Net Present Value (NPV) Definition _ Calculation _ Examples

3
9/2/2015 Net Present Value (NPV) Definition | Calculation | Examples http://accountingexplained.com/managerial/capitalbudgeting/npv 1/4 AccountingExplained Net Present Value (NPV) Net present value (NPV) of a project is the potential change in an investor's wealth caused by that project while time value of money is being accounted for. It equals the present value of net cash inflows generated by a project less the initial investment on the project. It is one of the most reliable measures used in capital budgeting because it accounts for time value of money by using discounted cash flows in the calculation. Net present value calculations take the following two inputs: Projected net cash flows in successive periods from the project. A target rate of return i.e. the hurdle rate. Where, Net cash flow equals total cash inflow during a period, including salvage value if any, less cash outflows from the project during the period. Hurdle rate is the rate used to discount the net cash inflows. Weighted average cost of capital (WACC) is the most commonly used hurdle rate. Calculation Methods and Formulas The first step involved in the calculation of NPV is the estimation of net cash flows from the project over its life. The second step is to discount those cash flows at the hurdle rate. The net cash flows may be even (i.e. equal cash flows in different periods) or uneven (i.e. different cash flows in different periods). When they are even, present value can be easily calculated by using the formula for present value of annuity . However, if they are uneven, we need to calculate the present value of each individual net cash inflow separately. Once we have the total present value of all project cash flows, we subtract the initial investment on the project from the total present value of inflows to arrive at net present value. Thus we have the following two formulas for the calculation of NPV: When cash inflows are even: NPV = R × 1 − (1 + i) n − Initial Investment i In the above formula, R is the net cash inflow expected to be received in each period; i is the required rate of return per period; n are the number of periods during which the project is expected to operate and generate cash inflows. When cash inflows are uneven: NPV = R 1 + R 2 + R 3 + ... − Initial Investment (1 + i) 1 (1 + i) 2 (1 + i) 3 Home > Managerial Accounting > Capital Budgeting > Net Present Value

description

npv calculations

Transcript of Net Present Value (NPV) Definition _ Calculation _ Examples

Page 1: Net Present Value (NPV) Definition _ Calculation _ Examples

9/2/2015 Net Present Value (NPV) Definition | Calculation | Examples

http://accountingexplained.com/managerial/capital­budgeting/npv 1/4

AccountingExplained

Net Present Value (NPV)

Net present value (NPV) of a project is the potential change in an investor's wealth caused by that project while time value of money is being accountedfor. It equals the present value of net cash inflows generated by a project less the initial investment on the project. It is one of the most reliablemeasures used in capital budgeting because it accounts for time value of money by using discounted cash flows in the calculation.

Net present value calculations take the following two inputs:

Projected net cash flows in successive periods from the project.

A target rate of return i.e. the hurdle rate.

Where,Net cash flow equals total cash inflow during a period, including salvage value if any, less cash outflows from the project during the period.Hurdle rate is the rate used to discount the net cash inflows. Weighted average cost of capital (WACC)is the most commonly used hurdle rate.

Calculation Methods and Formulas

The first step involved in the calculation of NPV is the estimation of net cash flows from the project over its life. The second step is to discount thosecash flows at the hurdle rate.

The net cash flows may be even (i.e. equal cash flows in different periods) or uneven (i.e. different cash flows in different periods). When they are even,present value can be easily calculated by using the formula for present value of annuity. However, if they are uneven, we need to calculate the presentvalue of each individual net cash inflow separately.

Once we have the total present value of all project cash flows, we subtract the initial investment on the project from the total present value of inflowsto arrive at net present value.

Thus we have the following two formulas for the calculation of NPV:

When cash inflows are even:

NPV = R ×1 − (1 + i)­n

− Initial Investmenti

In the above formula,R is the net cash inflow expected to be received in each period;i is the required rate of return per period;n are the number of periods during which the project is expected to operate and generate cash inflows.

When cash inflows are uneven:

NPV =R1

+R2

+R3

+ ... − Initial Investment(1 + i)1 (1 + i)2 (1 + i)3

Home > Managerial Accounting > Capital Budgeting > Net Present Value

Page 2: Net Present Value (NPV) Definition _ Calculation _ Examples

9/2/2015 Net Present Value (NPV) Definition | Calculation | Examples

http://accountingexplained.com/managerial/capital­budgeting/npv 2/4

Where,i is the target rate of return per period;R1 is the net cash inflow during the first period;

R2 is the net cash inflow during the second period;

R3 is the net cash inflow during the third period, and so on ...

