National Transmission And Dispatch Company (NTDC)
-
Upload
aneel-k-suthar -
Category
Engineering
-
view
240 -
download
3
Transcript of National Transmission And Dispatch Company (NTDC)
NATIONAL TRANSMISSION & DESPATCH COMPANY
MUMMAD DAUD
GENERAL MANAGER PLANNING
NTDC
NTDC’s PRESENT SYSTEM, FUTURE PLANS, BOTTLENECKS & KPIs
PRESENTATION BY
SEQUENCE OF PRSENTATION
1. General- WAPDA/PEPCO- Structure & Roles
2. NTDC system capacity
3. Future challenges & Target
4. NTDC expansion plan
5. Bottle necks
6. Key performance indicators
3
Pakistan Water and Power Development Authority (WAPDA)
WAPDA was formed in 1958. The major responsibilities of WAPDA were; – Meet electricity demand of the country (except area of Karachi) by
installing new power plants, transmission lines and distribution system.
– Develop hydro storage project ( dams) for meeting irrigation and demand of the country and install hydro plants at dams locations.
WAPDA consisted of two segments : Power Wing: For meeting electricity demand and responsible for generation, transmission and distribution. Water Wing : For developing hydro projects for irrigation requirements.
5
6
PAKISTAN POWER SECTOR: BACKGROUND
1. The GoP approved Pakistan Power Sector Strategic Plan for
restructuring and reform in 1992, according to which, the power wing of
WAPDA was structured into four (4) Generation Companies (GENCOs),
one (1) National Transmission and Dispatch Company (NTDC) and nine
(9) Distribution Companies (DISCOs).
2. PEPCO was established in 1998 as an independent entity with mandate
to restructure Pakistan Power Sector, corporatise & commercialize the
restructured entities, and to bring about reforms thru introduction of
competition, enhancement of efficiencies and best financial and prudent
utility practices.
3. PEPCO initiated the restructuring and reform process in 1998 with
limited initial success. The reform process was considerably slowed
down beyond 2001 when PEPCO was reduced to a Division in WAPDA.
4. The GoP reactivated the mandate of PEPCO in October 2007 to bridge
the increasing demand supply gap and to reduce the resulting load
shedding in the country. 6
Chairman WAPDAChairman WAPDA MD PEPCOMD PEPCO
PEPCO Management Team
PEPCO Management Team
WATER WING
WATER WING
FINANCEWING
FINANCEWING
POWERWING
POWERWING
COMMONSERVICESCOMMONSERVICES
RESIDUAL WAPDA WINGS PART
TRANSITION TO CORPORATE
ENTITIES
WATER WATER HYDELFINANCEHYDEL
FINANCEHYDELPOWERHYDELPOWER SERVICESSERVICES
RESTRUCTURED POWER WING
RESTRUCTURED POWER WING
GENCOsGENCOs NTDCNTDC DISCOsDISCOs
(4) (1) (9)
• HOSPITALS• ACADEMY• ETC
AUTONOMOUS COMPANIES WITH INDEPENDENT COMMERCIAL OPERATIONS THROUGH BOD
MEMBERS: Hydel power, Finance, Water
MEMBERS: Hydel power, Finance, Water
GOP/MW&PGOP/MW&P Chairman PEPCOChairman PEPCO
NEW FACE OF PAKISTAN’S POWER SECTORNEW FACE OF PAKISTAN’S POWER SECTOR
7
National Transmission and Dispatch Company Ltd.
National Transmission & Despatch Company (NTDC) Limited was incorporated on 6th November, 1998 and commenced commercial operation on 24th December, 1998. It was organized to take over all the properties, rights and assets, obligations and liabilities of 220 KV and 500KV Grid Stations and Transmission Lines/Network owned by Pakistan Water and Power Development Authority (WAPDA). .
8
NTDC Structure
NTDC segments.
