Multi-Criteria Assessment of Bridge Options › media › 1095258 › MCA-Assessment-of... · Urban...
Transcript of Multi-Criteria Assessment of Bridge Options › media › 1095258 › MCA-Assessment-of... · Urban...
Newmarket Level Crossing
Multi-Criteria Assessment of Bridge Options
Prepared by:
Public Transport Capital Improvements
2
Newmarket Level Crossing Removal
Document Information
Document Register
Issue Description Prepared by Reviewed by Authorised by Date
001 DRAFT v1 Adrian Price Nesh Pillay Nick Seymour 23 March 2015
002 FINAL Adrian Price Nesh Pillay Nick Seymour 20 April 2015
Client Auckland Transport
Title Newmarket Level Crossing MCA of Bridge Options
Prepared by Public Transport Capital Improvements
Date 20 April 2015
3
Newmarket Level Crossing Removal
Executive Summary
Three bridge variants were produced for stakeholder feedback and circulated to the following
groups:
Waitemata Local Board
Mana Whenua
Newmarket Community Groups (Parnell Community Committee, Newmarket Community
Association, Cycle Action Auckland)
Residents and Landowners in Sarawia Street, Cowie Street, Laxon Terrace and Youngs Lane
Workshops and discussions were held involving the designers Opus, Auckland Transport (AT) project
team and AT specialists from Walking and Cycling, Urban Design, Road Safety Engineering, Road
Corridor Operations, Stormwater, Maori Policy and Engagement, Property and Planning, Auckland
Council Sports, Parks and Recreation, KiwiRail and the project Road Safety Auditor (Aurecon).
The Multi-Criteria Assessment (MCA) workshop held in February 2015 concluded with Option 3,
Combined Space, as the preferred option but concerns were raised over the narrowness of the
bridge and the associated potential impact on the interactions of vehicles, cyclists and pedestrians.
Subsequent discussions on alterations to the option were held with AT Road Safety Engineering, AT
Road Corridor Operations, Opus and the Road Safety Auditor and it was concluded that the bridge
width needed to be increased to provide an adequate level of confidence in the traffic safety
outcomes.
Option 4 was developed in response to these concerns, with a separated pedestrian footpath of
1.8m width combined with a two-lane carriageway similar to Option 2. However, it incorporates and
modifies the traffic calming elements of Option 3 through narrowing of the carriageway at entry
points into the new road section, textured paving over the curve of the road as proposed for the
pedestrian-prioritised portion of Option 3, and a pedestrian refuge immediately before the Cowie
Street entrance onto the bridge.
The options were re-evaluated including Option 4, and the conclusion is that while Option 3 remains
first ranking in many criteria, Option 4 provides the best overall outcome while avoiding the
elements prompting safety concerns associated Option 3.
The inclusion of an observation platform on the curve of the bridge was also assessed, with the
conclusion being that this should be included in the bridge design.
4
Newmarket Level Crossing Removal
Table of Contents
Executive Summary ...................................................................................................................... 3
Table of Contents ......................................................................................................................... 4
Purpose ....................................................................................................................................... 5
Options Assessed ......................................................................................................................... 5
Option 1: Shared Path Bridge ............................................................................................................. 6
Option 2: Pedestrian Footpath Bridge ................................................................................................ 7
Option 3: Combined Space Bridge ...................................................................................................... 8
Multi-Criteria Assessment ............................................................................................................ 9
Criteria Definitions .............................................................................................................................. 9
Results Summary ....................................................................................................................... 12
Option 4: Optimised Mix of Options 2 and 3 .................................................................................... 13
Base Assessment........................................................................................................................ 15
Sensitivity Assessments.............................................................................................................. 17
Expert Assessed Weightings ............................................................................................................. 17
Specified Category Weightings ......................................................................................................... 19
Monte Carlo Simulation .................................................................................................................... 23
Conclusion ................................................................................................................................. 25
Appendices ................................................................................................................................ 26
Appendix 1: MCA Workshop Minutes............................................................................................... 27
Appendix 2: Newmarket Level Crossing Project – Survey Results .................................................... 34
5
Newmarket Level Crossing Removal
Purpose
Three variant options for a bridge linking Cowie Street to Laxon Terrace in Newmarket have been
prepared based on feedback received from stakeholders in 2014.
The purpose is to determine the final bridge footprint and features to be progressed to final
preliminary design via a multi-criteria assessment. Scoring for the assessment has been informed by
the following:
Survey of residents and community groups
Feedback from the Waitemata Local Board
Feedback from Auckland Council Parks, Sports and Recreation
Feedback from Mana Whenua and AT Maori Policy and Engagement
Feedback from KiwiRail
Road Safety Audit for the project
Internal workshop held February 2015 including AT Traffic Operations, Road Safety
Engineering, Walking and Cycling, Planners, Urban Design, Stormwater specialists and Opus
design team.
Subsequent discussion with workshop attendees and the Road Safety Auditor.
