) Whether applicant enjoys a builder’s lien over the property and
whether such lien extends to the entire property, and if so, what is
the content and extent of applicant’s builder’s lien in view of the
provision of clause 23 of the building contract?
c) Whether or not the respondent have interfered or disturbed the
applicant’s right to the builder’s lien.
The issues on interdict
[40] The issues to be decided are:
d) Whether the applicant is entitled to claim specific performance as a
remedy in view of the provision of clause 26 of the contract.
18
e) Whether the balance of convenience favour the granting of an
interdict in favour of the applicant and whether the applicant cannot
be afforded substantial redress in due course.
Spoliation
[41] I now turn to the legal principles applicable to spoliation and builder’s lien.
To succeed in an application for mandament van spolie, the applicant must
establish on a balance of probabilities that:
“He or she was in peaceful and undisturbed possession of the thing; and
that he or she was unlawfully deprived of such possession3”.
[42] It is generally accepted that the underlying rationale of the remedy of
spoliation is that no person is allowed to take law into his or her own hands. An
act that amounts to the breach of peace in the community should as a result be
discouraged.4 ‘In order to entitled the contractor to a spoliation order, it was
necessary that he proves not only that he was the de jure possessor of the
building but that he was actually in de facto possession of the building at the
moment when he was despoiled.’5
[43] Applicant further seeks a mandament van spolie based on the ‘unlawful
infringement of the applicant’s builder’s lien’ in that the respondent threatened
such lien by removing sign boards, chevron security tape, by commencing
construction on houses built by applicant. It is alleged that by making illegal
water and electricity connection to the property, the respondent has spoliated the
applicant of possession. It is the applicant’s case that it was dispossessed of the
property where it exercised a builder’s lien.
3 LAWSA vol. 27 at 78 par. 79; see also Bon Quelle (Edms) Bpk v Munisipaliteit van Otari 1989 (1) SA 508 (A); Telkom SA Ltd v Xsinet (Pty) Ltd 2003 (5) 309 (SCA).4 Nino Bonino v De Lange 1906 TS 120 at 122, Kuiiri and Another v Kandjoze and Others 2009 (2) NR 447 (SC).5 Ocean 102 Investment CC v Strauss Group Construction CC & Another (A) 119/2016)[2016] NAHCMD 274 (19 September 2016) at 12.
19
[44] A builder’s lien is a right of retention over the building or structure which a
builder has constructed to secure payment of the contract price.6 The applicant
exercised control over the property which is subject to a lien. A spoliation
remedy does not protect a lien, but it protects a person’s control over a thing, in
other words, the possession. A spoliation remedy therefore protects a factual
situation. Accepting that a lien is an interest protected by law, if control of the
property is removed from a lienholder against her will, she can institute the
spoliation remedy to restore such control. It is for this reason that a lien never
constitutes a cause of action but that it is a defense against the owner’s re
vindicatio or enrichment claim in case the dispossession is done by a non-
owner.7
[45] If a person (a lienholder) affected the necessary or useful improvement to
another person’s (the debtor) property by agreement, the lienholder can defend
his possession when the debtor sues him for the return of the thing before being
compensated for his work done thereupon. He can defend his possession
against his contractual counterpart on the basis of his debtor and creditor lien or
against the owner who is not a contracting party on the basis of his enrichment
lien8.
[46] The builder’s lien entitles applicant to retain the property for buildings for
which the payment is still outstanding9. The onus is on the applicant to prove, on
a balance of probabilities that his lien extended to the entire premises10 made up
of Block 9C, 10A and 10B.
[47] I pause briefly, to state my dissatisfaction with the manner in which this
application was drafted. Letters and emails, which made up the bulk of the
6 LAWSA Vol. 15 par. 70.7 M Wiese, the legal nature of a lien in South African law, 2014 vol 17 no 6 at 2541 to 2542.8 M Wiese, supr.9 Fynbosland 435 CC v Torro Ya Africa (Pty) Ltd and 2 Others (1861/2011) [2011] ZANWHC 68 (15 December 2011).10 Fynbosland supra at 12.
20
application, were attached and quoted in the body of the founding affidavit, while
containing mostly irrelevant facts. Photographs were inserted in the body of the
affidavit without providing sufficient details. The application, which essentially
ought to be short and simple, became instead lengthy and complicated. This has
caused severe prejudice to the court as a lot of time was spent deciphering
irrelevant facts in the founding affidavit and attachments (which at times are
duplicated). Urgent applications should be drafted in precise and accurate terms,
with reference to relevant facts to enable a court to provide its judgment
expeditiously.
