![Page 1: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/1.jpg)
Multidisciplinary Engineering Senior DesignProject PO6208 – ArcWorks Closure Tube Assembly
Adaptation Preliminary Design Review02/24/2006
Project Sponsor:ARC Works of Monroe County
Team Members:Team Leader George Gooch, Bill Lucas, Chris Donati, Drew Stone-
Briggs, Hui Kim, Mike Hayden, Mike Levis, Jeff Coppola
Team Mentor:
Dr. DeBartolo (ME) and Dr. Marshall (IE)
Acknowledgements:This material is based upon work supported by the National Science Foundation under
Award No. BES-0527358.Any opinions, findings, and conclusions or recommendations expressed in this material are those of the author and do not necessarily reflect the views of the National Science
Foundation.
![Page 2: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/2.jpg)
Presentation Overview Sponsor
Who they are What is their current process
Team Goals How are we going to help ArcWorks Needs, Feasibility, and Concepts
Final Concept What improvements are being made Time, Flow, Material Handling
SD II
![Page 3: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/3.jpg)
ArcWorks
ArcWorks is the vocational division of the Arc of Monroe County
Have been serving individuals with developmental disabilities and their families for over forty years.
Specialize in providing subcontracting manufacturing services
Comprised of over 250 assembly operators
![Page 4: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/4.jpg)
ArcWorks – Closure Tube Assembly (CTA) A process that supports the assembly of a
bent stem closure with a tube attachment
Quantities produced are close to 500,000 units per year
Currently there are 3 process steps The team is dealing primarily with steps 2 and 3
![Page 5: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/5.jpg)
CTA - Components
Finished Closure
Components
Closure (Various Sizes) Adapter Tube
(Various Lengths)
![Page 6: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/6.jpg)
Step 1 – Straw Cutting Process Machine
10 tubes at once are inserted into the top of the automated tube cutter. The machine cycles, cuts the tubes and they drop through into a box.
![Page 7: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/7.jpg)
CTA - Step 2 (Closure/Adaptor Sub-Assembly) Process MachinesClosures are placed in the bottom fixture and Adapters are placed in the top fixture of one of two style manual presses. The presses are cycled to create the Closure / Adapter Sub-assembly.
![Page 8: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/8.jpg)
CTA - Step 3 (Final Assembly Press) Process Machine
Closure / Adapter Sub-Assemblies are placed in the top fixture of the automated press. Tubes are placed in the bottom fixture. The machine is cycled to create the final assembly.
![Page 9: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/9.jpg)
Team’s Task
Lean Development – integration of sub assembly production orders/releases to ensure minimum/maximum quantities are on hand and flow as required (SD I)
Production Process – improvement of the assembly process, changeover & set-up, ergonomics/safety, and improvement of operator productivity (SD I)
Purchasing Function – ordering of the raw tubing that is cut to length for finished goods assembly (SD II)
Inventory Management – of both raw and cut tubing (SD II)
![Page 10: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/10.jpg)
Needs Assessment
Tools Used
Problem Scope/Definition The mission of this design project team, PO6208, is to redesign a
process that supports the assembly of a bent stem closure with tube attachment called the Closure Tube Assembly. In this design the team hopes to improve the process flow, daily production and worker safety/comfort.