Options Assessed
All bridge options share the following features:
Single span bridge over rail corridor beginning at Laxon Terrace and ending at the end of
Cowie Street, through 9 Cowie Street;
Traffic calming area at Cowie Street end of option;
An optional observation platform at the curve of the road, overlooking Newmarket Park
(evaluated separately as part of this MCA);
KiwiRail maintenance access from curve of road towards Parnell tunnel;
Stormwater treatment via vegetated swale located within Newmarket Park; and
Retention of existing Newmarket Park access at Laxon Terrace end.
The following options were initially evaluated:
6
Newmarket Level Crossing Removal
Option 1: Shared Path Bridge
This option includes a two-lane carriageway with a 3.0m wide shared pedestrian/cycle path running along one side of the bridge. The carriageway is widest at the Cowie Street end at 6.4m and narrows along the edge of Newmarket Park to 5.0m to join Laxon Terrace.
This option provides the greatest level of amenity for cyclists but also has the greatest impact on the adjoining Newmarket Park land.
Figure 1: Shared Path Bridge
7
Newmarket Level Crossing Removal
Option 2: Pedestrian Footpath Bridge
This option includes a two-lane carriageway with a 1.5m wide footpath running along one side of the bridge. The carriageway is widest at the Cowie Street end at 6.4m and narrows along the edge of Newmarket Park to 5.0m to join Laxon Terrace.
This option provides a compromise between separated pedestrian and vehicle movements and bridge width and most closely matches the existing amenity levels at Cowie Street and Laxon Terrace.
Figure 2: Pedestrian Footpath Bridge
8
Newmarket Level Crossing Removal
Option 3: Combined Space Bridge
A single combined carriageway and footpath totalling 5.6m width. The bridge width is wide enough for two vehicles to pass along most of the length but periodic buffers spaced approximately 20m apart seek to act as a traffic calming measure and protection for pedestrians. At the buffer points the bridge width is too narrow to permit two vehicles to pass each other, so that one vehicle must give way similar to the action at a one-way bridge or chicane.
This option intends to prioritise pedestrian and cycle movements using the narrow width and buffers and is the narrowest bridge option with least impact on Newmarket Park.
Figure 3: Combined Space Bridge
9
Newmarket Level Crossing Removal
Multi-Criteria Assessment
The criteria applied in the assessment are:
Economic:
Capital cost
Renewal/operating costs
Safety:
Traffic safety
CPTED
Environmental:
Stormwater
Landscape/Visual
Ecology
Earthworks
Urban Design
Noise
Cultural:
Maori values analysis
Heritage effects
Social:
Level of service
Wider community impact
Construction impact
Resident feedback
Criteria Definitions
Economic:
Capital cost: Cost estimates vary mainly due to size of the structure and amount of materials
required and surfacing differences between options. Cost estimates for each option are
based on the road, bridge deck and abutment cost estimates, including P&G and margins.
Renewal/Operating costs: Key differential being area of structure and differing surface
treatments. It is recognised that all options will require a similar, minimum amount of
operating expenditure and a figure of 1.5% of the capital cost estimate was calculated to
give an approximate annual maintenance and renewal cost for each option.
Safety
Traffic safety: Assessed by workshop and reviewed by Road Safety Auditor considering effectiveness of traffic calming, visibility and sight lines and the safe interaction of pedestrians, cyclists and vehicles using each option.
10
Newmarket Level Crossing Removal
CPTED: Assessed by workshop against Crime Prevention Through Environmental Design (CPTED) principles.
Environmental
Each assessed by workshop.
Stormwater: Key differential being the impervious surface of each option.
Landscape/Visual: The visual impact, size of the structure and any mitigations to reduce the landscape effects of the bridge.
Ecology: Impact on surrounding ecology, key differential is the size of the structure and area of Newmarket Park land affected.
Earthworks: Volume of earthworks required for each option.
Urban Design: Assessed against urban design principles.
Noise: Key differential being road surface treatment, e.g. speed tables or textured surface.
Cultural
Maori values analysis: Assessed by internal workshop between AT Planning, Project Manager, and AT Maori Policy and Engagement. Criteria includes effects on sites and places of value/significant, effects on waterways, effects on cultural landscapes and effects on customary rights.
Heritage: Assessed by workshop, identifying and evaluating the level of effect on any areas of historic or heritage value.
Social
Level of service: Assessed by workshop. Includes the quality of the connection for users, including adequate road widths, acceptable gradients, suitability for service and emergency vehicles and minimising of vehicle queuing.
Wider community impact: Derived from feedback gathered from the Waitemata Local Board, community groups and feedback from residents or landowners not located in directly-affected streets.
Construction impact: Assessed by workshop. The impact of the option’s construction on traffic flows and affected stakeholders.
Resident feedback: Derived from results of survey, represents feedback from residents or landowners in directly-affected streets of Sarawia Street, Cowie Street, Laxon Terrace and Youngs Lane.
Criteria for each option have been equally ranked in comparison to the other options shortlisted for
consideration as a baseline, with the sensitivity analysis altering weightings to test the options
analysis under different assumptions and priorities.
11
Newmarket Level Crossing Removal
How each option supports the project objectives was assessed and applied to each criterion on a 0
to 5 scale as follows:
0 Unacceptable
1 Poor
2 Mediocre
3 Neutral
4 Good
5 Excellent
Sensitivities applied consist of:
Expert Assessed: during the internal workshop, attendees weighted each category to reflect
the priorities of the project objectives.
