Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

27
SANIMA MAI HYDROPOWER LIMITED Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal Site office, Gunmune IIam MAI HYDROPOWER PROJECT (22 MW) MONTHLY PROGRESS REPORT OCTOBER, 2013

Transcript of Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Page 1: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

SANIMA MAI HYDROPOWER LIMITED Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal Site office, Gunmune IIam

MAI HYDROPOWER PROJECT (22 MW)

MONTHLY PROGRESS REPORT OCTOBER, 2013

Page 2: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

SANIMA MAI HYDROPOWER LIMITED Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal

MAI HYDROPOWER PROJECT (22 MW) MONTHLY PROGRESS REPORT Month: October, 2013

Quality Control Signature Date

Prepared by: Pratik Tiwari October 31, 2013

Checked by: Nabin Kumar Ijam October 31, 2013

Approved by: Bhoj Raj Paudel October 31, 2013

Page 3: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited i

Table of Contents  1.  PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENTS ......................................... 3 

2.  KEY DATES ................................................................................................................................ 3 

3.  CONTRACT PACKAGES AND IMPLEMENTATION ................................................................ 3 

4.  FINANCING ................................................................................................................................ 3 

5.  RESOURCES AT SITE .............................................................................................................. 4 

6.  CIVIL CONSTRUCTION PROGRESS AT SITE ........................................................................ 5 

6.1  HEADWORKS ........................................................................................................................... 5 

6.1.1  CUTOFF WALL, FLOOD WALL U/S OF WEIR ......................................................................... 5 6.1.2  WEIR BODY AND GUIDE WALL .......................................................................................... 5 6.1.3  STILLING BASIN AND FLOODWALL (D/S OF WEIR) ............................................................... 6 6.1.4  INTAKE, UNDERSLUICE AND INLET CANAL ......................................................................... 7 6.1.5  APPROACH CULVERT, SETTLING BASIN AND FLUSHING CULVERT ...................................... 8 6.1.6  HEADRACE CULVERT ....................................................................................................... 9 

6.2  HEADRACE TUNNEL ............................................................................................................... 10 

6.3  PENSTOCK, SADDLE SUPPORT AND ANCHOR BLOCK ............................................................. 11 

6.4  POWERHOUSE....................................................................................................................... 12 

7.  HYDROMECHANICAL PROGRESS ....................................................................................... 13 

8.  ELECTROMECHANICAL PROGRESS ................................................................................... 14 

9.  POWER EVACUATION LINE .................................................................................................. 15 

10.  EIA PROGRESS ...................................................................................................................... 15 

11.  VISITORS OF THE MONTH .................................................................................................... 16 

12.  NOTES ...................................................................................................................................... 17 

13.  WORK PROGRESS AT SITE .................................................................................................. 18 

14.  PHOTOS ................................................................................................................................... 19 

15.  EQUIPMENTS OF CIVIL CONTRACTOR AT SITE ................................................................ 23 

16.  STOCK BALANCE FROM 2070/07/03 TO 2070/07/09, WEEK 43 ......................................... 25 

   

Page 4: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited ii

List of Figures 

Figure 1: Flooding at weir and intake ............................................................................................. 5 

Figure 2: Intake and gravel trap .................................................................................................... 7 

Figure 3: Flood during Dashain holiday ......................................................................................... 7 

Figure 4: Headworks progress, concreting at settling basin. ......................................................... 8 

Figure 5: Headworks settling basin area. ...................................................................................... 8 

Figure 6: Concreting at settling basin panel ................................................................................. 8 

Figure 7: Headrace culvert transition part/ beam with provision for grating arrangement. .......... 9 

Figure 8: Formwork placed at tunnel from inlet portal. ............................................................... 10 

Figure 9: Penstock installation ..................................................................................................... 11 

Figure 10: Power house progress, concreting at corbel. ............................................................. 12 

Figure 11: Work at corbel before and after Dashain ................................................................... 12 

Figure 12: Concreting on spiral casing area ................................................................................ 14 

Figure 13: Conductors at site warehouse and foundation of tower leg ....................................... 15 

Figure 14: Community building at Chisapani and access road to Chisapani under construction.