1. Transmission Network Operator (TNO)2. System Operator (SO) 3. Central Power Purchasing Agency (CPPA)4. Contract Registrar and Power Exchange
Administrator (CRPEA)
9
Length of Transmission LinesYear 500kV (circuit kM) 220kV (circuit kM)
1980 315 2101
1985 1239 2422
1990 1863 2922
1995 3315 3848
2000 4094 5498
2005 4344 6993
2010 5078 7366
11
No MVA No1980 0 0 51985 2 1350 101990 6 4974 141995 7 6774 182000 9 8274 242005 9 8274 262010 12 14850 26*
No. & Capacity of Substations (NTDC)
*1 No. 220 KV gird station was added & 1No. 220 KV Grid station was converted to 500 KV
13
500- KV Substations 220- KV Substations
Year T&T Losses (%) Remarks
2005 7.63 Includes losses of 132 kV Sys
2006 7.26 Includes losses of 132 kV Sys
2007 3.80 500 & 220 kV only
2008 3.48 500 & 220 kV only
2009 3.58 500 & 220 kV only
2010 3.12 500 & 220 kV only
15
NTDC T&T LOSSES
Future Required Generation Capacity
Year Peak Demand (MW)
Gen Capacity Required (MW)
Gen Capacity Planned (MW)
2010 20101 25126 21388
2011 21705 27131 22697
2012 23441 29301 23788
2013 25306 31633 26279
2014 27438 34298 29405
2015 29463 36829 33630
2016 31672 39950 42530
2017 33154 41443 45338
2018 35568 44460 50034
2019 38557 48196 53284
2020 41783 52229 57470
18
PEPCO System Historical Data / ForecastHistorical PMS
Peak Peak Difference
Years ( MW ) (MW) (%)
1999-00 9289 9311 0.24
2000-01 9718 9736 0.18
2001-02 10922 10243 -6.21
2002-03 10484 10799 3.00
2003-04 11078 11398 2.80
2004-05 12035 12087 0.43
2005-06 13212 12916 -2.20
2006-07 15138 15213 0.50
2007-08 16838 16480 -2.10
2008-09 17252 17867 3.50
2009-10 17847 19451 8.9019
EXISTING GENERATING CAPACITY (Oct, 2010)
* Hydro availability based on last 5 years average ** Excludes 10% Forced Outages for GENCOs & 6.0% for IPPs & Rental
Type of Generation
Nameplate/Installed Capacity
(MW)
Derated/Dependable
Capacity (MW)
Availability (MW)
Summer Winter
WAPDA Hydro 6444 6444 6250 2300*
GENCOs 4829 3580 2780 3222**
IPPs (incl Nuclear) 7911 7695 5750 6900**
Rental 62 60 60 60**
Total 19246 17779 14840 12482
20
NTDC ONGOING DEVELOPMENT PROJECT
SR.NO.
NAME OF SUBSTATIONSTRANSFORMER CAPACITY (MVA)
ASSOCIATED TRANSMISSION LINES
EXPECTED COMMISSIONING
1 Ext. at 500 kV Sheikh Muhammadi
1x450 - Dec, 2010
2Ext. at 500 kV Tarbela. 1x237 - Dec, 2010
3 Ext. at 220 kV Bannu1x160 -
June, 2011
4 Augmentation of 220 kV at N.K.L.P Lahore
3x250 - T2 & T3 CommissionedT1: Dec. 2011
5 Upgradation of existing 132 kV to new 220 kV GIS Wapda Town Lahore.
3x160 220 kV Lahore - K.L.P D/C In/Out at Wapda Town. (10+10 km)
G/station commissioned T/Line by Mar.
2011
6 New 220 kV GIS Bandala
2x160 220 kV Gatti - K.S.K D/C In/Out at Bandala. (5+5 km) Dec, 2011
7 Installation of SVCs at 220 kV N.K.L.P. Lahore.
SVCs Static Var Compensators of appropriate capacity. Dec, 2011
SR.NO.NAME OF
SUBSTATIONSTRANSFORMER CAPACITY (MVA)
ASSOCIATED TRANSMISSION LINES
EXPECTED COMMISSIONING
8 Looping In/Out of 220 kV G/Barotha-S/Bagh T/L at Mardan -
Looping in & out of one circuit of Ghazi Barotha – Shahi Bagh at Mardan (30 km)
Mar, 2011
9 Extension/Augmentation at existing substations:
- Dec, 2011
500 kV Dadu 1x450
1x160
220 kV Burhan 1x160
220 kV Mardan 1x250
500 kV Sheikh Muhammadi 1x160
500 kV New Rewat 1x250
220 kV Shikarpur1x160 Commissioned
10 220 kV Okara3x250
220 kV Yousafwala - Sarfaraz Nagar D/C In/Out at Okara. (5 + 5km)
Dec, 2011
11 220 kV Toba Tek Singh/Gojra
3x250 220 kV Faisalabad-Multan D/C In&Out at T.T.Singh/Gojra. (1+1 km)
Dec, 2011
NTDC ONGOING DEVELOPMENT PROJECTS
SR.NO.