Economic: Economic criteria weighted at 75% collectively, with remaining criteria
collectively adding to 25%.
Safety: Safety criteria weighted at 75% collectively, with remaining criteria collectively
adding to 25%.
Environmental: Environmental criteria weighted at 75% collectively, with remaining criteria
collectively adding to 25%
Cultural: Cultural criteria weighted at 75% collectively, with remaining criteria collectively
adding to 25%
Social: Social criteria weighted at 75% collectively, with remaining criteria collectively adding
to 25%
Monte Carlo simulation: Probability-based simulation conducted to assess the sensitivity of
the MCA outcome to variations in weightings. This was achieved by carrying out ten
thousand tests in which random weightings were assigned to each criterion. A Monte Carlo
simulation was not performed for the observation platform analysis.
12
Newmarket Level Crossing Removal
Results Summary
The overall results are displayed in Figure 4 below:
Figure 4: Results Summary (3 Options Assessed)
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Observation Platform -
Yes Observation
Platform - No
Base Case 44 44 50 53 49
Expert Assessed Sensitivity 2.93 2.73 2.85 3.27 3.05
Economic Weighted Sensitivity 2.61 2.93 3.32 2.70 3.01
Safety Weighted Sensitivity 3.30 2.93 1.94 3.39 3.01
Environmental Weighted Sensitivity 2.50 2.94 3.33 3.52 3.02
Cultural Weighted Sensitivity 2.95 2.93 2.98 3.05 3.01
Social Weighted Sensitivity 2.95 2.24 3.15 3.22 3.18
Monte Carlo Sensitivity 2.75 2.75 3.13 N/A N/A
OVERALL Not
Preferred Not Preferred Safety Not Acceptable Preferred Not Preferred
Ranking: 1st
Yes
2nd
No
3rd
Option 3 is the preferred option in every scenario excluding the Expert Assessed and Safety
Weighted sensitivities. However, following comments emerging from the workshop and subsequent
discussion with AT Road Safety and the Road Safety Auditor, it was apparent that the combination of
a combined space for vehicles, pedestrians and cyclists with the narrow bridge width proved a
challenging combination to implement safely, even with the addition of the buffers spaced along the
length of the road. Accordingly, the Traffic Safety criterion was adjusted to score 0, an Unacceptable
score.
The concern is principally that vehicles pulling to one side behind a buffer to allow another
oncoming vehicle to pass will be inclined to steer into the area prioritised for pedestrians, potentially
blocking a pedestrian’s route of travel or pinning a pedestrian up against the handrail.
13
Newmarket Level Crossing Removal
Widening the carriageway would mitigate this risk, but results in a bridge width equivalent to Option
2, at which point many of the benefits allocated to Option 3 are equally shared by Option 2, being
associated with the lowest cost and lowest impact on Newmarket Park land area.
At this point, a new option seeking to combine the traffic calming benefits of Option 3 with the
separated footpath and wider footprint of Option 2 was prepared:
Option 4: Optimised Mix of Options 2 and 3
The option includes a two-lane carriageway, each lane 2.5m wide, with a 1.8m wide footpath
running along one side of the bridge. The carriageway includes a pedestrian refuge in Cowie Street
and narrowing of the carriageway at the Cowie Street end to assist with traffic calming. Textured
surface at the curve of the road further assists with traffic calming and a chicane near the Laxon
Terrace end of the carriageway is combined with a rain garden and rest area.
This option gives a separated pedestrian area and wider bridge footprint to address traffic safety
concerns of Option 3 while retaining some narrowing at either end of the construction to provide
traffic calming.
Figure 5: Optimised Mix of Options 2 and 3
The inclusion of an observation platform at the curve of the bridge was favoured by the assessment
in all criteria excluding the Economic Weighted sensitivity, due to its comparatively higher cost. The
cost of the addition is comparatively small, at 0.7% of the averaged total bridge construction costs,
14
Newmarket Level Crossing Removal
and the assessment concludes that on balance, the observation platform should be included in the
final design.
The new option was discussed with AT workshop attendees, the Waitemata Local Board and the AT
Maori Policy and Engagement team and a revised MCA analysis was undertaken, including the new
Option 4.
Figure 6: Results Summary (4 Options Assessed)
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt 2
and 3
Observ. Platform
- Yes
Observ. Platform
- No
Base Case 44 44 50 49 53 49
Expert Assessed Sensitivity 2.93 2.73 2.85 3.06 3.27 3.05
Economic Weighted Sensitivity 2.61 2.93 3.32 3.00 2.70 3.01
Safety Weighted Sensitivity 3.30 2.93 1.94 3.00 3.39 3.01
Environmental Weighted Sensitivity 2.50 2.94 3.33 3.12 3.52 3.02
Cultural Weighted Sensitivity 2.95 2.93 2.98 3.00 3.05 3.01
Social Weighted Sensitivity 2.95 2.24 3.15 3.00 3.22 3.18
Monte Carlo Sensitivity 2.75 2.75 3.12 3.06 N/A N/A
OVERALL Not
Preferred Not Preferred Safety Not Acceptable Preferred Preferred
Not Preferred
Ranking: 1st
Yes
2nd
No
3rd
4th
The revised MCA assessment continues to rank Option 3 highly, retaining 1st position in all but the
Expert Assessed, Safety Weighted and Cultural Weighted sensitivities. However, Option 4 presents
15
Newmarket Level Crossing Removal
the best overall balance, scoring 1st or 2nd ranking in all scenarios, and successfully mitigates the
traffic safety concerns of Option 3.
