Land Acquisition and Involuntary Resettlement Due Diligence Report
Document Stage: Draft for consultation
Project Number: 43524-014
April 2019
NEP: Kathmandu Valley Wastewater Management
Project – Core Area Sewer Network of Lalitpur (SN03) PART B
Prepared by the Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited, Ministry of Water Supply, Government of Nepal for the Asian Development Bank.
This draft due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Appendix 4 65
Notes of meeting discussions and agreed points between Lalitpur Metropolitan City
(LMC), NEA and PID regarding underground cabling of electric line
Date: July 22, 2018 Venue: NEA Head office Purpose of the meeting A meeting was called between Lalitpur Metropolitan City (LMC), Nepal Electricity Authority (NEA) and Project Implementation Directorate (PID) to discuss the issue about laying of underground electric cable from Lagankhel of Patan till Shankamul. The sewer rehabilitation project of Patan core area is in the final stage of completion of the DPR.Management of the existing utilities is one of the key issues within this project too. Many rounds of meeting have been held with the local office of NEA in regard to underground laying of the old electric cable so as to provide an improved system in the narrow alleys and roads of Patan falling within the sewer pipe route. The local unit of NEA had expressed their desire to have this system in place but due to the limitation of funds, had shown their inability to move forward. Visualizing the ground reality of doing any civil construction in these area without the support of the local authorities is going to be a herculean and near to impossible task to accomplice. So LMC has not only taken up the lead role in executing this project jointly with PID but is also sharing the project cost. Thus, all the agencies have understood the importance of this project and have acknowledged the working modality too. This also serves as a golden opportunity for all related utility owners to improve all their worn out and outdated utilities during the execution of this project. It was also informed by NEA officials that they are likely to execute the work of underground cabling of all electricity cable within the Kathmandu valley in near future. LMC and PID made aware to all about the likely timing of the actual construction work of the sewer project which is January 2019.The sewer route map and the related details were presented at meeting The following were present in the meeting: Attendees: 1.Mr.Chiri Babu Maharjan Mayor, LMC 2 Mr.Kul Man Gheising MD/NEA 3 Mr.Surat Bam PM/PID 4.Mr. Manoj Silwal Act.DMD 5. Mr.Rudra Adikari Senior Engineer/LMC 6.Mr. BharatMaharjan Engineer DSC04 7. Mr.Birendra Kumar Singh Chief, NEA Lagakhel Unit 8.MrJay Kumar Yadav Senior Engineer NEA Lagankhel Unit 9. Rajesh Pd Singh WME/PID 10.Mr. Ramji Bhandari Director, NEA Head office Discussions and Agreed Actions: There was discussion among all participants and final conclusions and agreed points are as follows:
(i) LMC and PID will proceed ahead in preparation of the DPR with close consultation with the local unit of NEA.
(ii) To have a safe and reliable underground system in place, NEA head office will assist and guide the local unit of NEA in preparation the required cost estimate with proper specifications.
(iii) LMC and PID will execute the single package contract with the civil works for the underground cable included.
(iv) The cost of the civil works for the electrical component will be borne by PID and LMC.
66 Appendix 4
(v) Realizing the opportunity of working with LMC in the forefront, NEA principally agreed to supply all the material required for the underground cabling work and will also explore and manage the budget for the same.
(vi) The supply of materials will be synchronized with the timing of the civil contractor being on board i.e. January 2019
(vii) NEA will also support the project with its expertise in this field and supervise the entire cable laying work.
Appendix 4 67
68 Appendix 4
Appendix 4 69
70 Appendix 4
Appendix 4 71
72 Appendix 4
Appendix 4 73
English Translation Minute
Consultation with stakeholders
A meeting is organized today on 26 Magh 2075 (10 Feb 2019) on Lalitpur Metropolitan City, for the public discussion for IEE of Sewer Rehabilitation from Lagankhel bus station (LMC ward no 5) to Sankhamul through Patan Durbar Square (SN03) under Kathmandu Valley Wastewater Management Project (KVWWMP), Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited (KUKL). From this sewer rehabilitation project, the problem of sewer flowing around the area Lagankhel bus station, Mahapal chowk, Mangal Bazar and Patan Bazar area would be solved. Regarding this, discussion for the suggestion and opinion of people for IEE and possible impact that the project may cause is being held today in presence of Lalitpur Metropolitan and concerned authority/stakeholers. Following is the list of candidates present in the meeting.
