NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet...
-
Upload
sara-miller -
Category
Documents
-
view
212 -
download
0
Transcript of NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet...
![Page 1: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/1.jpg)
NAESB “Strawman”
January 24-25, 2004
![Page 2: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/2.jpg)
2
Problem Statement
Enough generators must have fuel to meet peak load
New England Cold Snap crisis heightened interest in Energy Day issue
Chairman Wood’s letter to NAESB asks for better gas-electric communication and coordination
![Page 3: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/3.jpg)
3
New England Cold Snap Crisis
Key causes:1
Weather-related generation outages Fuel-related outages:
ISO-NE depends heavily (30%) on gas-only generation
Bid mitigation/caps
Economic outages
Bidding/settlement timelines
ISO-NE response includes: Generator run hours released early during cold
weather but existing market timelines not modified
1. Source: Final Report on Electricity Supply Conditions in New England During the January 14 - 16, 2004 “Cold Snap”
Market rules under stress
![Page 4: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/4.jpg)
4
NAESB Requests
Keyspan/Duke (R04016) Change gas pipeline and electric day-ahead
“operating day” start/end to midnight central time Does not revise bidding and settlement timelines
TVA (R04020) Standardize electric scheduling and timelines
Natural Gas Pipeline (R04021) Develop daily communication protocols between
pipelines and generators
![Page 5: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/5.jpg)
5
Energy Day Standardization
The requests do not address the root cause of the New England Crisis: lack of fuel diversity/security
A net benefit may not result from R04016 or R04020: Administrative cost impacts have not been quantified External costs (e.g, impacts on financial products) not
known Benefits have not been quantified
Many entities will only experience new costs Gas LDCs, electric distributors, gas pipelines and producers Regulated companies may not be able to recover costs
![Page 6: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/6.jpg)
6
Energy Day Standardization
Separate electric market timelines were established for a reason: Accommodate different system peaks Facilitate efficient interchange
![Page 7: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/7.jpg)
7
A Better Approach
Plan for adequate fuel diversity and security Dual fuel, non-gas generation Protect against regional or national fuel problems
Assure that alternative fuel units can/will be used when needed – e.g., Assure automatic fuel switching in some cases Maintain sufficient back-up fuel on-site
Address electric market rule issues locally
![Page 8: NAESB Strawman January 24-25, 2004. 2 Problem Statement Enough generators must have fuel to meet peak load New England Cold Snap crisis heightened interest.](https://reader036.fdocuments.us/reader036/viewer/2022082917/5514cca1550346b0478b4d48/html5/thumbnails/8.jpg)
8
Conclusions
Approve R04021 to respond to immediate concerns Create fuel diversity/security standards
Provide guidance to ad hoc working groups and task forces
Address fuel diversity mostly through electric markets Options include:
Capacity market rules Interconnection requirements Reliability rules (e.g., NYC loss of gas supply rule, testing) Regulatory barriers (e.g., emissions restrictions)
NAESB role?