The inclusion of an observation platform remains recommended.
Further detail on the assessment and sensitivities is provided below:
Base Assessment
Figure 7: Base Assessment with equal weighting across criteria
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic*
Capital Cost 2 3 4 3 2 3
Operating Cost 3 3 3 3 3 3
Safety
Traffic Safety 4 3 0 3 3 3
CPTED 3 3 3 3 4 3
Environmental
Stormwater 2 3 3 3 3 3
Landscape/Visual 2 3 4 3 5 3
Ecology 2 3 4 3 3 3
Earthworks 2 3 4 3 3 3
Urban Design 3 3 4 4 5 3
Noise 3 3 2 3 3 3
Cultural
Maori Values** 3 3 3 3 3 3
Heritage 3 3 3 3 3 3
Social
Level of Service 4 2 3 3 4 3
Wider Community† 3 1 4 3 4 3
Constr. Impact 3 3 3 3 2 3
Resident Feedback† 2 2 3 3 3 4
Total 44 44 50 49 53 49
16
Newmarket Level Crossing Removal
Ranking: 1st
Yes
2nd
No
3rd
4th
*Economic scores are calculated as follows:
Capital cost estimate: Costs are averaged and average cost assigned a score of 3. Every 1%
difference in cost from the average adds or subtracts 0.2 to the option’s score. To calculate
the observation platform score the zero cost option was scored at 3 and the additional cost
for including the platform reducing the score by 0.1 for every additional 0.1% of construction
cost. Results were rounded to the nearest whole number.
Renewal/Operating cost estimate: Costs are averaged and average cost assigned a score of
3. Every 1% difference in cost from the average adds or subtracts 0.1 to the option’s score.
This differential is lower than that for capital cost to reflect that the actual difference in
operating costs between options will be minor due to minimal costs to maintain the
structure at all.
**Maori values analysis was calculated by scoring the following sub-criteria and averaging the
results for an overall score:
Figure 8: Maori Values Analysis Sub-Criteria scores by option
Maori Values Analysis
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of
Opt 2 and 3
Observ. Platform
- Yes
Observ. Platform
- No
Effects on Sites/ Places of Value/Significance 4 4 5 4 5 2
Effects on Waterways 1 2 3 2 2 3
Effects on Cultural Landscapes 2 2 2 2 3 3
Customary Rights 3 3 3 3 3 3
AVERAGE 2.5 2.75 3.25 2.75 3.25 2.75
17
Newmarket Level Crossing Removal
Sub-criteria are measured by:
Figure 9: Maori Values Analysis Sub-Criteria Measures
Sub-Criteria Measures
Effects on Sites/ Places of Value/Significance Mauri; Waahi Tapu; Historical; Customary needs; Contemporary esteem
Effects on Waterways Mauri; Waahi Tapu; Historical; Customary needs; Contemporary esteem
Effects on Cultural Landscapes Mauri; Waahi Tapu; Historical; Customary needs; Contemporary esteem
Customary Rights Extent of effects on areas of protected customary rights (under Takutai Moana or Treaty Redress)
†Resident feedback is derived from results from Newmarket Level Crossing: Survey Results, January
2015, which collates responses received back from residents, landowners and community groups to
a survey distributed by AT. Only results from residents or landowners associated with properties in
Sarawia Street, Laxon Terrace, Youngs Lane and Cowie Street are included under Resident Feedback,
the other responses are reflected under the Wider Community Impact score.
Sensitivity Assessments
The sensitivities applied to the multi-criteria analysis are:
Expert Assessed Weightings
The February 2015 workshop attendees assessed each criterion and applied variable weightings to
reflect relative importance to achieving the project objectives.
The weightings were assessed to best reflect the priorities of the project objectives.