NAME OF NEW SUBSTATIONS
TRANSFORMER CAPACITY
(MVA)
ASSOCIATED TRANSMISSION LINES
EXPECTED COMMISSIONING
12 Installation of SVC at Quetta
SVC Static Var Compensators of appropriate capacity Jun, 2012
13 Ext. at Ghazi Brotha for addition of 600 MVA 500/220 kV T/F.
1x600 -
Jun, 2011
14 220 kV Loralai 2x250 220 kV D.G Khan – Loralai (250 km) Dec, 2012
15 Augmentation of 220 kV Ravi at Lahore.
3x250March, 2011
16 500kV D.G Khan Substation.
2x6002x250
500kV Guddu-Multan 2nd cct In/Out at D.G. Khan substation(20+20) km Dec, 2012
NTDC ONGOING DEVELOPMENT PROJECTS
SR.NO.
NAME OF NEW SUBSTATIONS
TRANSFORMER CAPACITY
(MVA)
ASSOCIATED TRANSMISSION LINES
EXPECTED COMMISSIONING
17 220 kV Rohri New for interconnection of IPPs at Engro Energy PP and Mari (Dharki) CCPP
2x250 220 kV D/C T/L Dharki CCPP– Rohri New (115 km)
Dec, 2011
132 kV D/C T/L for In/Out of Rohri-Khairpur/Gambat D/C T/L at Rohri New (1+1 km)
220kV D/C Rohri New-Shikarpur T/L (50 km)
220 kV D/C T/L for In/Out of Dharki -Rohri New at Engro CCPP (5+5 km)
132 kV Rohri New-Gambat D/C T/L (53 km)
18 220 kV Gridstation at Khuzdar,
2x160220kV D/C Dadu – Khuzdar Transmission Line (300 km) Dec, 2011
19 220 kV Grid Station at Ghazi Road, Lahore
3x160 220 kV D/C T/L for In&Out of NKLP – Sarfraz Nagar at Ghazi Road. (30 km)
Dec, 2012
220 kV D/C T/L for In&Out of Ravi– KSK at Ghazi Rd. (30 km)
NTDC ONGOING DEVELOPMENT PROJECTS
SR.NO.
NAME OF NEW SUBSTATIONS
T/F CAPACITY
(MVA)
ASSOCIATED TRANSMISSION LINES
EXPECTED COMMISSIONING
20 220 kV Grid Station at Kassowal along with associated 220kV D/C T/Lines.
2x160 220 kV D/C Transmission Line for In&Out of Vehari – Yousafwala at Kassowal. (45+45 km) Jan, 2012
21 220 kV GIS substation at Gwadar
2x160 220 kV D/C T/L from Pak-Iran border to Gwadar (100 km) Jun, 2012
22 500 kV R.Y.Khan 2x600 500 kV Guddu - Multan 3rd Circuit In/Out at R.Y.K (30+30 km) Jun. 2012
23220 kV GIS Shalamar (Mehmood Buti)
3x250220 kV Ravi-KSK D/C In/Out at Shalamar (9km long overhead T/L) & (3+3km) cable Jun.2012
NTDC ONGOING DEVELOPMENT PROJECTS
S.#Name of Project
Transfor-mer
Capacity(MVA)
ASSOCIATED TRANSMISSION
LINES
Estimated Cost
(Rs. in Million)
Eqt. US$ in Million
Approval by
ECNECFinancing
Expected commissi-
oning
1220 kV Gujrat
3x250220 kV Mangla-Ghakkar D/C In/Out at Gujrat (2+2 km)
2805 33 22.10.2007 JICA 2011-12
2220 kV Chishtian
2x250220 kV Vehari - Chishtian D/C T/Line. ( 65 km)
3740 44 22.10.2007 JICA2011-12
3 500 kV New Lahore
2x750 Two 500 kV S/C T/Lines for In/out of 500 kV Sahiwal – Lahore S/C at Lahore New (15+15 km)
