National Action Plan on Chemical (industrial) Disaster Risk Management

25
National Action Plan on Chemical (industrial) Disaster Risk Management Dr Rakesh Dubey Director Disaster Management Institute and Member Secretary, National Action Plan at CIDM 2010 Mumbai

description

National Action Plan on Chemical (industrial) Disaster Risk Management. Dr Rakesh Dubey Director Disaster Management Institute and Member Secretary, National Action Plan at CIDM 2010 Mumbai. - PowerPoint PPT Presentation

Transcript of National Action Plan on Chemical (industrial) Disaster Risk Management

Page 1: National Action Plan on Chemical (industrial) Disaster Risk Management

National Action Plan on Chemical (industrial) Disaster Risk

Management

Dr Rakesh DubeyDirector

Disaster Management Instituteand

Member Secretary, National Action Planat

CIDM 2010 Mumbai

Page 2: National Action Plan on Chemical (industrial) Disaster Risk Management

National Action Plan is under the process of preparation under the Chairmanship of Lt. Gen. (Dr) J R Bhardwaj, Hon’ble Member

NDMA, GOI

February 16, 2010 CIDM 2010, Mumbai 2

Page 3: National Action Plan on Chemical (industrial) Disaster Risk Management

Evolution of National idrm system

February 16, 2010 3CIDM 2010, Mumbai

Page 4: National Action Plan on Chemical (industrial) Disaster Risk Management

February 16, 2010 4CIDM 2010, Mumbai

Page 5: National Action Plan on Chemical (industrial) Disaster Risk Management

We suggest the model on the left for action plan

1. Prepardness : includes planning, prevention and mitigation i.e.

Risk assessment (HAZOP, FEMA, FTA, ETA, consequence assessment, probability estimation, etc. audits; on-site and off-site emergency plans, Training

Engineering change/modification for prevention and mitigation

ISO’s, OSHAS, Formal education in the area of safety, risk assessment, medical, fire fighting,

2. Response: Human behaviour, community involvement and participation in emergency process, response of fire fighters, medical response, police (law and order) eg Mock drills

These can be enhanced by Training, awareness building measures and integration with business continuity programme

1. Prepardness : includes planning, prevention and mitigation i.e.

Risk assessment (HAZOP, FEMA, FTA, ETA, consequence assessment, probability estimation, etc. audits; on-site and off-site emergency plans, Training

Engineering change/modification for prevention and mitigation

ISO’s, OSHAS, Formal education in the area of safety, risk assessment, medical, fire fighting,

2. Response: Human behaviour, community involvement and participation in emergency process, response of fire fighters, medical response, police (law and order) eg Mock drills

These can be enhanced by Training, awareness building measures and integration with business continuity programme

February 16, 2010 5CIDM 2010, Mumbai

Page 6: National Action Plan on Chemical (industrial) Disaster Risk Management

Prepardness :

• Planning: GIS based on-site and emergency

management plans Risk assessment should make a base for

plans Reach to all important stake holders by

using some common platform• Prevention: Compliance of laws and rules, by doing risk

assessment after assessing the consequences and probability by using HAZOP, FEMA, ETA, FTA and computer model for consequence analysis

• Mitigation Change in process, chemicals,

instrumention, machine, training of human beings, community and civil administartin invovment

• Training Planning, Prevention and mitigation

• Planning: GIS based on-site and emergency

management plans Risk assessment should make a base for

plans Reach to all important stake holders by

using some common platform• Prevention: Compliance of laws and rules, by doing risk

assessment after assessing the consequences and probability by using HAZOP, FEMA, ETA, FTA and computer model for consequence analysis

• Mitigation Change in process, chemicals,

instrumention, machine, training of human beings, community and civil administartin invovment

• Training Planning, Prevention and mitigation

includes planning, prevention and mitigation

i.e. Risk assessment (HAZOP, FEMA, FTA, ETA, consequence assessment, probability estimation, etc. audits; on-site and off-site emergency plans, ISO’s, OSHAS, compliance of the laws, engineering modification

Strengthening the regulators by knowledge upgradation to meet the challenges

Formal education in the area of safety, risk assessment, medical, fire fighting, for cadre development

February 16, 2010 6CIDM 2010, Mumbai

Page 7: National Action Plan on Chemical (industrial) Disaster Risk Management

HAZARD IDENTIFICATION METHODS:

- Process hazard checklist - Hazard survey: DOW index - HAZOP hazard & operability study - Safety review

RISK ASSESSMENT:

- What can go wrong & how ? - What are the chances ? - Consequences ?

EXTREMES:

- Low probability - Minimal consequences

February 16, 2010 7CIDM 2010, Mumbai

Page 8: National Action Plan on Chemical (industrial) Disaster Risk Management

Causality chainCausality chain

EmissionEmission

Environmentaldistribution

Exposure

Effects

MODELLINGor

MONITORING

February 16, 2010 8CIDM 2010, Mumbai

Page 9: National Action Plan on Chemical (industrial) Disaster Risk Management

Spatial scalesSpatial scales

Local scaleLocal scale Area around one point Area around one point

source/one industrysource/one industry Average environmental Average environmental

characteristicscharacteristics ““Reasonable worst Reasonable worst

casecase”” scenario scenario

Local scaleLocal scale Area around one point Area around one point

source/one industrysource/one industry Average environmental Average environmental