Figure 10: Expert-assessed Weightings
Category Criteria Weighting Sub-Weighting
Economic 24%
Capital Cost 17%
Operating Cost 07%
Safety 22%
Traffic Safety 17%
CPTED 05%
Environmental 22%
Stormwater 04%
Landscape/Visual 06%
Ecology 02%
Earthworks 02%
Urban Design 06%
Noise 02%
Cultural 08%
Maori Values Analysis 06%
Heritage 02%
Social 24%
18
Newmarket Level Crossing Removal
Level of Service 12%
Wider Community Impact 05%
Construction Impact 02%
Resident Feedback 05%
Figure 11: Sensitivity Assessment with Expert Weightings
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.34 0.51 0.68 0.51 0.34 0.51
Operating Cost 0.21 0.21 0.21 0.21 0.21 0.21
Safety
Traffic Safety 0.68 0.51 0.00 0.51 0.51 0.51
CPTED 0.15 0.15 0.15 0.15 0.20 0.15
Environmental
Stormwater 0.08 0.12 0.12 0.12 0.12 0.12
Landscape/Visual 0.12 0.18 0.24 0.18 0.30 0.18
Ecology 0.04 0.06 0.08 0.06 0.06 0.06
Earthworks 0.04 0.06 0.08 0.06 0.06 0.06
Urban Design 0.18 0.18 0.24 0.24 0.30 0.18
Noise 0.06 0.06 0.04 0.06 0.06 0.06
Cultural
Maori Values 0.18 0.18 0.18 0.18 0.18 0.18
Heritage 0.06 0.06 0.06 0.06 0.06 0.06
Social
Level of Service 0.48 0.24 0.36 0.36 0.48 0.36
Wider Community 0.15 0.05 0.20 0.15 0.20 0.15
Constr. Impact 0.06 0.06 0.06 0.06 0.04 0.06
Resident Feedback 0.10 0.10 0.15 0.15 0.15 0.20
Total 2.93 2.73 2.85 3.06 3.27 3.05
Ranking: 1st
Yes
2nd
No
3rd
4th
19
Newmarket Level Crossing Removal
Specified Category Weightings
Each sensitivity assigns 75% weighting to each high-level category (Economic, Safety, etc.) divided
equally across all criteria within this category. The remaining 25% is evenly divided across the
remaining criteria.
These sensitivities test the options analysis against a prioritisation of each category in turn to
establish if there are weak areas or inconsistencies in specific areas not revealed by the base
analysis.
Figure 12: Sensitivity Assessment prioritising Economic Outcomes
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.75 1.13 1.50 1.13 0.75 1.13
Operating Cost 1.13 1.13 1.13 1.13 1.13 1.13
Safety
Traffic Safety 0.13 0.09 0.00 0.09 0.09 0.09
CPTED 0.09 0.09 0.09 0.09 0.13 0.09
Environmental
Stormwater 0.02 0.03 0.03 0.03 0.03 0.03
Landscape/Visual 0.02 0.03 0.04 0.03 0.05 0.03
Ecology 0.02 0.03 0.04 0.03 0.03 0.03
Earthworks 0.02 0.03 0.04 0.03 0.03 0.03
Urban Design 0.03 0.03 0.04 0.04 0.05 0.03
Noise 0.03 0.03 0.02 0.03 0.03 0.03
Cultural
Maori Values 0.09 0.09 0.09 0.09 0.09 0.09
Heritage 0.09 0.09 0.09 0.09 0.09 0.09
Social
Level of Service 0.06 0.03 0.05 0.05 0.06 0.05
Wider Community 0.05 0.02 0.06 0.05 0.06 0.05
Constr. Impact 0.05 0.05 0.05 0.05 0.03 0.05
Resident Feedback 0.03 0.03 0.05 0.05 0.05 0.06
Total 2.61 2.93 3.32 3.00 2.70 3.01
20
Newmarket Level Crossing Removal
Ranking: 1st
Yes
2nd
No
3rd
4th
Figure 13: Sensitivity Assessment prioritising Safety Outcomes
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.06 0.09 0.13 0.09 0.06 0.09
Operating Cost 0.09 0.09 0.09 0.09 0.09 0.09
Safety
Traffic Safety 1.50 1.13 0.00 1.13 1.13 1.13
CPTED 1.13 1.13 1.13 1.13 1.50 1.13
Environmental
Stormwater 0.02 0.03 0.03 0.03 0.03 0.03
Landscape/Visual 0.02 0.03 0.04 0.03 0.05 0.03
Ecology 0.02 0.03 0.04 0.03 0.03 0.03
Earthworks 0.02 0.03 0.04 0.03 0.03 0.03
Urban Design 0.03 0.03 0.04 0.04 0.05 0.03
Noise 0.03 0.03 0.02 0.03 0.03 0.03
Cultural
Maori Values 0.09 0.09 0.09 0.09 0.09 0.09
Heritage 0.09 0.09 0.09 0.09 0.09 0.09
Social
Level of Service 0.06 0.03 0.05 0.05 0.06 0.05
Wider Community 0.05 0.02 0.06 0.05 0.06 0.05
Constr. Impact 0.05 0.05 0.05 0.05 0.03 0.05
Resident Feedback 0.03 0.03 0.05 0.05 0.05 0.06
Total 3.30 2.93 1.94 3.00 3.39 3.01
Ranking: 1st
Yes
2nd
No
3rd
4th
21
Newmarket Level Crossing Removal
Figure 14: Sensitivity Assessment prioritising Environmental Outcomes
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.06 0.09 0.13 0.09 0.06 0.09
Operating Cost 0.09 0.09 0.09 0.09 0.09 0.09
Safety
Traffic Safety 0.13 0.09 0.00 0.09 0.09 0.09
