NDR10 COUNTRY REPORT Presented B y Andrew Ochan Geologist,
description
Transcript of NDR10 COUNTRY REPORT Presented B y Andrew Ochan Geologist,
NDR10 COUNTRY REPORTNDR10 COUNTRY REPORT
PresentedPresented
BByy
Andrew OchanAndrew Ochan
Geologist,Geologist,Petroleum Exploration and Production Dept,Petroleum Exploration and Production Dept,Ministry of Energy and Mineral DevelopmentMinistry of Energy and Mineral Development
UgandaUganda
Rio de Janeiro, BrazilRio de Janeiro, Brazil18th March, 2011
THE REPUBLIC OF U GANDA
THE REPUBLIC OF U GANDA
2NDR10 Country Report - Uganda
A. INTRODUCTION
• The Albertine Graben• Status of Licensing
B. THE NDR• Organization• Available Data and oil and gas resources• NDR Organisation• Objectives of the NDR• Legislation&Reporting Requirements• Ongoing Projects• Challenges• Achievements• Lessons Learned and Future Plans
PRESENTATION OUTLINE
THE REPUBLIC OF U GANDA
3NDR10 Country Report - Uganda
INTRODUCTION
THE ALBERTINE GRABEN
Abu Graben
Abu Graben
Afa
r Dep
ress
ion
Afa
r D
epre
ssio
n
Aswa Shear zone
Aswa Shear zone
Lake Malawi
Lake Tanganyika
Lake Albert
Alb
ertin
e G
rabe
n
Alb
ertin
e G
rabe
n
!.!.
!.!. !.!.
!.!.
!.!. !.
!.
!.!.!.!.
!.!.
!.
!.!.
!.
LIBYA
NIGERIA
TanzanianTanzanianCratonCraton
The area with the highest potential for petroleum production in Uganda is the Albertine Graben
The Graben forms the northern most part of the Western arm of the East African Rift System
It is a Tertiary rift, 500 km long, averaging 45 km wide and 23,000 sq km (Ugandan part)
THE REPUBLIC OF U GANDA
4NDR10 Country Report - Uganda44
STATUS OF LICENSING
Albertine Graben is currently sub- divided into 10 Exploration Areas (EAs)
5 active Production Sharing Agreements (PSAs)
Companies currently licensed are Tullow Oil, Neptune Petroleum and Dominion Petroleum
Tullow is finalising the process of farming down its interests to Total and CNOOC (33.33% each) taking into account Government participation
INTRODUCTION
THE REPUBLIC OF U GANDA
5NDR10 Country Report - Uganda
MINISTER
MINISTER OF STATE FOR ENERGY MINISTER OF STATE FOR MINERAL DEVELOPMENT
PERMANENT SECRETARY
KILEMBE MINESRURAL ELECTRIFICATION AGENCYUGANDA ELECTRICITY BOARD
UGANDA ELECTRICITY GENERATION Co. Ltd.UGANDA ELECTRICITY TRANSMISSION Co. LtdUGANDA ELECTRICITY DISTRIBUTION Co. Ltd
DIRECTORATE OF ENERGY AND MINERAL DEVELOPMENT (D/E&MD)
FINANCE & ADMINISTRATIONDEPARTMENT
SECTORAL PLANNING/POLICY ANALYSIS UNIT
RESOURCE CENTRE
ENERGY RESOURCES
DEPARTMENT (ERD)
PETROLEUM EXPLORATION
& PRODUCTION DEPARTMENT
GEOLOGICAL SURVEYS
AND MINES DEPT.
PETROLEUM SUPPLIES
DEPARTMENT
MEMD ORGANISATION
THE REPUBLIC OF U GANDA
6NDR10 Country Report - Uganda
PEPD IN BRIEF Petroleum Exploration and Production Department (PEPD) is a
department in the Ministry of Energy and Mineral Development in Uganda
Formed in September 1991 from a Petroleum Unit under Geological Survey and Mines Department (GSMD)
Petroleum (Exploration and Production) Act, Chapter 150, Laws of Uganda 2000, vest upon PEPD the mandate to monitor and regulate upstream activities undertaken by oil companies
In the exploration, development and production of oil and gas resources, oil companies can participate in Uganda by entering into agreement (PSA) with Government
ORGANISATION
THE REPUBLIC OF U GANDA
7NDR10 Country Report - Uganda
Promotion of petroleum exploration in the country
Monitor and regulate licensees undertaking petroleum exploration and
production in the country
Acquire, process and interpret geophysical, geological and geochemical
data with a view of assessing the country's petroleum potential
Initiate policy and legislation on petroleum exploration and development
Build national capacity in the field of petroleum exploration and
development
Implement the National Oil and Gas Policy (2008)
MAIN FUNCTIONS OF PEPD
ORGANISATION
THE REPUBLIC OF U GANDA
8NDR10 Country Report - Uganda
NEW INSTITUTIONS IN THE OFFING
Petroleum Authority of Uganda
- Regulatory Body
Directorate of Petroleum in the Ministry responsible for oil and Gas
- Policy and Licensing
- Petroleum Data Mgt
National Oil Company
- participate in petroleum operations
ORGANISATION
THE REPUBLIC OF U GANDA
9NDR10 Country Report - Uganda
AVAILABLE DATA
Data Type Coverage
Geological Surface Mapping
>10,000 sq km
Aeromag&Aerogravity 16,560 line km
Ground/lake gravity and magnetic
10,500 line km