Whether applicant had, enjoyed undisturbed and peaceful possession since 2014
by having the applicant’s employees on site?
[48] In applying the well-known rule in the Plascon-Evans Paint vs Van
Riebeeck (Pty) Limited11, I shall base my decision on facts that are common
cause or otherwise on the respondent’s version.
[49] In demonstrating its possession applicant attaches numerous
photographs. No confirmatory affidavit of the photographer is attached to the
papers. To make matters worse, the photographs do not make out what is
alleged by the applicant. In one of the photographs, a person is indicated as ‘a
security guard on site’, but if one glanced at the photograph in question, it simply
depicts a person standing on an empty site. The name of the security guard is
neither given nor is the exact location provided.
[50] If a deponent intends to rely on the truth of the contents of a document,
the facts relied upon must be proved by direct evidence. This requires the
affidavit by the author of the documents to state how she or he knows the
11 1984 (3) SA 623 (A) at 634I-635D.
21
contents as true12. The photographs are disputed by the respondent for reasons
that there is no confirmatory affidavit annexed to the founding affidavit and the
photographer is unknown. I am of the view that the photographer is required to
clarifiy that the content of the photographs are true and correct, failing which, the
photographs cannot be relied upon to prove their content. If their content is not
proved, then there are no photographs to consider.
[51] It is common cause that during August 2014, applicant took possession of
block 10B, in February 2015 of block 9C and in April 2015 of block 10A
respectively. On applicant’s own version, the applicant suspended all works on
the project on 16 April 2015. The works were further suspended on instructions
of NHE in June 2015. This court can safely assume that no constructions work
has commenced on block 10A. Furthermore, it is apparent that applicant was in
possession of block 9C for less than 2 months before it suspended all works on
the project. The above position is confirmed by google maps depicting the
property.
[52] Of importance is the fact that the applicant could not have been is
possession of the property since 2014 as argued. It is obvious that the applicant
was in possession of portion or blocks of the property at different times within the
construction phase. In this regards, it is essential that the applicant’s possession
of the property as alleged be considered.
[53] The court accepts that the property as alleged is made up of three blocks.
No evidence was presented to this court as to the number of house constructed
or not constructed on each block. What building or structures, if any, were
erected on each block? The size and area of the property or each block is
unknown. The court is not enlightened about the extent to which the materials
and goods are either on or off site. 12Cultura 2000 and Another v Government of Republic of Namibia and other 1992 NR 110 HC at 129 para D. See also Ex Parte Minister van Justisie: In re S v Wagner 1965 (4) SA 507 (A).
22
[54] Moreover, it is not clear where on the property the security guards and
foreman were located, whether they were located on all or only some of the
blocks. Is the property easily accessible and where the entry point (s) (gate or
fence) to the property is located? Neither party informed this court who the owner
of the property is. It is thus accepted that the owners of the property is either
NHE or the government.
[55] The construction works on the property was suspended and the principal
agent of the respondent informed the applicant that the suspension shall be
subject to clause 23 of the contract. In terms of clause 23.1, the applicant
(contractor) was requested to remove all his goods, machinery and plant from
site. The court was not informed if this was in fact done. The applicant indicated
that all materials were stored off site at several of its sites and warehouses in
Walvis Bay and Windhoek for safety reasons. In other words, does it mean that
all materials were off site? In addition, all materials were ceded to the
respondent, who became the owner. The court accepts that all materials,
although owned by the respondent, are in the possession of the applicant as
highlighted herein.
[56] A possessor must prove actual possession and not a right to possess.13
‘The builder has the right from the owner to go on the land to erect the building.
He has that right for the purpose of continuously working at the building and
completing it, and for so long as he does so and goes on site for that purpose,
the work must be regarded as under his control. During his possession he cannot
prevent the owner from coming on to the work, but the owner cannot turn him off,
and the work itself is under his control’.14
13 Nufesha Investments CC v Namibia Rights and Responsibilities Inc and Others 2013 (3) NR 787 (HC).14Scholtz v Faifer 1910 TPD 243.
23
[57] In the Ocean 102 Investment CC case15 the court cited with approval the
principles set out in Scholtz v Faifer16:
‘But where work is suspended for a considerable time, then it seemed to me that
if the builder desire to preserve his possession he must take some special step,
such as placing a representative in charge of the work, or putting a hoarding
around it, or doing something to enforce his rights to its physical control’.