12665 149 PC-I cleared by CDWP on 18.03.2010
JICA 2012-13
Two 500 kV S/C T/Lines for In/out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km)
220 kV D/C T/Line for In/out of 220 kV NKLP-Ghazi Road at Lahore New. (50 km)
220 kV D/C T/Line for In/out of 220 kV NKLP-Wapda Town at Lahore New. (54km)
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.# Name of Project
Transfor-mer
Capacity(MVA)
ASSOCIATED TRANSMISSION
LINES
Estimated Cost
(Rs. in Million)
Eqt. US$ in
Million
Approval by ECNEC
Financing
Expected Year of
commissi-oning
4- 500 kV Shikarpur
2x600
Two 500 kV S/C T/Lines for In/out of 500 kV Dadu-Guddu circuit No:1 at Shikarpur (20+20 km)
8160 96
Pc-I Cleared
by CDWP on
18.03.2010
JICA 2012-13Two 500 kV S/C T/Lines for In/out of 500 kV Dadu-Guddu circuit No:2 at Shikarpur. (22+22 km)
220 kV D/C for In/Out of 500/220 kV Guddu – Sibbi S/C at Shikarpur (50 km)
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#Name of Project
Transfor-mer
Capacity(MVA)
ASSOCIATED TRANSMISSION
LINES
Estimated Cost (Rs. in Million)
Eqt. US$ in
Million
Approval by ECNEC Financing
Expected Year of
commissi-oning
5-
2nd source of supply to Islamabad University
-
220 kV D/C T/L for In/out of Manshera-Islamabad T/L (40 km)
1105 13PC-I under preparatio
nADB Tr-IV 2012-13
6-
2nd Source of supply to Hala Road Grid Station
-
220 kV D/C T/L from T.M Khan Road to Hala Road (30 km)
850 10PC-I under preparatio
nADB Tr-iV 2012-13
7-220 kV Nowshera 2x160 - 850 10 06.02.2008 ADB Tr-iV 2012-13
8- 220 kV Chakdara
2X250220 kV Chakdara – Mardan (85 km)
3230 38PC-I under preparatio
nADB Tr-iIV 2013-14
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.# Name of Project
Transfor-mer
Capacity(MVA)
ASSOCIATED TRANSMISSI
ON LINES
Estimated Cost (Rs. in Million)
Eqt. US$ in
Million
Approval by ECNEC
Financing
Expected Year of
commissi-oning
9-
Augmentation of 500 & 220 kV existing substations
-
3825 45
PC-I submitted to GoP in Aug,2010
ADB Tr-I (Ext-II) 2011-12
500 kV Rewat 1x750 -
500 kV Sh. Muhammadi
4x250 -
220 kV Mardan 2x250 -
220 kV Burhan 4x250 -
220 kV Bund Rd
4x250 -
220 kV Bahawalpur 2x250 -
220 kV Quetta Industrial
2X250 -
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#`
Name of Project
Transfor-mer
Capacity(MVA)
ASSOCIATED TRANSMISSION
LINES
Estimated Cost (Rs.
in Million)
Eqt. US$ in Million
Approval by ECNEC
Financing
Expected Year of
commissi-oning
10- 220 kV Mirpur Khas 2x160
220 kV D/C T/L from Hala Rd. to .M.Khan Rd. (10 km)In/Out of one circuit of above 220 kV proposed T/L at Mirpur Khas New (70 km).