CPTED 0.09 0.09 0.09 0.09 0.13 0.09
Environmental
Stormwater 0.25 0.38 0.38 0.38 0.38 0.38
Landscape/Visual 0.25 0.38 0.50 0.38 0.63 0.38
Ecology 0.25 0.38 0.50 0.38 0.38 0.38
Earthworks 0.25 0.38 0.50 0.38 0.38 0.38
Urban Design 0.38 0.38 0.50 0.50 0.63 0.38
Noise 0.38 0.38 0.25 0.38 0.38 0.38
Cultural
Maori Values 0.09 0.09 0.09 0.09 0.09 0.09
Heritage 0.09 0.09 0.09 0.09 0.09 0.09
Social
Level of Service 0.06 0.03 0.05 0.05 0.06 0.05
Wider Community 0.05 0.02 0.06 0.05 0.06 0.05
Constr. Impact 0.05 0.05 0.05 0.05 0.03 0.05
Resident Feedback 0.03 0.03 0.05 0.05 0.05 0.06
Total 2.50 2.94 3.33 3.12 3.52 3.02
Ranking: 1st
Yes
2nd
No
3rd
4th
22
Newmarket Level Crossing Removal
Figure 15: Sensitivity Assessment prioritising Cultural Outcomes
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.06 0.09 0.13 0.09 0.06 0.09
Operating Cost 0.09 0.09 0.09 0.09 0.09 0.09
Safety
Traffic Safety 0.13 0.09 0.00 0.09 0.09 0.09
CPTED 0.09 0.09 0.09 0.09 0.13 0.09
Environmental
Stormwater 0.02 0.03 0.03 0.03 0.03 0.03
Landscape/Visual 0.02 0.03 0.04 0.03 0.05 0.03
Ecology 0.02 0.03 0.04 0.03 0.03 0.03
Earthworks 0.02 0.03 0.04 0.03 0.03 0.03
Urban Design 0.03 0.03 0.04 0.04 0.05 0.03
Noise 0.03 0.03 0.02 0.03 0.03 0.03
Cultural
Maori Values 1.13 1.13 1.13 1.13 1.13 1.13
Heritage 1.13 1.13 1.13 1.13 1.13 1.13
Social
Level of Service 0.06 0.03 0.05 0.05 0.06 0.05
Wider Community 0.05 0.02 0.06 0.05 0.06 0.05
Const. Impact 0.05 0.05 0.05 0.05 0.03 0.05
Resident Feedback 0.03 0.03 0.05 0.05 0.05 0.06
Total 2.95 2.93 2.98 3.00 3.05 3.01
Ranking: 1st
Yes
2nd
No
3rd
4th
23
Newmarket Level Crossing Removal
Figure 16: Sensitivity Assessment prioritising Social Outcomes
Option 1 - Shared
Path
Option 2 - Pedestrian Footpath
Option 3 - Combined
Space
Option 4 – Mix of Opt
2 and 3
Observ. Platform -
Yes
Observ. Platform
- No
Economic
Capital Cost 0.06 0.09 0.13 0.09 0.06 0.09
Operating Cost 0.09 0.09 0.09 0.09 0.09 0.09
Safety
Traffic Safety 0.13 0.09 0.00 0.09 0.09 0.09
CPTED 0.09 0.09 0.09 0.09 0.13 0.09
Environmental
Stormwater 0.02 0.03 0.03 0.03 0.03 0.03
Landscape/Visual 0.02 0.03 0.04 0.03 0.05 0.03
Ecology 0.02 0.03 0.04 0.03 0.03 0.03
Earthworks 0.02 0.03 0.04 0.03 0.03 0.03
Urban Design 0.03 0.03 0.04 0.04 0.05 0.03
Noise 0.03 0.03 0.02 0.03 0.03 0.03
Cultural
Maori Values 0.09 0.09 0.09 0.09 0.09 0.09
Heritage 0.09 0.09 0.09 0.09 0.09 0.09
Social
Level of Service 0.75 0.38 0.56 0.56 0.75 0.56
Wider Community 0.56 0.19 0.75 0.56 0.75 0.56
Constr. Impact 0.56 0.56 0.56 0.56 0.38 0.56
Resident Feedback 0.38 0.38 0.56 0.56 0.56 0.75
Total 2.95 2.24 3.15 3.00 3.22 3.18
Ranking: 1st
Yes
2nd
No
3rd
4th
Monte Carlo Simulation
A Monte Carlo simulation was conducted to assess the sensitivity of the MCA outcome to variations
in weightings. This was achieved by carrying out ten thousand tests in which random weightings
were assigned to each criterion. The average rank and average weighted score of the four bridge
24
Newmarket Level Crossing Removal
options across the 10,000 simulations is shown in figure 17, while the ranking occurrence for each
option over the 10,000 simulations is shown in figure 18.
This sensitivity was not performed for the observation platform.
Figure 17: Sensitivity Assessment with Monte Carlo analysis
Average Rank
Average Score
Option 1 3.48
Option 1 2.75
Option 2 3.49
Option 2 2.75
Option 3 1.34
Option 3 3.13
Option 4 1.69
Option 4 3.06
Figure 18: Ranking Occurrences over 10,000 Monte Carlo Simulations
Rank Option 1 Option 2 Option 3 Option 4
1 0.0% 0.0% 68.7% 30.9%
2 2.0% 0.2% 28.6% 68.7%
3 47.6% 50.1% 2.0% 0.0%
4 50.0% 49.3% 0.3% 0.0%
Ranking: 1st
2nd
3rd
4th
25
Newmarket Level Crossing Removal
Conclusion
The results indicate Option 3 as the highest-scoring option in most criteria, but Option 4 presents the
best overall position, ranking 1st or 2nd in every criterion. Option 3 has fundamental challenges
meeting the traffic safety criterion and achieved an unacceptable score in this area.