SN Name of Participants Organization
1 Chiri Babu Maharjan Mayor LMC
2 Geeta Satyal Deputy Mayor LMC
3 Raju Maharjan Ward chairman -9
4 Suprava Sakya Ward member 16 no ward
5 Pancha Bajra Bajracharya Ward member 16 no ward
6 Bu lal Maharjan Ward member
7 Nuchhche Ratna Khadgi Ward member
8 Dikshya Dhakal PID/DSC-6
9 Raj Lal Thakur PID/DSC-5
10 Hera Kaji Maharjan Nepal Telecom
11 Surat Malla Nepal Telecom Patan
12 Krishna Govinda Joshi Treasurer Tole committee
13 Bhagwan Maharjan Secretary Tole committee
14 Kaji Pyakurel Patan Durbar Squre office
15 Sarika Gharana DSC-6/PID
16 Rajesh Pd .Singh PID
17 Bharat Maharjan Network Eng./DSC-6 /PID
18 Min Dahal FC/CASSC/PID
19 Shisir Gautam SDE /DSC-6/ PID
20 Rudra Pd Adhikari LMC
Decision
SN03 project would be started considering the suggestions obtained from discussion for the possible impacts of the project and for IEE.
74 Appendix 4
Feedback/ consultation with stakeholders
Appendix 4 75
76 Appendix 4
Appendix 4 77
English Translation Minute
Feedback/ consultation with stakeholders
Opinion/Feedback of public required in (10 January 2019) for the preparation of IEE report of Sewer Rehabilitation in the core city area of Lalitpur Metropolitan City under Kathmandu Valley Wastewater Management Project (KVWWMP), Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited is as follows. The project is 2.8 km sewer system that is proposed in Lalitpur Metropolitan City ward no 5, 9, 11, 12, 16 and 19 from Lagankhel, Patan Durbar Square to Sankhamul Area.
S.N Name Opinion
1. Raju Maharjan Ward chairman LMC-9
In present situation, it is highly necessary to improve the
condition road from Mangalbazar to Gapuhiti. If the road cannot
be improved then it is difficult to convince the public of this area.
2. Suprava Shakya Stone pavement should be made along the area of the
heritage site as it is done in present condition. Project should be
completed in time as it is necessary to satisfy the public
otherwise it would be difficult to the concerned people.
3. Pancha Bajra
Bajracharya
The condition of sewer and drinking water within the Lalitpur
Metropolitan City should be taken into consideration and
work should be completed without creating any difficulties to the
concerned people.
4. Nhuchhe Ram Khadgi,
ward no 19
I request you to work efficiently to finish the project in time.
5. Surat Malla, Nepal
Telecom office , Patan
I hope for the successful completion of the SN03 project.
During the construction phase of this project, facilities given by
Nepal Telecom to the public would be interrupted. So,
considering this and the government revenue, it is necessary to
run this project by side with NTC. Moreover, to continue to give
the service of NTC, provision of additional budget is not available
at present with NTC. Hence the additional budget would be
incorporated for damaged line by project side.
6. From the side of Lalitpur
Metropolitan City office
1. Design should be made considering the worst condition of site such as narrow road and in such situation construction methodology should be recommended for carrying out the construction activities.
2. For the safety of the people during the construction phase, hard cover fence and blinking light should be kept around the project area. Work schedule should be prepared considering the festivals according to Nepali, Newari and English calendar and also considering the ‘Visit Nepal 2020’.
3. As the section from Bhimsen temple to Sankhamul and Mahapal Iti road are tourist areas, there should be a provision for the pavement of the roads in that area should with high quality stone.
4. A maintenance manual containing maintenance plan, technology, and equipment should be recommended such that the project runs smoothly after the construction and completion of project.
