Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders,...
Transcript of Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders,...
![Page 1: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/1.jpg)
LECTURE 13
Introduction to Sustainable Urban
Development Planning
Strategic Environmental Assessment
Theory and Application
![Page 2: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/2.jpg)
I. Introduction to SEA
II. Stages and activities
III. The EU SEA Directive
IV. SEA vs. EIA
V. Towards Sustainability: Case Studies
VI. Bibliography
Table of Contents
![Page 3: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/3.jpg)
Part I – Introduction to SEA
![Page 4: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/4.jpg)
Origins
Since the early 1970s, it was recognized that taking
environmental effects into early consideration is crucial for
a substantially environmental- and sustainable-friendly
process.
In 1989, Strategic Environmental Assessment was
introduced as a concept in the context of a European
research project, as “the environmental assessment’s
appropriate to policies, plans and programs […] of a more
strategic nature than those applicable to individual projects
[…] likely to differ from them in several important respects”
(Wood & Djeddour, 1989).
![Page 5: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/5.jpg)
What is SEA?
The keyword is “strategic”, as it qualifies ways of thinking,
attitudes and actions related to strategies, while positioning
SEA in crucial stages of the decision-making process.
• definition:
“a systematic process for evaluating the environmental
consequences of proposed policy, plan or programme
initiatives in order to ensure they are fully included and
addressed at the earliest appropriate stage of decision
making on par with economic and social considerations“
(Sadler & Verheem, 1996)
![Page 6: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/6.jpg)
Key characteristics
1• Flexible position within the decision-making process
(strong, frequent, iterative interaction)
2• Integration of relevant biophysical, social, institutional
and economic aspects
3
• Assessment of environmental and sustainability opportunities and risks to help drive development into sustainability pathways
4• Active stakeholders engagement through collaborative
processes (conflict reduction, win-win achievement)
![Page 7: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/7.jpg)
Principles
A SEA process should:
• fit the purpose and be customized for application at the P/PP* level
• have integrity (application in accordance with objectives and provisions)
• be focused on delivering relevant information, and address the key issues
• be driven by all sustainable development principles
• be integrated with parallel analysis of all issues / with other processes
• relate to project EIA where appropriate (e.g. through tiering mechanisms)
• be transparent and open
• be practical, easy to implement, cost-effective, oriented to problem-solving
• introduce creativity and new perspectives
• be a learning process
*Policies / Plans and Programmes; these are separated because, although SEA can be applied to all three, the
EU Directive as presented later on requires that SEA be applied in plans and programmes exclusively.
![Page 8: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/8.jpg)
Principles
A SEA process should ensure:
Screening
Timing
Environmental scoping
Sufficient information on other factors (e.g. socioeconomicconsiderations)
Review
Participation (of all legitimate stakeholders, including the publicaffected)
Documentation
Decision-making and accountability
Post-decision
![Page 9: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/9.jpg)
But why is it important?
SEA is an important instrument to help facedevelopment challenges generated by:
a) Adaptation and mitigation to climate changes
b) Poverty eradication and overcome of inequalities
c) Enhancement of biodiversity values, ecosystem services,human well-being
d) Social and territorial cohesion
e) Promotion of regional development potential
f) Innovation and cultural diversity of the population
g) Promotion of environmental quality, landscape and culturalheritage, and sustainable use of natural resources
![Page 10: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/10.jpg)
Application in Sustainable Urban
Development and Planning
SEA’s potential to promote urban sustainability is
linked to the following advantages:
• Systematic, integrated framework for considering sustainability
principles
• Early examination of projected impacts of P/PPs on the urban
environment
• Higher-level, comprehensive scope to consider cumulative impacts
• Tiering to carry sustainability principles from P/PPs to Projects
• Monitoring and mitigation measures for adaptive environmental
management
• Substantive, early public involvement
![Page 11: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/11.jpg)
Application in Sustainable Urban
Development and PlanningExamples of potential SEA application in sustainable urban
development and planning include:
national water plans
river basin management plans
green energy policies
electricity transmission grid planning
regional development plans
sustainable tourism policies
urban detailed area plans
small-scale changes to municipal master plans
urban infrastructure programs (energy, water, waste, transport, and
telecommunication systems)
![Page 12: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/12.jpg)
Example
“Renewable energy projects are unlikely to be developed in
a region whose energy strategy promotes gas-fired power
stations.”
