NATIONAL TREASURYNEIGHBOURHOOD DEVELOPMENT PARTNERSHIP GRANT
OUR OBJECTIVES AND AGENDA FOR TODAY
• Strengthen strategic and practical alignment between City of Matlosana Municipality and NT: NDGP on the approach to pursuing more integrated, equitable spatial and economic development
• Focus on spatial urban form and spatial targeting using the Urban Networks Strategy
• Accelerating catalytic interventions in City of Matlosana Municipality
Objective
• Strategic partnership based alignment of City of Matlosana Municipality and NT and implementation of the Urban Networks Strategy
• This requires clarity on the next steps with:• Strategic spatial planning• Pipeline of catalytic interventions
Desired outcome
2
CONTEXT OF THE NEIGHBOURHOOD DEVELOPMENT PROGRAMME
• The NDP was established in 2006 and is responsible for managing the Neighbourhood Development Partnership Grant. Grant Purpose:
• From the start of the programme until the end of 2012/13 the NDP has:– Approved municipal business plans to a value of R4.0bn– Approved project plans to the value of R 3.9 bn. – Completed 129 municipal NDP projects – Disbursed a total of R615m to service providers and municipalities,
94% of its budget.
To support and facilitate the planning and development of neighbourhood development programmes and projects that provide catalytic infrastructure to leverage 3rd party public and private sector development towards improving the quality of life of residents in targeted underserved neighbourhoods (townships generally) Division of Revenue Bill, 2013 (Bill No. 02 of 2013)
NDPG FUNDED URBAN HUBS IN SA CITIES: BRIDGE CITY, ETHEKWINI
5
NDPG: LESSONS LEARNT IN TOWNSHIP REGENERATION
• Multiple spatially disparate “ad-hoc” township projects in the absence of an integrated and co-ordinated city-wide urban regeneration strategy has very low impact– All spheres of government need to be involved.
• Project prioritisation not to be informed by vested interests• Private fixed investment is dependant on the above• Limited municipal capacity to plan, assemble and align
multiple funding sources in single large-scale mixed use development
• Land issues dictate project progress and viability• Opportunities exist to develop and diversify township
economies by leveraging mixed-use transit orientated development
6
FOCUS IS ON CITIES AS THEY ARE THE CENTRES OF SOCIO-ECONOMIC ACTIVITY
A TARGETED INVESTMENT PROGRAMME IN SA’S 18 LARGER URBAN CENTRES
7
URBAN GROWTH MAY DEEPEN INEQUALITY AND EXCLUSION IN OUR CITIES
8
• Poverty and unemployment, especially among youth• Sprawling, monotonous, dormitory landscapes, with long
travel times for poor to access amenities, services & opportunities
• Compounded by climate change and weak governance, and may result in rising social conflict (service delivery protests)
• Accelerating economic growth required that we address:– future supply side bottlenecks from unavailability of public
infrastructure (new, expanded and rehabilitated assets)– continued low levels of private sector fixed investment in the built
environment
A MORE STRATEGIC APPROACH IS CRITICAL TO LEVERAGE REAL CHANGE
Available Public Resources
Need inmarginalised areas
DIFFERENTIALPrivate fixed investment
… and strategy requires:
• Consensus on concepts
• A programmatic approach
• Strong partnerships
GA
P
WHY FOCUS ON URBAN SPATIAL FORM?
• Severe inequality is clearly represented in the spatial form of all our cities– Exclusionary (spatial patterns of access to services and opportunity)– Inefficient (growing fiscal and economic costs in supporting the current
spatial form and design)– Unsustainable (severe environmental and social risks)
• Public policy unwittingly reinforced these divides, and set them in concrete– A lack of adequate forward planning to deal with continuing pulling
power of cities & environmental factors affecting cities– A renewed focus on the quality of urban and economic growth is
required
10
THE NATIONAL DEVELOPMENT PLAN URGES COORDINATED ACTION
– Tackle spatial development patterns directly– Combine the use of multiple instruments:
• Strengthen strategic spatial planning• Coordinate the use of Planning, regulatory and investment tools
and strategies• Leverage public transport, infrastructure, land and housing
investments• Use a spatial focus to target more public resources
11
“The Commission provides a proposed schema for spatial targeting that indicates where investment should be focused, and we identify elements of the existing broad consensus for transforming towns and cities”
National Development Plan, 2012
THE URBAN NETWORKS STRATEGY
An integrated hierarchy of land use clustering & connectivity
THE NEW APPROACH WILL ENABLE GROWTH & DEVELOPMENT
• Transit-orientated• Partnership-based • Targeted (precinct) investment • Aimed at strategic spatial transformation • Optimise access to social & economic opportunities,
especially for the poor • Minimise transaction costs to participate in the urban
economy• Replicable model
13
I. Primary Network
II. Secondary Network
14
THE TWO SPATIAL PRINCIPLES UNDERPIN THE URBAN NETWORKS STRATEGY
The primary network is at city-wide scale and consists of anchor nodes, i.e. the CBD and a number of Urban Hubs, as well as Activity Corridors between these anchor nodes .
Secondary Nodes are smaller nodes within township areas connected to the Urban Hub and serving as “neighbourhood” or lower order nodes.
. . . IDENTIFY & STRENGTHEN HUBS . . .