78 Appendix 4
Opinion/Suggestion collected for SN03 project during Focus Group Discussion
Appendix 4 79
80 Appendix 4
Appendix 4 81
82 Appendix 4
Appendix 4 83
84 Appendix 4
Appendix 4 85
English Translation of focus group discussion 24th March 2019
Opinion and suggestion of public required for the preparation of IEE report of Sewer Rehabilitation in the core city area of Lalitpur Metropolitan City was collected on 24th March 2019. The list of people who were consulted are as follows:
NAME PLACE
1. Saru Rai K.K Mart- Department Store
2. Hari Humagain K.K Mart- Cloth shop
3. Kalpana Silwal K.K Mart- Cloth shop
4. Sabita Nepal Shoes shop
5. Bijay Raj Chirag Sweets
6. Umesh Duwal Umesh store- Owner of a house
7. Bhawani Timalsina MBS Fancy
8. Devraj Karki Dev Cloth shop
9. Prachanda Raj Jibi Cloth Shop
10. Nutan Tamrakar Nutan Kitchen Store
11. Dipak Adhikari Worship Utensils shop
12. Narayan Lal Shrestha Beans shop
13. Suresh Singh Gift shop- Owner of a house
14. Sanu Hira Shakya/Sharmila Maharjan Owner of a house/ Owner of a Tailor Shop
15. Bipin Bajracharya Patan Durbar Square Museum
16. Prem Lama Art Gallery
17. Dikesh Maharjan Tea Shop-Owner of the house
18. Yogendra Maan Bajracharya Owner of a house
19. Bishnu Limbu Little City Kids School
20. Amit Shah Bagmati Multi-Speciality Clinic
21. Bharat Bhujel Shoes Shop-Vendor
22. Laxmi Shrestha Vendor
23. Krishna Bahadur Shrestha Vendor
24. Subachandra Mandal Mixed things Vendor
25. Shahbaj Ansari Chatpate/Paanipuri Vendor
26. Babita Chitrakar Handicraft Vendor
27. Durga Dahal Chatpate/Paanipuri Vendor
86 Appendix 4
Meeting for discussion of SN03
Appendix 4 87
88 Appendix 4
English Translation of the minutes of meeting 31st March 2019
A meeting is organized today on Sunday, 31st March 2019 (16 Chaitra 2075) on Lalitpur Metropolitan City in presence of Mayor of LMC. With the budget of Government of Nepal, LMC and ADB, a 2.8 km sewer line will be constructed from Lagankhel bus station to Sankhamul through Patan Durbar Square (SN03) that will manage the storm water and sewer line. In this regard, group of people from different organization as well as public people had a discussion, interaction and exchange of information. The list of people present in the meeting is listed as
follows:
SN Name of Participants Organization
1 Chiri Babu Maharjan Mayor LMC
2 Geeta Satyal Deputy Mayor LMC
3 Surendra Govinda LMC
4 Prayag Lal Johari Expert
5 Kiran Man Pradhan Mangaltol
6 Rudra Adhikari LMC
7 Narayan Lal Awale Ward chairman -12
8 Saafale Amatya
9 Prafulla Man Singh Pradhan LMC-Adviser
10 Rohit Ranjitkaar LMC-Adviser
11 Suresh Saras Shrestha Department of Archaeology
12 Sandeep Khanal In charge of heritage site
13 Devendra Bhattrai Department of Archaeology
14 Surat Kumar Bam KUKL/PID
15 Rajesh Pd .Singh KUKL/PID
16 Vidhya Bhandari PID
17 Madhav Prasad Ghimire Media LMC
18 Rama Luitel Media LMC
19 Ramiya Maharjan Ward member 19 no ward
20 Ram-Bhakta Thapa Ward member 4 no ward
21 Bharat Prasad Acharya CASSC/PID
22 Pushpa Koirala CASSC/PID
23 Sarika Gharana DSC-6/PID
24 Bharat Maharjan DSC-6 /PID
25 Min Dahal CASSC/PID
26 Bijay Karki Naya Patrika
27 Gopal Man Shrestha Cultural organisation
28 Bishweshor Koirala LMC
29 Pramod Ward no 3
Appendix 4 89
Presentation to LMC and LCCC on 31 March 2019
90 Appendix 4
Appendix 4 91
92 Appendix 4
Appendix 4 93
94 Appendix 4
Appendix 4 95
96 Appendix 4
Appendix 4 97
98 Appendix 4
Appendix 4 99
100 Appendix 4
Appendix 4 101
102 Appendix 4
Summary of public consultation (Brief Translation of Minutes of Meetings)
S.N. English
Date Nepali Date
No of
participants Male Female Location Participants Major issues/Translation
1. 6 Feb
2018 2074/10/23 55 51 4
Assembly
Hall, Lalitpur
Metropolitan
city
Mayor, House of
representative member,
state assembly member,