...................................................................................................................................................... 16 

Figure 15: Bio- Engineering in penstock section ........................................................................ 16 

Figure 16: Site visit by team of promoters. .................................................................................. 16 

Figure 17: Rosan and CDO family from Jhapa .......................................................................... 17 

Figure 18: Work progress chart ................................................................................................... 18 

List of Tables

Table 1: Cut-off wall, flood wall (u/s of weir) .................................................................................. 5 

Table2: Weir progress work ........................................................................................................... 6 

Table 3: Stilling basin work progress ............................................................................................. 6 

Table 4: Intake, under-sluice and inlet canal progress work ......................................................... 7 

Table 5: Approach culvert and settling basin work progress ......................................................... 9 

Table 6: Headrace culvert work progress .................................................................................... 10 

Table 7: Headrace Tunnel work progress ................................................................................... 11 

Table 8: Quantity records of penstock saddle support and anchor block ................................... 11 

Table 9: Quantity record of powerhouse ..................................................................................... 13 

Table 10: Status of transmission line ........................................................................................... 15 

Table 11: Work progress till October 2013 ................................................................................... 18 

Page 5: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 3

1. PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENTS The 22 MW installed capacity Mai Hydropower Project (MHP) is a run-of-river project located in Chisapani, Danabariand and Soyak Village Development Committees (VDCs) of Ilam district and utilizes the water from Mai Khola. The project comprises diversion weir with undersluice, intake arrangements followed by inlet canal, settling basin, headrace culvert, headrace tunnel, surge-shaft followed by penstock pipe and powerhouse followed by tailrace canal. The generated power is evacuated through 132 kV transmission lines of 10.6 km and connected with the Integrated Nepal Power System (INPS) at Nepal Electricity Authority (NEA)’s proposed Godak substation in Ilam district. The project’s headworks site can be reached from East-West Highway at Birtamode of Jhapa district via a 25 km road of which 9 km is black topped and rest is earthen/gravel type. A project road of 5 km length has been constructed to connect the headworks with the powerhouse.

The Employer/Owner: Sanima Mai Hydropower Ltd. (SMHL)

The Engineer/Consultant: Sanima Hydro and Engineering (P.) Ltd. (SHE)

The Contractor (Civil Construction):Himal Hydro and General Construction Limited, Kathmandu, Nepal

The Contractor (Hydro-Mechanical):Structo- Udeco JV

The Contractor (Generating Equipment): Asia Pacific Power Tech.

The Contractor (Power evacuation line): Aster Tele Service Nepal Pvt. Ltd.

2. KEY DATES PPA signed on 8th Baishakh 2067 (21st April 2010),

Generation License obtained on 13thBhadra 2067 (29th Aug 2010) (valid till 28th Aug 2045),

Main Civil Construction Contract awarded to Himal Hydro and General Construction Limited on 3rdOctober 2010 with a target completion date of 18thMay 2014 (Required Commercial Operation Date as per PPA is ~14thJuly 2014, i.e. end Ashad 2071),

Facility Agreement (Financial Closing) signed on 18th November 2010 (2ndMangsir 2067).

Up-gradation of project capacity to 22 MW on 6th July 2012 (22ndAsar 2069).

3. CONTRACT PACKAGES AND IMPLEMENTATION

Main Civil construction works: Civil Contractor CONTRACT Package 1

Hydro-mechanical and Penstock: HM Contractor CONTRACT Package 2

Equipment (Electromechanical):EM Supplier CONTRACT Package 3

Power evacuation Transmission: TL Contractor CONTRACT Package 4

Preparatory works, Owner’s housing, Socio-environmental: Employer Direct

4. FINANCING Equity: Promoters (SMHL) 25% of the total Project Cost

Debt: Consortium of Local Banks 75% of the total Project Cost: Lead-Laxmi Bank, Co-lead- Nabil Bank, Members: Kumar iBank, Bank of Kathmandu, Siddhartha Bank, Machapuchchhre Bank, Janata Bank Nepal, NIC Asia Bank,Grand Bank, Nepal SBI Bank, Ace Development Bank.

Page 6: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 4

5. RESOURCES AT SITE EMPLOYER:

Description Number Resident Engineer 1 Electrical engineer 1 Mechanical Engineer 1 Site Engineer 6 Engineering Geologist 1 Admin/Account 2 Sub-Engineer(Overseer) 6 Surveyor 1 Social and Environment Unit 4 Site supervisor 8 Driver 2 Office boy 4Cook 4

Total: 41

CIVIL CONTRACTOR: Human resources:

Description Number Admin/ finance 38 Contract /HSE 4 Store 28 Civil 241 Electrical 11 Electromechanical 85 Security 29 Total: 435

HYDROMECHANICAL CONTRACTOR: Human resources:

Description Number Site In-charge 1 Electrician 1 Surveyor 1 Welding Inspector 1 Store In-charge 2 Rolling Operator 1 Welder 6 Fitter 6 Gas cutter 2 Helper 10 Painter 3 Mechanical Supervisor 4

Total: 38 # For equipments detail in Mai HP, please refer the attached sheet at the end section of report

Page 7: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 5

6. CIVIL CONSTRUCTION PROGRESS AT SITE 6.1 HEADWORKS 6.1.1 CUTOFF WALL, FLOOD WALL U/S OF WEIR

• No work has been done on this section due to flood pond.

