Transcript of My Resume PlannerScheduler
![Page 1: My Resume PlannerScheduler](https://reader035.fdocuments.us/reader035/viewer/2022081807/577cdcc71a28ab9e78ab6281/html5/thumbnails/1.jpg)
7/28/2019 My Resume PlannerScheduler
http://slidepdf.com/reader/full/my-resume-plannerscheduler 1/5
Shakil Memon (MBA, B.Eng.)Eligible to Sit in PMP examEligible for APEGA Registration
Objective:
Looking for a long term career as a Project Planner/Scheduler.
Executive Summary:-
14+ years of professional engineering experience in various engineering EPC projects such as Greater Karachi Water &
supply scheme, Hydropower projects, oil & gas, building & Construction Projects. Project Control Lead experience in oil & gas Projects, area development, construction and maintenance of roads, building
and pumping stations, earth filling work, pipe laying, planning and scheduling of various engineering activities onPRIMAVERA PROJECT PLANNER ( P3 To P6).
Have a recognized ability to successfully assume responsibility on multi-billion dollar projects from estimating; costing andallotting funds appropriately, budgeting for sub-contractors, labour & equipment and materials, planning scheduling;execution to completion of the projects
Highly self-motivated with a natural, recognized ability to overcome challenges; apply past experience and assume newresponsibilities with minimum supervision
Well organized and systematic: function productively while under high pressure situations; set sights on the goal aheadand complete assignments on schedule without diminishing quality
Possess strong leadership, interpersonal and communication skills
Prepared to put my knowledge and attributes to the test and prove to be a punctual, innovative, cooperative and valuable
employee Professional engineer with experience in area development, construction and maintenance of roads, building and
pumping stations, earth filling work, pipe laying, planning and scheduling of various engineering activities onPRIMAVERA PROJECT PLANNER.
PROFESSIONAL SUMMARY:-
Successful completion of different EPC & Oil & gas Projects as a Project Planner/Scheduler Lead in different diversifiedenvironment and culture setup.
Extensive experience in controls, management, cost engineering, scheduling, estimating and industrial engineering.Proven skills in communicating and establishing working relationships with all levels of management, both client andinternal, and with multi-discipline crafts.
Able to monitor, update and successfully meet construction schedule and finish at budget or under budget. Skills in project budgeting and cost analysis with excellent background in estimating.
Capable of sequencing work to maintain existing operations.
Experience in bidding and contracting construction work.
Implementation experience includes Business Requirement analysis, mapping client's business process to SAPprocesses, GAP analysis, Configuration, Re-engineering, Prototyping, Testing, Training, Documentation and Post Go-Live Support.
Flexible and versatile to adapt to any new environment. Well passionate about the work performs and works just aseffectively either as part of a team or independently. Capable to handle multi-tasks, has lead experience in Offshore-Onsite delivery model environment with good communication and interpersonal skills and able to coordinate activities.
TRAININGS AND CERTIFICATION DETAIL:
MS Project & Primavera Project Planner and recently completed 45 PDU hrs. (PMP).
SAP R/3, SAP Project System, SAP Plant Maintenance and SAP Reporting ( SAP Certified Associate Consultant)
MS Word, MS Excel and AutoCAD R-15.
Professional Experience & Project Engagement Details:-
Planner/Scheduler (SaskPower) Boundary Dam Project Budget 50 Million USD August 2012 to March 2013
Managed Construction & supervised the whole area.
Prepared, Plan/schedule and control various Project control & monitoring activities on primavera project planner and onSAP Plant maintenance e.g. creating Maintenance plant, task list, assign task to crew member, managing SAP workorder management module etc.
Hands on complete PM business Cycle Reliability Maintenance, turnaround, shutdown to Breakdown Maintenance etc. Configured and maintain project overheads (actual and planning).
Shakil A Memon, Phone :( 403) 771-6519, (403)-475-5598 [email protected] 1
![Page 2: My Resume PlannerScheduler](https://reader035.fdocuments.us/reader035/viewer/2022081807/577cdcc71a28ab9e78ab6281/html5/thumbnails/2.jpg)
7/28/2019 My Resume PlannerScheduler
http://slidepdf.com/reader/full/my-resume-plannerscheduler 2/5
Configured and maintain PM Order types (e.g. Preventative Maintenance, Corrective Maintenance.
