Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts...

16
Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts •Fill Removal •Oxbow Enhancements 3. Timeline and Next Steps

description

2009 Kahler Reach Assessment - USBR KDIZ-3 Reconnect Disconnected Inner/outer Zone KOZ-20 and KOZ-19 Fill Removal

Transcript of Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts...

Page 1: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Nason Creek RM 3.5 – 4.7 Restoration Actions

1. Project History and Development

2. Design Concepts•Fill Removal•Oxbow Enhancements

3. Timeline and Next Steps

Page 2: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

2004 Channel Migration Study, Jones and Stokes

• 2007 Oxbow (N3)• 2009 Oxbow (N4)• N1

Page 3: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

2009 Kahler Reach Assessment - USBR

• KDIZ-3 Reconnect Disconnected Inner/outer Zone• KOZ-20 and KOZ-19 Fill Removal

Page 4: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Project Development• 2010 Alternatives Analysis• 2010 SRFB Application• January 2011 RTT

Presentation• 2011 SR 207 Relocation

Feasibility Study– Geomorphology– EDT Biological Benefit– Geology

• April 2012 RTT Presentation

Page 5: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Project DevelopmentSRFB Application 2012 for reach based restoration1. Fill Removal2. 2007 Oxbow

Enhancements3. ELJ4. Side Channel

Reconnection

Page 6: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Design Concepts1. Fill Removal2. 2007 Oxbow

Enhancements

Page 7: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Fill Removal

Page 8: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Fill Removal

Page 9: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Parking Lot Fill Removal

Page 10: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Parking Lot Fill Removal Sections

Page 11: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Abuttment Removal

Page 12: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

2007 Oxbow Enhancements

Page 13: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

2007 Oxbow

Page 14: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

2007 Oxbow Enhancements

Page 15: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Next Steps and Timeline• Route link to presentation• Comments on design concepts (fill removal

and oxbow enhancements) until 5-31-13• Revise designs based upon stakeholder and

USFS input Summer 2013• USFS Resource Reviews Summer 2013• Permit ready designs Sept-October 2013• Permit submittal and NEPA kick-off Fall 2013• Construction summer 2014

Page 16: Nason Creek RM 3.5 – 4.7 Restoration Actions 1.Project History and Development 2. Design Concepts Fill Removal Oxbow Enhancements 3. Timeline and Next.

Questions?