Objective Trees
5 Why’s
![Page 11: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/11.jpg)
Needs Assessment - Outcome
It was decided through evaluations that this machined needed to: Combine assembly steps Decrease the number of moving parts Limit complexity of design Create fixtures that can be used for all product
sizes Use standard components Improve ergonomics Add counters
![Page 12: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/12.jpg)
Feasibility Assessment
Tools Used
REST Resource, Economics, Schedule, Technical
Pugh Method Un-weighted, all attributes equally important
Weighted Comparison Method Looks at attribute importance
![Page 13: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/13.jpg)
REST Method
Compares the chance of success of each idea Rating Scale
1=low chance 5=high chance
Design Idea Avg. Score 1 - 4.10 2 - 4.13 3 - 3.36 4 - 4.10 5 - 3.90 6 - 3.83
Top 3 = Idea 2, 1, 4
![Page 14: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/14.jpg)
Pugh Method
Idea 1 Idea 2 Idea 3 Idea 4 Idea 5 Idea 6
+ 7.00 7.33 6.00 8.50 5.83 4.67
- 2.60 2.60 7.50 1.33 3.17 5.00
0 12.50 12.17 8.17 11.83 12.67 12.00
Compares against a baseline considering all attributes are equally important
Top 3 – Idea 4, 1, 2
![Page 15: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/15.jpg)
Weighted Method
1 2 3 4 5 6
3.854 3.663 2.786 3.779 2.953 3.115
Compares against a baseline considering all attributes are not equally important, but have a weighting Idea
Top 3 – Idea 1, 4, 2
![Page 16: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/16.jpg)
Feasibility Assessment - Outcome Main concerns after feasibility assessment:
Fixtures Closure Holding and Size Variation Tube Holding and Size Variation Adapter Holding
Assembly Alignment Combining Operations Budgeting
![Page 17: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/17.jpg)
Feasibility Assessment - Results Top 3 ideas from feasibility methods
Idea 1 Idea 2 Idea 4
These ideas were the basis for the teams final design.
![Page 18: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/18.jpg)
Final Concept
![Page 19: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/19.jpg)
Step 1 – Part Placement
![Page 20: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/20.jpg)
Step 2 – Press Anti-Tie Down Buttons
![Page 21: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/21.jpg)
Step 3 – Adapter Press
![Page 22: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/22.jpg)
Step 3 – Close Up of Adapter Press
![Page 23: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/23.jpg)
Step 4 – Cylinder Returns
![Page 24: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/24.jpg)
Step 5 – Manual Sub-Assembly Move
![Page 25: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/25.jpg)
Step 6 – Manual Straw Placement
![Page 26: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/26.jpg)
Step 7 – Gripper Press
![Page 27: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/27.jpg)
Step 8 – Dual Cylinder Press
![Page 28: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/28.jpg)
Step 9 – Gripper Return
![Page 29: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/29.jpg)
Step 10 – Dual Cylinder Return
![Page 30: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/30.jpg)
Step 11 – Assembly Removal
![Page 31: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/31.jpg)
Performance Needs
Pneumatic Design Objectives
Improve safety OSHA 1910.217(b)(6)(i)
Limit cost Limit the stroke length of the press cylinders Actuate the press cylinders simultaneously or
independently Control speed and force
![Page 32: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/32.jpg)
Pneumatic Layout
![Page 33: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/33.jpg)
Analysis of Design ( Mechanical ) Design Parameters
FEA Calculations
Assembly Step Force (lbs) Comments
Closure - Adapter 8.75 Max5.40 Average
24mm red closure and clear adapter create max force
Tube - Adapter 3.00 Max2.11 Average
PPCO tube and red adapter create max force
![Page 34: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/34.jpg)
Engineering AnalysisResultant Displacement
Air Cylinder Bracket Support Max Displacement
5.86 x 10-4 inches Location: End of Bracket
Deformation Scale = 3464 Conclusion:
Bracket Support is Rigid
![Page 35: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/35.jpg)
Engineering AnalysisVon Mises Stress Contour Plot
Air Cylinder Bracket Support Max Stress
780 PSI Location: Bracket Connection