SEA would:
incorporate environmental and sustainability
considerations in strategic decision making
inform decision makers about the urban development
sustainability implications of using renewable energy
versus fossil fuel power generation
facilitate public participation in decision-making
![Page 13: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/13.jpg)
Example
“Renewable energy projects are unlikely to be developed in
a region whose energy strategy promotes gas-fired power
stations.”
SEA would also:
help to ensure that the strategic action, whichever this
would be, will be implemented effectively, without any
unintended impacts resulting from this action
help decision makers to better understand their plan
and promote confidence in it
![Page 14: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/14.jpg)
Example
“Renewable energy projects are unlikely to be developed in
a region whose energy strategy promotes gas-fired power
stations.”
SEA would eventually:
make the decision-making process more transparent
and robust
streamline decision-making, since decisions taken at
one planning stage need not be revisited at subsequent
stages
![Page 15: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/15.jpg)
Part II – Stages and activities
![Page 16: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/16.jpg)
i. the P/PP authorities responsible for intendedstrategies
ii. the P/PP development teams
iii. the SEA team (including a coordination team, theexpert teams, a stakeholders engagement expert)
iv. public institutions that are part of environmentalresponsible authorities (alongside public, privateand non-governmental organizations)
v. the public (as a whole, or as selected targetgroups)
Who gets involved?
![Page 17: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/17.jpg)
Five-stage Approach
![Page 18: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/18.jpg)
Stage A: Context, Baseline &
Scoping
Task Purpose
Identifying other relevant P/PPs and
environmental protection objectives
Establish how the P/PP is affected by
outside factors, suggest ideas on
addressing constraints, help to identify
objectives
Collecting baseline informationProvide an evidence base for environmental
problems, prediction of events, monitoring
Identifying environmental problemsHelp focus the SEA and streamline next
stages
Developing SEA objectives
Provide a means by which the performance
of the P/PP and alternatives can be
assessed
Consulting on the scope of SEAEnsure that the SEA covers the likely
significant environmental effects of the P/PP
![Page 19: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/19.jpg)
Stage B: Alternatives &
Assessment
Task Purpose
Testing the P/PP objectives against the SEA
objectives
Identify potential synergies or conflicts and
help in developing alternatives
Developing strategic alternatives Develop and refine strategic alternatives
Predicting the effects of the P/PP (including
alternatives)
Predict the significant environmental effects
of the P/PP and alternatives
Evaluating the effects of the P/PP (including
alternatives)
Evaluate the predicted effects; refine the
P/PP
Mitigating adverse effects
Ensure adverse effects are identified and
potential mitigation measures are
considered
Proposing measures to monitor effects
Detail the means by which the
environmental performance of the P/PP can
be assessed
![Page 20: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/20.jpg)
Stage C: Preparing the
Environmental Report
Task Purpose
Preparing the Report
Present the predicted environmental effects
of the P/PP (including alternatives) in a form
suitable for public consultation and use by
decision-makers.
This is the key output of the SEA process
that will present information on the effects of
the draft P/PP.
![Page 21: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/21.jpg)
Stage D: Consultation
Task Purpose
Consulting the public and Consultation
Bodies on the draft P/PP and the Report
Give the public and the Bodies an
opportunity to express opinions on the
findings of the Report; gather more
information through opinions and concerns
Assessing significant changes
Ensure that the environmental implications
of any significant changes to the P/PP are
taken into consideration
Making decisions
Provide information on how the
Environmental Report and consultees’
opinions were taken into account
![Page 22: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/22.jpg)
Stage E: Monitoring
Task Purpose
Developing aims and methods for
monitoring
Track the effects of the P/PP to show
whether they are as projected; help identify
adverse effects
Responding to adverse effectsPrepare for appropriate responses where
adverse effects are identified
![Page 23: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/23.jpg)
Level 1: Objective and targets
[Source: http://sea.unu.edu/course/index.html%3Fpage_id=92.html]
![Page 24: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/24.jpg)
Level 2: Assessment
[Source: http://sea.unu.edu/course/index.html%3Fpage_id=92.html]
![Page 25: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/25.jpg)
Level 3: Monitoring
[Source: http://sea.unu.edu/course/index.html%3Fpage_id=92.html]
![Page 26: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/26.jpg)
Stakeholder engagement:
• Stakeholder analysis to identify those affected and involved
• Consultation surveys
• Consensus building processes
Predicting environmental & socio-economic effects:
• Modeling or forecasting techniques for direct effects
• Matrices and network analysis
• Participatory or consultative techniques
• GIS as a tool to analyze, organize and present information
Analyzing and comparing:
• Scenario analysis and MCDA techniques
• Risk analysis
• Cost-benefit analysis
• Opinion surveys to identify priorities
Tools
![Page 27: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/27.jpg)
Part III – The EU SEA Directive
![Page 28: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/28.jpg)
Directive 2001/42/EC
The EC made several attempts to adopt regulations on SEA. After
many rounds of revisions, this directive was agreed upon in 2001 and
finally entered into force in 2004.
