    NOUR MWProjectsPresented to:

    Saudi Telecom Company STC

    Mobile Network Department

  • 8/12/2019 MW Projects

    2/20

    Presentation Contents

    Clients and Suppliers

    Introduction to MW Turnkey Implementation

    Capabilities Completed MW Projects

    ProjectsSummary

    Question Session

  • 8/12/2019 MW Projects

    3/20

    Clients & Suppliers

    Nour completed several MW Projects through largeManufacturers and Solution Providers, such as, LucentTechnologies International, Ericsson, Nokia and Motorola

    Nour utilized the MW Equipments from HARRIS, NERA,ERICSSON, NOKIA, ALCATEL, P-COM and DMC

    Nour completed the mentioned variety of projects for severalclients such as, Saudi Telecom Co., General IntelligenceDepartment, Public Security Directorate, Qatars Ministry ofInterior, Saudi Border Guard Forces, Saudi ConsolidatedElectric Company, Ministry of Defense & Civil Aviation andmuch more.

  • 8/12/2019 MW Projects

    4/20

    MW TURNKEY

    CAPABILITIES

    Site & LOS

    Survey

    MW

    Design

    MW

    Installation

    & Testing

    As-BuiltDocument

    Production

    System

    Integration,

    Operation,

    Maintenance &Optimization

    Civil Major &

    Minor Design,

    & Construction

    Complete

    Administrative,

    Engineering &

    Skilled Stuff

  • 8/12/2019 MW Projects

    5/20

    Site & LOS Survey

    Green Filed Site Survey: for availability of Main Power &suitability of Site-Lot for civil construction

    Existing Site Survey: for availability of Floor Space,Communication Channels, DC Power, Sizing the HVAC,Tower Survey with existing loads, etc.

    Line-of-Sight Survey: to verify the connection possibilitybetween the two sites under study utilizing DGPS Survey Set

    Documentation: to gather all the collected information and tointroduce a Basic Analysis of sitessuitability

  • 8/12/2019 MW Projects

    6/20

    MW Design

    Verify the possible connectivity by means of Collected

    Data along the path using Differential GPS, and to

    compare it with the Digital Maps Data-Points as well

    Finding the most suitable Antenna Heights and Mast

    Height Design Optimization by suggestion of Space Diversity,

    Frequency Diversity, Passive Repeaters, Passive

    Reflectors, etc.

  • 8/12/2019 MW Projects

    7/20

    MW System Installation, Power-up and Commissioning

    MW System Testing (Connectivity and Stability Tests) overstandard periods to ensure the Application of Design Criteria

    and to suggest necessary Corrective Action or Optimization MW Network Management System Installation, especially

    the FarScan of Harris MW Radios

    MW Installation & Testing

  • 8/12/2019 MW Projects

    8/20

    Major Civil Design

    Site Layout Design

    Tower Analysis and Suggestion of Reinforcement (if necessary)

    Electrical Network Design for Grounding, Power

    Connectivity, Lightning Protection, etc.

    Minor Civil Design

    Antenna Mount and Feeder Gantry

    Upgrading of Existing Sites to house the new equipment

    Ability to Design a Roof-Top Site

  • 8/12/2019 MW Projects

    9/20

    Civil Constructions

    A Complete Site Construction, including Foundation

    Casting, Tower Erection, Equipment & Generator Shelters

    Erection, Site Fencing and Electrical Network Preparation

    Shelter Preparation and Testing at Nour Warehouses

  • 8/12/2019 MW Projects

    10/20

    As-Built Documentation

    It is being prepared throughout the Construction and

    Installation Process to Document any changes

    As-Built Document is considered the most important

    document in the Hand-Over Stage, Hence, it is Checkedcarefully and its Softcopy is saved on CD-Archives

  • 8/12/2019 MW Projects

    11/20

    Operation & Maintenance

    Specialized Engineers and Technicians to Operate and

    Configure the Various Network Elements.

