Network Managers Forum 23 rd April 2015. Agenda 8.30am – Breakfast 9.05am – Welcome and Schools...
-
Upload
mitchell-moris-hunt -
Category
Documents
-
view
215 -
download
1
Transcript of Network Managers Forum 23 rd April 2015. Agenda 8.30am – Breakfast 9.05am – Welcome and Schools...
Agenda• 8.30am – Breakfast
• 9.05am – Welcome and Schools ICT UpdateJason Waring, ICT Schools Service Relationship Manager
• 9.20am – “The Link” UpdateRichard May, Schools ICT Transition Manager
• 9.55am – SIMS Autumn ReleaseJon Osborn, Schools ICT Operations Consultant
• 10.15am – SQL MigrationJon Osborn, Schools ICT Operations Consultant
• 10.30am – Break
• 11.00am – Teacher App DemoGeorge Rowlands, Schools ICT Senior Training Officer
• 11.30am – eSafeguardingDiscussing social media, regulations and eSafeguarding
Chris Whitelaw, Schools ICT Senior Training Officer
• 12.30pm – Close
Backhaul Update
East Sussex Schools
Hove Exchange
County Hall Tunbridge Wells Exchange
Telehouse
RM Network Easynet Network
JANET Internet500Mb
500M
b
1Gb
1Gb
2Gb
Original Configuration:
Please excuse the poor diagram!
Backhaul UpdateUpdated Configuration:
Another bad example of using Visio in a rush!
East Sussex Schools
Hove Exchange
Tunbridge Wells Exchange
Telehouse
RM Network Easynet Network
JANET Internet1Gb
1Gb
1Gb
2Gb
FWA Migration Project
• Coming to the end of a seven year contract for FWA circuits
• Schools were connected via a variety of topologies
• Some connect through multiple schools
• Some connect through secondary schools
• Others connect through other council buildings
• Often third party masts were used
Replacing FWA
• Some schools were already migrated onto new circuits in 2014
• Usually where existing ‘hub’ sites were being decommissioned
e.g. Newhaven and The Grove
• c130 schools still left running FWA this year
• Where possible using Fibre to the Cabinet (FTTC)
• Alternatively using Ethernet First Mile (EFM)
• Some sites (<20) where neither is currently available
• Still investigating options for these sites including ADSL, Bonded
ADSL, Satellite Broadband and even FWA
Timescales
• FWA Contract expires end of August 2015
• Main project work began at the start of the year
• 3 visits required per site
• Planning on completing rollout by End of July
• Hoping to complete most sites by End of June
• Might have to pick up a few visits in the summer
FWA Decomission
• Will begin decommissioning after the summer
• All existing and no longer required aerials will be removed
• Further information to follow
Current Progress
FTTC EFM Total % Complete
Total Number of Sites 94 14 108
Stage 1Pre check visits complete 92 14 106
81%Pre site checks signed off 83 5 88
Stage 2
BT 1st Visit to be confirmed 23 11 34
44%BT 1st Visit arranged 23 3 26
BT 1st Visit Complete 48 0 48
Stage 3
BT 2nd Visit to be confirmed 48 14 62
26%BT 2nd Visit arranged 18 0 18
BT 2nd Visit Complete 28 0 28
Stage 4
Site migration to be confirmed 54 14 68
7%site migration visit arranged 32 0 32
Site migration Complete 8 0 8
Managed Services
• Will soon begin a review of the existing ESEN Managed Services
• Filtering
• Firewall
• DNS
• SMTP Filtered Feeds
• Web Hosting
• etc…
System support (Retirement dates)
System Last Supported Date
Windows XP Summer 2013
Windows Vista Spring 2013
Windows Server 2003 Summer 2013
Office 2003 Autumn 2012
Office 2007 Autumn 2013
SQL Server 2008 R1 Spring 2015
SQL Server 2008 R2 Spring 2015
SOLUS2 Spring 2016 will the be final release that will be available on SOLUS2
System support (New support dates)
System New Support Start Date
SQL Server 2012SQL Server 2014
Spring 2013Autumn 2014
Windows 8Windows 8.1
Spring 2013Spring 2014
Windows Server 2012Windows Server 2012 R2
Spring 2013Spring 2014
Office 2013Internal use of Office 2010
Spring 2014Summer 2014
SIMS – Spring Release 2015
• Release Date 30th March 2015
• Support NET Document ID: 110315
• Schools ICT will potentially release on Wednesday 29th April
• Several report issues which may mean a re-release
• We may delay release if Spring 2 will be available
SIMS – Spring Release 2015
• The SIMS 2015 Spring Release contains updates to:– Admissions– Assessment, – Attendance, – Course Manager,– Exams Organiser, – InTouch, – NOVA-T6, – SIMS Personnel, – Partnership – Exchange, – SIMS Learning Gateway – Teacher App.