ward representatives, ADB
consultant, PID,KUKL,
CASSC, DSC, LMC staffs
other concerned
stakeholders
Presentation and discussion on
Dhobighat waste water treatment
plant and sewer system
rehabilitation
2. 24 May
2018 2075/02/10 34 29 5
Assembly
Hall, Lalitpur
Metropolitan
city
Mayor, PD, ward
representatives, PID,KUKL,
CASSC, DSC, LMC staffs
other concerned
stakeholders
Presentation on DPR at LMC to
different stakeholders; Discussion
on DPR of the trunk line for SN-03
3. 6 June
2018 2075/02/23 38
Assembly
Hall, Lalitpur
Metropolitan
city
Mayor, PD, ward
representatives, PID,KUKL,
CASSC, DSC, LMC staffs
Presentation on DPR and Design
Revision and Discussion on SN-03
4. 25 June
2018 2075/03/11 12 7 5
Ward no 5 Ward chairperson, ward
secretary, local people,
CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
5. 26 June
2018 2075/03/12 21 6 15
Ward no 12 Ward chairperson, ward
secretary, local people,
,CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
Appendix 4 103
S.N. English
Date Nepali Date
No of
participants Male Female Location Participants Major issues/Translation
6. 26 June
2018 2075/03/12 15 11 4
Ward no 19 Ward chairperson, ward
secretary, local people,
,CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
7. 29 June
2018 2075/03/15 28 23 5
Ward no 9 Ward chairperson, ward
secretary, local people,
,CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
8. 29 June
2018 2075/03/15 16 14 2
Ward no 11 Ward chairperson, ward
secretary, local people,
CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
9. 29 June
2018 2075/03/15 19 14 5
Ward no 16 Ward chairperson, ward
secretary, local people,
CASSC
Information dissemination of the
project. Coordination with ward
committee and local community
members and further discussion
on the combined sewerage line of
SN-03 and underground utilities
over the planned stretch.
104 Appendix 4
S.N. English
Date Nepali Date
No of
participants Male Female Location Participants Major issues/Translation
10. 19 July
2018 2075/04/03 21
Assembly
Hall, Lalitpur
Metropolitan
city
Mayor, Chief Administrative
officer, ward
representatives, PID,KUKL,
CASSC, DSC, LMC staffs,
NEA representative, NTC
representative
Discussion on the existing
underground utilities from and their
reinstatement after dislocation.
1. The project will provide civil cost
for the relocation of underground
electricity cables and conduit.
2. Nepal electricity authority will
supply all required underground
cables and conduit and civil cost
will be included in the project
BOQ.
3. It is agreed that MOA between
KUKL (PID) and LMC will be
signed on 31 July 2018.
4. KUKL (PID) will provide all
discussed topics and particulars to
all stakeholders by email within 22
July 2018.
11. 22 July
2018 2075/04/06 10
NEA Head
office
Mayor, KUKL-PID, DSC, NEA staffs and LMC staffs
Preparation of the DPR, cost of the civil works
12. 18 Nov
2018 2075/08/02 34 30 4
L
MC Ward no
Ward Chairperson 12,19 and 5 ward LMC Tole committees leaders, Shopkeepers, venders, Community members and
Information dissemination of the project. Coordination with ward committee and local community members The excavation work for this section will be 50-100 meters which will be backfill immediately after finishing work. Therefore, there will be no disturbance on local business.
Appendix 4 105
S.N. English
Date Nepali Date
No of
participants Male Female Location Participants Major issues/Translation
12 office KUKL /DSC-6/ PID Project will inform shopkeeper and vender at least one week prior to the excavation so that the street vendors could manage their business for that time. Locals including vendors shopkeepers agreed to provide their support by clearing the construction area and construction activities will be carried with protecting public assets and small temples.