Directive 2001/42/EC is popularly referred to as the SEA Directive,
although its title does not refer to SEA: “Directive on environmental
assessments of certain plans and programs”.
The directive requests that the competent authorities elaborate an
environmental statement and perform consultations with the
authorities and the general public.
However, it only addresses plans and programmes (PP), whereas the
SEA process can, in principle, be applied to policy levels as well.
![Page 29: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/29.jpg)
Requirements
The EC Directive includes requirements for consultations of:
• environmental authorities when deciding on the scope and level of
detail of the information that must be included in the
environmental report (Article 5.4)
• environmental authorities and the public, who must be given an
effective opportunity within rational timeframes to express
opinions on the draft PP and the respective environmental report
before the PP is adopted (Articles 6.1, 6.2)
• other EU Member States where the plan’s implementation is
considered likely to have significant effects on the environment of
those States.
![Page 30: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/30.jpg)
Application criteria
Source: Scottish Executive, 2005
![Page 31: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/31.jpg)
Part IV – SEA vs. EIA
![Page 32: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/32.jpg)
Environmental Impact
AssessmentThe Environmental Impact assessment (EIA) definition adopted by
the International Association for Impact Assessment (IAIA) is “the
process of identifying, predicting, evaluating and mitigating the
biophysical, social, and other relevant effects of development
proposals prior to major decisions being taken and commitments
made”.
In other words, EIA is both:
(a) a technical tool for analysis of the consequences of a planned
P/PP or project or an unplanned event (natural disasters, wars
etc), providing information to stakeholders and decision makers;
and
(b) a legal procedure linked to the decision-making process of a
planned intervention.
![Page 33: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/33.jpg)
SEA: An EIA-based process?
Initial understanding of the concept of SEA was based firmly on EIA
principles and processes, although it was recognized that procedure and
methodology would need to be adapted.
Subsequently, the range of interpretations of SEA has grown much wider
and, arguably, now extends beyond its EIA foundations: “this diversity in SEA
practice indicates a rebellion against the straightjacket of being
conceptualized as a narrow impact assessment instrument”.
Early definitions saw SEA as a tool derived from EIA, extending its process
and procedure upstream from the project to the strategic level, and focusing
on the environmental impacts of PP/Ps already proposed.
Recent definitions take a broader perspective: they see SEA as including the
social and economic dimensions.
In other words, SEA is seen as a key tool for sustainable development.