SOLUS 3 • SOLUS 3.9 current release
• Support for SQL 2014,
• Better migration tools for moving SIMS to new servers.
• Agent automatic retry if machine off or unavailable
• Upgrades: timeout period extended to increase success rate
• Schools ICT is underway with SOLUS 3 migration• SOLUS2 – Last release available will be Spring 2016 for both Maintained and
Academy – Only Independent schools by 1st September 2015• Currently have a master SOLUS 3 server and testing10 pilot schools for the spring
release.
SOLUS 3 • SOLUS 3.9 current release
• Support for SQL 2014,
• Better migration tools for moving SIMS to new servers.
• Agent automatic retry if machine off or unavailable
• Upgrades: timeout period extended to increase success rate
• Schools ICT is underway with SOLUS 3 migration• SOLUS2 – Last release available will be Spring 2016 for both Maintained and
Academy – Only Independent schools by 1st September 2015• Currently have a master SOLUS 3 server and testing10 pilot schools for the spring
release.
InTouch • Has anyone moved across to the SSM?
– How did it go?– Was it easy?– Is it working better now?
• Spring Changes: – Scheduler service re-write for inclusion in SIMS Service Manager – Removal of manual input fields on install to make process even more automated – Remove need for: – Data service address – Hosted service address – Routing service address – Exam reminders fully automated – Templates moved to School Databases to improve performance – Improve Emergency Alerts Visibility – Ability to flag and organise messages within School and Individual InTouch Mailboxes
Teacher App
•Live Demo after Break
•Has anyone seen this before/using it?
• Spring Updates:– SIMS Dinner Money integration (Now summer term) – Assessment Mark sheet enhancements – Student detail enhancements – User interface updates
Questions?
Any more questions please contact
Email: [email protected]
Web: czone.eastsussex.gov.uk/ict
Twitter: @ESCCSchoolsICT / @schoolsapps
Forum: Czone NMF
Questions?
Any more questions please contact
Email: [email protected]
Web: czone.eastsussex.gov.uk/ict
Twitter: @ESCCSchoolsICT / @schoolsapps
Forum: Czone NMF
Background
•SQL2008 R1 & R2 will not be supported after Summer 2015 release
•SQL2014 - Now supported
•Migration Tools (2012 & 2014) and documentation on FTP – 10.135.51.101 or 217.180.30.142 – Username: sqlmigration – Password: sqlmigration– Re-Index patched for SIMS & FMS
• These will be updated to work on Spring shortly
– Text file with download location and password to extract– InTouch Re-Configuration guide
Migration
•Fairly simple process
•Things to check OS is Server 2008 R1 SP2 or above for SQL2012 OS is Server 2008 R2 or above for SQL2014 Space on disks being used 3rd Party software that connects to SIMS/FMS
•Install SQL2012 or 2014 (express/standard) Please set instance name SQL2012 or SQl2014 if Schools ICT do your
upgrades
•Run Re-Index patches for SIMS & FMS Shrinks log files and sets restore point to simple Available on the FTP
• Create backups
• Run Migration Tool: Screen below is final screen once all the connections from old and new instances
have been entered
• Re-directing SIMS/FMS• If connect.ini files are using redirect S:\SIMS then not needed• Same for FMS• Can use group policy to change these on clients if needed
• It is recommended that Discover and SIMS are migrated at the same time.
• Check SIMS/FMS/Discover are working
• Change any connection files for 3rd Party software and test
• InTouch re-configuration document on the FTP
Performance issues
• Capita – they are advising to postpone SQL 2008 to SQL 2014 until the performance issues have been resolved
• Change database to 2012 compatibility mode
Pricing
• Per core price for 2014 (per 2 core (min purchase 4)) - £439 (£878 min.)