characteristicscharacteristics ““Reasonable worst Reasonable worst

casecase”” scenario scenario

February 16, 2010 9CIDM 2010, Mumbai

Page 10: National Action Plan on Chemical (industrial) Disaster Risk Management

Regional scaleRegional scale Area can be 200 x 200 kmArea can be 200 x 200 km 20 million inhabitants 20 million inhabitants 100 or 10% of production 100 or 10% of production Average environmentalAverage environmental

characteristicscharacteristics Two or more sourcesTwo or more sources

Regional scaleRegional scale Area can be 200 x 200 kmArea can be 200 x 200 km 20 million inhabitants 20 million inhabitants 100 or 10% of production 100 or 10% of production Average environmentalAverage environmental

characteristicscharacteristics Two or more sourcesTwo or more sources

February 16, 2010 10CIDM 2010, Mumbai

Page 11: National Action Plan on Chemical (industrial) Disaster Risk Management

Types of EmissionsTypes of EmissionsTypes of EmissionsTypes of Emissions

0

2

4

6

8

10

12

1 2 3 4 5 6 7

Continuous emissions

0

2

4

6

8

10

12

1 2 3 4 5 6 7

Intermittent emissions

Peak emissions

0

2

4

6

8

10

12

1 2 3 4 5 6 7

0

2

4

6

8

10

12

1 2 3 4 5 6 7

Block emissions

February 16, 2010 11CIDM 2010, Mumbai

Page 12: National Action Plan on Chemical (industrial) Disaster Risk Management

Hazards and Risks in industriesHazards and Risks in industries

• LPG , Propane (under pressure in liquid phase)• Ammonia (under pressure/refrigeration in

liquid phase) • Chlorine (under pressure in liquid phase)• Hydrogen (under pressure in gases)• CO + CH4 (under atmosphere )

February 16, 2010 12CIDM 2010, Mumbai

Page 13: National Action Plan on Chemical (industrial) Disaster Risk Management

Response

• Recognize• Avoid• Isolate• Notify

What can I do

February 16, 2010 13CIDM 2010, Mumbai

Page 14: National Action Plan on Chemical (industrial) Disaster Risk Management

Response

• Training Plant staff from top to bottom including

the contractual labours, visitors, associates likes traders, suppliers consumers

• Community Involvement of community in all

important activities, disclosure of vital information with preparedness

• National/state/local Governments Assessment of weakness in medical

preparedness, fire fighting, law and order and corrective measures

• Mockdrills By involving all stakeholders including,

armed forces and NDRF

• Training Plant staff from top to bottom including

the contractual labours, visitors, associates likes traders, suppliers consumers

• Community Involvement of community in all

important activities, disclosure of vital information with preparedness

• National/state/local Governments Assessment of weakness in medical

preparedness, fire fighting, law and order and corrective measures

• Mockdrills By involving all stakeholders including,

armed forces and NDRF

Human behaviour, community involvement and participation in emergency process, response of fire fighters, medical response, police (law and order) eg Mock drillsCompliance of regulations

February 16, 2010 14CIDM 2010, Mumbai

Page 15: National Action Plan on Chemical (industrial) Disaster Risk Management

Protection layers for disaster free society

February 16, 2010 15CIDM 2010, Mumbai

Page 16: National Action Plan on Chemical (industrial) Disaster Risk Management

Knowledge platform for example:www.hrdp-idrm.in

February 16, 2010 CIDM 2010, Mumbai 16

Page 17: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

SAFETYMANAGEMENT

ERRORTRAININGEDUCATIONMOTIVATIONTASK DESIGN

1

2 3 4 5 6 7

February 16, 2010 17CIDM 2010, Mumbai

Page 18: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

SAFETYPROGRAM

DEFECTREVISE INFORMATIONCOLLECTIONANALYSISIMPLEMENTATION

2

3 4 5 6 71

February 16, 2010 18CIDM 2010, Mumbai

Page 19: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

COMMANDERROR

TRAININGEDUCATIONMOTIVATIONTASK DESIGN

3

4 5 6 71 2

February 16, 2010 19CIDM 2010, Mumbai

Page 20: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

DESIGN REVISION VIA-- - SOP- REGULATIONS- POLICY LETTERS- STATEMENTS

4

5 6 71 2 3SYSTEM DEFECT

February 16, 2010 20CIDM 2010, Mumbai

Page 21: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

ENGINEERINGTRAININGMOTIVATION

5

6 71 2 3 4OPERATING

ERROR

February 16, 2010 21CIDM 2010, Mumbai

Page 22: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

7PROTECTIVE EQUIPMENTBARRIERSSEPARATION

6

1 2 3 4 5 MISHAP

February 16, 2010 22CIDM 2010, Mumbai

Page 23: National Action Plan on Chemical (industrial) Disaster Risk Management

Seven Avenues

Potential countermeasures for each modern causation approach include:

CONTAINMENTFIREFIGHTINGRESCUEEVACUATIONFIRST AID

7

1 2 3 4 5 6 RESULT

February 16, 2010 23CIDM 2010, Mumbai

Page 24: National Action Plan on Chemical (industrial) Disaster Risk Management

Preparedness + Response have base Preparedness + Response have base

February 16, 2010 24CIDM 2010, Mumbai

Page 25: National Action Plan on Chemical (industrial) Disaster Risk Management

[email protected]

kindly visit www.hrdp-idrm.in

February 16, 2010 25CIDM 2010, Mumbai