MWH Environmental Quantitative Risk Assessment (EQRA)

2
www.mwhglobal.com Planning & Environmental Permitting Environmental Quantitative Risk Assessment (EQRA) Facilities falling under the Environmental Permitting regime in the UK are required to prevent, reduce and eliminate pollution by prioritising efforts on the most significant industrial and agricultural activities. To gain an Environmental Permit, Operators will have to show that they have systematically developed proposals to apply the sector specific Best Available Techniques (BAT) and meet certain other requirements, taking account of relevant local factors The continuing use of underground or partially underground vessels or pipework without secondary containment can be an obstacle to obtaining a Permit as they do not reflect sector specific BAT standards due to the inability to undertake a regular inspection and maintenance programme. However, the replacement of existing assets with above-ground structures, for example, double-skinned vessels with leakage detection, can be economically challenging when the replacement costs outweigh the environmental benefits . However, such departures from BAT can be justified at the installation level by taking into account the technical characteristics of the installation concerned, its geographical location and the local environmental conditions. The Environmental Quantitative Risk Assessment (EQRA) has been developed to provide such justification and can be equally applied to both new and existing assets. It works by assessing the source-pathway-receptor linkage of specific assets and identifies those assets with potential to cause harm to controlled waters through fugitive emissions. The source-pathway-receptor linkage model is commonly used as the basis for risk assessment methodologies with respect to environmental releases, particularly for contaminated land analysis. The theory dictates that for harm to occur there must be a pollutant linkage. Such a linkage is deemed to exist if there is a potential contaminative source present, a receptor sensitive to that contamination and a pathway that would allow the contamination to pass between the two. Where at least one of these three elements is not present, no harm can occur. The Environmental Quantitative Risk Assessment (EQRA) assesses this pathway in a manner which is repeatable, robust, transparent and acceptable to the Environment Agency. e Environmental Quantitative Risk Assessment has been developed to justify departures from the indicative Best Available Techniques standards for both new and existing assets.

description

The Environmental Quantitative Risk Assessment has been developed to justify departures from the indicative Best Available Techniques standards for both new and existing assets.

Transcript of MWH Environmental Quantitative Risk Assessment (EQRA)

www.mwhglobal.com

Planning & Environmental Permitting

Environmental Quantitative Risk Assessment (EQRA)

Facilities falling under the Environmental Permitting regime in

the UK are required to prevent, reduce and eliminate pollution

by prioritising efforts on the most significant industrial and

agricultural activities. To gain an Environmental Permit,

Operators will have to show that they have systematically

developed proposals to apply the sector specific Best

Available Techniques (BAT) and meet certain other

requirements, taking account of relevant local factors

The continuing use of underground or partially underground

vessels or pipework without secondary containment can be

an obstacle to obtaining a Permit as they do not reflect sector

specific BAT standards due to the inability to undertake a

regular inspection and maintenance programme. However, the

replacement of existing assets with above-ground structures,

for example, double-skinned vessels with leakage detection,

can be economically challenging when the replacement costs

outweigh the environmental benefits .

However, such departures from BAT can be justified at

the installation level by taking into account the technical

characteristics of the installation concerned, its geographical

location and the local environmental conditions.

The Environmental Quantitative Risk Assessment (EQRA)

has been developed to provide such justification and can be

equally applied to both new and existing assets. It works by

assessing the source-pathway-receptor linkage of specific

assets and identifies those assets with potential to cause harm

to controlled waters through fugitive emissions.

The source-pathway-receptor linkage model is commonly

used as the basis for risk assessment methodologies

with respect to environmental releases, particularly for

contaminated land analysis.

The theory dictates that for harm to occur there must be a

pollutant linkage. Such a linkage is deemed to exist if there is

a potential contaminative source present, a receptor sensitive

to that contamination and a pathway that would allow the

contamination to pass between the two. Where at least one of

these three elements is not present, no harm can occur.

The Environmental Quantitative Risk Assessment (EQRA)

assesses this pathway in a manner which is repeatable,

robust, transparent and acceptable to the Environment

Agency.

The Environmental Quantitative Risk Assessment has been developed to justify departures from the indicative Best Available Techniques standards for both new and existing assets.

0813

- E

QR

A-0

413

Nick GillEnvironmental Consultant

t: + 44 (0)1925 845219

e: [email protected]

The EQRA approach is based on a two-stage assessment

process comprising preliminary screening followed by a

detailed EQRA for appropriate assets.

Each asset is screened to determine whether the existing

infrastructure materially complies with the requirements

of BAT. Where this is the case, in line with the EA’s

guidance, fugitive surface and groundwater emissions from

infrastructure should not occur during normal operations.

Consequently it is considered that no further assessment of

the assets is required.

Remaining assets are then subject to a quantitative risk

ranking to determine priorities for further action.

The assessment has been developed based upon a

numerical system that assigns scores according to the

perceived likelihood of fugitive emissions causing harm to

controlled waters. This final risk rating score is a function of

the likelihood of the asset to leak, the potential severity of

that leak should it occur, the readiness that any pathways

present would transmit contaminants and the sensitivity

of receptors that may be impacted upon. Assets are then

banded based upon this total score (or any component of it)

into Band A, Band B or Band C.

The absence of a source-pathway-receptor linkage is

demonstrated by a score of 0 in the relevant section. This

means that the model generates a final asset ‘Risk of Harm’

of 0, indicating that there is no risk of harm.

Band C assets, those with the lowest total score, are those

reflecting the same low pollution risk as assets that comply

with BAT standards. For assets which score higher and cannot

be shown to meet the BAT equivalent standards, the ERQA

allows the Operator to run mitigation improvement scenarios to

determine to most cost effective improvements

In broad terms the model is designed to assign a numerical

score to each of the three parts of the source-pathway-

receptor model and then multiply those scores. Multiplication

of section scores has the added benefit of resulting in a

greater spread of risk ratings allowing easier identification of

those assets that require improvement works.

Peter DuncanEP/PPC Team Leader

t: + 44 (0)1925 845207

e: [email protected]

Printed on 100% recycled material. © This document and the material

contained therein remain the property of MWH UK Limited.

Total Leak Likelihood

Total Pathway Rating

Total Receptor Rating Risk of Harmx x =