[58] It is common cause that the applicant took the step to exert physical
control only after spoliation allegedly took place. In view of the scantiness of the
particulars to sway the court in holding in favour of the applicant, this court is of
the view that there is no evidence that there was sufficient exercise of physical
control by the applicant of the three blocks (the property) to constitute effective
control of the property. The ‘site field’, according the applicant, was too wide to
exercise effective control.
[59] Furthermore, and it is noteworthy, that on applicant’s own version the site
security was provided by the applicant for the benefit of the respondent during
the suspension of the works. This much is apparent from applicant’s email to the
effect that the security guards and the Chinese foremen are intended to protect
the suspended area or houses or materials ‘for our Client’. Furthermore, the
respondent is responsible for payment of the costs of the foreman and the
security guards, as additional costs of ‘site security’ during the suspension of the
works.
[60] On 29 September 2015, the applicant informed the respondent’s principal
agent that if the respondent does not want to pay for site security, the following
shall happen:
15 Supra.16 Supra.
24
‘Withdraw two security guards on site; but the security risk will be much higher
than before and New Era cannot promise the safe of the whole big area. If Client
insist to not to pay the 25000N$/month for the Chinese, we can withdraw the
Chinese from site, but Client must take the risk of secure on site and bear the
loss if any accident happened after that. As we all know, most of the stealing
cases on Construction sites are premeditated by Security Guards’
[61] On the conspectus of the common cause and the undisputed facts, the
contention that the applicant was in possession of the site by having its
employees on site is not established. The employees were on site to guard the
premises for the primary purpose to secure the safety of the site from outside
threats. It is doubtful that the applicant would have been in possession of the site
for its interests given the fact that the applicant was in possession of the
materials belonging to the respondent in its several warehouses. The
possession alleged by the applicant would not have been to the exclusion of the
respondent, given what I have just elaborated hereinabove.
[62] The possession of the blocks was not given to the applicant at the same
time, and therefore constructions on the block would vary. Possession of the
blocks would equally vary. It is more likely that the security services were
provided on block 10B where houses are visible on the google map provided, as
opposed to block 10A and 9C. In the absence of clear and direct evidence, the
court cannot hold in favour of the applicant on this point.
[63] I agree with the arguments advanced on behalf of the respondent that the
applicant did not have ‘exclusive possession’ of the site. It possessed the site to
mitigate the risks of the respondent, and for the safety of the site. The putting up
of lien boards and chevron tapes happened, on the version of the applicant, after
construction by the respondent commenced. The respondent contended that it
was in possession of block 10A and 9C already in October 2016 when it
commenced constructions. ‘The applicant must prove peaceful and undisturbed
25
possession at time of deprivation of possession. The possession must be without
interference or interruption.’17 Based on common cause facts, the applicant
failed to show that it was in undisturbed and peaceful possession of the property.
Whether applicant enjoys a builder’s lien over the property and whether such lien
extends to the entire property, and if so, what is the content and extent of
applicant’s builder’s lien in view of the provision of clause 23 of the building
contract?
[64] It is common cause that the respondent admits that it owes the applicant
money. Although the amount owing is disputed, it is accepted that the principal
agent determined the amount to be N$6 554 829.61.
[65] The respondent contends that the applicant builder’s lien is limited to what
is provided in clause 23 of the contract. The applicant on the other hand,
contends that in addition to the lien provided for in clause 23, it is entitled to a lien
over the constructions works. The applicant can equally claim compensation for
damages arising out of the suspension. In this respect, the builder’s lien is wider
than the provisions of section 23.
[66] The applicant has a right of retention over all the unfixed materials and
goods to secure payment of the contract price in full. Such a right is derived from
the contract. However in respect of compensation for damages, I am in
agreement with Mr Heathcote that a lien for compensation for damages would fall
outside the provisions of clause 23 of the contract. In this respect, the applicant is
entitled to withhold the buildings or structures which it has constructed until it has
been paid.
17Kuiiri and Another v Kandjoze and Others 2007 (2) NR 749 (HC).
26
[67] Mr Muhongo conceded that the applicant has a lien over buildings or
structures which the applicant has built, but disputed that the applicant has made
out such a case. I agree with him. The applicant’s case is that its builder’s lien
applies to the site in general and as such, the applicant did not elaborate on the
works completed or partially completed. No direct evidence was presented on the
building works conducted on each block. The court does not know the
construction works constructed by the applicant, and nor the value of such works
which remained unpaid.
