Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction...
Transcript of Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction...
![Page 1: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/1.jpg)
Nevada Irrigation DistrictCentennial Reservoir Project
Draft Conceptual Engineering Report
July 12, 2017
![Page 2: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/2.jpg)
Agenda
ØAlternative Selection
ØDam Foundation and Rock Borrow Area Characterization
ØDam and Appurtenant Works
ØConstruction Schedule and Cost Estimate
![Page 3: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/3.jpg)
Selection of RCC Dam at Axis 2
– Considered roller compacted concrete (RCC) dam and concrete facerockfill (CFR) dam at Axes 2 & 6• RCC dam alternative at Axis 2 has lowest expected construction cost of
alternatives.• RCC dam could be constructed in less time than a CFR dam.• RCC dam more capable of withstanding flood overtopping during
construction than CFR dam.• Axis 2 would have a 3-ft lower reservoir elevation than for Axis 6 to store
110,000 AF.o Lower reservoir elevation would reduce level of inundation around reservoir
– RCC dam at Axis 2 carried forward to design.CFR DamRCC Dam
![Page 4: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/4.jpg)
July 5, 2017Presentation Title
Proposed Reservoir andDam Axis Location
Rock Borrow Area
Dam Axis
Water Surface El. 1885
![Page 5: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/5.jpg)
Dam Foundation and Rock Borrow Area– Summary of site investigation activities
– Geotechnical conditions at Dam Site
– Geotechnical conditions at South RockBorrow Area
![Page 6: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/6.jpg)
Summary of Field Investigations
– Three phases of investigations:• Phase I: 2015• Phase II: 2015• Phase III: 2016
– Geologic mapping
– Seismic refraction surveys
– Core borings
– Hydraulic conductivity testing
– Bore hole geophysical surveys
– Rock strength testing
![Page 7: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/7.jpg)
Regional Geologic Map
Upper Lake Combie Complex rocks: volcanic rock:basalt, locally metamorphosed;dipping slightly to the west
![Page 8: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/8.jpg)
Historical Seismicity and Regional Fault Map
July 5, 2017 Page 8
![Page 9: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/9.jpg)
Geologic Mapping• Mapping of rock outcrops, alluvium and
landslides
• Evaluation of photo lineaments
• Developed plans for seismic line andboring locations
• Confirmed regional geologic mapping
![Page 10: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/10.jpg)
Independent Evaluation of Potential for Active Faulting
Conclusions
– Lack of positive evidence of active faulting at Axis 2site.
– Stratigraphy near Axis 2 site appears to be consistentacross the river.• Absence of vertical separation of contacts supports conclusion that
faulting is not present.
July 5, 2017 Page 10
![Page 11: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/11.jpg)
Site Exploration Map – Seismic Refraction Surveys
July 5, 2017 Page 11
![Page 12: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/12.jpg)
Surface Geophysical Surveys
– 15 seismic refractionsurvey lines at Axis 2 site
– Close confirmation withbore hole data
![Page 13: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/13.jpg)
Geotechnical Drilling Investigation – Axis 2
• 16 core boringso 2 verticalo 14 inclinedo Up to 254 feet deepo Total drilling 2715 ft
• Water pressure (packer)testing
• Televiewer and caliperlogging
• Downhole seismicvelocities
• Rock strength testing
![Page 14: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/14.jpg)
Boring CB-15 on Bear River
![Page 15: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/15.jpg)
Site Exploration Map - Borings
July 5, 2017 Page 15
![Page 16: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/16.jpg)
Geotechnical Profile - Axis 2
CB-12
CB-1CB-17
CB-2
CB-16CB-16A
CB-13
CB-3 CB-4
![Page 17: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/17.jpg)
Detail of Exploratory Boring “Stick Logs”
![Page 18: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/18.jpg)
CB-1, 120.0 – 133.9 ft.
CB-1, 133.9 – 147.5 ft.
Core Boring Sample: south (left) abutment
Ø Weathering and fracturing decrease with depth
![Page 19: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/19.jpg)
Optical Televiewer Log: CB-13, 69.5 – 85.4 ft.
