Multimodal Corridor Planning & Engineering Analysis Project PRESENTATION FOOTERT TAC/CAC, TPO Project Update February 2016 A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSIS Florida Department of Transportation

Transcript of Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning &...

Page 1: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

PRESENTATION FOOTERT

TAC/CAC, TPO Project UpdateFebruary 2016

A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSISFlorida Department of Transportation

Page 2: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Meeting Agenda – What We Plan To Discuss– Project Background– New Analysis– RRR Projects– Improvement Concepts – Status– Questions and Comments

Page 3: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Project Background– Initiated by Space Coast TPO & Action Team– Addresses multimodal transportation along SR

A1A– From the Pineda Causeway (SR 404) to SR

528 in Cape Canaveral– Goal: Develop Implementation Plan

Page 4: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Project Constraints & Opportunities– Most improvements are within the existing right-of-way

• Limited by narrow road and lack of extra space

– Several improvementsto be implemented byothers

• Land use changes• Utility improvements• Wayfinding signage

Page 5: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Existing Conditions• Data Collection• Previous Studies• Identify Right-of-Way

(based on maps)

Identification of Needs• Transportation Needs

Assessment• Stakeholder

Interviews• Public Charrette

Planning Phase -Visioning

Planning Phase– Engineering

Analysis

ProjectDevelopment

Phase forSelected

Improvements

Implementation

Depending on theProject, Next Stepscould include:

• DrainageAnalysis

• EnvironmentalAnalysis

• Design• Right-of-Way

Engineering Analysis• Identification of Range

of Improvements• Concept Plans• Cost Estimates• Evaluation Criteria• Comparative Analysis• Public Workshop• A1A Action Team

Mtg.

Prepare PrioritizedProject List

• Conceptual DesignPlans

• Refined CostEstimates

Public MeetingFinal Presentations

• Stakeholders,• TPO• FDOT

Current Steps

Page 6: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Wayfinding– Implementation Guide

• Resolutions• Examples• Potential Destinations• Recommended steps

– Cities to design & implement– FDOT to review

Page 7: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Utilities– Implementation Guide

• Recommendations on PhasedApproach

• Locations• Types of Changes• Potential Destinations• Recommended steps

– Cities to design & implement– FDOT to review

Page 8: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Right of Way– New Information– Most is similar to previous assumed ROW– Area near the Air Force Base is different

Page 9: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

New Pedestrian Analysis– North end of One-Way Pairs– Results: Crosswalk included in RRR

Page 10: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendations – South toNorth– Applications through TPO

• Some sent by Cocoa Beach• Some sent by Cape Canaveral

– To be Prioritized / Funded, thenDesigned RRR

Project

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

Path

Page 11: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Patrick Air Force Base– Right-of-Way is significant concern– Improvements must be driven by the AFB.

NEED SPONSOR

Right-of-WayRecommended Path

Page 12: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRR Project Details– Public Meeting November 19– Purpose is Resurfacing– Construction 2016

RRRProject

Rec: Streetscaping

Rec: Sidewalk –One-Way Pairs

Page 13: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRR Project Changes– Based on additional funds from

TPO and City– Sidewalk – fill in all gaps– Bulb outs– No Landscaping - TBD by City RRR

Project

Rec: Streetscaping

Rec: Sidewalk –One-Way Pairs

Page 14: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendations – Streetscaping / Drainage

Page 15: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRRProject

Rec: Streetscaping

Rec: Sidewalk –One-Way Pairs

60% Plans – Subject To Change

60% Plans – Subject To Change

Page 16: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

60% Plans – Subject To Change

Page 17: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

60% Plans – Subject To Change

Page 18: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

– Consider modifications toexisting curbs?

• More sidewalk space• Significant design

complexities

– Extend curb and gutter?• Between N 1st St and N 4th

St?• North beyond N 4th St?• South beyond existing

curb?

– Landscaping &Streetscaping?

Considerations after RRR is accomplished

Page 19: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendation: Sidewalk betweenSunflower St and SR 520

Path

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

West Side – 8’East Side – Existing (Summer 2015)

Page 20: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendation: SR 520 Intersection

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

Path

Page 21: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban ProfileSR 520 Intersection – Status:– Too many complexities to add

to SR 520 RRR– Consider as stand alone

improvement– Scope for Design is under way

Path

Page 22: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendation: Sidewalk betweenSR 520 and International / Atlantic

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

West Side – 8’East Side – 8’

Path

Page 23: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban ProfileSidewalk - SR 520 to Atlantic Ave –Status:– Consider as stand alone improvement– Scope for Design is under way

Path

Page 24: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

Recommendation: International /Atlantic Realignment

Path

Page 25: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Recommendation: Boulevard fromInternational / Atlantic to George King

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban Profile

SW (West Side) – 8’SW (East Side) – 8’Median – 22’ or 19.5’Bike Lane – 4’

Path

Page 26: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban ProfileInternational Drive and BoulevardImprovements – Status:– Will require additional coordination,

analysis, and drainage considerations.– Being considered to move into design– Will not require a PD&E

Path

Page 27: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Path

RRRProject

Streetscaping

Sidewalk

Sidewalk

Sidewalk

Modify Intersection

Modify Intersection

Median, Urban ProfileWhat’s The Status?– Path in front of PAFB – working on agreement– Sidewalks in One-Way Pairs – in RRR– Streetscaping Projects Downtown Coca Beach –

some elements in RRR– SR 520 - prioritized, scope is complete– International Drive Intersection – prioritized,

scope is in development– Cape Canaveral median / Urban Profile –

prioritized, scope is in development (PD&E notneeded)

Page 28: Multimodal Corridor Planning & Engineering Analysis Project€¦ · Multimodal Corridor Planning & Engineering Analysis Project Project Contacts – Project Manager: Todd Davis attodd.davis@dot.state.fl.usor

Multimodal Corridor Planning &Engineering Analysis Project

Project Contacts– Project Manager: Todd Davis at [email protected] or at 386-

943-5422– Planning and Corridor Development Manager: Heather Garcia at

[email protected] or 386-943-5077

Check out the project website at www.actiona1a.com