[68] Suffice to say that the content of the applicant’s builder’s lien was not
established on the likelihoods of facts presented in this case. I am of the view
that is necessary to determine the extent of the applicant’s builder’s lien.
‘the fact that he has built houses on a portion of Naledi Extension 25 premises,
does not necessarily extend his builder’s lien to the entire part of the premises
where the construction of the remainder of the housing units has not
commenced.’18
[69] It is common cause that the builder’s lien is security for the work done on
the property, and not for breach of the agreement by the respondent. The latter
relief cannot be addressed by an order for mandament van spolie. It is clear in
this case that the applicant assert its builder’s lien over the entire property, while
it is not clear from the papers which portion of the property the applicant
occupies, if at all. Based on the version of the respondent, it is in occupation of
the area (block 10 A and 9C), where the applicant did not construct houses or
few houses were constructed. This much is evident from the letter dated 14
October 2016 addressed to the applicant by the respondent’s legal practitioner.
[70] The applicant has the onus to prove on balance of probabilities that it was
in possession of the entire property (Block 10A, 10B and 9C). This, the applicant 18 Fynbosland case supra.
27
did not establish. The applicant established a lien in respect of clause 23 of the
contract. However all materials and goods are not in the possession of the
respondent but the applicant in its warehouses and sites around the country.
The applicant failed to show that it had a lien either over the entire premises or in
respect of any building works.
[71] In the applicant’s letter of demand for the restoration of the property, the
applicant asserted that the respondent has entered upon ‘a portion of portion’ of
the property occupied by the applicant. It further alleged that the portion is on
block 10A, 10B and 9C. Yet again, the applicant asserted that the entire property
was disposed from it.
Whether or not the respondent have interfered or disturbed the applicant’s right
to the builder’s lien.
[72] Based on the respondent’s version, the applicant was not in exclusive
possession of the site. On 8 June 2016, the applicant was made aware that the
respondent intends to bring on site a new contractor to complete the
construction. The reason why the aforesaid contractor was not instated is
because the local financier fell through.
[73] On 7 October 2016, the plaintiff was informed to ‘remain’ off the premises.
The theft of bricks took place already on 7 October 2016. The respondent does
not know who stole the 500 bricks. The illegal water and electricity connection
occurred on 14 October 2015. Furthermore, and on the same day, the applicant
was informed that construction on site 10A and 9C commenced two weeks
earlier and the respondent reported that the applicant was unlawfully obstructing
construction on site.
[74] On 24 October 2016, the applicants were warned that the applicant would
be charge for trespassing on the respondent’s property. The applicant was also
28
warned not to obstruct the works on the respondent’s site. Granted the size of
the property, it is likely that the respondent’s contactors’ presence on the
property at the beginning of October 2016 went unnoticed by the applicant. The
applicant however contends that the premises was spoliated on 1 November
2016 when second defendant’s employees removed 40 lien sign boards
belonging to the applicant and when the second respondent’s employees started
with constructions on houses built by the applicant. On the balance of
probabilities, if the applicant was in possession of block 10A and 9C, it lost
possession of the blocks already in October 2016 before the alleged spoliation
took place.
[75] In view of what I have already decided that the applicant’s builder’s lien is
limited to construction works actually done and the provisions of clause 23 of the
contract. It is inconceivable that the respondent could disturb the applicant’s
builder’s lien. The respondent took possession of block 10A and 9C for purpose
of completing the project. As stated previously, it most likely (based on the facts
as presented by the applicant, not denied by the respondent) that applicant was
not in possession of the entire property. It follow therefore that applicant’s
builder’s lien was not disturbed by the respondent.
[76] In any event, the applicant had to convince this court that its builder’s lien
was indeed disturbed as it alleged and this applicant failed to do.
Interdict
Whether the applicant is entitled to claim specific performance as a remedy in
view of the provision of clause 26 of the contract.
[77] The applicant seeks to interdict the respondent from commencing or
continuing with any building construction work on the property pending the
outcome of an action or arbitration to be instituted by applicant against first
respondent for specific performance of the building contracts entered into
29
between applicant and respondent in respect of the property. This relief is sought
independently from the spoliation claim dealt with above in this judgment.
[78] Specific performance is claimed as a remedy aimed to fulfil the envisaged
results at the conclusion of the contract.19 This remedy is granted at the
discretion of the court.