Table 1: Cut-off wall, flood wall (u/s of weir)

S No Description of works Unit Quantity

Previous month

This month Total Remark

1 Earthwork m3 1.1

Excavation work in boulder and gravel mixed soil with lead up to 50 m

2612 - 2612

2 Concrete Work m3 2.1 Placing of 75 mm thick C15

blinding concrete 53.25 - 53.25

2.2 Placing of C25 concrete 653.36 - 653.36

2.3 Placing of C25 plum concrete 137.556 - 137.556

2.4 Placing of C15 plum concrete 130.78 130.78 3 Formwork m2 1326.664 1326.664 4 Rebar ton 32.04 - 32.04

6.1.2 WEIR BODY AND GUIDE WALL

• There is no work at weir section after flood of 16thJestha 2070.

Figure 1: Flooding at weir and intake

 

Page 8: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 6

Table2: Weir progress work

S.No. Description of Work Unit Quantity

Remark Previous month

This Month Total

1 Earthwork m³            

1.1 Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 3502.73 - 3502.73   

2 Concrete Work m3         

2.1 Placing of 75 mm thick C15 blinding concrete m³ 127.145 - 127.145   

2.2 Placing of C25 concrete m³ 5035.827 - 5035.827   

2.3 Placing of C35 concrete m³ 214.56 - 214.56  

2.4 Placing of C25 Plum m³ 1269.76 - 1269.76  

3 Formwork m2 2633.947 - 2633.947   4 Reinforcement ton 93.398 - 93.398

6.1.3 STILLING BASIN AND FLOODWALL (D/S OF WEIR)

• There is not any progress at this area after flooding. Table 3: Stilling basin work progress

S.No. Description Unit Quantity

Remarks Previous month

This Month Total

1 Earthwork            1.1 Excavation work in boulder

and gravel mixed soil with lead upto 50 m

m³ 13,780.94 - 13,780.94   

2 Concrete Work   

2.1 Placing of 75 mm thick C15 blinding concrete m³ 275.183 - 275.183   

2.2 Placing of C25 concrete m³ 1660.71 - 1660.71   2.3 C25 Plum Concrete m³ 2890.116 - 2890.116   

3 Formwork m2 4703.15 - 4703.15   

4 Reinforcement ton 99.493 - 99.493   

Page 9: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 7

6.1.4 INTAKE, UNDERSLUICE AND INLET CANAL

• Concreting on intake piers up to level of hosting slab is completed. • Frame installation by Structo is continuing. • No major work has been performed this month.

Figure 2: Intake and gravel trap Figure 3: Flood during Dashain holiday Table 4: Intake, under-sluice and inlet canal progress work

S.No. Description of Work Unit

Quantity

Remarks Previous month

This Month Total

1 Earthwork            

1.1 Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 9120.96 - 9120.96   

2 Concrete Work         2.1 Placing of 75 mm thick C15

blinding concrete m³ 152.73 - 152.73   

2.2 C25 (40%) Plum concrete 254.521 - 254.521 New item

2.3 Placing of C25 concrete m³ 4638.49 - 4638.49   

3 Formwork m2 6176.65 - 6,176.65   4 Reinforcement ton 250.78 - 250.78   

Page 10: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 8

6.1.5 APPROACH CULVERT, SETTLING BASIN AND FLUSHING CULVERT

Figure 4: Headworks progress, concreting at settling basin. Following works have been done on settling basin area:

• Earthwork Excavation/Backfilling works in settling basin panel-03, panel -02 and panel-01 is ongoing.

• Settling basin base slab concreting up to wall kicker level has been completed on panel 09, 08, 06, 05 and 04 being panel 04 done on this month.

• Base slab concreting on panel 07 is ongoing. • Intermediate flushing pipe provision made on panel 04 and 07.

Figure 5: Headworks settling basin area. Figure 6: Concreting at settling basin panel

Page 11: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 9

Table 5: Approach culvert and settling basin work progress

S.No. Description of Work Unit Quantity

Remarks Previous month

This Month Total

1 Earthwork            

1.1 Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 2449.57 - 2449.57   

1.2 Compacted backfill m³ 4355 - 4355  

2 Concrete Work   

2.1 Placing of 75 mm thick C15 blinding concrete m³ 401.909 -   

2.2 Placing of C25 concrete m³ 2374.316 360.78 2735.096   

2.3 C25 plum concrete m³ 390.128 - 390.128 3 Formwork m2 1756.556 149.82 1906.386   

4 Reinforcement ton 180.552 24.05 204.602   

6.1.6 HEADRACE CULVERT

Figure 7: Headrace culvert transition part/ beam with provision for grating arrangement.