Maintain different types of SAP PM Planner group in SAP System and trained the Engineers, Tradesman
Configured and maintain different types of Technical Objects e.g. equipment hierarchy, BOM, Asset Master etc.
Configured and maintain Work Center types
Configured and maintain Different types of Notification, permit, issue permit and coordinate with journeyman etc.
Configured and maintain functional location and equipment Hierarchy
Workout the resource charts on primavera project planner and give timely feedback to the management.
Prepared, planned and scheduled various engineering activities on primavera project planner specific to roads, buildingand water supply schemes.
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings
Analyzed various planning and scheduling reports and give timely feedback.
Workout the resource charts on primavera project planner and give timely feedback to the management.
Calculate total workforce required to complete a single task.
Supervise and execute various civil works involving mass concrete.
Tracked and validated all billing related activities of subcontractor.
Prepared and conduct rate analysis and quantity analysis as per project requirement
Planner/Scheduler Lead (Qatar Petroleum, Qatar) Project Budget 100 Million USD Jan 2012 to July 2012
Responsible for budgeting, estimating, allotment of funds, monitor progress of home office costs, and effectively reportingthe results to management and client
Prepared, Plan/schedule and control various Project control & monitoring activities on primavera project planner.
Workout the resource charts on primavera project planner and give timely feedback to the management. Analyzed various planning and scheduling reports and give timely feedback.
Hands on complete PM business Cycle Reliability Maintenance, turnaround, shutdown to Breakdown Maintenance etc.
Configured and maintain project overheads (actual and planning).
Configured and maintain PM Order types (e.g. Preventative Maintenance, Corrective Maintenance.
Maintain different types of SAP PM Planner group in SAP System and trained the Engineers, Tradesman
Configured and maintain different types of Technical Objects e.g. equipment hierarchy, BOM, Asset Master etc.
Configured and maintain Work Center types
Configured and maintain Different types of Notification, permit, issue permit and coordinate with journeyman etc.
Configured and maintain functional location and equipment Hierarchy
Tracked & monitor progress of different engineering activities on different stages of the projects
supervised project demobilization prepared turn-over packages upon project completion
Developed and implemented the planning and cost tracking for various contracts & input of information into the clientowned system
Prepare and calculate Resources Histogram, and Cash Flows
Ensure the project follows the planning aspects, schedule of activities forecasts of cash flows (Bar chart & CPM)
Compare actual work with schedule progress and advice of any development threatening the delay of completion andrecommended any necessary actions to facilitate timely completion
Assessment of progress of work of the Contractors with the overall project Control Plan.
Performed daily unit cost analysis to identify the activities for profitability.
Project Planner/Scheduler (RAS GAS, Qatar) Project Budget 100 Million April 2011 to December 2011
Responsible for budgeting, estimating, allotment of funds, monitor progress of home office costs, and effectively reporting
the results to management and client Prepared, Plan/schedule and control various Project control & monitoring activities on primavera project planner.
Workout the resource charts on primavera project planner and give timely feedback to the management.
Analyzed various planning and scheduling reports and give timely feedback.
Tracked & monitor progress of different engineering activities on different stages of the projects
supervised project demobilization prepared turn-over packages upon project completion
Developed and implemented the planning and cost tracking for various contracts & input of information into the clientowned system
Prepare and calculate Resources Histogram, and Cash Flows.
Ensure the project follows the planning aspects, schedule of activities forecasts of cash flows (Bar chart & CPM)
Compare actual work with schedule progress and advice of any development threatening the delay of completion andrecommended any necessary actions to facilitate timely completion
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings
Shakil A Memon, Phone :( 403) 771-6519, (403)-475-5598 [email protected] 2
![Page 3: My Resume PlannerScheduler](https://reader035.fdocuments.us/reader035/viewer/2022081807/577cdcc71a28ab9e78ab6281/html5/thumbnails/3.jpg)
7/28/2019 My Resume PlannerScheduler
http://slidepdf.com/reader/full/my-resume-plannerscheduler 3/5
Assessment of progress of work of the Contractors with the overall project Control Plan.