• CALs - £27
• SQL Server Std Single MVL - £115
• As a guide if your school has 28+ users we would suggest Per Core Licencing
• Flyer available
• Secondary schools will typically use SQL Server Standard
What we can offer for IT11 and IT12 Schools:
•Schools ICT can facilitate a remote migration for IT11/IT12 schools*
•All IT10 Premier schools have successfully migrated to SQL 2012 Express
•Please register interest early if using our services and want a May half term date as it is already being booked up and resource may not be available for long
•See flyer for more information
*prices are subject to completion of checklist.
Questions?
Any more questions please contact
Email: [email protected]
Web: czone.eastsussex.gov.uk/ict
Twitter: @ESCCSchoolsICT / @schoolsapps
Forum: Czone NMF
Questions?
Any more questions please contact
Email: [email protected]
Web: czone.eastsussex.gov.uk/ict
Twitter: @ESCCSchoolsICT / @schoolsapps
Forum: Czone NMF
We believe that great teaching matters and every school can be outstanding
The SIMS Teacher App allows teachers to do more of what they do best...teach
Attendance registration
Conduct – achievement/behaviour
Student/teacher timetables
Student & teacher search
Cover & Emergency cover
Student Details
Assessment marksheets
Automated school sign-up
Offline Working (summer term)
Teacher App: PrioritiesTeacher App functionality:
Roadmap – looking ahead
Dinner Money, AWoL, PP/SEN details, record image, seating planner, student summary+, alerts, lesson reflection
Sign in with
Microsoft
(summer term)
(from Easter)
School - SIMS (Local or Centrally Hosted)
How does the Teacher app work?
No data is stored in Cloud
Data is only transferred in real-time & encrypted
SIMS Services Manager configuration
24/7-365 secure web access to management console
School always controls which devices and which teachers have access
School can block a registered device immediately
Unique device association key
3-step teacher activation process
Teacher App Introductory Pricing
1 Year Subscription 3 Year Subscription
STANDARD PRICING:
All school types£2.00 per pupilper year
10% discount: £1.80 per pupil, per year
Min charge: £200 per year for schools with less than 100 pupils on roll / Max charge: £2,500 per year
SIMS LEARNING GATEWAY SCHOOL PRICING:
Capita Hosted SLG school
Included as part of the school’s Capita Hosted SLG subscription
Self-Hosted SLG school
£1.00 per pupil,per year
as per 1 year subscription
Min charge: £100 per year for schools with less than 100 pupils on roll / Max charge: £1,250 per year
The SIMS Teacher App
Trusted
Easy-to-use
Unique SIMS integration
Unique real-time information
Developed with teachers… for teachers
eSafeguardingDiscussing social media, regulations and eSafeguarding
Chris Whitelaw, Schools ICT Senior Training Officer
Ofsted do not advertise what they ask- stable doors and horses!
Social Media in schools - considerations
Social Media – the upside
Social Media
Ease of contact
Ease of contact
Two-way dialogue
Common formatMultiple
users
Partial Privacy
Resource intensive
Predation
IncursionDuty of
care
Social Media – the downside
Social Media
Subversive use
Inspection
“Reasonability”Complicity with broken
Court Orders
Familial predation
QA
EvidenceCP
procedures
Supervision
Liaison
Social Media – the upside
Best/Worst
PromulgationEase of contact
Shop windowImages
Instantaneous
Duplication
IncursionEvery errer multiplide
Relies on users
Who owns what you
post?
Social Media – 50 shades of grey
Who Knows?
Extremism Resilience
Street Speak(Gotta know
your jive)
Overt/covert sexual
material
Governing legislation
AUP/DUP
Metadata
Tagging
Sale of data
DOS attacks
Access
Rights, responsibilities
and conflicts
Parental responsibility
Your content
Your membership
AUP
visibility
conflict
Friends of friends?
Misc. Prov Regs
Enforcement
Marketing/sponsored links
Quantifiable benefit?
KPIs – is it worth doing?
Website Email/phone
SLG
Parent contact
VLE
Stakeholder representation?
Duplication?
Feedback?
Complaint management
Staff hours for support?
Website
VLE
The “Jurassic Park” Factor
“Just because they could, they didn’t
stop to think whether or not they should”
Dr Ian Malcom – chaostician.
Best practice is emergent
You can try to be secure, but…
Some parent/student
bodies “demand it”
Essential for some schoolsQuantifiable
benefits are unclear
No firm guidelines from DfE
Horror stories happen
Still families with no
internet at home
“Hot & Cold” view from
Ofsted
…life will find a way
For more…. To book training/consultancy visits
To let us know about what Ofsted asked, and/or for support with an incident