NATIONAL FERTILIZERS LIMITED, NANGAL UNIT
Transcript of NATIONAL FERTILIZERS LIMITED, NANGAL UNIT
![Page 1: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/1.jpg)
NATIONAL FERTILIZERS LIMITED,NANGAL UNIT
![Page 2: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/2.jpg)
REVAMP OF STEAM TURBINE FOR SYNTHESIS GAS COMPRESSOR AT NFL NANGAL
By:Rakesh MarkanDeputy General Manager(Mech)NFL Nangal
![Page 3: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/3.jpg)
BOIGRAPHY:
Rakesh Markan
Graduate in Mechanical Engineering Nearly 30 Years of Experience in Maintenance, Troubleshooting and Major Overhaul of Steam
Turbines and Centrifugal Compressors, Erection and preventive maintenance of connected Steam and Process Gas Piping in Fertilizer Industry.
Worked in Ammonia Plant- Shell Gasification Process, Ammonia Plant-SMR Process, Urea Plant and Boiler Plants at various positions.
Worked in Various organizations in Fertilizer Sector, besides the four Units of National Fertilizers Limited, for trouble shooting and subsequent maintenance of high speed rotating machines,.
Presented papers, on case studies related to reliability maintenance/Improvement in productivity, at various forums in India
Hands on experience in planning and execution of major turnarounds of Fertilizer Plants.At present holds the position as Chief Manager (Mechanical) in Nangal Unit of National
Fertilizers Limited.
![Page 4: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/4.jpg)
ABSTRACT:National Fertilizers Limited, Nangal Unit, India hadunder taken the revamp of Steam Turbine of SynthesisGas Compressor in January 2014. The plant startup,after machine revamp, was delayed by 40 days,because of various activities related to machine revampwhich were not envisaged before commencement ofthe revamp. This paper throws light on thoseunforeseen jobs which lead to delay in startup and thelessons learnt to avoid such delays in future.
![Page 5: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/5.jpg)
SYNTHESIS GAS COMPRESSOR, NFL NANGALSYNTHESIS GAS COMPRESSOR, NFL NANGAL
![Page 6: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/6.jpg)
MAJOR JOBS SCHEDULED TO BE CARRIED-OUT DURING REVAMP
• Replacement of Rotor with New High Efficiency one• Replacement of Nozzle Segment with High Efficiency
one• Replacement of guide blade carrier with New High
Efficiency one• Replacement of Steam Glands• Replacement of Steam Control Valves with Modified
ones
![Page 7: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/7.jpg)
MAJOR JOBS SCHEDULED TO BE CARRIED-OUT DURING REVAMPReplacement of Rotor
with New High
Efficiency one
• Replacement of guide blade carrier with New High
• Efficiency one
MAJOR JOBS SCHEDULED TO BE CARRIED OUT DURING REVAMP
REPLACEMENT OF ROTOR AND GUIDE BLADE CARRIER
![Page 8: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/8.jpg)
REPLACEMENT OF STEAM NOZZLE BLOCK WITH NEW HIGH EFFICIENCY ONE
REPLACEMENT OF STEAM INLET NOZZLES
![Page 9: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/9.jpg)
REPLACEMENT OF STEAM GLANDS
MAJOR JOBS SCHEDULED TO BE CARRIED-OUT DURING REVAMPREPLACEMENT OF STEAM GLANDS
![Page 10: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/10.jpg)
REPLACEMENT OF STEAM CONTROL VALVE ASSEMBLY WITH MODIFIED ONES
REPLACEMENT OF STEAM CONTROL VALVES’ ASSEMBLY
![Page 11: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/11.jpg)
OPEN TOP CASINGDISMANTLING THE BEARINGSREMOVE ROTOR,STEAM GLANDS,GUIDE BLADE CARRIERS,NOZZLE BLOCKCLEANING OF CASING AND PLACE NEW BEARINGSCENTRING OF NEW NOZZLE BLOCKCENTRING OF NEW ROTOR WITH TURBINE CASING AND BEARING PEDESTALSINSTALL NEW NOZZLE BLOCK,CENTRING OF NEW NOZZLE BLOCK WITH ROTOR AND TURBINE CASING
TIME AS PER ORIGINAL SCHEDULE : 27 DAYSACTUAL TIME TAKEN: 67 DAYS
MAJOR ACTIVITIES INVOLVED IN MACHINE OVERHAUL AS PER NORMAL PRACTICE
![Page 12: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/12.jpg)
MAJOR ACTIVITIES INVOLVED IN MACHINE OVERHAUL AS PER NORMAL PRACTICE
INSTALL NEW STEAM GLANDS, CENTRING OF GLANDS w.r.t ROTOR AND TURBINE CASING
INSTALL NEW GUIDE BLADE CARRIER, CENTRING OF NEW GUIDE BLADE CARRIER w.r.t TURBINE CASING AND ROTORBOXUP TOP CASING COVER.