13. 10 Feb
2019
27 Magh
2075 20 16 4
LMC office
Meeting Hall
Mayer, Deputy Mayer, Ward Chairperson of LMC tole committee member of LMC Tole committee leaders ,Nepal Telecom, DOA Patan Darbar Office and PID/DSC-6,and CASSC DSC-5
Public consultation with different stake holders in presence of Lalitpur Municipality Project SN03 would be continued to incorporate of IEE mitigation measures (Please refer minute which is attached in this minute Report)
106 Appendix 5
Appendix 5: List of Participants
SN. Name of participants Organization
Meeting at LMC Assembly Hall on 6 February 2018
1. Chiri Babu Maharjan Mayor, LMC
2. Pampha Bhusal House of representative member
3. Jiwan Khadka State assembly member
4. Raj Kaji Maharjan State assembly member
5. Ashish Ghimire HPCIDBC
6. Kishor Thapa Bagmati Cleaning Campaign
7. Bijaya K Shrestha ADB consultant
8. Rahul Muni Bajracharya ADB consultant
9. Ajar Man Joshi Lalitpur Chamber of Commerce
10. Rudra Gautam LMC
11. Dilendra Raj Shrestha Advisor, LMC
12. Sabin Shrestha Lalitpur Chamber
13. Nabin Mangal Joshi Kebhal Tole Sudhar Samittee
14. Birendra Lal Shrestha Mangal Bazar Tole Sudhar Samittee
15. Binod Tamrakar Ward Chairperson; ward no 19
16. Prayag Joshi Engineer, ward no 19
17. Kiran Man Pradhan Mangal Bazar Tole Sudhar Samittee
18. Gyanu Raja Shrestha Mangal Bazar Tole Sudhar Samittee
19. Sunil Shakya Mahapal Tole Sudhar Samittee
20. Suvendra Raj Joshi Swothe Tole Lalitpur
21. Garinets Safbon water
22. Dinesh Maharjan Choba Gahitee tole
23. Narayan Lal Awale Ward Chairperson; ward no 12
24. Suresh Maharjan Ward Chairperson; ward no 26
25. Indraman Maharjan Ward Chairperson; ward no 11
26. Nirmal ratna shakya Ward Chairperson; ward no 16
27. Bishow mani Jyawali Executive Director; SWMTSC
28. Kishor Shakya Nepal Engineering Association
29. Sanjib Bikram Rana Executive Director; KVWMSB
30. Diwakar Pd Dhakal DPD; PID
31. Nanda lal Banjade
CDE; Department of water supply &
Sewerage
32. Dipak Puri DSC -04/PID
33. Dhurba Bd Shrestha ADB/PPTA
34. Himesh Anand Baidya DPD/PID
35. Dhurba Raj Regmi PMD/PID
36. Suman Pd Sharma PID/ADB
37. Mahesh Bhattarai KUKL
38. Tiresh Pd Khatri EDPID
39. Anil Bhadra Khanal Joint Secretary; Ministry of Water supply
40. Jhanj Honglogn PID Consultant
41. Bharat Maharjan DSC04/ PID
42. Raju Maharjan Ward no 9
43. Krishna Lal Maharjan Lalitpur Metropolitian City
Appendix 5 107
SN. Name of participants Organization
44. Suranjan Ghimire Ba rakhari.com
45. Narayan K.C Ward Chairperson; ward no 4
46. Rikesh Chitrakar Envt. Expert; DSC04
47. Kishor Pantee Engineer/ PID
48. Sangitanjali Koirala Engineer/ PID
49. Rukesh Bataju SARBON/ Engineer
50. Bhagwan Maharjan
51. Pushpa Koirala Envt. Expert; CASSC
52. Bharat K.C CSE; DSC04
53. Bharat Acharya CME; CASSC; DSC 04
54.
55.
56.