Performed daily unit cost analysis to identify the activities for profitabilityProject Control Analyst (Worley parson) Calgary, Alberta Project Budget less than 100 Million Mar 2010 Mar 2011
Responsible for budgeting, estimating, allotment of funds, monitor progress of home office costs, and effectively reportingthe results to management and client Prepared, Plan/schedule and control various Project control & monitoring activities on primavera project planner.
Workout the resource charts on primavera project planner and give timely feedback to the management.
Analyzed various planning and scheduling reports and give timely feedback.
Tracked & monitor progress of different engineering activities on different stages of the projects
supervised project demobilization prepared turn-over packages upon project completion
Developed and implemented the planning and cost tracking for various contracts & input of information into the clientowned system
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings.
Prepare and calculate Resources Histogram, and Cash Flows.
Ensure the project follows the planning aspects, schedule of activities forecasts of cash flows (Bar chart & CPM)
Compare actual work with schedule progress and advice of any development threatening the delay of completion andrecommended any necessary actions to facilitate timely completion
Assessment of progress of work of the Contractors with the overall project Control Plan.
Performed daily unit cost analysis to identify the activities for profitability.
Project Control Analyst (ADNOC, United Arab Emirate) December 2008 Feb 2010
Responsible for budgeting, estimating, allotment of funds, monitor progress of home office costs, and effectively reportingthe results to management and client
Prepared, Plan/schedule and control various Project control & monitoring activities on primavera project planner.
Workout the resource charts on primavera project planner and give timely feedback to the management.
Analyzed various planning and scheduling reports and give timely feedback.
Hands on complete PM business Cycle Reliability Maintenance, turnaround, shutdown to Breakdown Maintenance etc.
Configured and maintain project overheads (actual and planning).
Configured and maintain PM Order types (e.g. Preventative Maintenance, Corrective Maintenance.
Maintain different types of SAP PM Planner group in SAP System and trained the Engineers, Tradesman
Configured and maintain different types of Technical Objects e.g. equipment hierarchy, BOM, Asset Master etc.
Configured and maintain Work Center types
Configured and maintain Different types of Notification, permit, issue permit and coordinate with journeyman etc.
Configured and maintain functional location and equipment Hierarchy
Tracked & monitor progress of different engineering activities on different stages of the projects
supervised project demobilization prepared turn-over packages upon project completion
Developed and implemented the planning and cost tracking for various contracts & input of information into the clientowned system
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings
Ensure the project follows the planning aspects, schedule of activities forecasts of cash flows (Bar chart & CPM)
Compare actual work with schedule progress and advice of any development threatening the delay of completion andrecommended any necessary actions to facilitate timely completion
Assessment of progress of work of the Contractors with the overall project Control Plan.
Performed daily unit cost analysis to identify the activities for profitability
Planning/Scheduling Engineer (ADNOC, United Arab Emirate) April 2006 to December 2007
Prepared technical documents and participates in tendering documentation process for the sublet of various engineeringphases.
Managed Construction of houses & supervised the whole area approximately 20000sqft.
Prepared, planned and scheduled various engineering activities on primavera project planner specific to roads, buildingand water supply schemes.
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings
Analyzed various planning and scheduling reports and give timely feedback.
Workout the resource charts on primavera project planner and give timely feedback to the management.
Calculate total workforce required to complete a single task.
Supervise and execute various civil works involving mass concrete.
Shakil A Memon, Phone :( 403) 771-6519, (403)-475-5598 [email protected] 3
![Page 4: My Resume PlannerScheduler](https://reader035.fdocuments.us/reader035/viewer/2022081807/577cdcc71a28ab9e78ab6281/html5/thumbnails/4.jpg)
7/28/2019 My Resume PlannerScheduler
http://slidepdf.com/reader/full/my-resume-plannerscheduler 4/5
Tracked and validated all billing related activities of subcontractor.
Prepared and conduct rate analysis and quantity analysis as per project requirement.