[79] Smuts J20 quoted and described specific performance as:
‘This right has been described as a cornerstone of our law relating to specific
performance. Once that is realised, it seems clear, both logically and as a matter
of principle, that any curtailment of the court's discretion inevitably entails an
erosion of the plaintiff's right to performance and that there can be no rule,
whether it be flexible or inflexible, as to the way in which the discretion is to be
exercised, which does not affect the plaintiff's right in some way or another.
……………
Practically speaking it follows that, apart from the rule just referred to, no rules
can be prescribed to regulate the exercise of the court's discretion. This does not
mean that the discretion is in all respects completely unfettered. It remains, after
all, a judicial discretion and from its very nature arises the requirement that it is
not to be exercised capriciously, nor upon a wrong principle. It is aimed at
preventing an injustice ……………….
Another principle is that the remedy of specific performance should always be
granted or withheld in accordance with legal and public policy.
Furthermore, the court will not decree specific performance where performance
has become impossible. Here a distinction must be drawn between the case
where impossibility extinguishes the obligation and the case where performance
is impossible but the debtor is still contractually bound. It is only the latter type of
case that is relevant in the present context, for in the former the creditor clearly
has no legal remedy at all.’
19 M A Fouche on Legal Principles of Contracts and Commercial law, 8th ed at 117.20 Ashipala v Nashilongo and Another 2011 (2) NR 740 (HC) at 748.
30
[80] In this case, the plaintiff alleged that it has fulfilled its obligation in terms of
the contract. On the other hand, the respondent failed to honour its obligation to
pay the applicant the amount due to it in terms of the contract and damages
arising out a breach.
[81] The fulfilment of the contract as envisaged is what is being enforced.
Consequently, it is a concomitant to the exceptio non adimpleti contractus which
admittedly applies to all contracts where the obligations of the parties are
reciprocal21. It would, of course, be inconsistent to claim cancellation and at the
same time enforcement, but I can see no objection to a claim in the alternative22.
[82] I accept that the applicant may enforce the contract and demand
performance from the respondent in terms of the contract. In this regard, the
applicant may enforce payment due to it. The applicant can demand that the
respondent continue to employ it as its main contractor on conditions that the
applicant tenders to perform its obligations in term of the contract. The applicant
has tender to perform in terms of its obligations as per contract.
[83] While I fully agree that the applicant can enforce the contract, I do not hold
a view that applicant can bring an action to this court without compliance with the
terms of the contract. The route opened to the applicant to enforce the contract is
the dispute resolution mechanism stipulated in the contract. As such, the
applicant is obliged to declare a dispute. In the absence of a declared dispute
this court cannot entertain the application for an interdict.
[84] In Scriven Bros v Rhodesian Hides and Produce Co Ltd and Others23, an
argument was presented that on cancellation of a contract, the contract lost all
efficacy and was of no further force and effect. Incidentally, the case dealt with
an arbitration clause and the attempt to circumvent the operation of dispute
resolution clause which gave rise to the following dictum:
21Scholtz v Thompson 1996 (2) SA 409 (C).22Jardin v Agrela 1952 (1) SA 256 (T).231943 AD 393 at 401
31
‘….But the heads of argument of Mr De Villiers, who appeared for Scrivens in this
Court, make the point that the company repudiated the contract in toto and was
therefore not entitled to avail itself of the arbitration clause, the claim and the
counterclaim going to the root of the contract. The fallacy underlying this
contention is the assumption that a repudiation of a contract in the sense of a
refusal to continue performance under it by one party puts the whole contract out
of existence. It is true that a repudiation of a contract by one party may relieve
the other party of the obligation to carry out the other terms of the contract after
the date of repudiation, but the repudiation does not destroy the efficacy of the
arbitration clause. The real object of that clause is to provide suitable machinery
for the settlement of disputes arising out of or in relation to the contract, and as
that is its object it is reasonable to infer that both parties to the contract intended
that the clause should operate, even after the performance of the contract is at
an end.
….if, for example, this contract had come to an end on a date stipulated for its
termination I do not think it could have been contended successfully that the
arbitration clause was no longer operative. So, too, it seems to me, that when the
contract is prematurely terminated by repudiation by one of the parties, the
arbitration clause is still operative. When such repudiation takes place it may or
may not be justified. Whether it is justified or not will be a question of difference
arising out of or in relation to the contract.’
