ND Oil & Gas Research Program North Dakota Pipeline Authority
Justin J. Kringstad January 23, 2014 - Bismarck, ND
![Page 2: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/2.jpg)
ND Drilling Stats
2 JJ Kringstad - North Dakota Pipeline Authority
![Page 3: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/3.jpg)
US Williston Basin Oil Production - 2013
3
3 JJ Kringstad - North Dakota Pipeline Authority 3
![Page 4: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/4.jpg)
November 2013
Estimated Williston Basin Oil Transportation
4
4 JJ Kringstad - North Dakota Pipeline Authority 4
![Page 5: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/5.jpg)
Cushing $96.74
Brent $108.18 WTI + $11.44
Crude Oil Prices – Jan. 22, 2014
5 JJ Kringstad - North Dakota Pipeline Authority
![Page 6: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/6.jpg)
Estimated Williston Basin Oil Transportation
6
6 JJ Kringstad - North Dakota Pipeline Authority 6
![Page 7: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/7.jpg)
Estimated ND Rail Export Volumes
7 JJ Kringstad - North Dakota Pipeline Authority 7
![Page 8: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/8.jpg)
Williston Basin Oil Production & Export Capacity, BOPD
Production forecast is for visual demonstration purposes only and should not be considered accurate for any near or long term planning.
8 8 JJ Kringstad - North Dakota Pipeline Authority
![Page 9: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/9.jpg)
Sandpiper Pipeline Open Season
9
9 JJ Kringstad - North Dakota Pipeline Authority 9
North Dakota Pipeline Company LLC - formerly known as Enbridge Pipelines (North Dakota) LLC • Open Season Dates: November 26, 2013 – January 24, 2014 • 225,000 BOPD ND Capacity to Clearbrook, MN (24”) • 375,000 BOPD Clearbrook, MN to Superior, WI (30”) • In-service Date: Q1 2016 • Project cost: $2.6 Billion
Map: Enbridge
![Page 10: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/10.jpg)
Simple Terms Orange – Challenges on existing infrastructure Blue – Lack of pipelines
GREEN – % of gas captured and sold Orange – % flared from wells with at least one mcf sold. Blue – % flared from zero sales wells
November 2013 Data – Non-Confidential Wells Statewide
Solving the Flaring Challenge
10 JJ Kringstad - North Dakota Pipeline Authority
*
*Hess Tioga Gas Plant shut-in for 140 MMCFD expansion starting in November
![Page 11: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/11.jpg)
Capturing the 11% Faster Well Connections
11 11 JJ Kringstad - North Dakota Pipeline Authority
![Page 12: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/12.jpg)
12
ND Gas Gathering Statistics
12 JJ Kringstad - North Dakota Pipeline Authority
![Page 13: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/13.jpg)
13
ND Gas Plant Capacity
13 JJ Kringstad - North Dakota Pipeline Authority
![Page 14: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/14.jpg)
New NDPA Natural Gas Report
14 JJ Kringstad - North Dakota Pipeline Authority
![Page 15: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/15.jpg)
Faster Connections
Target New Wells
High Volume Areas
Conclusion 1: Getting the right wells connected quickly is moving in the right direction
15 JJ Kringstad - North Dakota Pipeline Authority
![Page 16: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/16.jpg)
Understanding Which Wells Are Flaring
16 JJ Kringstad - North Dakota Pipeline Authority
![Page 17: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/17.jpg)
Capturing the 11% Catching Early Production
17 17 JJ Kringstad - North Dakota Pipeline Authority
![Page 18: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/18.jpg)
Gas Plant Capacity
Looping & Compression
Maintenance & Pigging
Conclusion 2: Finding a way to quantify system enhancements would greatly assist in
understanding the timeline
18 JJ Kringstad - North Dakota Pipeline Authority
![Page 19: ND Oil & Gas Research Program · 2017-07-18 · ND Oil & Gas Research Program North Dakota Pipeline Authority Justin J. Kringstad January 23, 2014 - Bismarck, ND . ... New Wells High](https://reader033.fdocuments.us/reader033/viewer/2022042414/5f2f1110fa6c400a125d848a/html5/thumbnails/19.jpg)
Justin J. Kringstad, Director North Dakota Pipeline Authority
600 E. Boulevard Ave. Dept. 405 Bismarck, ND 58505-0840
Phone: (701)220-6227
Fax: (701)328-2820 E-mail: [email protected]
Websites:
www.pipeline.nd.gov www.northdakotapipelines.com
19 JJ Kringstad - North Dakota Pipeline Authority
Contact Information
19