The principal differentiators in the assessment are found in some criteria more than others. Key
differentiating criteria emerging from the assessment are:
Capital Cost Estimate: principally, the wider the structure, the higher the cost.
Traffic Safety: mostly affects the more novel Option 3, but also reflected in the higher-
scoring Option 1 which includes a shared cycle and pedestrian path separated from the
vehicle carriageway.
Environmental Criteria: principally Landscape/Visual, Ecology and Earthworks where the
wider structures have a greater impact visually and on nearby Newmarket Park. This is an
important factor in why Option 3 consistently scores highly in the MCA.
Level of Service: greater amenity provided by the wider bridge footprints is reflected in this
score.
Wider Community Impact: opinion tended to be polarised in this criterion, with little
support for Option 2 and a division between the higher cycle amenity levels of Option 1
versus the lower cost, lower impact on Newmarket Park of Option 3. Option 4 picked up
some of the support for Option 3, following the traffic safety issues, as the next best option
in this respect, balancing width with traffic safety with traffic calming measures.
Resident Feedback: The scores are not widely varied, but the criterion warrants further
discussion as the survey results were polarised between options. The averaged survey
results led to scores of 2 or 3 as the feedback in favour and opposed to each option,
particularly Options 1 and 3, tended to cancel one another out. There was no single clear
preferred option emerging from the feedback, and the similar scores reflect this. The results
of the survey are described in greater detail in Appendix 2.
The other criteria tended to score similarly as the differences in impact between options were
usually minor. For example, heritage impact for each option are identical as the heritage impacts for
any bridge in this location are the same or very similar.
The observation platform assessment indicates that this should be included in the final design. The
comparatively minor cost to include it (0.65% of the construction capital cost estimate for Option 4)
and potential lost opportunity if this is not included in the structure now and considered desirable
later due to growth in pedestrian and cycle use of the bridge also support inclusion of the
observation platform in the design.
Based on the MCA outlined in this report, bridge concept Option 4 with an observation platform
included is selected as the preferred option to progress to detailed design. This option consists of
two traffic lanes of 2.5m width each with a 1.8m footpath on one side of the carriageway.
26
Newmarket Level Crossing Removal
Appendices
Appendix 1: MCA Workshop Minutes, 3rd February 2015
Appendix 2: Newmarket Level Crossing Project – Survey Results, January 2015
27
Newmarket Level Crossing Removal
Appendix 1: MCA Workshop Minutes
MINUTES OF MEETING
File: Newmarket Level
Crossing
Sheet: Concept Options
MCA Workshop Date: 03/02/2015 Time: 10AM - 2PM
Subject Concept Options MCA Workshop – minutes
Location Meeting room 1, Opus International
Consultants, The Westhaven, Auckland, NZ
Minutes By: Moustafa Al-Ani
Persons Present Organisation
1. Moustafa Al-Ani (MA) Opus
2. Shane Dale (SD) Auckland Transport
3. Andy Irwin (AI) Auckland Transport
4. Michael Perry (MP) Auckland Transport
5. Nesh Pillay (NP) Auckland Transport
6. Adrian Price (AP) Auckland Transport
7. Sarah Rowan (SR) Opus
8. Jarrod Snowsill (JS) Opus
9. Ina Stenzel (IS) Auckland Transport
10. Peter Wiles (PW) Opus
Item Discussion and Action Actions
0 Apologies: Simon Lough, Nick Seymour, Irene Tse
28
Newmarket Level Crossing Removal
Item Discussion and Action Actions
1
Purpose of Workshop
MA detailed the purpose of the workshop – to evaluate the 3 concept design
options for the purposes of a Multi-Criteria Analysis (MCA) for 9 criteria. The
aim of the MCA is to facilitate a decision for the preferred concept design
option.
AP clarified that a similar process is also to be undertaken for the observation
platform.
Both
2
Project Background
AP presented a brief background of the project. ALL in attendance indicated at
least a moderate level of knowledge of the project background.
3
Scoring of Criteria
The scoring process involved a fluid discussion of the advantages and
disadvantages of each option by ALL in attendance, with scores allocated as
follows:
1. Poor
2. Mediocre
3. Neutral
4. Good
5. Excellent
The main points of discussion were recorded and have been captured below.
3.1
Traffic Safety:
Options 1&2:
o road could be narrowed earlier (closer to Cowie St end)
o ~300mm wide kerb before barriers
o could also include buffers, as per option 3
Option 3:
o Distance between buffers could be shortened (to 10m?)
o Different (rougher) pavement texture should be used along the
footpath side for the visually-impaired
o Preference would be for no lowered speed limit at this stage but
to revisit this issue at a later date if required.
Option 1 2 3
Score 4 3 2
29
Newmarket Level Crossing Removal
Item Discussion and Action Actions
3.2
Crime Prevention through Environmental Design (CPTED):
The differences between the three options are not expected significantly affect
the CPTED outcomes of the design.