[85] I agree that the claim for specific performance must be resolved as
provided for in clause 26. This court cannot entertain the interdict at this stage
because the dispute resolution mechanisms are yet to be engaged. I fully
endorsed the statements by Justice Parker in Harold Schmidt t/a Prestige Home
Innovations v Heita,24 where the following is stated:
‘I find that clause 11 of the contract provides for an alternative dispute resolution (ADR)
mechanism. There is no evidence that the parties did attempt to take advantage of this
domestic remedy before resorting to judicial proceedings in the court below. In my
respectful opinion, the procedures in clause 11 could have greatly assisted the parties in
242006 (2) NR 555 (HC) at 565
32
resolving their dispute outside the surrounds of the Court. What is the point, if I may ask,
in providing for the ADR mechanism in the contract if the parties were not prepared to try
it out?’
Whether the balance of convenience favours the granting of an interdict in favour
of the applicant and whether applicant cannot be afforded substantial redress in
due course.
[86] It is accepted that an applicant seeking an interdict is required to establish
a prima facie right, reasonable apprehension of irreparable harm and to prove
that the balance of convenience favour the granting of an interdict and there is no
other remedy. The respondent contents that the applicant was aware of the
substantial redress that it would be afforded at the hearing in due course in
respect of its claim, but did not take steps in terms of clause 26 of the contract.
The applicant has since 2015 to 2016 been aware of the dispute regarding the
amount payable to it. In September 2016, the applicant mooted its intention to
institute legal proceedings against the respondent in the event that the monies
(the amount in respect of which has not been finally determined by the principal
agent) due to it remained unpaid. The applicant did not exercise any of the
option available in terms of the contract and no dispute was declared.
[87] The respondent contends that the applicant fails to demonstrate in its
papers that it could not be afforded substantial redress in due course for its
unpaid claim. In other words if the amount due and payable to the applicant was
determined, the respondent would have been obliged to continue engaging the
applicant as its main contractor.
[88] I also take into account the fact that the contract between the respondent
and NHE was terminated. A new agreement was entered into between the
government and the respondent. The respondent is obliged to complete the
housing project. The applicant is aware of the change of the party founding its
33
contractual relationship with the respondent to the mass housing project. It can
simply not ignore the consequences flowing from such a change.
[89] Although the right of the applicant to claim specific performance is
established by virtue of the contract I do not believe, having regard to the
inherent probabilities, that applicant could, on the facts before me, obtain final
relief at the trial. I say so because since 2015, applicant was aware of its claim
but did not commence with the adjudication procedure. The applicant has not
abandoned its claim for payment nor has it followed the adjudication procedure
[90] The respondent contends the claims for cancellation of the contact and for
contractual damages are adequate remedies in the circumstances of the matter.
It is therefore unsubstantiated why a claim for specific performance is an
adequate remedy, given the alleged financial position of the applicant.
[91] I come to the conclusion that specific performance would not be an
adequate as I found that the applicant is not entitled to possession of the
property to the exclusion of the respondent I cannot make an order interdicting
the respondent from continuing to complete the houses as stipulated by the
contract with the Government. It is not in the wider public interest that this court,
in the circumstances of this case, prevents the respondent from completing the
housing project which commenced since October 2016.
[92] This court is bound to recognise that the Government was not joined as a
party in this litigation. While I do not agree that non-joinder of the Government is
fatal to the applicant’s case, as a rule nisi could be issued and be anticipated, if
necessary. I hold however that the Government has a substantial and a direct
interest in the outcome of the interdict proceeding.
Urgency
[93] The respondent argue that this application is not urgent in view of the fact
that firstly, the urgency alleged by the applicant is self-created and secondly, that
34
the applicant does not demonstrate that it cannot be afforded substantial redress
at the hearing in due course. In respect of the first argument, respondent
contends that the applicant’s claim is entirely and purely commercial in nature
being for unpaid monies.
[94] I am of the satisfied that applications for mandament for spolie are by their
very nature urgent, however having found that the applicant did not succeed in
establishing that it exercised a builder’s lien over the property or the entire
property, and that the applicant was not in effective possession of the property, I
do not deem it necessary to decide on urgency.
[95] For these reasons I make the following order:
1. That the applicant’s application is dismissed with costs.
_______________E ANGULA
Acting Judge
APPLICANT RAYMOND HEATHCOTEassisted by SALOMON JACOBSInstructed by Fisher, Quarmby & Pfeifer
FIRST RESPONDENT TUHAFENI MUHONGOTjombe-Elago Inc.
SECOND TO FIFTH RESPONDENTS NO APPEARANCE