2975 35 PC-I under preparation ADB Tr-IV 2013-14
11- 220 kV Taxila. 2x250In/Out of 220 kV Burhan - ISPR S/C at Taxila. (6 km)
2295 27 PC-I under preparation ADB Tr-IV 2013-14
12- 220 kV Manshera 2x160
In/out of 220 kV Alai Khawar-Sangjani T/L at Manshera (0.5+.0.5 km)
1105 13 PC-I under preparation
Iranian Loan 2013-14
13- 220 kV D.M Jamali
1x1601x100
in/out of 220 kV Uch-Guddu S/C at D.M. Jamali (5 km)
850 10PC-I
submitted to GoP
PM’s Fund 2013-14
14-
Interconnection of 1200 MW AES Imported coal based Power Plant near Karachi (Part-I)
-
500 kV Jamshoro--R.Y.K (535 km)500 kV Moro-Dadu (55 km)
25330 298
PC-I cleared by CDWP
on 18.03.2010
ADB Tr-III 2015-16
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST* (Rs.in
Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
1- 220 kV Chakwal2x160
In/out of 220 kV Mangla-Rewat S/C at Chakwal (50 km)
2890 34 2012-13
2- 220 kV GIS Jhang Rd. Faisalabad 2x250
220 kV Samundri Rd. – Jhang Rd. D/C T/L (40 km) 2975 35 2012-13
3- 220 kV Chiniot. Industrial 2x250
220 kV Gatti - Ludewala D/C In/Out at Chiniot Industrial. (2+2 km)
2380 28 2012-13
4- 220 kV Shadman
2x250
220 kV D/C cable from Shadman to Bund Road (30 km)
4250 50 2012-13
5- 220 kV D.I Khan 2x250 220 kV D/C T/Line for In/out of 220 kV Chashma Nuclear – Ludewala S/C at D.I Khan (100 km)
3825 45
2012-13
7- 220 kV Gharo2x250
220 kV Gharo – T.M Khan Road ((130) 4590 54 2012-13
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRD YEAR OF
COMMISSIO-NING
8- 220 kV Jhimpir2x250
In/Out of 220 kV Gharo – T.M Khan Road at Jhimpir (65 km)
3230 38 2012-13
9- 220 kV Mastung 2x250
220 KV Mastung Sibbi (120 km) 4080 48 2013-14
10- 220 kV Jamrud`2x250
220 kV Jamrud – Sh. Muhammadi (10 km) 1445 17 2013-14
11- 500 kV Faisalabad New 2x750
In/out of 500 kV Muzaffargarh – Gatti 1st circuit at at Faisalabad new (1+1 km) 6630 78 2013-14
2x250220 kV Faisalabad New – T.T Singh D/C T/Line (70 km)
12- 220 kV M-3 Industrial Estate Faisalabad 2x250
220 kV M3 Industrial Estate – Faisalabad New (70 km)
In/Out of 220 kV Faisalabad New - M3 Industrial Estate at 220 kV Chinot Industrial New (30 km)
3570 42 2013-14
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
13- 500 kV Peshawar New
2x750
In/out of Tarbela – Sh. Muhammadi at Peshawar New (2+2 km)
In/Out of 220 kV Sh. Muhammadi-Shahibagh at Peshawar New (5 km)
5440 64 2014-15
14- 220 kV Kohat
2x250
220 kV Kohat – Peshawar New (50 km)
220 kV Kohat – Bannu (150 km)
5950 70 2014-15
15- 220 kV Islamabad I-10 2x250
In/Out of 220 kV Rewat – Islamabad University D/C at Islamabad I-10 (30+30 km)
2635 31 2014-15
16- Ext. at 220 kV Gujrat 1x250
-425 5 2014-15
17- 220 kV Kamalabad 2x250
In/out of Rewat – Islamabad Peshawar Rd. at Kamalabad (5+5 km)
1445 17 2015-16
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
18- Ext. at 500 kV Gujranwala 1x600
-1700 20 2015-16
19- Ext. at 500 kV Lahore New 1x750
-2040 24 2015-16
20- 220 kV Kamra2x250
In/out of 220 kV Tarbela – Taxila at Kamra (5 km) 1275 15 2015-16
21- 220 kV Iqbal Town 2x250
In/Out of 220 kV Lahore – Wapda Town D/C at Iqbal Town (20+20 km)
2125 25 2015-16
22- 220 kV Gujranwala
New2x250
In/Out of 220 kV Mangala – K.S.K at Gujranwala New (20 km)
220 kV Nokhar - Gujranwala New (50 kM)
2890 34 2015-16
23- 220 kV Pindi Bhattian 2x250
220 kV Pindi Bhattian Ind. – Gujranwala (50 km) 2380 28 2015-16