Factor Of Safety= 65 Conclusion:
Withstands Applied Forces
![Page 36: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/36.jpg)
Engineering AnalysisFatigue Analysis
Air Cylinder Bracket Support Fa=Fm= 10 lbs Fatigue Strength=Endurance Limit Factor Of Safety w/
Mod Goodman Criterion= 35 Conclusion:
Withstands Infinite Cycles
Fa, Fm
![Page 37: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/37.jpg)
Engineering AnalysisBuckling Analysis
Tube Holder Section 1
Euler Method: Pcr= 11 lbs Factor Of Safety= 2
Section 2 JB Johnson Method: Pcr= 3446 lbs Factor Of Safety= 626
Conclusion: Neither Section will Buckle Possible Improvement:
Limit exposed tube length in Section 1Pcr
2
1
![Page 38: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/38.jpg)
BOM
![Page 39: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/39.jpg)
Improvements - Time
Time Comparison Current Process New Design Process
Step Description Time Step Description Time (sec) (sec) Insert Closure 2 Insert Closure 2 Insert Adapter 2 Insert Adapter 2 Press 2 Press 2 Remove CA 2 Move CA 1.5 Insert Tube 2 Insert Tube 2 Insert Closure 2 Insert CA 2 Insert Adapter 2 Press 4 Press 3 Remove CTA 2 Remove CTA 2 Total Time 18 Total Time 12.5
•Estimated productivity increase of 88 CTA’s per hour
![Page 40: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/40.jpg)
Improvements – Material Handling
Retrieve TubesFrom Hallway(Time – 60)
Cut Tubes(Time – 2)
Place Cut TubesIn Box
(Time – 10)
Move Tube from
Cutter to Pallet(Time - 12)
Move Tube from Pallet to
Final Assembly(Time - 10)
Retrieve Closure
And Adapters From Hallway
(Time - 45)
Transfer Parts from Boxes to
Bins(Time – 12)
Assemble ClosureWith Adapter
(Time – 8)
Place CA In Box
(Time – 2)
Move CAto Pallet
(Time - 12)
Move CA from Pallet to Final
Assembly(Time - 10)
Fill Bins with TubesAnd Closure Assembly
From Box(Time - 20)
Assemble into Final Assembly
(Time – 8)
CurrentManufacturing
Process(All times in seconds)
Box Final Assembly(Time - 5)
27 ft
1 ft
13 ft
8 ft
1 ft
1 ft
1 ft
1 ft
8 ft
12 ft
1 ft
1 ft
10 ft
Transfer Parts from Boxes to
Bins(Time - 12)
1 ft
Tube CuttingOperation 1
Closure Sub-AssemblyOperation 2
Final AssemblyOperation 3
Final Times and DistanceTube Cutting
Time - 106 secDistance - 51 ft.
Closure Sub-AssemblyTime - 99 secDistance - 33 ft.
Final AssemblyTime - 33 secDistance - 2 ft.
Retrieve TubesFrom Hallway
(Time - 60)
Cut Tubes(Time – 2)
Place Cut TubesIn Box
(Time -10)
Move Tube from
Cutter to Pallet(Time - 12)
Move Tube from Pallet to
Final Assembly(Time - 10 )
Retrieve Closure
And Adapters From Hallway
(Time - 45)
Fill Bins with Tubes,Closures, and
Adaptors From Box(Time - 20)
Assemble into Final Assembly
(Time – 8)
FutureManufacturing
Process(All times in seconds)
Box Final Assembly(Time - 5)
27 ft
1 ft
13 ft
8 ft
1 ft
1 ft
1 ft
10 ft
Transfer Parts from Boxes to
Bins(Time - 12)
1 ft
Tube Cutting Process
Operation 1Final
Assembly Operation
2 + 3(Combined)
Final Times and DistanceTube Cutting
Time - 106 secDistance - 51 ft.
Final AssemblyTime - 78 secDistance - 12 ft.
![Page 41: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/41.jpg)
Improvements – New Machine Multiple operations done by one operator
Machine mounted to table for stability
Combines two process steps Eliminates material handling between stations Reduces process time
![Page 42: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/42.jpg)
Improvements – Ergonomic/Safety Ergonomically friendly
Eliminates repeated manual motion Reduces ranges of motion Common plane of motion
Safety Anti-tie-down buttons E-stop
![Page 43: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/43.jpg)
SD II - plans
Investigate Warehouse/Inventory Issues Re-order Points Safety Stock Flow of Material
Desired Outcomes – Manufacturing Area Increased productivity by the ArcWorks team Fewer rejects Higher satisfaction of workers Layout Redesign
![Page 44: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/44.jpg)
Economic Order Quantity -EOQ
Defines the optimal quantity to order that minimizes total variable costs required to order and hold inventory. Q * = optimal order quantity C = cost per order event (not per unit) R = monthly demand of the product P = purchase cost per unit F = holding cost factor; the factor of the purchase cost that is
used as the holding cost (this is usually set at 10-15%, though circumstances can require any setting from 0 to 1)
H = holding cost per unit per month (H = PF)
![Page 45: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/45.jpg)
Questions?
