NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

27
NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank

Transcript of NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Page 1: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

NATHAN BLACKETERJEFF MORRIS

BRIAN WILDER

The Great Plains Lions Eye Bank

Page 2: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Definition & Conceptualization

Page 3: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

What We Did

Analyzed potential business with problemsAnalyzed potential solutions for problemsGPLEB was selected as client

Identified business need GPLEB stakeholder meeting Develop feasible solution

Page 4: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Problem

GPLEB filing system Bulky, inefficient Wastes time, space, resources

GPLEB statistical method Numerous logs Manual tallies

Page 5: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Solution

BMW custom software solution Relational Database Web-based

Reporting One-click reporting PDF format

Documentation Generation of necessary chart work Secured on server

Page 6: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Benefits Expected

Streamline OperationsIncrease accuracyImproved efficiency

Page 7: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Planning & Budgeting

Page 8: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

What We Did

Conducted stakeholder interviewsPresented Project Proposal Assigned resources based on work loadSecured 50% of budgetUtilized Agile MethodologiesSuccessful Phase Completion

Page 9: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Methodology

Page 10: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

WBS

Page 11: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Tracking Gantt Chart

Page 12: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Progress Tracking

Page 13: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Network Diagram

Page 14: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Network Diagram

Page 15: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Network Diagram

Page 16: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Budget

Task Name Cost

Eye Bank System $19,120.00

Implementation $14,960.00

Documentation $3,360.00

Training $800.00

Page 17: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Break-even Analysis

Page 18: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Execution & Control

Page 19: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

What We Did

Utilized Open-Source SoftwareExisting server utilizedExisting OS utilized

Started with LAMP Ended with WAMP

Implemented eRaider

Page 20: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Technology Applied

Custom Web-based software solution WAMP setup CakePHP

MVC model

Weekly and Daily Backups Local and external servers Amazon S3 services

PDF Reports Daily, Weekly, Monthly and Yearly reports Local, State, and National Reports FPDF

Page 21: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Progress to Date

Working prototypeDaily SCRUM meetings100 % client acceptance thus farAnalysis stage completeStarting Implementation

Page 22: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Earned Value Analysis

Page 23: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Status

About 6 days into projectTAC: 32 days totalETAC: 46.5 daysProject Behind Schedule

SPI: 0.69Project Under Budget

CPI: 1.001

Page 24: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Termination & Closure

Page 25: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

What We Will Do

Finish up Implementation phaseCreate DocumentationConduct TrainingDistribute Acceptance Testing

Page 26: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Updated Completion Date

Should have 26 days leftCurrently, more like 40 daysEstimated Finish Date: May 26, 2009

Page 27: NATHAN BLACKETER JEFF MORRIS BRIAN WILDER The Great Plains Lions Eye Bank.

Lessons Learned

Microsoft ProjectPlanningStakeholder signaturesTeam member cooperation