Multi-Resource Packing for
Cluster Schedulers
Robert Grandl Aditya Akella
Srikanth KandulaGanesh AnanthanarayananSriram Rao
![Page 2: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/2.jpg)
Diverse Resource Requirements
Tasks need varying amounts of each resource E.g., Memory [100MB to 17GB] CPU [2% of a core to 6 cores]
Need to match tasks with machines based on resource
Demands for resources are not correlated Correlation coefficient across resource demands [–0.11, 0.33]
![Page 3: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/3.jpg)
Current Schedulers do not Pack
Resources allocated in terms of “slots”
Resource Fragmentation
T1: 2 GB
T2: 2 GB
T3: 4 GB
4 GB Memory Machine A
4 GB Memory Machine B
Current Schedulers Packer Schedulers
T1: 2 GB
T2: 2 GB
T3: 4 GB
4 GB Memory Machine A
4 GB Memory Machine B
![Page 4: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/4.jpg)
Current Schedulers do not Pack
Resources allocated in terms of “slots”
Over-allocation
20 MB/sIn Nw.
T1: 2 GB Mem
Current Schedulers
4 GB Memory 20 MB/s In Nw.
Machine A
20 MB/sIn Nw.
T2: 2 GB Mem
20 MB/sIn Nw.
20 MB/sIn Nw.
Packer Schedulers
20 MB/sIn Nw.
T1: 2 GB Mem
4 GB Memory 20 MB/s In Nw.
Machine A
20 MB/sIn Nw.
T2: 2 GB Mem
T3: 2 GB Mem
![Page 5: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/5.jpg)
Current Schedulers do not Pack
Slots allocated purely on fairness
considerations
Cluster [18 Cores, 36 GB] / Job: [Task Prof.], # tasks
A [1 Core, 2 GB], 18
B [3 Cores, 1 GB], 6
C [3 Cores, 1 GB], 6
6 tasks
2 tasks
2 tasks
18cores
16 GB
6 tasks
2 tasks
2 tasks
6 tasks
2 tasks
2 tasks
18cores
16 GB
18cores
16 GB
A
B
Ct 2t 3t
18 tasks
0 tasks
0 tasks
18cores
36 GB
6 tasks
0 tasks 6 tasks
18cores
6 GB
18cores
6 GB
A
B
Ct 2t 3t
Durations:
DRF Packer
Resources used: DRF share = 1/3 Resources used: Packer
Current Schedulers Packer Schedulers
A: 3tB: 3tC: 3t
Durations:A: tB: 2tC: 3t
33% improvement
![Page 6: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/6.jpg)
It is all about packing ?
Multi-dimensional bin packing is NP-hard for #dimens. ≥ 2 Several heuristics proposed But they do not apply here … size of the ball, contiguity of allocation, resource demands are elastic in time
Will perfect packing suffice ?
Competing objectives: Cluster utilization vs. Job completion times vs.
Fairness
![Page 7: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/7.jpg)
Something reasonably simple and which can be applied
Intuition behind the solution
Cluster efficiency Job completion time
Cluster efficiency Fairness
![Page 8: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/8.jpg)
Tetris
Pack tasks along multiple resources Cosine similarity between task demand vector
and machine resource vector
Multi-resource version of SRTF Favor jobs with small remaining duration
and small resource consumption
Incorporate Fairness Fairness knob (0, 1] f → 0 close to perfect fairness f = 1 most efficient scheduling
A
T
F
1: while (resources R are free)2: among FJ jobs furthest from fair share3: score (j) = 4: max task t in j, demand(t) ≤ R A(t, R) + T(j)5: pick j*, t* = argmax score(j)6: R = R – demand(t*) 7: end while
(simplified) Scheduling procedure
![Page 9: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/9.jpg)
Learning task requirements From tasks that have finished in the same phase Coefficient of variation [0.022, 0.41] Collecting statistics from recurring jobs
Task Requirements and resource usages
Resource Tracker measure actual usage of resources enforce allocations aware of activities on the cluster other than
tasks assignment: ingest and evacuation
Peak usage demands estimates for tasks
Machine - In Network
850
1024
0
512
MBy
tes /
sec
Time (sec)In Network UsedIn Network Free Task In Network Estimates
Resource Tracker
![Page 10: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/10.jpg)
Prototype atop Hadoop 2.3
Evaluation
Tetris as a pluggable scheduler to RM Implement RT as a NM service Modified AM/RM resource allocation
protocol
Cluster capacity: 250 Nodes
4 hour synthetic workload
60 jobs with complementary task demands
Reduction (%) in Job Duration - DRF
CDF
Reduces average job duration by up to 40%
Reduces makespan by 39%
Large scale evaluation
![Page 11: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/11.jpg)
Evaluation
Facebook production traces analysis
Fairness knob: fewer than 6% of jobs slow down; by not more than 8% on average
Knob value of 0.75 offers nearly the best possible efficiency with little unfairness
Trace-driven simulation
Fairness Knob - Fair
Slow
dow
n (%
)
Fairness Knob - DRF
Slow
dow
n (%
)
![Page 12: Multi-Resource Packing for Cluster Schedulers Robert Grandl Aditya Akella Srikanth Kandula Ganesh Ananthanarayanan Sriram Rao.](https://reader035.fdocuments.us/reader035/viewer/2022070413/5697bff51a28abf838cbd888/html5/thumbnails/12.jpg)
Conclusion
Identify the importance of scheduling all relevant resources in a cluster
Resource Fragmentation
Over-allocation and Interference
New scheduler that pack tasks along multiple resources
Reduce makespan
Job Completion Time
Enable a trade-off between packing efficiency and fairness
Fairness Knob
Come and see our poster !