57. Mahesh Bhattarai KUKL
58. Tiresh Pd Khatri PID
59. Suman Pd Sharma PID/ADB
60. Arjun babu Dhakal LMC
61. Dhurba Raj Regmi PMD/PID
62. Pinky Bijayananda Social Development Expert/DSC04
63. Rikesh Chitrakar Envt. Expert; DSC04
64. Surat Bd Malla Nepal Telecom
65. Ram Sundar Hamal Nepal Telecom
66. Kaji Pyakural Patan Durbar Square
67. Krishna Lal Maharjan LCCI
68. Indra Man Maharjan Ward Chairperson; ward no 11
69. Niran Man Pradhan
Ward No 11
70. Chanda lal Maharjan Ward Chairperson; ward no 20
71. Narayan Lal Awale Ward Chairperson; ward no 12
72. Binod Tamarkar Ward Chairperson
73. Nabin Mangal Joshi TLO; Mangalbazar
74. Gyanendra Kalauni Engineer, Lalitpur
75. Prayag Joshi Engineer, ward no 19
76. Nirmal ratna shakya Ward Chairperson; ward no 16
77. Birendra K Singh NEA; Pulchowk
78. Mohamad Rayan NEA; Pulchowk
79. Jay K Yadav NEA; Lagankhel
80. Munny pradhan Consultant ADB
81. Vivan Castro ADB
82. Rajesh Pd Singh PID
83. Bipul Das PID
84. Surak K Bam PID/KUKL
85. Jhang Hong Kyu PID Consultant
Meeting at 16 Ward Office, 29 June 2018
108 Appendix 5
SN. Name of participants Organization
86. Nirmal Ratna Sakya, Chief, 16 Ward LMC
87. Dilip Joshi, Advisor, 16 Ward LMC
88. Bal Krishna Maharjan, 16 Ward LMC
89. Prabin Bahadur Shakya, DMC, 16 Ward LMC
90. Narayan Maharjan CDMC, 16 Ward LMC
91. Sapina Karki, 16 Ward LMC
92. Anusha Karki, 16 Ward LMC
93. Sarita Shakya, 16 Ward LMC
94. Deepak Pokharel, Secretary, 16 Ward LMC
95. Puskar Kumar Thapa, 16 Ward LMC
96. Sabin Narayan, 16 Ward LMC
97. Khushi Shakya, 16 Ward LMC
98. Sandeep Budhathoki, 16 Ward LMC
99. Yanalal Maharjan, 16 Ward LMC
100. Raskumar Nepali, 16 Ward LMC
101. Nutana Shrestha, Enumerator, CASSC CASSC/PID
102. Ramesh Deuba, CASSC CASSC/PID
103. Bharat Acharya, CASSC CASSC/PID
Meeting at 5 Ward Office, 25 June 2018
104. Ashok Kumar Shrestha, Ward 5, Chief LMC
105. Manju Rijal, 5 Ward, Member LMC
106. Shova Devi Pradhan Shrestha, 5 Ward, Member LMC
107. Punam K.C. Niraula, 5 Ward, Member LMC
108. Sangita Maharjan, 5 Ward LMC
109. Raghab Dangol, 5 Ward LMC
110. Krishna Ram Shrestha, 5 Ward LMC
111. Bharat Acharya, CASSC PID
112. Min Dahal, CASSC PID
113. Radha Krishna Shrestha, 5 Ward LMC
114. Ravi Kumar K.C. 5 Ward LMC
115. Raj Kumar K.C. 5 Ward LMC
Meeting at 12 Ward Office, 26 June 2018
1. Sarita Maharjan, Ward 12 Representative LMC
2. Sanu Awale, 12 Ward Chief LMC
3. Nidhi Tamrakar, 12 Ward LMC
4. Astalaxmi Shrestha, 12 Ward LMC
5. Mohan Laxmi Shakya, 12 Ward LMC
6. Jayenti Maharjan, 12 Ward LMC
7. Budha Laxmi Awale, 12 Ward LMC
8. Rama Maharjan, 12 Ward LMC
9. Gita Tamrakar, 12 Ward LMC
Appendix 5 109
SN. Name of participants Organization
10. Keshari Shakya, 12 Ward LMC
11. Komal Shakya, 12 Ward LMC
12. Laxmi Dangol, Secretary, 12 Ward office LMC
13. LMC
14. LMC
15. Shreejana Bhaidya, 12 Ward office, Member LMC
16. Maiya Bista, Secretary, 12 Ward office LMC
17. Maiya Maharjan, Chief LMC
18. Indu Bajracharya, 12 Ward LMC
19. Min Dahal, CASSC KUKL/PID
20. Bharat Acharya, CASSC KUKL/PID
Meeting at 19 Ward Office