ALIGNMENT OF TURBINE WITH DOWNSTREAM MACHINE.
![Page 13: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/13.jpg)
• NUMEROUS HIGH PRECISION MACHINING JOBS CAME UP DURING JOB EXECUTION, WHICH WERE NOT ANTICIPATED BEFORE COMMENCEMENT OF REVAMP.
• THESE JOBS WERE NOT COVERED IN THE ORIGINAL SCHEDULE BUT THE SAME WERE EXECUTED AND PLAYED A MAJOR ROLE IN EXTENDING THE SCHEDULED TIME
![Page 14: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/14.jpg)
ACTIVITIES WHICH LEAD TO DELAY IN EXECUTIONAS PER AGREEMENT BETWEEN OEMs & CUSTOMER ALL THE NEW REDESIGNED PARTS SHALL BE WITH IMMPROVED EFFICIENCY BUT INTERCHANGEABLE WITH THE ONES ORIGINALLY INSTALLED.
JOURNAL DIAMETER OF THE NEW ROTOR WAS 124.83 MM AGAINST THE ORIGINAL ONE AS 119.82MM.
DESIGN OF BEARINGS WAS CHANGED TO TILTING PAD TYPE INPLACE OF BUSH TYPE.
150mm φ 260mm φ
![Page 15: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/15.jpg)
MODIFICATION OF SEATING AREAS OF FRONT END BEARING PEDESTAL
Packing Plates
BEFORE MACHINING
AFTER MACHINING
![Page 16: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/16.jpg)
HIGH PRCISION MACHINED COMPONENTS FABRICATED IN LOCAL W/S
Centering keys for Parallel alignment of Turbine Casing with Bearing Pedestal
Centering Keys
![Page 17: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/17.jpg)
HIGH PRCISION MACHINED COMPONENTS FABRICATED IN LOCAL W/S
MAIN AXIAL KEY UNDER FRONT BRG PEDESTAL
MAIN AXIAL KEY
![Page 18: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/18.jpg)
DELAY DUE TO WRONG SEALING ANGLE OF THE OF SEAL RING ON EMERGENCY STOP VALVE 25 DEG. INSTEAD OF 15 DEG.
![Page 19: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/19.jpg)
FIXTURES FOR MACHINING OF STEAM GLANDS WERE MADE TO ACCOMMODATE THE NEW STEAM GLANDS ON LATHE MACHINES IN NFL WORKSHOP
Weld deposit to achieve required diameter
Balance Piston Gland
![Page 20: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/20.jpg)
MACHINING OF ‘L’ RING SEATING AREA IN THE TOP CASING.