Option 1 2 3
Score 3 3 3
3.3
Stormwater:
Option 3 has the lowest impervious surface of the three options,
followed by option 2, with option 1 introducing the largest impervious
area.
Option 3 has the largest potential for stormwater treatment due to the
reduced impact on Newmarket Park land allowing for greater areas of
treatment swales.
If possible, stormwater from Cowie St catchment is to be collected and
treated along with the stormwater from the new impervious surface.
This will require separation of the existing combined sewer at the
bottom of Cowie St.
Option 3 increased treatment potential is dependent on the ability of
the reduced carriageway width to carry stormwater from the Cowie St
catchment. If this is confirmed, the score for option 3 should be
increased to a 4.
Option 1 2 3
Score 2 3 3*
3.4
Landscape/Visual:
Planting on rail side unlikely for all options
Patterning on walls and abutments will be used to enhance the overall
aesthetic appeal of the project
Planted trees will likely need 10-15 years to re-grow to existing
age/height
Ayr St residents are keen to retain view of Newmarket Park, not bridge.
Option 1 2 3
Score 2 3 4
30
Newmarket Level Crossing Removal
Item Discussion and Action Actions
3.5
Ecology:
Ecological impact influenced by footprint. Largest footprint is for option
1, followed by option 2, with option 3 having the smallest footprint.
Stormwater treatment swales also support life, and therefore the option
allowing the largest area of swales (option 3) provides the most
ecological mitigation.
Option 1 2 3
Score 2 3 4
3.6
Earthworks:
The option with the smallest footprint (option 3) has the smallest impact
in terms of earthworks.
Option 1 2 3
Score 2 3 4
3.7
Urban Design:
Option 3 provides more opportunities for incorporation of urban design
elements, including into the buffers.
Option 1 2 3
Score 3 3 4
3.8
Heritage:
The differences between the three options are not expected significantly affect
the heritage impact of the design.
Option 1 2 3
Score 3 3 3
31
Newmarket Level Crossing Removal
Item Discussion and Action Actions
3.9
Level of Service:
The access and level of service provided to pedestrians and cyclists is
prioritised over that provided to vehicular traffic.
Option 2, designed to match the existing widths at Laxon Terrace and
provide minimal impact on Park land for a separated roadway option,
falls below AT Codes of Practice and is considered the weakest option
due to inadequate footpath width and the shifting of cyclists onto the
road.
While the 3m combined path in option 1 meets minimum standards,
current thought is that pedestrians prefer to not share space.
Option 3 doesn’t provide defined space for cyclists.
Option 1 2 3
Score 4 2 3
4
Observation Platform
Local resident feedback is generally split but roughly estimated to be
60% against to 40% in favour of the observation platform
Mana Whenua feedback has been strongly in favour of the platform
CPTED:
o The observation platform introduces additional passive
surveillance
o The platform will need to be well-lit, and not concealed
o The platform is expected to encourage positive use of the route.
Criteria Observation platform - Yes
Observation platform - No
Traffic Safety 3 3 CPTED 4 3 Stormwater 3 3 Landscape/Visual
5 3
Ecology 3 3 Earthworks 3 3 Urban Design 5 3 Heritage 3 3 Level of Service
4 3
32
Newmarket Level Crossing Removal
Item Discussion and Action Actions
5
Expert Weightings
ALL in attendance were asked for input into the relative weightings of the
criteria to be used for the MCA.
The following comments were noted during this process:
The weighting for cost can be increased in this case as the difference
between the three options for the remaining criteria is generally not
prominent.
Traffic safety and level of service remain prominent as they directly
address the project objectives.
Where the differences between the three options are notably minor,
such as for noise or earthworks, relatively small weighting has been
attached to these criteria.
Criteria Weighting
Economic 24%
Capital Cost Estimate 17%
Renewal/Operating Cost Estimate 7%
Safety 22%
Traffic Safety 17%
CPTED 5%
Environmental 22%
Stormwater 4%
Landscape/Visual 6%
Ecology 2%
Earthworks 2%
Urban Design 6%
Noise 2%
Cultural 8%
Mana Whenua Impact 6%
Heritage 2%
33
Newmarket Level Crossing Removal
Item Discussion and Action Actions
6
Other Comments and Wrap-up
General comments:
Fencing will be required at KiwiRail accessway
Additional signage will be required on Cowie St for all options
Signage and traffic calming will be required at the Cowie St-Parnell Rd
intersection
The location of turning heads, if any, needs to be addressed
No parking or stopping is to be allowed along the bridge for all options
Colour and/or texture of pavement surface can be used to differentiate
between vehicle and pedestrian regions for option 3
The use of rough-textured pavement surface could lead to noise issues
Wrap-up:
The scores arrived at from the workshop will be combined with scores for other
criteria to determine the preferred concept option and the preferred
observation platform option. The timeline for this decision is anticipated to be
by the end of the week (6th February, 2015).
AP, MA, NP,
JS
34
Newmarket Level Crossing Removal
Appendix 2: Newmarket Level Crossing Project – Survey Results