![Page 34: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/34.jpg)
Key differences
EIA SEA
Legislation
Directive 97/11/EC amending
Directive 85/337/EEC on the
assessment of the effects of certain
public and private projects on the
environment
(“EIA Directive”)
Directive 2001/42/EC on the
assessment of the effects of certain
PPs on the environment
(“SEA Directive”)
Aim of the process
To ensure that planning decisions are
made with full knowledge of a
project’s likely significant
environmental effects; prevent,
reduce or offset any negative effects;
enhance any positive ones
To provide for a high level of
protection of the environment and to
contribute to the integration of
environmental considerations into the
preparations and adoption of PPs
with a view of promoting sustainable
development
ScreeningIdentify whether a project falls within
Annex 1 or 2 of the EIA Directive,
and therefore requires EIA
Identify whether a PP requires SEA
ScopingNot mandatory, but accepted as good
practice
Mandatory requirement to consult
designated statutory bodies on the
scope and level of detail of the
information to be included in the
Report
![Page 35: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/35.jpg)
Key differences
EIA SEA
Focus of assessment
Issues set out in Article 3 of the EIA
Directive including (in)direct effects of
a project on human beings, fauna
and flora, soil, air, water, climate,
landscape, material assets, cultural
heritage and the interaction of the
above factors
Issues set out in Annex I of the SEA
Directive including biodiversity,
population, human health, flora,
fauna, soil, water, air, climate
landscape, material assets, cultural
heritage and the interaction of the
above factors
Alternatives
Requires the Environmental
Statement (ES) to include —where
appropriate— an outline of the main
alternatives studied by the developer
and an indication of the reasons for
choosing an alternative, taking into
account their environmental effects
Requires the Environmental Report
(ER) to identify, describe and
evaluate reasonable alternatives
taking into account the objectives and
the geographical scope of the PP
Effect of the result of
the assessment on
the decision
In determining the project application,
the competent authority is required to
have regard to the ES, as well as to
other material considerations. The
authorities may also request the
developer to provide further
information where they consider that
the ES is inadequate
Provides information to be taken into
consideration prior to any decision,
but does not determine it; a post-
adoption statement must be
produced outlining changes made to
the PP as a result of the SEA,
responses to consultations, and the
main reasons for choosing the plan
versus other reasonable alternatives
examined
![Page 36: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/36.jpg)
Key differences
EIA SEA
Monitoring
The EIA Directive contains no explicit
monitoring requirements; these are
implicit in the identification of
“measures to prevent, reduce and
where possible offset any significant
adverse effects on the environment”;
predicted effects and delivery of
commitments in the ES should be
monitored
The SEA Directive places a duty on
Member States to monitor the
significant environmental effects of
the implementation of PPs in order
to […] identify at an early stage
unforeseen adverse effects, and to
be able to undertake appropriate
action
![Page 37: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/37.jpg)
Part V – Towards Sustainability:
Case Studies
![Page 38: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/38.jpg)
Case Studies
Argentina: Policy Reform in Water and Sanitation Sectors
During the late 1990s, Argentina requested World Bank assistance in
reforming its water and sanitation sectors (cases of medium-size cities and
issues linked to earlier reforms in larger cities).
As per World Bank’s request, the government hired consultants to prepare an
SEA focusing on linkages between Argentina’s environmental regulatory
activities and its water and sanitation sectors.
The SEA was conducted during project preparation, in order to identify
priority issues by examining negative external effects: excessive water losses
(e.g. leaks), water quality deterioration (e.g. degradation due to pollution);
water and waste treatment systems (e.g. noise and odors).
The ministry had reservations about the SEA, feeling EIAs for individual
projects would satisfy World Bank requirements; after the report, the ministry
became a supporter of the SEA.
![Page 39: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/39.jpg)
Case Studies
Canada: Review of the North American Free Trade Agreement (NAFTA)
A few years before issuance of the 1993 guidelines implementing a 1990
directive that requires ex ante SEAs for PPPs, Canada undertook an
environmental review of NAFTA; the case is viewed as an SEA.
NAFTA negotiations took place between June 1991 and August 1992;
however, the Canadian SEA for NAFTA (published in October 1992) did not
reflect an effort to fully integrate SEA-related activities, as the SEA was
conducted after the negotiations had started.
The SEA process included provisions for interagency coordination, but was
only one element of a four-part plan to integrate environmental concerns into
treaty design.
It is unlikely that the SEA played a major role in negotiations, because treaty
negotiators learned of such concerns through earlier work.
![Page 40: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/40.jpg)
Case Studies
The Czech Republic: Tourism Policy 2000
In 1992, the government enacted the Czech Environmental Impact
Assessment Act, according to which the proponent of a development concept
must prepare SEA documentation (including elements typically contained in
project-level EIAs), which is subject to public review.
The Ministry for Regional Development created Tourism Policy 2000
(followed by Sectoral Operational Program for Tourism and the Spa Industry -
SOP) without a required SEA; the Ministry of the Environment advised that
SEAs were required, and the government withheld its final approval of the
policy.
Although both SEAs were conducted after the Ministry for Regional
Development had completed much of its policy design work, they led to
notable changes in the tourism policy and SOP.