Planning Engineer (ACL Constructor United Arab Emirate) February 2005 to March 2006Role: Planning & Scheduling Engineer
Managed Construction of a around 100M US Dollars.
Supervised engineering team of 12.
Prepared technical specifications in liaison with client and project team.
Ensured quality of design documentation throughout the design process.
Prepared contract documents, review and evaluate tenders for constructions project
Produced design compliant with project strategies on planning, the environment, risk, safety and quality.
Advised on procurement, manufacture, assembly, construction techniques and sequencing of work as appropriate.
Prepared and schedule master project plan on primavera project planner.
Weekly updated master project plan and scheduled on primavera project planner.
Give timely report on critical/overload resources on the basis of master scheduled.
Give timely reports on critical activities and milestones.
Workout master project plan if it deviate from the original plan
Compare target v/s actual project plan on primavera project plan
Prepared and submit weekly and monthly reports to the client and senior management.
Project Control Lead NUROL CONSTRUCTION (ABU DHABI-UAE)) July 2003 January2005Role: Project Control Analyst.
Responsible for overall project management from conception to completion.
Develop, implement and update programs of works based on critical path of network.
Analyze and monitor the cost of running projects on daily, weekly and monthly basis to complete the job in time withallocated budget.
Prepare and Update shop drawings, material procurement and subcontractors logs and the sub-contractors workingprograms.
Liaise with Project Manager for the progress reporting and monitoring of all time, resources/cost and attending theprogress meetings.
Highlight Time Impacts/Problems and prepare Programs for Time Extension Claims.
On the directions of project Control manager update/changed/enter the master project scheduled
With the help of project manager prepared, gathered important related information for timely completion of projects.
Procedures review and revisions if required in conjunction with project manager. Coordination and preparation of project closed out reports
Preparation, development and review of project quality plans.
Supervised and coordinate multiple contractors at sites.
Review and agree project measurement, cost assessments and monthly valuations.
Assistant Civil Engineer (Dong Fong Electric Corporation United Arab Emirate) April 2002 to June 2003Role: Embankment Engineer
Supervised the earth filling related work at various embankment sections
Supervised the compaction test on various embankment sections
Deals with various important earth filling materials required for a embankment
Study designs of various embankment sections.
Supervised and coordinate multiple contractors at sites.
Review and agree project measurement, cost assessments and monthly valuations.Graduated Civil Engineer (Karachi Water & Sewerage Board) March 1997 to March 2002Role: Site Supervisor (Civil Engineer)
Constructions of 100mgd pump house, roads and office block.
Construction and lying of 4km (1500mm dia) steel rising main.
Construction of storm water drain and sewer installations.
Involved in Heavy reinforced concrete while supervising the construction of reservoir.
Supervised the hydrostatic pressure testing of pipes.
Supervised the dewatering at various sections.
Supervised the workforce and applied all safety measures at site.
Supervised, arranged and look after all temporary residencies to workforce.
Shakil A Memon, Phone :( 403) 771-6519, (403)-475-5598 [email protected] 4
![Page 5: My Resume PlannerScheduler](https://reader035.fdocuments.us/reader035/viewer/2022081807/577cdcc71a28ab9e78ab6281/html5/thumbnails/5.jpg)
7/28/2019 My Resume PlannerScheduler
http://slidepdf.com/reader/full/my-resume-plannerscheduler 5/5
Supervised and coordinate multiple contractors at sites.
Review and agree project measurement, cost assessments and monthly valuations.
EDUCATIONS AND TRAININGS:
• B.Sc. (Civil Engineering) 1998
NED University of engineering and technology, Karachi, Pakistan.
• Master of Business Administration 2002
Specialization in Management of information system/ Marketing Karachi University, Pakistan.
• SAP Certified SD Consultant 2007
Siemens Learning Center Karachi, Pakistan.• Oracle 9i 2002
Center of Continuing Education NED, Karachi, Pakistan.
• Primavera Project Planner 2000
Information Technology 2000, Karachi, Pakistan
Shakil A Memon, Phone :( 403) 771-6519, (403)-475-5598 [email protected] 5