Rock Core: CB-13, 69.5 – 85.4 ft.
Rock Core and Televiewer Log: north (right) abutment
![Page 20: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/20.jpg)
Findings• Hard basaltic rock• Favorable topographic conditions• Close to the dam site area
Potential Rock Borrow Area Investigation• Geologic mapping• Seismic refraction surveys• 5 core borings totaling 585 ft• Downhole seismic velocities• 2 piezometers• Rock strength testing• Durability testing
![Page 21: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/21.jpg)
Geotechnical Sections South Borrow Area
CB-B2
CB-B1
CB-B4
CB-B5 CB-81
CB-B2
![Page 22: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/22.jpg)
Geotechnical Investigation Findings –Foundation Conditions
– Depth to weathered rock generally less than 20 ft.
– Weathered rock found to depths of 100 – 130 ft. at somelocations
– All borings encountered less fractured rock with depth
– Evaluation of significant joint sets and shears indicates alack of persistence between adjacent bore holes
– Hydraulic conductivities mostly decrease with depth andwith decreasing fracture intensity
![Page 23: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/23.jpg)
Geotechnical Investigation - Conclusions
– Confirmed no fatal flaws at Dam Axis 2 site
– Hard volcanic and metavolcanic rock is suitable damfoundation
– Evidence for lack of active faulting along mappedlineaments at site
– Potential rock borrow area present on north side ofreservoir, upstream of dam
– Further investigations needed to develop final design
![Page 24: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/24.jpg)
![Page 25: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/25.jpg)
Excavation Plan
![Page 26: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/26.jpg)
Plan of Dam
![Page 27: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/27.jpg)
Dam Profile
![Page 28: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/28.jpg)
Maximum Spillway Section
![Page 29: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/29.jpg)
Non-Overflow Sections
![Page 30: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/30.jpg)
Outlet Works
![Page 31: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/31.jpg)
Spillway Bridge
![Page 32: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/32.jpg)
Instrumentation Plan
![Page 33: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/33.jpg)
River Diversion Concept
![Page 34: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/34.jpg)
Construction Site Layout – 1 (On-site Rock Borrow)
![Page 35: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/35.jpg)
Construction Site Layout – 2 (Bear River Quarry Borrow)
![Page 36: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/36.jpg)
Basis of Construction Schedule
– Work performed up to 6 days per week, 2 shifts per day
– No overly restrictive constraints on trucking materials to thesite
– Dam foundation excavation: 15,000 cy per week
– Foundation grouting (drilling and grouting): 600 lf per weekfor each drill rig and grout plant.
– RCC construction: 16,000 cy per week
![Page 37: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/37.jpg)
Construction Schedule (Conceptual)
Ø Estimated 2.5-year construction duration
![Page 38: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/38.jpg)
Opinion of Probable Construction Cost (2017 dollars)
WBSCategory Description Category Total
Category % ofTotal
A Mobilization and Demobilization $18,737,000 7.3%
B Site Development $21,497,000 8.4%
C River Diversion $2,600,000 1.0%
D Dam Foundation $41,862,000 16.3%
E RCC, Facing Concrete and Gallery $136,325,000 53.3%
F Spillway and Dam Crest $12,766,000 5.0%
G Spillway Bridge $2,340,000 0.9%
H Outlet and Intake Structures and Pipe $14,759,000 5.8%
I Miscellaneous Civil $3,224,000 1.3%
J Instrumentation and SCADA $1,950,000 0.8%
Total OPCC $256,059,000 100.0%
Estimated Range - Low (-15%) $217,685,000Estimated Range - High (+20%) $307,320,000
![Page 39: Nevada Irrigation District Centennial Reservoir Project ... · Opinion of Probable Construction Cost (2017 dollars) WBS Category Description Category Total Category % of Total A Mobilization](https://reader033.fdocuments.us/reader033/viewer/2022060409/5f102b317e708231d447c8d0/html5/thumbnails/39.jpg)