Mvar Management

download Mvar Management

of 20

Transcript of Mvar Management

  • 8/10/2019 Mvar Management

    1/20

    Reactive Power Management

    - Case study

    -- Nandan Pathak (AE)

  • 8/10/2019 Mvar Management

    2/20

    ICT -1 ICT -2 G-3 G-4 G-5

    200 MW160 MVAR

    160 MW135 MVAR200 MW

    160 MVAR

    160 MW135 MVAR

    160 MW140 MVAR

    LOAD LOAD

    220 kVGirwali Bus

    220 kV ParliBus

  • 8/10/2019 Mvar Management

    3/20

    ~

    GENERATION

    870 MW

    730 MVAR

    LOAD:

    A ) GENERATORS:a) High MVAR drawl

    b) High excitation currentB) ICT:

    a) Overloading due to MVARb) Low voltage on 220 kV bus ( 200 kV)

  • 8/10/2019 Mvar Management

    4/20

    C) LOAD:11 kV side:

    a) Overload trippingb) Very low voltagesc) Conductor snappingd) Local load shedding

    440 V side:

    a) Failure of transformersb) Conductor snapping

  • 8/10/2019 Mvar Management

    5/20

    A)High seasonal load especially agriculture

    during October to March

    B) Failure of reactive compensation

  • 8/10/2019 Mvar Management

    6/20

    A) Identification of areas

    a) Beed districtb) Solapur districtc) Nanded district

    d) Pabhani districte) Latur district

  • 8/10/2019 Mvar Management

    7/20

    A) Identification of radial feeders

    220 kVGirwali Bus

    220 kV Nanded160 MW 100 MVAR

    220 kV Parbhani100 MW 80 MVAR 132 kV Parli

    Bus

    132kV Beed80 MW 60 MVAR

    ~ ~

    132 kV Latur -190 MW 75 MVAR

    132 kV Latur -260 MW 45 MVAR

    132 kVGirwali Bus

    On similar lines loaded 11 & 33 feeders were identified.

  • 8/10/2019 Mvar Management

    8/20

    I) Reactive power compensation available :i. Substation ----- 164 MVAR

    ii. Switched capacitors on 11kV 240 MVAR (0.6 X405)II) Focus Area 11 kV , 0.6 MVAR capacitors

    a. Repairs in a central laboratoryb. On site replacement, checking, modification, training

  • 8/10/2019 Mvar Management

    9/20

    Modifications adopted foroptimum compensation

    1. Cell rating 0.66 Mvar at 12 kV

    2. De-rating at Low Voltage

    3. Modification

    A. Fixed capacitors

    B. Addition to basic scheme

  • 8/10/2019 Mvar Management

    10/20

  • 8/10/2019 Mvar Management

    11/20

  • 8/10/2019 Mvar Management

    12/20

    4. On site demonstrations

    5. Team visit Nasik , Pune (R ),Kolhapur, Sangli,Parbhani

  • 8/10/2019 Mvar Management

    13/20

    1. Reduction in overload tripping of 11 kV &

    33 kV feeders. 2. Reduction in blowing of HG fuses at 33/11

    kV transformers.

    3. Reduction in conductor snapping.

    4. Improvement in voltage profiles

    LT 105 Volts to 190 volts

    11kV 7.6 kV to 9.8 kV

  • 8/10/2019 Mvar Management

    14/20

    ICT -1 ICT -2 G-3 G-4 G-5

    250 MW (200)100 MVAR(160)

    200 MW(160)60 MVAR(135)250 MW(200)

    100MVAR(160)

    200 MW60 MVAR

    195 MW(150)80 MVAR(140)

    LOAD LOAD

    220 kVGirwali Bus

    220 kV ParliBus

  • 8/10/2019 Mvar Management

    15/20

    ~

    GENERATION

    1095 MW (870)

    400 MVAR (730)

    LOAD:

    Voltage changes:220 kV 215 kV (200 kV)

    132 kV 125 kV (106 kV)33 kV 31 kV (27 kV)

  • 8/10/2019 Mvar Management

    16/20

    Radial load changes

    132 kVParli Bus

    132kV Beed95 MW 30 MVAR(80 MW 60 MVAR)

    ~ ~

    132 kV Latur 1105 MW 40 MVAR

    (90 MW 75 MVAR)

    132 kV Latur 270 MW 30 MVAR

    (60 MW 45 MVAR)

    132 kVGirwaliBus

  • 8/10/2019 Mvar Management

    17/20

    MONTH KWH 1998 KWH 1999 KWH 2000 KWH 2001

    January 791500 1101100 1014800 401700

    February 545000 938100 699100 239400March 667900 819800 663300* 262200

    April 539400 790900 87400* 183400

    May 512000 473200 -* 275400

    June 164400* 459800 167700* 43800**

    July 313900 1170300 442100

    August 310400 948000 490900

    September 330600 630400 342700October 500300 706100 350100

    November 530400 854700 626000

    December 307300* 1104100 542000

    ---Load shifted to another feeder --- Load of other feeder taken on this feeder

    ** --- kWh meter stopped due to leading PF

    Note:

    0.6 MVAR capacitor bank recommissioned at village Pandharee on Dt.28.11.2000

    0.6 MVAR capacitor bank added at same location on Dt.4.12.2000

    New 0.6 MVAR capacitor bank commissioned at Pokharni Phata on Dt.8.12.2000

    KWH recorded on 11kV Matkuli feeder from 132 / 11 kV T/F at 132 kV Ashti substation

  • 8/10/2019 Mvar Management

    18/20

    0

    200000

    400000

    600000

    800000

    1000000

    1200000

    Janu

    ary

    Feb

    ruary

    March

    April

    May

    June Ju

    ly

    Aug

    ust

    Septembe

    r

    Octob

    er

    Novembe

    r

    Decembe

    r

    1998

    1999

    2000

    2001

  • 8/10/2019 Mvar Management

    19/20

    Month Forecasted Energy sentout (kWH)

    Actual Energy sent out(kWH)

    Savings(kWH)

    Remark

    Dec 2000 689997 542000 147997 21.45

    Jan 2001 624172 401700 222472 35.60

    Feb 2001 520905 239400 281505 54.00

    Mar 2001 562029 265200 296829 52.00

    Apr 2001 511766 183400 328366 64.10

    May 2001 451451 275400 176051 39.00

    Total 3360320 1907100 1453220 43.24

    Energy savings on 11 kV Matkuli feeder

  • 8/10/2019 Mvar Management

    20/20

    1.System requires high order reactive compensation.

    2.Use of fixed value non switched/seasonal manual switchedcapacitors is economical.

    3. Complementary switching for optimum compensation.

    4. Dedicated setup for overall line loss reduction.