• Work has completed from Ch. 0+038 to Ch. 1+020 in HRC • No major work is done on this section this month. • Civil contractor is planning to proceed on with work on SB-HRC transition for the next month.

Page 12: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 10

Table 6: Headrace culvert work progress

S.No. Description of Work Unit

Quantity

Remarks Previous month

This Month Total

1 Earthwork            

1.1 Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 39,656.98 - 39,656.98   

2 Concrete Work   

2.1 Placing of 75 mm thick C15 blinding concrete m³ 308.225 - 308.225   

2.2 Placing of C25 concrete m³ 4608.46 - 4608.46   

2.3 C35 Concrete m³ 69.3 - 69.3 New item

3 Formwork m2 18349.73 - 18349.73   

4 Reinforcement ton 458.5 - 458.25   

6.2 HEADRACE TUNNEL

Figure 8: Formwork placed at tunnel from inlet portal.

• Invert lining has been completed (2197m, i.e. 99.5%) ( From Ch 0+000 to 2+197) • Wall and crown lining using steel and wooden formwork, 456m out 1356m, i.e. 34% is

completed . • 90m long concrete wall of height 2.05m (spring level) has been completed using wooden

forms. • Similarly 844m of 1 meter concreting has been completed till date. • 1 meter lining has been done at all niches. • Ladder installation and roof truss installations are completed surge shaft.

Page 13: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 11

Table 7: Headrace Tunnel work progress

S.No. Description of Work Unit

Quantity

Remarks Previous month

This Month Total

1 Invert lining length m 2197 - 2197

2 Length of lining in crown and wall m 408 48 456

 

3 Concreting on wall (Spring level) m 90 0 90

 4 Length of 1m wall only m 780 64 844

5 Placing of C25 concrete m³ 3863.6 212.8 4076.4   

6 Formwork m2 5359.064 596.096 5955.16

7 Reinforcement ton 161.207 6.468 167.675   

6.3 PENSTOCK, SADDLE SUPPORT AND ANCHOR BLOCK

• Transportation, placing and tagging of 100m long penstock pipe have been completed.

Figure 9: Penstock installation Table 8: Quantity records of penstock saddle support and anchor block

Description of Work Unit

Quantity

Remarks Previous month

This Month Total

Earthwork            

Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 13668 - 13668   

Concrete Work m³   

Placing of 75 mm thick C15 blinding concrete    106.547 0.113 106.66   

Placing of C25 concrete    413.794 - 413.794   

Placing of C25 Plum Concrete 1197.61 - 1197.61

Rebar Ton 43.225 - 43.225   

Page 14: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 12

Description of Work Unit Quantity Remarks Formwork m2 950.178 - 950.178   

1:4 Stone masonry work m3 401.61 - 401.61 6.4 POWERHOUSE Major works done on powerhouse during this month are as follows:

• Concreting at corbel beam of Bay 3 and Bay 4. • Concreting at bay 2 generator casing.

Figure 10: Power house progress, concreting at corbel.

Figure 11: Work at corbel before and after Dashain

Page 15: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 13

Table 9: Quantity record of powerhouse

Description of Work Unit Quantity

Remark Previous month

This Month Total

Earthwork            Excavation work in boulder and gravel mixed soil with lead up to 50 m

m³ 12,914.7 - 12,914.7   

Hard rock excavation m³ 1424.96 - 1424.96

Concrete Work m³   

Placing of 75 mm thick C15 blinding concrete m³ 103.443 - 103.443   

Placing of C25 concrete m³ 3768.497 68.925 3837.422   Placing of C15 plum (40%) concrete 155.807 - 155.807

 Formwork m2 6337.458 42.562 6380.02   

Reinforcement ton 363.663 11.901 375.564   

7. HYDROMECHANICAL PROGRESS

Page 16: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 14

Key works executed:

• Transportation, placing & tagging of 100m long penstock pipe at upstream of AB04 has been completed along with one bend and expansion joint, work is undergoing at bend and expansion joint.

8. ELECTROMECHANICAL PROGRESS

Figure 12: Concreting on spiral casing area

Key works executed are as follows:

• EM work 20% completed • Crane rail fixing completed at tailrace side. • Rail bolt fixing completed at all bays, grouting is undergoing.