700 mm
JOBS SUBSEQUENT TO THE VISIT OF FACT FINDER DEPUTED BY THE OEMs
![Page 21: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/21.jpg)
REPLACEMENT OF EXISTING VALVE SEAT RINGS WITH NEW ONES
JOBS SUBSEQUENT TO THE VISIT OF FACT FINDER DEPUTED BY THE OEMs
![Page 22: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/22.jpg)
REMOVAL OF DAMAGED STUDS IN TOP CASINGREPLACEMENT OF ALL OLD STUDS INSTALLED IN THE TOP CASING
![Page 23: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/23.jpg)
REPLACEMENT OF STRAINERS IN THE MAIN STEAM INLET LINES. THE JOB REMAINED HELD UP DUE TO NON AVAILABILITY OF SPARE STRAINERS
![Page 24: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/24.jpg)
REPLACEMENT OF ALL OLD DAMAGED STUDS INSTALLED IN THE BOTTOM CASING
BROKEN BOLTS/STUDS IN THE BOTTOM CASING
![Page 25: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/25.jpg)
BOTTOM CASING AFTER REMOVAL OF NOZZLE BLOCK AND GUIDE BLADE CARRIER
NOZZLE BLOCK
![Page 26: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/26.jpg)
BASIC REFERENCES OF BOTTOM CASING W.R.TFOUNDATION AND BEARING PEDESTALS LOST
SHIFTING OF BOTTOM CASING TO MECHANICAL WORKSHOP FOR REMOVAL OF CENTER GUIDE KEYS & ECCENTRIC BUSHES
CENTRE GUIDE KEYS
![Page 27: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/27.jpg)
REMOVAL OF CENTRE GUIDE KEYS IN MECHANICAL WORKSHOP
![Page 28: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/28.jpg)
REMOVAL OF ECCENTRIC BUSH FOR NOZZLE BLOCK IN MECHANICAL WORKSHOP
![Page 29: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/29.jpg)
SPRING SUPPORTS WERE FOUND BADLY RUSTED AND FEW WERE FOUND DAMAGED
![Page 30: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/30.jpg)
MISALIGNMENT OF STEAM INLET FLANGES
50MM
3.85MM
![Page 31: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/31.jpg)
CORRECTION OF PIPING MISALIGNMENT BY CUTTING AND REWELDING THE HIGH PRESSURE/HIGH TEMPERATURE STEAM
PIPINGWelding Joints cut and Pipe relocated
Steam Inlet to Turbine
91 ATA Steam from Boilers
![Page 32: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/32.jpg)
MISALIGNMENT OF STEAM INLET FLANGESS.
No
.
Descripti
on
Main Steam
Flange(Left)
Main Steam
Flange
(Right)
Before
Correc
tion
After
Corr
ectio
n
Befor
e
Corre
ction
After
Corre
ction
1 Parallel
Misalign
ment, in
mm
50 2 45 2.5
2 Angular
Misalign
ment,
In mm
3.85 0.10 2.30 0.10
![Page 33: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/33.jpg)
Provision of Key Phasor
![Page 34: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/34.jpg)
TEMPORARY STRAINERS WERE INSTALLED IN THE OIL PIPING FOR CLEANING OF LUBE OIL
![Page 35: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/35.jpg)
DELAY ANALYSISMACHINING OF BEARING PEDESTALSMACHINING OF L-RING SEATING AREAS IN TOP CASINGREPLACEMENT OF CONTROL VALVE SEATS IN TOP CASINGREMOVAL OF OLD STUDS AND FIXING OF NEW ONESFABRICATION OF HIGH PRECISION KEYS, LEVELLING PLATES,FIXTURESCORRECTION OF SIZES OF ESV SEAL RING-15 DEG. Vs 25 DEG.REMOVAL OF CENTER GUIDE KEYS & ECCENTRIC BUSHES IN BOTTOM
CASINGREPAIR OF SPRING SUPPORTSCORRECTION OF ALLIGNMENT OF PIPINGCLEANING OF LUBE OIL-Bar Chart
![Page 36: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/36.jpg)
Lessons Learnt:
Workshop facilities required during revamp to be recorded and suitable workshop to be located in advance. All machining jobs required to be done to be listed down and procedures to be framed.
Suitable Piping Team for carrying out alteration in Steam piping, consisting of skilled piping fitters and the IBR certified welders to be kept ready. Decision in this regard to be taken at the appropriate time inorder to save time loss due to decision making.
![Page 37: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/37.jpg)
Lessons Learnt:
New set of Spring Supports may be kept available
Pre revamp meetings to be held between core team who has been assigned the revamp project from customer side as well as the OEM side.
Availability of Spares required during revamp.
Availability of all special tools and standard tools.
Cleaning of Lubricating Oil well in advance
![Page 38: NATIONAL FERTILIZERS LIMITED, NANGAL UNIT](https://reader030.fdocuments.us/reader030/viewer/2022040620/624bd3145c534448c63f080c/html5/thumbnails/38.jpg)
THANKS