24- 220 kV Head Faqirian 2x250
220 kV Head Faqirian – Ludewala (60 km) 2380
282015-16
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
25- 220 kV Joharabad 2x250
In/out of 220 kV D/C Ludewala –Chashma at Jauharabad (5+6 km)
1445 17 2015-16
26- 220 kV Alizai2x250
220 kV Kohat – Ali zai D/C (110 km) 3825 45 2015-16
27- 2nd Source of supply to 220 kV Chakwal substation
-
In/out of 220 kV Mangla -Rewat 2nd circuit at Chakwal (60 km) 1530 18 2015-16
28- 2nd Source of supply to 220 kV Bhawalpur
substation
-
220 kV R.Y.K – Bahalawlpur D/C T/L (150 km)
3825 45 2015-16
29- 220 kV Arif Wala 2x250
In/Out of 220 kV Yousafwala – Kassowal D/C at Arifwala (5+5 km)
1445 17 2015-16
Total: 82620 972
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIREDYEAR OF
COMMISSIO-NING
1-Power Dispersal from 747 MW CCPP at Guddu
-
500 kV Guddu New PP – M. Garh (256 km)
In/Out of Guddu – Multan at New Guddu (10+10 km)
7735 91 2012-13
2- Dispersal of Power from Uch-2
- 220 kV Uch-II – Sibbi D/C (125 km)
2975 35 2012-13
3-
UAE Combined Cycle power plant at GTPS Faisalabad
1x160In/out of existing 220 kV T/lines at Proposed power plant
1700 20 2012-13
4-
Interconnection of 1200 MW AES Imported coal based power near Karachi (Part-II)
500 kV switch
ing station at
Matiari
500 kV S/C T/Line from AES Power Plant to Matiari switching station (200 km)
In/Out of 500 kV Hub-Jamshoro S/C T/Line at AES (45+45 km)
In/out of 500 kV Jamshoro-R.Y.K at Matiari (5+5 km)
14450(PC-I
cleared by CDWP on 18.3.10)
170 2015-16
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in
Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
5-
Interconnection of 1200 MW Engro & 1200 MW PEPCO’s Thar Coal Based Power Plants at Thar
-
500 kV D/C T/L form Thar coal power plants to Matiari (275 km)
500 kV HVDC Matiari –Lahore/ Faisalabad T/L (1100 km)
Terminal Stations at both ends
88400 1040 2015-16
6
Interconnection of 1200 MW Imported coal based PPIB and 1000 MW Imported Coal based PEPCO’s power Plants at Karachi
-
Two 500 kV circuits from Power Plants to Matiari (200 km each)
500 kV HVDC Matiari –Lahore/Faisalabad T/L (1100 km)
Extension of Terminal Stations at both ends
85000 1000 2015-16
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
7-Import of 1000 MW Power from Iran -
Two 500 kV HVAC S/C T/Lines from Zahidan to Quetta with series compensation (198 km)
Switching station at Zahidan, Quetta and midpoint between Zahidan & Quetta
40120 472 2015-16
8-
Import of 1000 MW Power from Tajikistan (CASA-1000)
-
500 kV HVDC T/L from Pak-Afghan Border to Peshawar (71 km)
500 kV Converter Station Peshawar
16065 189 2015-16
9-Dispersal of Power from 340 MW Chashma-III
-
220 kV Chashma New – Bannu (125 km)
In/out of 220 kV D.I. Kahan – Jahurabad S/C at Chashma New (1 km)
3000 35 2016-17
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION LINES
ESTIMATED COST (Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
10-
Interconnection of 2x1000 MW Nuclear Power Plants at Karachi
-Three 500 kV Circuits from Nuclear Plants to Matiari (200 km each)
25500 300 2018-19
Total 284945 3352
POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION
LINES
ESTIMATED COST
(Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
1-
Dispersal of Power from 969 MW Neelum Jhelum Hydro Power Project to Rawat & Gujranwala
-
500 kV Neelum Jhelum – Rawat S/C T/Line (110 km).
