NATIONAL RAILWAY INFRASTRUCTURE COMPANY

Transcript of NATIONAL RAILWAY INFRASTRUCTURE COMPANY. All main Bulgarian railway sections are included in the...

NATIONAL RAILWAY INFRASTRUCTURE COMPANY

All main Bulgarian railway sections are included in the comprehensive network

Intermodal terminals – Sofia, Plovdiv, Varna, Burgas, Ruse, Vidin, Lom, Dragoman, Svilengrad and Gorna Oryahovitsa

TEN-T Comprehensive Network

Ongoing projects2007-2013

• Plovdiv-Svilengrad Railway Electriffication & Upgrading of Corridors IV and IX

• Phase 1 – Kruomovo - Parvomai: Contractor Terna – Greece

– Contract value: 99 792 441 € – financing under ISPA programme

• Phase 2 – Parvomai – Dimitrovgrad: Contractor Astaldi – Italy

– Contract value : 68 000 000 € – financing under ISPA programme

• Phase Systems – Plovdiv-Svilengrad-turkish border: Contractor Thales-Alcatel-Lucent – Austria

– Contract value : 35 557 047, 06 € – financing under ISPA programme

• Phase 3 – Svilengrad – turkish border: Contractor OHL ŽS – Czech Republic

– Contract value: 69 999 666 BGN without VAT – financing under Operational Programme on Transport

• Phase 4 – Dimitrovgrad - Svilengrad: completed tender procedure, expected contract signing on 3 implementation positions.

Ongoing projects 2007-2013

• Rehabilitation of Railway Infrastructure along Sections of the Plovdiv-Burgas Railway Line

• Total investment value: 316 968 850,42 BGN without VAT

• Main contractor: G.S.F. S.p.A – SK 13 – Trace Railinfra

• Modernization of the railway section Septemvri-Plovdiv

• LOT 1 – Septemvri – Pazardzhik: Contractor Swietelsky – RVP Köhne

• LOT 2 – Pazardzhik – Stamboliyski: Contractor IGA Rail Infra

• LOT 3 – Stamboliyski – Plovdiv: Contractor Porr Bau GmbH

• Total contracts value: 157 860 835,75 BGN without VAT

Ongoing projects 2007-2013

• Construction of an Intermodal terminal in South-Central planning region of Bulgaria

• Forthcoming activities

– Preparation of Detailed Structural Plan and Plot Plan for expropriation procedures

– Technical design

– Construction

• Indicative budget: 16 166 249 BGN without VAT

• Design and implementation of geographical information system (GIS) for the NRIC needs

• Total investment value: 12 000 000 BGN

• Main Contractor: Consortium „EuroGeoRail“

• Project completion date: April 2011

2014-20202014-2020 priority implementation projects priority implementation projects

The projects are grouped in to A, B and V direction for effective management and operability achievement

National Railway Infrastructure Company

Group A projects – To the direction Dragoman-Sofia-Plovdiv-Svilengrad and Plovdiv-Burgas part of the transeuropean transport corridors IV, IIIV and X;

1. Modernization of Sofia – Dragoman Railway Line

• Preparation of Environmental impact assessment (EIA) report and technical design: 2007-2013

• Construction: 2014 – 2020

• Indicative budget: 132 260 000 €

2. Modernization of Sofia – Plovdiv Railway Line

• Technical design for Sofia – Septemvri railway section : 2007-2013

• Preparation of Environmental impact assessment (EIA) report of Elin-Pelin – Septemvri railway section: 2007-2013

• Construction of Sofia – Septemvri railway section : 2014 – 2020

• Indicative budget: 1 081 000 000 €

National Railway Infrastructure Company

Group A projects – To the direction Dragoman-Sofia-Plovdiv-Svilengrad and Plovdiv-Burgas part of the transeuropean transport corridors IV, IIIV and X;

3. Projects of Plovdiv – Burgas section completion – Corridor VIII• Indicative budget: 82 700 000 €• Including projects:

• Construction of optic cable along Plovdiv-Burgas railway line, indicative budget:15 512 000 €. Construction: 2014-2020;

• Introduction of interlockings in Karnobat-Burgas section, indicative budget: 5 466 000 €. Construction: 2014-2020;

• Development of Burgas Railway Junction, indicative budget: 20 000 000 €. Design and construction: 2014-2020;

• Rehabilitation of Plovdiv-Orizovo railway section, indicative budget: 30 677 000 €. Construction: 2014-2020;

• Modernization of sections along Plovdiv-Burgas railway line (Orizovo – Mihaylovo, Yambol – Zimnitsa, etc.), indicative budget: 10 000 000 €, Technical design: 2007-2013. Construction: 2014-2020;

National Railway Infrastructure Company

Group B projects – To the direction Vidin-Sofia-Radomir-Kulata part of the transeuropean transport corridor IV;

1. Modernization of Vidin-Sofia Railway Line

• Preparation of Environmental impact assessment (EIA) report and technical design: 2007-2013

• Construction of separate sections along the route will start in 2014-2020 programming period:

• Modernization of Vidin – Medkovets railway section 62,5 км;

• Modernization of Medkovets – Ruska Byala/Mezdra railway section 84,3 км;

• Modernization of Ruska Byala/Mezdra – Stolnik railway section 76,3 км;

2. Modernization of Sofia –Pernik – Radomir Railway Line

• Technical design: 2007-2013

• Construction: 2014 – 2020

• Indicative budget: 359 576 884 €

National Railway Infrastructure Company

Group V projects – Passangers and freights intermodality projects

1. Development of Sofia Railway Junction

• Technical design: 2007-2013

• Design and construction: 2014 – 2020

• Indicative budget: 309 847 000 €

2. Construction of an Intermodal terminal in Sofia

• Indicative budget: 31 345 000 €

• IProject preparation will be implemented in 2007-2013

3. Construction of an Intermodal terminal in Central-Nord planning region of Bulgaria-Ruse

• Fisibility study and preliminary design: 2007-2013

• Design and construction: 2014 – 2020

THANK YOU FOR YOUR ATTENTION

National Railway Infrastructure Company