Page 17: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 15

9. POWER EVACUATION LINE • The contractor Aster Tele Service Nepal Pvt. Ltd. was mobilized at site & started the work

from excavation of foundation trench.

Figure 13: Conductors at site warehouse and foundation of tower leg Table 10: Status of transmission line

S/NO Tower No

Tower Type

Soil Type

Foundation Status Remarks

Open Running Closed1 2 B+0 Normal

2 3 B+3 Soft Rock

3 7 DM+3 Soft Rock

4 8 B-3 Normal 5 9 B+0 Normal 6 10 C+0 Normal 7 17 C-3 Normal 8 18 C+12 Normal 9 24 DM+0 Normal 1 Leg Pending Due to 11kv line

10 25 B+0 Soft Rock

11 26 B-3 Normal

12 27 C+0 Soft Rock Pending due to rock.

13 28 C+3 Normal 14 31 DM+0 Normal

15 32 C-3 Soft Rock 2 pit completed.

16 33 DM+3 Normal 17 34 B+6 Normal 18 35 DM-3 Normal 1 Leg Pending Due to LT line

10. EIA PROGRESS

• Routine monitoring and maintenance of access road around project area is going on.

Page 18: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 16

Figure 14: Community building at Chisapani and access road to Chisapani under construction.

Figure 15: Bio- Engineering in penstock section 11. VISITORS OF THE MONTH

• Promoter team visited site on 18th of Ashoj, 2070.

Figure 16: Site visit by team of promoters.

Page 19: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 17

Figure 17: Rosan and CDO family from Jhapa 12. NOTES

• Site was closed form 19th of Ashoj to 2nd of Kartik for Dasain Holiday and resumed from 3rd of Kartik 2070(about 2 weeks working days before Tihar)

• HH, the civil contractor will continue with work during Tihar beside festival days in Headworks and tunnel part.

• Good progress observed at Tunnel site. 1 meter lining is completed. Full lining is 34% completed. 4 set of formworks have arrived at site. Three set of formworks have been used inside the Tunnel.

• 45% foundation work has been completed for project transmission line from Muse to Godak. • Good progress at Headworks settling basin slope slab, backfilling and stone masonry

ongoing at settling basin area. • Corbel concrete completed at all bay. • Mai cascade and NEA transmission line are in critical stage for timely commissioning of

project. • Abutment for river crossing at muse, PH is under construction. • Moderate rain is observed during evening time for 2/3 days. • Minor flood during Dashain time has been observed.

Page 20: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 18

13. WORK PROGRESS AT SITE Work progress in site has been calculated with reference to various items as per their quantity used. Table 11: Work progress till October 2013

Description Unit Revised

BOQVolume

completed%

completed%

Remaining ReferenceCu-toff wall, flood wall(weir u/s) m3 660 653.36 99% 1% C25 Intake and undersluice m3 4933 4638.49 94% 6% C25 Weir body and guide wall m3 7072 6305.587 89% 11% C25+C25P Stilling basin, flood wall (weir d/s) m3 6075.5 4550.826 75% 25% C25+C25P Approach culvert/ settling basin/flushing culvert m3 5475.43 2735.096 50% 50% C25 Headrace culvert m3 4989.6 4608.46 93% 7% C25

Headrace tunnel m3 7197.8 4076.4 57% 43% C25 concrete

Surge shaft m3 321 321 100% 0% C25, Concrete

Penstock alignment m3 3922.6 1611.632 42% 58% C25+C25P Powerhouse m3 4953.57 3837.422 78% 22% C25 Tailrace m3 1326.774 1326.774 100% 0 C25

Figure 18: Work progress chart

0%10%20%30%40%50%60%70%80%90%

100%

Work progress till October 

% completed % remaining

Page 21: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 19

14. PHOTOS

Concreting at spiral casing, PH

Substation under construction at Godak

Page 22: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 20

River Deposit at upstream of weir, Headworks

Transmission line tower layout at tea garden

Page 23: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 21

Surge shaft roofing

Staff quarter at powerhouse

Page 24: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 22

Abutment for Muse Khola crossing at powerhouse

Camp area powerhouse site

Page 25: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 23

15. EQUIPMENTS OF CIVIL CONTRACTOR AT SITE

Page 26: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 24

Page 27: Narayanchour, Naxal, G. P.O.Box. 19737 Kathmandu, Nepal ...

Mai Hydropower Project Progress Report October, 2013

Sanima Mai Hydropower Limited 25

16. STOCK BALANCE FROM 2070/07/03 TO 2070/07/09, WEEK 43