Geological Surface Mapping data
>10,000 sq km
2-D Seismic ~6,000 line Km
3-D Seismic
Well data 51 wells
THE REPUBLIC OF U GANDA
10NDR10 Country Report - Uganda
PETROLEUM RESOURCE POTENTIAL
18 oil and/or gas discoveries made to date
5 discoveries (Mputa, Kasamene, Kingfisher, Waraga & Nzizi) at FDP stage
Discovered resources currently estimated at ~ 2.5 billion bbls of oil equiv in place
Type of crude is 30-34 API low sulphur, waxy crude, Pour point of ~40 degrees Celsius.Excellent reservoir qualities with 20-30% porositiesWell flow rates in the range of 1,000 – 14,000 bopd indicative of good permeabilities
THE REPUBLIC OF U GANDA
11NDR10 Country Report - Uganda
DATA MANAGEMENT ORGANIZATION AT PEPD
Honey Malinga
Geological Data (Andrew Ochan)
IT (Alex Nyombi)
Geophysical Data (Frank Mugisha)
Registry (Joyce Mba-bazi)
Wells
Geochem
GIS (Nurudin Njabire)
Robert Wandera Steven Enach William Kasasa Nathan Namukoye
David Mulinde Michael Weteka
Anthony Ayaa David Mulinde Yahya Muzaani Michael Weteeka Susan Byona
Abdala Higayi Grace Namukasa
Andrew Senabulya Peter Wathum Julius Bagole
Seismic
Potential Field
Steering Group (Data Custodians)
Support Group
NDR ORGANISATION
THE REPUBLIC OF U GANDA
12NDR10 Country Report - Uganda
Protection and preservation of the country’s E&P data for the benefits of future generations;
Encouragement of exploration activity by making high quality data available quickly to potential investors; and,
To strengthen information sharing and exchange of E&P data among the various stakeholders.
OBJECTIVES OF THE NDR
THE REPUBLIC OF U GANDA
13NDR10 Country Report - Uganda
Currently semi-permanent storage for: Seismic data tapes well data (reports, logs, CDs) Rock (cores, cuttings, fluids)
Future plan for storage in a modern data centre IT infrastructure includes various servers, LAN, Backup and
recovery mechanisms: Software: Desktop OS (windows), Geoscience and Mapping, MS
office
NDR INFRASTRUCTURE
THE REPUBLIC OF U GANDA
14NDR10 Country Report - Uganda
Petroleum Exploration and Production Act (1985)
Petroleum E&P Regulations (1993)
Production Sharing Contracts
LEGISLATION/REPORTING REQUIREMENTS
THE REPUBLIC OF U GANDA
15NDR10 Country Report - Uganda
Personnel 1 Geophysicist 4 Technicians
ONGOING PROJECTS
Hardware/Software
Tape Drives (IBM 3480E1A, 3490E, 3590E1A , STK 4280 Dual 3480 & Exabyte 8505) Tape CartridgesMAGMA Software
Field Tape Copying & Transcription
Commenced: Feb 2010
THE REPUBLIC OF U GANDA
16NDR10 Country Report - Uganda
Task Create run lists and copy raw seismic and support data from various
media (3480, 3490, LT02, etc) onto computer hard disk Carry out QC, reformatting and data header standardization measures to
ensure the data conform to accepted industry standard Security back-up onto external disks and servers Transcription of data onto PEPD acceptable media i.e 3590 which
guarantee reasonable level of data durability.
ONGOING PROJECTS
Output 96% of 3,114 tapes copied to disk, QC’ed and ready for transcription to
IBM 3590 cartridges
THE REPUBLIC OF U GANDA
17NDR10 Country Report - Uganda
ONGOING PROJECTS
Crane MS Access Dbase Development
Commenced: Feb 2010
Personnel: VariousStatus: 90% done, populating
THE REPUBLIC OF U GANDA
18NDR10 Country Report - Uganda
DM Structure is loosely defined
Lack of dedicated data management/IT personnel
Seismic data on various media with lack of reading capabilities
Lack of data submission guidelines
Storage facilities (buildings) and methods not conforming to industry
standards
Naming conventions! Funding
CHALLENGES
THE REPUBLIC OF U GANDA
19NDR10 Country Report - Uganda
Improved IT infrastructure
Seismic data transcription to common media
Data backup solutions in the offing
Institutional Framework in offing with data management functions to be
vested on the Petroleum Authority
New legislation being drafted to address data submission
ACHIEVEMENTS
THE REPUBLIC OF U GANDA
20NDR10 Country Report - Uganda
Even for small amounts of data, careful planning is key You need dedicated people on DM
Consideration to employ at least one dedicated IT Resource Development of data submission guidelines Complete tape transcription Current law being updated to clearly define DM roles Construction of a modern data centre Consideration to scan all hard copy data Complete Crane Dbase devt, make data avail on portal/web
LESSONS LEARNED AND FUTURE PLANS