![Page 41: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/41.jpg)
Case Studies
The Slovak Republic: Energy Policy 2000
Under the Slovak Republic’s EIA Law (1994), environmental assessments
are required for development policies in the energy sector.
The SEA process was indistinguishable from the process employed to design
Energy Policy 2000; the way in which SEA is integrated into the policy
formulation process has probably been the most important factor behind the
effectiveness of Slovak SEAs.
Although not obligated to, the Ministry of Economy revised its draft policy
based on results of the SEA, conducted by the Ministry of the Environment.
Public involvement was a hallmark: government websites, newspaper
announcements, university and NGO websites, extensive media coverage,
kiosks. By the end of the public comment period, authorities had received
hundreds of comments.
![Page 42: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/42.jpg)
Case Studies
South Africa: KwaZulu-Natal Trade and Industrial Development Policy
The Development Facilitation Act (1995) provides the foundation for
addressing environmental concerns in the context of spatial planning, but
requires no SEAs; however, several jurisdictions in South Africa have
voluntarily undertaken SEAs.
In response to the Act, the KwaZulu-Natal Regional Economic Forum asked
the Council of Scientific and Industrial Research to prepare an SEA providing
input for creating the forum’s trade and industry policy for the region.
The SEA process was completed before the policy-making process started,
but is unclear how or whether the SEA was integrated into policy.
The Council began its SEA work with technical studies, then held a
stakeholder workshop to discuss key environmental issues. The SEA team
later identified assessment criteria for technical issues, the demands of the
scenario on use of natural resources, and the suitability of particular land
areas for different types of industry
![Page 43: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/43.jpg)
Case Studies: Analysis
Complete
Partial /
Simultaneou
s effort
Partial / Late-stage Effort
Partial /
Technical
Support
Level of integration Slovak
RepublicArgentina Canada
Czech
RepublicSouth Africa
Intersectoral coordination Yes Yes Yes Yes No
Public Involvement Yes Yes Yes Yes No
Influence on policy design Yes Yes Unclear Yes Unclear
Influence on monitoring Yes Yes Unclear Unclear No
[Source: Ahmed & Triana, 2008]
![Page 44: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/44.jpg)
Featured Case Study: China’s
GWD StrategyChina: The Great Western Development (GWD) Strategy
China’s western region remains relatively underdeveloped; the
Government’s GWD Strategy provides a strategic framework
linking over 20 national policies and a range of key
construction projects.
The GWD SEA was commissioned by the State Environmental
Protection Administration and its aim was to examine
environmental consequences and risks, and investigate
possible modifications to specific elements of the Strategy.
![Page 45: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/45.jpg)
Featured Case Study: China’s
GWD StrategyBackground
A number of regions in Eastern & Central China had achieved rapid
economic development in the last decade, a transition with profound impact:
on one hand increasing job opportunities, providing access to new
technologies and contributing to significant advances in education and
healthcare; and on the other hand generating ongoing challenges (pollution,
environmental degradation and access to natural resources).
China’s western region includes 12 provinces, regions and municipalities;
hosts a diverse range of ecosystems, communities and economic activities;
and holds more than half of the country’s natural resources.
In October 2000, the government acknowledged that the distributions of
productive forces should be rationally readjusted for the benefit of the
strategy of developing China’s western areas and the efforts should be
intensified to improve infrastructure, protect the environment and strengthen
control of population growth and resources so as to maintain sustainable
development.
![Page 46: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/46.jpg)
Featured Case Study: China’s
GWD StrategyThe Strategy
The GWD Strategy includes a range of public policy instruments with links to
more than 20 national policies and a range of construction projects.
At the most strategic level, policies address issues such as foreign
investment, infrastructure development, natural resource management,
energy, telecommunications, education and urbanization. Projects include
water diversion, natural gas transfer, power transmission and the
construction of a railway.
Purpose of the SEA
In October 2002, China passed an EIA Law requiring SEAs for PPs in certain
sectors (such as energy and transportation).
The Ministry of Environment also wanted to examine the environmental risks
of the Strategy in order to suggest modifications to its concrete elements.
![Page 47: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/47.jpg)
Featured Case Study: China’s
GWD StrategyMethodology
The analysis focused on a broad range of environmental media.
The interim report included chapters on water, air and biodiversity, land
resources and social impacts.