Decision Rule

In case of standalone projects, accept a project only if its NPV is positive, reject it if its NPV is negative and stay indifferent between accepting orrejecting if NPV is zero.

In case of mutually exclusive projects (i.e. competing projects), accept the project with higher NPV.

Examples

Example 1: Even Cash Inflows: Calculate the net present value of a project which requires an initial investment of $243,000 and it is expected togenerate a cash inflow of $50,000 each month for 12 months. Assume that the salvage value of the project is zero. The target rate of return is 12%per annum.

Solution

We have,Initial Investment = $243,000Net Cash Inflow per Period = $50,000Number of Periods = 12Discount Rate per Period = 12% ÷ 12 = 1%

Net Present Value= $50,000 × (1 − (1 + 1%)^­12) ÷ 1% − $243,000= $50,000 × (1 − 1.01^­12) ÷ 0.01 − $243,000≈ $50,000 × (1 − 0.887449) ÷ 0.01 − $243,000≈ $50,000 × 0.112551 ÷ 0.01 − $243,000≈ $50,000 × 11.2551 − $243,000≈ $562,754 − $243,000≈ $319,754

Example 2: Uneven Cash Inflows: An initial investment of $8,320 thousand on plant and machinery is expected to generate cash inflows of $3,411thousand, $4,070 thousand, $5,824 thousand and $2,065 thousand at the end of first, second, third and fourth year respectively. At the end of thefourth year, the machinery will be sold for $900 thousand. Calculate the net present value of the investment if the discount rate is 18%. Round youranswer to nearest thousand dollars.

Solution

PV Factors:Year 1 = 1 ÷ (1 + 18%)^1 ≈ 0.8475Year 2 = 1 ÷ (1 + 18%)^2 ≈ 0.7182Year 3 = 1 ÷ (1 + 18%)^3 ≈ 0.6086Year 4 = 1 ÷ (1 + 18%)^4 ≈ 0.5158

The rest of the calculation is summarized below:

Year 1 2 3 4Net Cash Inflow $3,411 $4,070 $5,824 $2,065Salvage Value 900Total Cash Inflow $3,411 $4,070 $5,824 $2,965× Present Value Factor 0.8475 0.7182 0.6086 0.5158

Present Value of Cash Flows $2,890.68 $2,923.01 $3,544.67 $1,529.31

Total PV of Cash Inflows $10,888− Initial Investment − 8,320

Net Present Value $2,568 thousand

Strengths and Weaknesses of NPV

Strengths

Net present value accounts for time value of money which makes it a sounder approach than other investment appraisal techniques which do notdiscount future cash flows such payback period and accounting rate of return.

Net present value is even better than some other discounted cash flows techniques such as IRR. In situations where IRR and NPV give conflictingdecisions, NPV decision should be preferred.

Weaknesses

NPV is after all an estimation. It is sensitive to changes in estimates for future cash flows, salvage value and the cost of capital.

Page 3: Net Present Value (NPV) Definition _ Calculation _ Examples

9/2/2015 Net Present Value (NPV) Definition | Calculation | Examples

http://accountingexplained.com/managerial/capital­budgeting/npv 3/4

Net present value does not take into account the size of the project. For example, say Project A requires initial investment of $4 million to generate NPVof $1 million while a competing Project B requires $2 million investment to generate an NPV of $0.8 million. If we base our decision on NPV alone, wewill prefer Project A because it has higher NPV, but Project B has generated more shareholders’ wealth per dollar of initial investment ($0.8 million/$2million vs $1 million/$4 million).

Written by Irfanullah Jan

Related Topics

Internal Rate of Return

Adjusted Present Value

Profitability Index

Present Value of Annuity

Managerial Accounting

Managerial Accounting Intro

Cost Classifications

Cost Accounting Systems

Cost Allocation

Cost Behavior Analysis

Cost­Volume­Profit Analysis

Relevant Costing

Capital Budgeting

Payback Period

Discounted Payback Period

Accounting Rate of Return

Net Present Value

NPV and Inflation

NPV and Taxes

Internal Rate of Return

NPV vs IRR

Profitability Index

Adjusted Present Value

Master Budget

Inventory Management

Standard Costing

Performance Measurement

Copyright © 2011 ­ 2013 AccountingExplained.com | All Rights Reserved

Be the first of your friends to likethis

Accounting Ex…21,350 likes

Like Page Share