NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber...
-
Upload
princess-lake -
Category
Documents
-
view
213 -
download
0
Transcript of NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber...
![Page 1: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/1.jpg)
FL4 Remodel ProjectNETS Network Upgrade!
![Page 2: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/2.jpg)
Engineers at Work
![Page 3: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/3.jpg)
304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed.
255,000 Feet of CAT6A copper cable were installed, over 48 miles.
60,000 Feet of Multi Mode OM4 fiber were installed, more than 11 miles
2432 station fiber terminations + 336 trunk fiber terminations were completed.
Installation Factoids:
![Page 4: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/4.jpg)
Install new, ground up, network in 3300 Mitchell Lane capable of supporting current and foreseeable networking needs in accordance with NETS, NCAB, UCAR/NCAR, BICSI, and federal, state, and local jurisdictions building codes.
Project Goal:
![Page 5: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/5.jpg)
A method to deliver a project in which the design and construction services are contracted by a single entity. It relies on a single point of responsibility and is used to minimize risks for the project owner and reduce the delivery schedule.
Design Build Theory
![Page 6: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/6.jpg)
The design build can take the owner out of the loop by the contractor/designer making decisions that the owner should be involved in. In the more traditional Design-Bid-Build, Change Controls are more prevalent and keep the Owner more informed and there more involved in the project.
Design Build in FL4
![Page 7: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/7.jpg)
Ed Snyder (Primary) Fabian Guerrero (Second) Mike Martinez (On Site Supervisor)
Personnel:
![Page 8: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/8.jpg)
Safety Equipment?
![Page 9: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/9.jpg)
Bryan Anderson Rick Mumford Jerome Martinez Carlos Rojas-Torres Wes Wildcat Armando Cisneros Teresa Shibao NETS Admin Team
NI Team
![Page 10: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/10.jpg)
FIRST PULL!
![Page 11: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/11.jpg)
3-year Bond (Equipment) $0
15-year Bond (Permanent Infrastructure) $300,000
Conduit Installation $150,000
NETS FL4 Budget
![Page 12: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/12.jpg)
3-year Bond -$0 - Existing equipment used.
15-year Bond $298,188.2
Conduit Installation $150,000
FL4 Budget Summary:
![Page 13: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/13.jpg)
◦ Marking of facilities not to be demoed◦ Temp (construction) network installation◦ Relocation of Multi-use fiber to FLA◦ Relocation of FLR(B) to FLA◦ Preparing drawings for installation crew◦ Order all parts for installation
NETS start-of-work preceded contractor work
![Page 14: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/14.jpg)
Broken Conduit
![Page 15: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/15.jpg)
NETS work during contractor work
◦ Monitoring contractor progress to ensure that network specifications were being adhered to
◦ Attending OAC Meeting to ensure that changes were not made that affected the NETS installation
◦ Scheduling NETS installation with other trades
Construction (contractor)
![Page 16: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/16.jpg)
Conduit Runs
![Page 17: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/17.jpg)
Project installation followed construction progress
◦ installation of distributor [room] infrastructure (tray, racks, and cable managers)
◦ cable installation and termination◦ Testing and documentation◦ Coordination of people move information
Construction (NETS)
![Page 18: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/18.jpg)
Comm Room Cable Routing
![Page 19: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/19.jpg)
5 Gang Box
![Page 20: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/20.jpg)
Need for Another Core
![Page 21: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/21.jpg)
Equipment installation followed construction progress
◦ installation of network equipment: Switches, VG242’s (analog), UPS’s, AP’s, Monitoring
(Geese), Patch Cables◦ Activation of network ports: Network, Analog,
Special◦ Verification of networks
Post-Construction (NETS)
![Page 22: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/22.jpg)
The project schedule changed due to◦ HVAC Design and Installation problems
Installation of additional Ducting all floors Room remodel required on all floors Replace undersized fan on roof
NETS Schedule◦ Personnel then reassigned to other projects
NWSC Marshall Ongoing normal WR’s
Schedule Summary
![Page 23: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/23.jpg)
Previous occupants returning, few new phones needed
AP’s already in update schedule
Reusing the NETS Switches and UPS’s
◦ Not due for regular replacement◦ Still under maintenance
Budgetary Advantages
![Page 24: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/24.jpg)
Keeping the installation up to UCAR/NETS Standards when the scope of work changed
◦ Full remodel instead of partial◦ Addition of Comm Outlets after budget set◦ Multi-use fiber removal and replacement◦ All new comm conduits throughout the building
Budgetary Challenges
![Page 25: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/25.jpg)
Strong technical installation team
UCAR/NETS Specifications
All Product arrived on time
Same electrical contractor as FLA
What Went Right
![Page 26: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/26.jpg)
◦ Construction timeline Comm Rooms and Chases built first
Always Promised Never Delivered
◦ Move Template Information The sooner the better
From NETS sooner To NETS sooner
What Could Have Gone Better?
![Page 27: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/27.jpg)
Comm Room size, minimum of 130 sq ft, prefer 150 sq ft
Only straight sleeves in cores between floors
Increase the number of cores between floors◦ Increased size of cable
Daily morning meetings kept the whole team informed to the ever changing Design build Project. This is critical for keeping ahead of a project of this size.
Lessons Learned
![Page 28: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/28.jpg)
BAS on NETS cabling◦ Building Automation Systems
Becoming Industry Standard to use IP◦ Space in our cores◦ Space in our Comm Rooms
This project was a design build◦ Design and Construction done together◦ Changes come fast and often◦ Harder for NETS to remain within budget
Other Cahllenges
![Page 29: NETS Network Upgrade!. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper.](https://reader038.fdocuments.us/reader038/viewer/2022110205/56649cb15503460f94976e03/html5/thumbnails/29.jpg)
Thanks to the NI Crew for all of the hard work and long hours that went into this project.
Thanks!