![Page 46: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/46.jpg)
Backup Slides
Following Slides
![Page 47: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/47.jpg)
Straw Cutting Improvements Manual Tube Feeding Concept
![Page 48: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/48.jpg)
Needs Worksheets
Following Slides
![Page 49: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/49.jpg)
Objective Tree – Inventory Management
Inventory Management
Purchasing Warehousing Final Product
Reorder Points Warehousing
Quantity Reorderd
Frequency of Reorder
Order High Volumes
Order Low Volumes
Order Frequently Order Infrequenty
LocationSize of
Inventory
Product LocationWarehouse
locationLow Inventory
QuantityHigh Inventory
Quantity
Quantity Quality
Inspection
BadGood
![Page 50: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/50.jpg)
Objective Tree – Production Process
Production Process
Material Handling Assembly Quality Inspection
Frequency of Handling
Less Manual Process
Determine good products
Determine bad products
High handling frequency
Low Handling Frequency
Failsafes ConsistencyErgonomically
Correct
Take responsibility off of workers
Leads to better Quality
Better worker enviornment
![Page 51: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/51.jpg)
Objective Tree – Fixture Development
Fixture Development
Aid in AssemblyImprove
ErgonomicsIncrease Product
Quality
Produce more parts at one time
Less Manual Machine
Combine multiple processes into one
Lower range of motion
More parts at once to reduce repetition
More like parts with less variance
Go-nogo checkReduce Cycle Time
Easier to use than current process
Quicker Machine Changeover
Less Scrap Parts
![Page 52: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/52.jpg)
5 Why’s
A) Inventory Management
Why do you want us to improve your purchasing and inventory management system? Don’t want to run out of parts.
Why don’t you want to run out of parts? There is a 4 week lead time to
receive the parts from the vendor.
Why is there a 4 week lead time? That’s what the vendor gives us.
Why do you use that vendor? That’s the supplier we have
always used
Why have you always used that supplier? That’s who Nalgene used before
us and we never looked at any other options.
B) Fixture Evaluation
Why do you need new fixturing for your machines? The old ones are not efficient
enough.
Why aren’t they efficient enough for you? The current process is too
manual.
Why is the current process so manual? That’s the way the original
machines were designed.
Why were they designed like that? It met the needs at that time.
Why did it meet the needs then and not now? The demand from the customer
for Closure Tube Assemblies has increased. (This has created a bottleneck in the assembly department.)
![Page 53: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/53.jpg)
Feasibility Worksheets
Following Slides
![Page 54: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/54.jpg)
Weighted Method – How the weightings were achieved
![Page 55: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/55.jpg)
Weighted Method – How the weightings were used
![Page 56: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/56.jpg)
Top 3 Ideas
Following Slides
![Page 57: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/57.jpg)
Original Concepts
Idea 1
![Page 58: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/58.jpg)
Idea 2
Original Concepts
![Page 59: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/59.jpg)
Original Concepts
Idea 4
![Page 60: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/60.jpg)
Concepts from Peer Review
Following Slides
![Page 61: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/61.jpg)
Assembly Process Improvement
Pin Style Automated Press Discussion: Pin tube support
Sliding Adapter Fixture Press Discussion: Closure Interference,
Fixture Alignment, Adapter Orientation
![Page 62: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/62.jpg)
Assembly Process Improvement Two Stage CTA Press
Discussion: CTA Removal, Rotation
CTA Process w/ Magazine Feeder Discussion: Alignment
![Page 63: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/63.jpg)
Feeding Concepts Automated Feeding
Discussion: Cost, Complexity, Durability, Clip Manufacturability
Also… Closure?
Feed Escapement
Tube Adapter
![Page 64: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/64.jpg)
Gantt Chart – SD I
![Page 65: Multidisciplinary Engineering Senior Design Project PO6208 – ArcWorks Closure Tube Assembly Adaptation Preliminary Design Review 02/24/2006 P roject Sponsor:](https://reader035.fdocuments.us/reader035/viewer/2022062714/56649d025503460f949d5220/html5/thumbnails/65.jpg)
Gantt Chart – SD II