NC AWWA-WEA 93rd Annual Conference
November 12, 2013
Tim WoodyResource Recovery Division Director, City of Raleigh
Jonathan TreadwayP.E, BCEE, CDM Smith
TAKE 2 – BIOSOLIDS STRATEGY MODIFICATIONS FOR THE CITY OF RALEIGH TO TAKE ADVANTAGE OF
TECHNOLOGY ADVANCEMENTS
1
NC AWWA-WEA 93rd Annual Conference
Presentation Outline
1. Project Background and Objectives2. Biosolids Management Alternatives3. Selected Project Direction4. Implementation Plan5. Conclusion
2TW
NC AWWA-WEA 93rd Annual Conference
City of Raleigh provides wastewater service to nearly 500,000 people
• Neuse River WWTP– 44 mgd average
• Smith Creek WWTP– 1.2 mgd
• Little Creek WWTP– 0.7 mgd average
3TW
NC AWWA-WEA 93rd Annual Conference
Goals for Master Plan Update
• Identify financially feasible management strategy• Demonstrate cost-effectiveness compared to the
“base case”• Update 2008 Biosolids Master Plan with new
technologies• Account for changing conditions• Advance the goals of the City’s EMS program for
biosolids
TW
NC AWWA-WEA 93rd Annual Conference
Changing Conditions Driving Update
TW
NC AWWA-WEA 93rd Annual Conference
Changing Conditions Driving Update
2008
2012
TW
NC AWWA-WEA 93rd Annual Conference
Overview of Management Strategies Considered
Alternative Management Strategy1 Base Case*
2 Anaerobic Digestion + Solar Drying3 Thermal Hydrolysis + Anaerobic
Digestion + Solar Drying
* Base case includes diversified outlets:• Alkaline stabilized Class A product (Raleigh-Plus)• Third party composting• Aerobically digested Class B product• Landfill
JT
NC AWWA-WEA 93rd Annual Conference
Management StrategiesAlt. 1 - Base Case (Aerobic Digestion)
7 DT/day
57 DT/day
JT
NC AWWA-WEA 93rd Annual Conference
Management StrategiesAlt. 2 - Anaerobic Digestion + Solar Drying
9
40 DT/day
New Facilities Include:• New GBT Building• Three An. Digesters (2.75 MG each)• Biogas Storage• Upgraded Dewatering• 16 Solar Dryers
JT
NC AWWA-WEA 93rd Annual Conference
Management StrategiesAlt. 3- Thermal Hydrolysis + Anaerobic Digestion + Solar Drying
10JT
New Facilities Include:• Pre-screening and Pre-dewatering• Thermal Hydrolysis Equipment• Two An. Digesters (1.6 MG each)• Upgraded Dewatering • Biogas Storage• 8 Solar Dryers
32 DT/day
NC AWWA-WEA 93rd Annual Conference11JT
NC AWWA-WEA 93rd Annual Conference
Comparison of Alternatives - 20 year net present worth
Alt. No.
Description Capital Cost($M)
O&M Cost($M)
Total Cost($M)
2008 An. Digestion + Thermal Drying $153.4 $43.6 $197.0
1 Base Case $ 28.3 $82.1 $110.4
2 An. Digestion + Solar Drying $ 97.5 $ 34.1 $131.6
3Thermal Hydrolysis + An. Digestion + Solar Drying
$ 81.2 $ 27.6 $ 108.8
JT
NC AWWA-WEA 93rd Annual Conference
Evaluation Criteria and Summary of Results
Alt. No.
Description Net Present Value of
Costs($M)
O&M Cost per Dry Ton
Non-Cost
Criteria
Greenhouse Gas Off-
Set (metric ton
CO2/yr)
1 Base Case $110.4 $237 58% 1,000
2 An. Digestion + Solar Drying $131.6 $144 83% 5,000
3 Thermal Hydrolysis + An. Digestion + Solar Drying $ 108.8 $140 82% 14,000
13
Non-cost factors include: 1) regulatory requirements, 2) public health and environmental impacts, 3) outlet diversification, 4) operator friendliness, 5) ease of maintenance, plus 6 others.
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsPre-Screening Platform
14
• Free-standing outdoor structure
• Two mechanical screens for co-settled sludge on top
• Screening drop to dumpster below
JT
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsPre-Dewatering Facility
15
• Pre-Dewatering (2-Story Bldg.) • Cake Bins Storage (Outdoors)
– Screened solids are pre-dewatered by centrifuges – Discharged to outdoor cake bins using screw conveyors
THP FEED PUMPS
TO THPCAKE BINS
CENTRIFUGES
JT
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsThermal Hydrolysis Process
PulperFlashTank
Reactors (3)Digester
Feed Pumps
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsAnaerobic Digesters
• Prestressed concrete tanks• 64-ft diameter• Cone bottom• Draft tube mixers mounted
to concrete cover• Digester gas flare• Adjacent digester building
for pumps, etc.• Outdoor heat exchangers for
cooling sludge from THP
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsFinal Dewatering Building
• Option A: Reuse Existing Facilities– Refurbish or replace 3 BFPs– Continue to operate centrifuge– Ventilation and other improvements to
mitigate corrosion problems– Can continue to use truck loading
station• Option B: New Final Dewatering
Building and Truck loading Station
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsSolar Dryers
19
• Eight modules, 42-ft x 435-ft• Fans, louvers, controls to optimize
temperature and humidity for drying
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsNutrient Recovery
• Optional addition for enhanced sustainability
• Reduce sidestream loading on liquid treatment process
• Recover phosphorous• Third-party responsible for
product marketing• Can be added at any time
Photo Courtesy of Ostara
JT
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsCombined Heat and Power (CHP) Engine Generator
21
– Single 1.75 MW generator – Containerized units available– Optional, but recommended for
sustainability when THP is implemented– Generate electricity and heat– Requires biogas conditioning system– Engine can be purchased, leased, or
procured via 3rd-party Energy Services Co. (ESCO)
Photos Courtesy of GE
JT
NC AWWA-WEA 93rd Annual Conference
Recommended ImprovementsImplementation Schedule
22
Phase Year Description Cost
Phase I 2016
Pre-screening, pre-dewatering, thermal hydrolysis, anaerobic digesters, CHP engine, additional cake storage
$59.3 M
Phase II 2021 Eight solar drying modules, BFP replacement and
final dewatering building improvements $26.2 M
Phase III 2028 Replace existing conveyance equipment and truck
loading station $4.3 M
TW
NC AWWA-WEA 93rd Annual Conference
Recommended Improvement Planvs. 2008 Master Plan
2016-2020 2021-2025 2026-2030$0
$20
$40
$60
$80
$100
$1202008 MP ($151 M) 2012 Update ($90 M)
(mill
ions
)
TW