500 kV Neelum Jhelum – Gujranwala S/C T/Line (235 km)
19125 225 2015-16
2-Dispersal of Power from 720 MW Karot HPP
-
500 kV Karot – Lahore New (270 km)
In/Out of 500 kV Neelum Jhelum – Gujranwala at Karot (10 km)
13250 156 2015-16
3-Power Dispersal of 740 MW Munda HPP
-
In/Out of 220 kV Peshawar – Shahi Bagh at Munda (35 km)
850 10 2016-17
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION
LINES
ESTIMATED COST
(Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
4-
Dispersal of Power from 1100 MW Kohala Hydro Power Project to Gujranwala
Three 500 kV line bays at Kohala
One 500 kV line bay at Gujranwala
500 kV 225 km long Kohala – Gujranwala S/C T/L
Two 500 kV T/Lines 15 km each for in/out of 500 kV Neelum Jhelum – Gujranwala at Kohala
11000
129 2017-18
5-
Dispersal of Power from Karot HPP (Phase-II)
-
500 kV Kohala – Karot – Gujranwala (240 km)
In/out of 500 kV Neelum Jhelum – Karot circuit at Kohala (4+4)
11820 139 2017-18
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION
LINES
ESTIMATED COST
(Rs.in Million)
Eqt. US$ in Million
REQUIRED YEAR OF
COMMISSIO-NING
6-
Dispersal of Power from 4500 MW Diamer Basha HPP to Lahore with interconnection at Dasu and Gujar Khan
765 kV HVAC substations at Gujar Khan & Lahore with 765/500 kV 3x500 MVA T/Fs
500 MVAR SVC at Gujar Khan
Three 765 kV HVAC T/Ls from Basha to Gujar Khan (407 km long each)
Two 765 kV HVAC T/Ls from Gujar Khan to Lahore (260 km long each)
113900 1340 2018-19
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
SR#.
NAME OF NEW SUBSTATIONS
T/F CAP. (MVA)
ASSOCIATED TRANSMISSION
LINES
ESTIMATED COST
(Rs.in Million)
Eqt. US$ in Million
REQUIREDD YEAR OF
COMMISSIO-NING
7-
Dispersal of Power from 5400 -7000 MW Bunji Hydro Power Project to Lahore with interconnection at Gujar Khan
765 kV HVAC substatin extn at: Basha, Dasu, Thakot, Gujar khan Lahore
765 kV new substation at Bunji.
2 x 765 kV HVAC 110 km long Bunji - Basha S/C T/Lines
1x765 kV HVAC 759 km long Bunji –Dasu-Thakot-Gujar Khan-Lahore S/C T/Lines
126225 1485 2019-20
Total 296170 3484
LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER PLANTS
PC-I for dispersal of Power from Neelum Jhelum HPP has been approved by ECNEC
Studies are being carried out to ascertain the interconnection schemes for the projects at Sr. No: 2 to 7
Bottle Necks
• At present no major system constraints • Intermittent over-loading of transformers at
some places being addressed by addition of following transformation capacities up to 2014-15– 500/220 KV 11400 MVA– 220/132 KV 19330 MVA
49
50
• For huge future development the bottle necks would be
1. Availability of finance
2. Responsibility of dispersal from power plants & uncertainty of generation project.
• Capacity of 1. Planning department
2. Local Consultant
3. Local contractors
• Inconducive Law & order situation for foreign consultants and contractors.
Reference documents
• NTDC GRID CODE (JUNE 2005)• NEPRA PERFORMANCE STANDARDS
(TRANSMISSION) RULES (NOV. 2005)
52
KEY PERFORMANCE INDICATORS1.System Reliability• Transmission System incl. Tie Lines
a) System Duration of Interruption
= A/Nwhere
A= sum of the total outage hours recorded at all the interconnection points (other than 132 kV line tripping) in a period
N = Number of monitoring points (Interconnection Point)
Tie lines means interconnection facility for the transfer of electric power between the licensee and other utilities not governed by the Act.
53
KEY PERFORMANCE INDICATORS1. System Reliability
b)System Frequency Interruption
= A/NWhere
A= sum of the total outage hours recorded at all the interconnection points (other than 132 kV line tripping) in a period
N= Number of circuits
54
KEY PERFORMANCE INDICATORS
2. System Security
(Energy not served)
= ∑ Pi x TWherePi = Power interrupted in MW in a circuit
T = Time Duration in Hours
55
KEY PERFORMANCE INDICATORS
3. Quality of SupplyA) System Voltage Variation Grid
PerformanceCode Standard
-500 kVUnder Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+ 10%
-220 kVUnder Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+ 10%
-132 kVUnder Normal Conditions -5 +8% -+ 5% Under N-1 Conditions -+10% -+ 10%
56