Fighting for Survival: USS Yorktown (CV5) Damage Control ...
Mylars to Models: Managing Legacy Data Migration · Mylars to Models: Managing Legacy Data...
Transcript of Mylars to Models: Managing Legacy Data Migration · Mylars to Models: Managing Legacy Data...
Mylars to Models: Managing Legacy Data Migration
Charles LeeIntegrated Product LeadBoeing IDS Rotorcraft
Mylar Drawings
2D CV4
3D CV4
Engineering Service Center
ENOVIA Load3D CV5
3D CV5 in
ENOVIA
High Level Process Flow for Converting Legacy Data to CV5
Work Package: 1300 Unique Detail Parts
Total Conversion Summary by ComplexityV4-V5 Pilot Conversion
Total Converted Parts Count (1175) Distribution Summary by Complexity
36
50
4
121
291
19
283
341
30
0 100 200 300 400 500 600 700 800
MBD
Mylar
Red. Dim
Complex Medium Simple
Total Conversion Summary by ComplexityV4-V5 Pilot Conversion Total Converted Parts (1175)
Percentage Distribution Summary by Complexity
3.1%
4.3%
0.3%
10.3%
24.8%
1.6%
24.1%
29.0%
2.6%
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0%
MBD
Mylar
Red. Dim
Complex Medium Simple
Total Conversion Summary by Complexity
V4-V5 Pilot Conversion Total Converted Parts (1175)
Average Hours Summary by Complexity
24.0
39.2
17.6
10.3
19.2
11.1
4.1
12.0
7.6
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0
MBD
Mylar
Red. Dim
Complex Medium Simple
•Greater IPT involvement in SOW development•Highly detailed SOW
Off-site Execution
Supplier Setup
Lessons Learned
Daily Activity
On-site Execution
Verification
Close Out
•Provide loft models, key interface points, etc. to allow Supplier to model detail parts in context.
•Provide onsite representative at supplier to resolve engineering, drafting and modeling problems real time.
•Use a large digitizer to accurately transfer key geometry into the CAD program or have the drawings scanned on a high resolution scanner.
•Provide easily accessible metadata•Need tailored training similar to supplier symposium for Engineering Service Centers
Lessons Learned
Off-site Execution
Supplier Setup
Daily Activity
On-site Execution
Verification
Close Out
•Define performance metrics earlier
Lessons Learned
Off-site Execution
Supplier Setup
Daily Activity
On-site Execution
Verification
Close Out
•Verify all required hardware, software, and account access are functional (1) week prior to supplier’s arrival
Lessons Learned
Off-site Execution
Supplier Setup
Daily Activity
On-site Execution
Verification
Close Out
•Include line items in the quality checklist for geometry errors. These items should then be weighted for determining severity and therefore supplier performance.
•Use graphic art software which allows layering and overlaying raster and vector data to virtually check Mylar defined parts. Screen shots of this comparison can be used for feedback to the supplier for corrections.
•Too many modelers and only one checker. More checkers are needed.
Lessons Learned
Off-site Execution
Supplier Setup
Daily Activity
On-site Execution
Verification
Close Out
•Document process developed•Track lessons learned on weekly basis
Lessons Learned
Off-site Execution
Supplier Setup
Daily Activity
On-site Execution
Verification
Close Out
Quality Summary
• Re‐mastered PCM (Mylar) part Overlay
• Re‐mastered Dimensioned part CADIQ and manual inspection of dimensions
• Model Based Definition (Automated Conversion) CADIQ plus manual comparison of FD&T
• All datasets checked for proper database format per SOW Checklist
Typical Errors
The original V4 part thickness is .032”. The V5 converted part thickness is .061”.
• PCM (Mylar) part
• Dimensioned part
Typical Errors
Was Is Should Be
Typical Errors• Model Based Definition (Automated Conversion)
Conclusion
• Re‐engineer not Re‐master
• Program Support = Program Buy‐in
QUESTIONS