The Delphi method among experts was used to examine direct (intended)
and indirect (unintended) impacts, as well as alternative impact mitigation
options.
Sector-based studies applied a range of additional techniques; e.g.
demand gap analysis in the case of water resources.
There were no references to any formal mechanisms for public
participation within the SEA process.
![Page 48: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/48.jpg)
Featured Case Study: China’s
GWD StrategyResults
The matrix of possible direct and indirect impacts was really thorough and
complex, but the main message emerging was that the environmental
situation in Western China was already serious and the GWD Strategy would
exacerbate some crucial environmental risks. For example:
Increased water demand
High pressure on scarce groundwater resources
Increased water pollution
Pressure on biological diversity from large infrastructure projects and
urbanization
Potential increase in air pollution (due to industrialization, and despite
technological development)
![Page 49: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/49.jpg)
Part VI - Bibliography
![Page 50: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/50.jpg)
Ahmed, K., Triana, E. S. (Eds.). (2008). Strategic environmental assessment for policies: an
instrument for good governance. World Bank Publications.
Arts, J., Tomlinson, P., Voogd, H. (2005, September). EIA and SEA tiering: the missing link. In
International experience and perspectives in SEA”, Conference of the International Association of
Impact Assessment (pp. 26-30).
Dalal-Clayton, B., Sadler, B. (1999). Strategic Environmental Assessment: A rapidly evolving
approach. Environmental Planning Issues No. 18. International Institute for Environment and
Development.
Dalkman, H. (2007, April). Strategic environmental assessment—a promising instrument for
sustainable urban development in China. In Holcim Forum (pp. 155-160).
Ehrhardt, K., Nilsson, M. (2006). Strategic environmental assessment. Advanced Techniques for
Evaluation of Sustainability Assessment Tools, 6th Framework Programme, Brussels, available at:
http://ivm5. ivm. vu. nl/sat.
Holder, J., Lee, M. (2007). Environmental protection, law and policy: text and materials. Cambridge
University Press.
Organisation for Economic Co-operation and Development. (2006). Applying strategic environmental
assessment: good practice guidance for development co-operation. OECD Publishing.
Partidário, M. (2012). Strategic Environmental Assessment Better Practice Guide-methodological
guidance for strategic thinking in SEA. Lisbon: Portuguese Environment Agency and Redes
Energéticas Nacionais (REN).
Bibliography on SEA
7/28/2016 www.sustainedu.com
![Page 51: Multicriteria Decision Analysis/Aid · Review Participation (of all legitimate stakeholders, including the public affected) ... •Early examination of projected impacts of P/PPs](https://reader035.fdocuments.us/reader035/viewer/2022071009/5fc7496980bbd04d8223fc8f/html5/thumbnails/51.jpg)
Sadler, B. (1998). Institutional requirements for strategic environmental assessment. In Paper to the
2nd Intergovernmental Policy. Forum, Christchurch, New Zealand (held in association with the IAIA
Annual Meeting).
Sadler, B., Dalal-Clayton, D. B. (2012). Strategic environmental assessment: a sourcebook and
reference guide to international experience. Earthscan.
Sadler, B., Verheem, R. (1996). SEA: Status, Challenges and Future Directions, Report 53, Ministry of
Housing, Spatial Planning and Environment.
Scottish Executive (2005). A Practical Guide to the Strategic Environmental Assessment Directive.
Office to the Deputy Prime Minister, London.
Schmidt, M., Joao, E., Albrecht, E. (Eds.). (2006). Implementing strategic environmental assessment
(Vol. 2). Springer Science & Business Media.
Shepherd, A., Ortolano, L. (1996). Strategic environmental assessment for sustainable urban
development. Environmental Impact Assessment Review, 16(4), 321-335.
Therivel, R. (2012). Strategic environmental assessment in action. Routledge.
Verheem, R. A. A., Tonk, J. A. M. N. (2000). Strategic environmental assessment: one concept,
multiple forms. Impact Assessment and Project Appraisal, 18(3), 177-182.
Wood, C., Djeddour, M. (1989). Environmental assessment of policies, plans and programmes. Interim
report to the Commission of European Communities. Contract, (B6617-571), 572-89.
Bibliography on SEA
7/28/2016 www.sustainedu.com