1. Binod Tamrakar, 19 Ward, Chief LMC
2. Bulal Maharjan, 19 Ward, Representative LMC
3. Ramiya Maharjan, 19 Ward, Representative LMC
4. Renu Maharjan, 19 Ward LMC
5. Nhuche Ratna, 19 Ward LMC
6. Prem Lal Maharja, 19 Ward LMC
7. Devi Chaulagai, 19 Ward LMC
8. Asha Lal, 19 Ward LMC
9. Bhai Krishna, 19 Ward LMC
10. Asta Bahadur Nemkul, 19 Ward LMC
11. Dibesh Maharjan, 19 Ward LMC
12. Ramesh Shrestha, 19 Ward LMC
13. Bharat Acharya, CASSC/PID KUKL-PID
14. Min Dahal, CASSC/PID KUKL-PID
24 May 2018 meeting at LMC hall
1. Chiribabu Maharjan, Mayor (Chairman) LMC
2. Gita Satyal, Vice Chairman LCM
3. Mahesh Bhattarai, Coordinator KUKL
4. Suman Prashad Aryal, Consultant
5. Arjun Babu Dhakal,
6. Dhurba Raj Regmi, PID Consultant KUKL,PID
7. Pinky Bijayanand, Social Development Expert DSC04, KUKL, PID
8. Rikesh Chitrakar, Environment Specialist DSC04, KUKL, PID
9. Surat Bahadur Malla, Office Chief, Representative NTC
10. Ram Sundar Hamal, Technical Officer,
Representative
NTC
11. Kaji Pyakurel, Chief Palace Officer, Representative DOA
12. Krishna Lal Maharjan, Chief, Representative LCCI
13. Indraman Maharjan, 11 Ward, Chief LMC
110 Appendix 5
SN. Name of participants Organization
14. Raju Maharjan, 9 Ward, Chief LMC
15. Kirna Man Pradhan, 19 Ward, Chief LMC
16. Chandra Lal Maharjan, 20 Ward, Chief LMC
17. Narayan Lal Awale, Ward Chief LMC
18. Binod Tamrakar, 2 Ward Chief LMC
19. Nabin Mangal Joshi, Coordinator, Area
Development Committee
LMC
20. Gyanendra Kalauni, Engineer, LMC
21. Prayag Joshi, Drainage Engineer, Local
Representative
LMC
22. Nirmal Ratna Shakya, 16 Ward Chief LMC
23. Birendra Kumar Singh, Chief, Representative NEA, Lagankhel
24. Kul Mohammad Rayem, Engineer, Representative NEA, Pulchowk
25. Jay Kumar Yadav, Envineer, Representative NEA, Lagankhel
26. Amy, Consultant ADB
27. Munny Pradhan, Consultant ADB
28. Vivian Casteo.Wooldridge, Consultant ADB
29. Rajesh Prasad Singh, WME KUKL, PID
30. Bipul Kumar Lal Das, SDE KUKL, PID
31. Surat Kumar Bam, PM KUKL, PID
32. Jhang Hong Kyu, TL DSC/PID/KUKL
33. Bishnu P. Joshi KUKL
19 July 2018 meeting at LMC hall
1. Chiri Babu Maharjan, Mayor LMC
2. Gita Satyal, Vice Mayor LMC
3. Hari Prashad Dahal, Chairman of Administrative
Office
LMC
4. Rudra Prashad Gautam, Chief of Infrastructure
Development Unit
LMC
5. Kumar Yadav, Engineer, Representative NEA
6. Pradip Adhakari, Engineer, Representative NEA
7. Surat Bahadur Malla, Office Chief, Representative NTC
8. Ram Sundar Dhakal, Representative NTC
9. Sumita Ghimire, Representative NTC
10. Rabindra Amatya, Representative KUKL
11. Rajendra Desar, Representative KUKL
12. Hiranya Prashad Parajuli, Under Secretary, Account LMC
13. Surat Bam, PM KUKL (PID)
14. Laxmi Pant, SDE KUKL (PID)
15. Rajesh Prasad Singh, WME KUKL (PID)
16. Dhurba Raj Regmi, FMC KUKL (PID)
17. Jhang Hong Kyu, TL DSC/PID/KUKL
18. Rikesh Chitrakar, Env. Specialist DSC04/PID/KUKL
19. Ramesh Deuba, Community Mobilizer CASSC/PID
20. Bharat Maharjan, Network Engineer DSC04/PID
Appendix 5 111
SN. Name of participants Organization
21.