15
URBAN NETWORKS STRATEGY
16
. . . CONNECT . . . PRIMARY NETWORK
. . . CONNECT . . . SECONDARY NETWORK
17
• Strong urban network with a hierarchy of well connected nodes
• Efficient flows of people, goods & information
• Targeted public infrastructure that catalyses ubiquitous distribution of public & private sector investment
• Good access to jobs & amenities
The urban networks strategy is aimed at integrated growth & development
19
INVESTMENT CASE STUDY: MAMELODI
Numerous ad-hoc non integrated or aligned projects. Little co-ordination of public funds
20
INVESTMENT CASE STUDY: MAMELODI
R138m
Urban Hub and secondary nodes, spatial logic, spatial targeting results in integrated or aligned projects. Better leverage through the
co-ordination of Public funds
21
Urban Network
Network Elements Intervention Investment Phasing
Primary Network
CBD Regeneration and management
• Spatial Development Objectives
• Network Connectivity Optimisation
Urban HubsMixed-use development and management
Primary Transport Link
Develop/Upgrade and management
Activity Corridor
Infill & Densification
Secondary Network
Secondary Transport Link
Develop/Upgrade
IDENTIFICATION & PLANNING WILL UNLOCK A PIPELINE OF PRIORITISED CATALYTIC PROJECTS…
… THAT ARE CRITICAL TO THE STRENGTHENING OF THE PRIMARY NETWORK
CBD
• CBD
• Urban Hubs
• Primary Public Transport Links
• Activity Corridors
& Secondary Transport Links
Network Topology:
FROM STRATEGY TO ACTION …
23
Strategic spatial planning• Urban network
identification & planning
Intervention planning• Precinct planning• Identification of
catalytic projects
Project Planning• Detailed design• Pipeline• Implementation
management
Life-cycle Management• Performance
monitoring and evaluation
• Precinct management• Investment facilitation
24
NDPG FUNDED URBAN HUBS IN SA CITIES: MITCHELLS PLAIN
VIBRANT URBAN HUBS ARE KEY ENTRY POINTS• High density, mixed use precinct that contains a diverse variety of land
uses, services and activities• Function:
– “Town centre” for township/s– Gateway to the rest of the wider urban area
• Efficient multi-modal public transport system & a precinct network of public spaces and walkways
• Leveraging of investment:– Retail– Recreation, hospitality & tourism– Offices, banking– Community facilities & govt services– Higher density housing
• Within an urban design framework that promotes a vibrant sense of place in which to live, work and play
25
26
Diversity
Inve
stm
ent
• No & Type of tenants (Traders, SME’s, National Chains) • Land Use Mix• Private/Public Split
INDIVIDUAL URBAN HUB STRATEGY TO BE DETERMINED VIA INVESTMENT INDEX
High
Low High
3. On a road to nowhere
CBD & HUBS REQUIRE A CLEAR PRECINCT MANAGEMENT STRATEGY TO ENSURE FULL LIFE CYCLE OPTIMISATION
27
Objective: An inclusive, vibrant, safe, investment friendly hub
• Economic Development• Place marketing• Lifestyle event management • Risk management• Safetyo Security presenceo Active edges rather than dead zones - e.g. walls
& vacant stands• Clean and well maintained precinct public spaces
27
CommunityMunicipality
Public Sector InvestorsPrivate Sector Investors Developers
TradersTenants
Property Owners
Precinct Management
… AND AN URBAN DESIGN TOOLKIT WILL ASSIST CITIES TO OPTIMISE VIBRANCY & INVESTMENT
28
• Identification of spatial structuring elements:– Rail & road infrastructure– Modal facilities– Pedestrian network– Public spaces
• Planning & design principles for:– Optimal clustering– Making of a qualitative public realm– Investment phasing towards private sector leveraging
29
CONVERGENCE OF PEOPLE IN HUBS TO ATTRACT PRIVATE SECTOR INVESTMENT
MIG
PTIS
NDPG
UDZ
SHRZCBD
Developed Area
Underserved Townships
Underserved Townships
Underserved Townships
THE PIPELINE IS AIMED TOWARDS AN INTEGRATED FISCAL PACKAGE
TIME-FRAMES: PLANNING
ENGAGE COMPILE WORK PLAN
PREPARE URBAN
NETWORK PLAN
PREPARE PRECINCT
PLANEngage 1 Engage 2
Compile Municipal Work
Plan
Procure Service Provider
Compile Service Provider
Work Plan
In-progress Date? Date Date Date Date Date
COUNCIL RESOLUTION
URBAN NETWORK ELEMENTSIDENTIFIED
MEMORANDUM OF AGREEMENT
MUNICIPAL WORK PLAN
4 WEEKS
4 MONTHS
2 WEEKS
3 MONTHS
6 MONTHS
3 WEEKS
KEY ACTIONS AND TIMELINES
Stage I: (DATE)
• Engagement Two (Technical Meeting)
Stage II: (DATE)
• Council resolution approving participation in the NDPG• Institutional / Governance arrangements• Confirmed NDPG conditions (Memorandum of Agreement)• Urban Network Identification• Service Provider procurement & capacity support requirements
Stage III: (DATE)
• Urban Network Plan completed
Stage IV: (DATE)
• Precinct Plan completed• Catalytic NDPG projects identified with timeframes
32
Way forward