    All the Necessary Test Equipment for Fault Finding and

    Rapid Maintenance

    Team Capability of Integrating the various elements to theNetworksManagement System

    Equipment and Skills to Monitor the Site Performance for

    Preventive Maintenance

    Nour Offices are distributed in different cities of the

    Kingdom, to ensure quick response to customer needs

  • 8/12/2019 MW Projects

    12/20

    Completed MW Projects

    1- MW Backbone Network for Saudi PSD (West)

    2- MW Backbone Network for Saudi GID (West)

    3- MW Network for Riyadh PSD (Central)

    4- MW Network Upgrading for Lucent Technologies

    5- Junction MW Network for Saudi Telecom Co.

    6- MW Connectivity Links for GSM Base Stations ofLucent, Ericsson & Nokia Sites

  • 8/12/2019 MW Projects

    13/20

    MW Network for PSD (West)

    Client: Public Security Directorate

    Location: Makkah, Jeddah and Taif

    Period: 1998

    MW Equipment: Alcatel PDH Radio

    Frequency Band: 2 and 4 GHz

    No. of Hops: 12 Hops

    Job Description:

    MW System Design MW Installation, Testing & Commissioning

    Complete MoP and As-Built Documentation

  • 8/12/2019 MW Projects

    14/20

    MW Network for GID (West)

    Client: General Intelligence Department

    Location: Makkah, Jeddah and Taif

    Period: 1999

    MW Equp.: Harris Quadralink 4 T1 PDH Radio

    Frequency Band: 2 GHz

    No. of Hops: 7 Hops

    Job Description:

    MW Installation, Testing & Commissioning Complete MoP and As-Built Documentation

    Installation and Setup of Harris FarScan NMS

  • 8/12/2019 MW Projects

    15/20

    MW Network for PSD (Center)

    Client: Public Security Directorate (Central)

    Location: Riyadh

    Period: 2000

    MW Equipment: Harris Microstar PDH 4E1

    Frequency Band: 7 GHz

    No. of Hops: 6 Hops

    Job Description:

    MW Installation, Testing & Commissioning Complete MoP and As-Built Documentation

    Installation and Setup for Harris FarScan NMS

  • 8/12/2019 MW Projects

    16/20

    MW System Upgrading

    Client: Lucent Technologies International

    Location: Kingdom Wide

    Period: 1999

    MW Equp.: Harris Microstar PDH Radio 16E1

    Frequency Band: 7, 15, 23 and 38 GHz

    No. of Hops: More than 120 Hops

    Job Description:

    Software Upgrading for 1+1 Protected System Complete Documentation and Inventory

  • 8/12/2019 MW Projects

    17/20

    Junction MW Network for STC

    Client: Saudi Telecom Co. ( Through LTII )

    Location: Kingdom Wide Period: 1997 up to 1999

    MW Equipment: NERA SDH STM-1 Radio

    Frequency Band: 6 and 11 GHz

    No. of Hops: 64 Hops

    Job Description:

    MW System Design and Optimization

    MW Installation, Testing & Commissioning

    Complete Frequency Plan, Interference Analysis, PropagationSurvey, MoP and As-Built Documentation

    Setting-up the Space Diversity Delay Cable, Adjusting GroupDelay (ATDE) and Optimizing Diversity Spacing

    Passive Re eater Ali nment

  • 8/12/2019 MW Projects

    18/20

    GSM MW Connectivity (1 of 2)

    Client: Saudi Telecom Co. (Direct Contracting)

    Location: Kingdom Wide

    Period: 2000 up to Present

    MW Equipment: Microstar (Harris), Flexihopper (Nokia),Tel-link (P-COM) and Mini-link (Ericsson) PDH Radios 4, 8and 16 E1

    Frequency Band: 7, 15, 23 and 38 GHz

    No. of Hops: More than 500 Hops

  • 8/12/2019 MW Projects

    19/20

    GSM MW Connectivity (2 of 2)

    Job Description: Line-of-Sight Survey (Preliminary Design Step)

    MW Documentation and Preparation of PAT Documents

    Procurement of Materials (Radio, Cabling, Data Rack, etc.)

    MW Systems Swap (low capacity to higher one)

    Complete MW System Installation, Alignment, Panning andConfiguration

    Alignment of Passive Repeaters

    Performing Fade Margin and Stability Test.

    MW Hop Testing (PAT to customerssatisfaction)

    System Handover to O&M Department

  • 8/12/2019 MW Projects

    20/20

    Questions & Answers Session