Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning &...
Transcript of Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning &...
Multimodal Corridor Planning &Engineering Analysis Project
PRESENTATION FOOTERT
TAC/CAC, TPO Project UpdateFebruary 2016
A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSISFlorida Department of Transportation
Multimodal Corridor Planning &Engineering Analysis Project
Meeting Agenda – What We Plan To Discuss– Project Background– New Analysis– RRR Projects– Improvement Concepts – Status– Questions and Comments
Multimodal Corridor Planning &Engineering Analysis Project
Project Background– Initiated by Space Coast TPO & Action Team– Addresses multimodal transportation along SR
A1A– From the Pineda Causeway (SR 404) to SR
528 in Cape Canaveral– Goal: Develop Implementation Plan
Multimodal Corridor Planning &Engineering Analysis Project
Project Constraints & Opportunities– Most improvements are within the existing right-of-way
• Limited by narrow road and lack of extra space
– Several improvementsto be implemented byothers
• Land use changes• Utility improvements• Wayfinding signage
Multimodal Corridor Planning &Engineering Analysis Project
Existing Conditions• Data Collection• Previous Studies• Identify Right-of-Way
(based on maps)
Identification of Needs• Transportation Needs
Assessment• Stakeholder
Interviews• Public Charrette
Planning Phase -Visioning
Planning Phase– Engineering
Analysis
ProjectDevelopment
Phase forSelected
Improvements
Implementation
Depending on theProject, Next Stepscould include:
• DrainageAnalysis
• EnvironmentalAnalysis
• Design• Right-of-Way
Engineering Analysis• Identification of Range
of Improvements• Concept Plans• Cost Estimates• Evaluation Criteria• Comparative Analysis• Public Workshop• A1A Action Team
Mtg.
Prepare PrioritizedProject List
• Conceptual DesignPlans
• Refined CostEstimates
Public MeetingFinal Presentations
• Stakeholders,• TPO• FDOT
Current Steps
Multimodal Corridor Planning &Engineering Analysis Project
Wayfinding– Implementation Guide
• Resolutions• Examples• Potential Destinations• Recommended steps
– Cities to design & implement– FDOT to review
Multimodal Corridor Planning &Engineering Analysis Project
Utilities– Implementation Guide
• Recommendations on PhasedApproach
• Locations• Types of Changes• Potential Destinations• Recommended steps
– Cities to design & implement– FDOT to review
Multimodal Corridor Planning &Engineering Analysis Project
Right of Way– New Information– Most is similar to previous assumed ROW– Area near the Air Force Base is different
Multimodal Corridor Planning &Engineering Analysis Project
New Pedestrian Analysis– North end of One-Way Pairs– Results: Crosswalk included in RRR
Multimodal Corridor Planning &Engineering Analysis Project
Recommendations – South toNorth– Applications through TPO
• Some sent by Cocoa Beach• Some sent by Cape Canaveral
– To be Prioritized / Funded, thenDesigned RRR
Project
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
Path
Multimodal Corridor Planning &Engineering Analysis Project
Patrick Air Force Base– Right-of-Way is significant concern– Improvements must be driven by the AFB.
NEED SPONSOR
Right-of-WayRecommended Path
Multimodal Corridor Planning &Engineering Analysis Project
RRR Project Details– Public Meeting November 19– Purpose is Resurfacing– Construction 2016
RRRProject
Rec: Streetscaping
Rec: Sidewalk –One-Way Pairs
Multimodal Corridor Planning &Engineering Analysis Project
RRR Project Changes– Based on additional funds from
TPO and City– Sidewalk – fill in all gaps– Bulb outs– No Landscaping - TBD by City RRR
Project
Rec: Streetscaping
Rec: Sidewalk –One-Way Pairs
Multimodal Corridor Planning &Engineering Analysis Project
Recommendations – Streetscaping / Drainage
Multimodal Corridor Planning &Engineering Analysis Project
RRRProject
Rec: Streetscaping
Rec: Sidewalk –One-Way Pairs
60% Plans – Subject To Change
60% Plans – Subject To Change
Multimodal Corridor Planning &Engineering Analysis Project
60% Plans – Subject To Change
Multimodal Corridor Planning &Engineering Analysis Project
60% Plans – Subject To Change
Multimodal Corridor Planning &Engineering Analysis Project
– Consider modifications toexisting curbs?
• More sidewalk space• Significant design
complexities
– Extend curb and gutter?• Between N 1st St and N 4th
St?• North beyond N 4th St?• South beyond existing
curb?
– Landscaping &Streetscaping?
Considerations after RRR is accomplished
Multimodal Corridor Planning &Engineering Analysis Project
Recommendation: Sidewalk betweenSunflower St and SR 520
Path
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
West Side – 8’East Side – Existing (Summer 2015)
Multimodal Corridor Planning &Engineering Analysis Project
Recommendation: SR 520 Intersection
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
Path
Multimodal Corridor Planning &Engineering Analysis Project
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban ProfileSR 520 Intersection – Status:– Too many complexities to add
to SR 520 RRR– Consider as stand alone
improvement– Scope for Design is under way
Path
Multimodal Corridor Planning &Engineering Analysis Project
Recommendation: Sidewalk betweenSR 520 and International / Atlantic
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
West Side – 8’East Side – 8’
Path
Multimodal Corridor Planning &Engineering Analysis Project
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban ProfileSidewalk - SR 520 to Atlantic Ave –Status:– Consider as stand alone improvement– Scope for Design is under way
Path
Multimodal Corridor Planning &Engineering Analysis Project
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
Recommendation: International /Atlantic Realignment
Path
Multimodal Corridor Planning &Engineering Analysis Project
Recommendation: Boulevard fromInternational / Atlantic to George King
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban Profile
SW (West Side) – 8’SW (East Side) – 8’Median – 22’ or 19.5’Bike Lane – 4’
Path
Multimodal Corridor Planning &Engineering Analysis Project
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban ProfileInternational Drive and BoulevardImprovements – Status:– Will require additional coordination,
analysis, and drainage considerations.– Being considered to move into design– Will not require a PD&E
Path
Multimodal Corridor Planning &Engineering Analysis Project
Path
RRRProject
Streetscaping
Sidewalk
Sidewalk
Sidewalk
Modify Intersection
Modify Intersection
Median, Urban ProfileWhat’s The Status?– Path in front of PAFB – working on agreement– Sidewalks in One-Way Pairs – in RRR– Streetscaping Projects Downtown Coca Beach –
some elements in RRR– SR 520 - prioritized, scope is complete– International Drive Intersection – prioritized,
scope is in development– Cape Canaveral median / Urban Profile –
prioritized, scope is in development (PD&E notneeded)
Multimodal Corridor Planning &Engineering Analysis Project
Project Contacts– Project Manager: Todd Davis at [email protected] or at 386-
943-5422– Planning and Corridor Development Manager: Heather Garcia at
[email protected] or 386-943-5077
Check out the project website at www.actiona1a.com