18 November 2018 meeting at LMC Ward no 12 office
SN Name of Participants Organization
1 Narayan Lal Awale Ward Chairman ward no12 Ward no 12, LMC
2 Sarita Maharjan ,Ward female member ward no12 Ward no 12, LMC
3 Tirth Raj Bajracharya,Chairman Te tole committee Ward no 12, LMC
4 Hira Man Pradhan, Chairman Mangal tole committee Ward no 12, LMC
5 Gyan Lal Maarjan, Member Heugal tole committee Ward no 12, LMC
6 Hari Narshing Amatya,Treasurer Mangal tole committee Ward no 12, LMC
7 Sambhu Prashad Baral, Secretary Mangal tole committee Ward no 12, LMC
8 Ram lal Maharjan, Member Heugal tole committee Ward no 12, LMC
9 Asok Maharjan Businesman, Mangal Bazar committee Ward no 12, LMC
10 Sunil Maharjan Member Heugal tole committee Ward no 12, LMC
11 Surje Bausar Member Heugal tole committee Ward no 12, LMC
12 Santa Man Maharjan Heugal tole committee Ward no 12, LMC
13 Binod Shilpakar Member Lagan khel tole committee Ward no 12, LMC
14 Raju Kapali, Office Assistant Mangal tole committee Ward no 12, LMC
15 Suresh Maharjan, Vice chairman Mangal tole Committee Ward no 12, LMC
16 Dharma Raj Lama, Businessman, Prayg Pokhari tole Ward no 12, LMC
17 Laxman Awale, Businessman Prayg Pokhari tole Ward no 12, LMC
18 Sanu Awale, Ward member ward no12 Ward no 12, LMC
19 Kedar Bahadur Shrestha, Chairman Prayg Pokhari tole
20 Rajesh Shrestha,, MD Om Apartment
21 Jiwan Jimin Badiya ,Ward member ward no12 Ward no.12, LMC
22 Bikash Man Shrestha, Ward Chairman ward no 5 Ward no.5, LMC
23 Indra Bahadur Kunwar, Businessman Prayg Pokhari Kumaripati 19, LMC
24 Nisha Shrestha, Student Ward no 5, LMC
25 Punam Niroula, Ward member ward no 5 Ward no 5, LMC
26 Sudeep Aryal, Businessman ward no 5
27 Paru Aryal, Businessman ward no 5 Ward no 5 LMC
28 Sangita Maharjan Social Mobilizer Ward no 5 LMC
29 Brijendra Bikram Thapa Businessman ward no 5 Ward no 5 LMC
30 Ram Singh Basnet, Businessman ward no 5 Ward no 5 LMC
31 Kumar Shrestha
32 Binod Tamrakar, Ward Chairman ward no 19 Ward no.19, LMC
33 Shisir Gautam , SDE DSC-6/ KUKL/PID
34 Min Dahal FC CASSC KUKL/PID
10 February 2019 meeting at LMC Office Hall for IEE
Consultation
SN
Name of Participants
Organization
1 Chiri Babu Maharjan Mayor LMC
2 Geeta Satyal Deputy Mayor LMC
112 Appendix 5
3 Raju Maharjan Ward Chairman -9
4 Suprava Sakya Ward member 16 no ward
5 Pancha Bajra Bajracharya Ward member 16 no ward
6 Bu lal Maharjan Ward member
7 Nuchhche Ratna Khadgi Ward member 19
8 Dikshya Dhakal DSC-6/ PID
9 Raj Lal Thakur DSC-5/ PID
10 Hera Kaji Maharjan Nepal Telecom
11 Surat Malla Nepal Telecom Patan
12 Krishna Govinda Joshi Treasurer Tole committee
13 Bhagwan Maarjan Secretary Tole committee
14 Kaji Pyakurel Patan Durbar Square office
15 Sarika Gharana DSC-6/PID
16 Rajesh Pd .Singh PID
17 Bharat Maharjan Network Eng./DSC-6 /PID
18 Min Dahal FC/CASSC/PID
19 Shisir Gautam SDE /DSC-6/ PID
20 Rudra Pd Adhikari LMC
Appendix 6 113
Appendix 6: List of Major Festivals SN Name of festival Affected date Affected alignment/Chainage
1 Rato Macchindra Nath Jatra Baisakh (15-April-15 May)
Pulchowk-Gabahal-sundhara-lagankhel-Jawlakhel
2 Krishna Asthami Shrawan (15 July-15 August)
Inside Mangalbazar
3 Bhimshen Jatra Shrawan (15 July-15 August)
Mangalbazar-Sundhara-Okhu bahal- Tangal- Kumbeswori- Mangalbazar
4 Matiya Jatra Shrawan (15 July-15 August)
People visit whole Patan area for puja organized by gabahal (patan)
5 Gai Jatra Shrawan-Bhadra (15 July-30 August)
Throughout the alignment
6 Janaipurnima Shrawan-Bhadra Bhadra (15 July-30 August)
Patan Darbar Square -Baglamukhi