Mukabi Jn (Ph.d)_cv_edited Jan2012
-
Upload
john-ngaya-mukabi -
Category
Documents
-
view
96 -
download
0
Transcript of Mukabi Jn (Ph.d)_cv_edited Jan2012
![Page 1: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/1.jpg)
JN Mukabi
(Ph.D)
Curriculum
Vitae
January 18
2012 Dr. Mukabi is vastly experienced in the field of Geotechnical Engineering, Soil Mechanics, Geoscience, Geophysics, Geomathematics and Civil Engineering
Proffessional CV
![Page 2: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/2.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
CURRICULUM VITAE
1. NAME OF STAFF : JOHN NGAYA MUKABI
2. MAIN POSITIONS : Chief Executive Officer/Chief Technical Advisor (CTA)/LEAD CONSULTANT 3. NAME OF FIRM : Kensetsu Kaihatsu Limited/Kensetsu
Kaihatsu Consultants CTA /DIRECTOR for various other firms
4. PROFESSION : Geotechnical /Civil Engineer
5. DATE OF BIRTH : 12th September 1959
6. NATIONALITY : Kenyan
7. MEMBERSHIPS OF PROFESSIONAL SOCIETIES:
MISSMGE (MEMBER OF THE INTERNATIONAL SOCIETY OF SOIL MECHANICS AND GEOTECHNICAL
ENGINEERING)
MAIPE (MEMBER ADVISOR OF THE INTERNATIONAL PANEL OF ENGINEERS)
MEGEP (MEMBER OF THE SPECIAL RESEARCH AND EXECUTIVE WORKING GROUP OF THE EUROPEAN
GEOGRIDS EXPERTS PANEL)
MASCE ( MEMBER OF THE AMERICAN SOCIETY OF CIVIL ENGINEERS)
MTCISSMGE (MEMBER OF THE TECHNICAL COMMITTEE OF THE INTERNATIONAL SOCIETY OF SOIL
MECHANICS AND GEOTECHNICAL ENGINEERING)
![Page 3: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/3.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
MRCARSSMGE (MEMBER OF THE RESEARCH COMMITTEE OF THE AFRICAN REGION - INTERNATIONAL
SOCIETY OF SOIL MECHANICS AND GEOTECHNICAL ENGINEERING)
MPRARSSMGE (MEMBER OF THE PEER REVIEW OF THE AFRICAN REGION - INTERNATIONAL SOCIETY OF
SOIL MECHANICS AND GEOTECHNICAL ENGINEERING)
MIAEG (MEMBER OF THE INTERNATIONAL ASSOCIATION OF ENGINEERING GEOLOGY)
CMWRA (CORPORATE MEMBER OF THE WORLD ROAD ASSOCIATION)
CMWRF (CORPORATE MEMBER OF THE WORLD ROAD FEDERATION)
MJGS (MEMBER OF THE JAPAN GEOTECHNICAL SOCIETY)
MJSCE (MEMBER OF THE JAPAN SOCIETY OF CIVIL ENGINEERS)
MCKGS (FOUNDER MEMBER AND PRESIDENT OF THE KENYA GEOTECHNICAL SOCIETY)
MAFACE (MEMBER ADVISOR TO THE ETHIOPIAN ASSOCIATION OF CIVIL ENGINEERS)
PRMWASET (PEER REVIEW MEMBER OF WORLD ACADEMY OF SCIENCE, ENGINEERING AND TECHNOLOGY
– SCIENTIFIC & TECHNICAL COMMITTEE & EDITORIAL REVIEW BOARD ON NATURAL AND APPLIED
SCIENCES)
MIEEE (MEMBER OF THE INSTITUTE OF ELECTRICAL & ELECTRONICS ENGINEERS)
MIECE (MEMBER OF THE INTERNATIONAL INSTITUTION OF CIVIL ENGINEERS)
MIAMG (MEMBER OF THE INTERNATIONAL ASSOCIATION OF MATHEMATICAL GEOSCIENCES)
MIUGG (MEMBER OF THE INTERNATIONAL UNION OF GEODESY AND GEOPHYSICS)
EBMIJGEOMATE (EDITORIAL BOARD MEMBER OF THE INTERNATIONAL JOURNAL OF GEOTECHNIQUE,
MATERIALS AND ENVIRONMENT)
EBMIRJESTI (EDITORIAL BOARD MEMBER OF THE INTERNATIONAL RESEARCH JOURNAL OF
ENGINEERING, SCIENCE, TECHNOLOGY AND INNOVATION)
MICASIT (MEMBER OF THE INTERNATIONAL ASSOCIATION OF COMPUTER SCIENCE AND INFORMATION
TECHNOLOGY)
![Page 4: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/4.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
8. DETAILED TASKS ASSIGNED
For most Civil Engineering Projects, Dr. Eng. John Ngaya Mukabi is usually the Team Leader, Lead
Consultant and/or Project Manager, Project Director, Chief Technical Advisor, Materials,
Pavement, Highway and Geotechnical Engineer/Expert as well as Lead Researcher.
Dr. Mukabi has also been charged with the responsibility of offering technical advisory services in
various aspects regarding sustainable infrastructure development in general, and roads, airports,
foundations for civil engineering structures and to Research & Development (R&D) a nuber of
Government Agencies in the East and Central African Region (mainly; Ethiopia, Tanzania, Kenya,
South Sudan and Burundi).
9. KEY QUALIFICATIONS
Being one of the most brilliant Engineers and Scientist of our times and a leading African Engineer,
Dr. Mukabi is vastly experienced in the field of Geotechnical Engineering, Soil Mechanics,
Geroascience, Geophysics, Geomathematics and Civil Engineering. His achievements are vast,
showing the highest value input, some of which have made him earn numerous awards. He is
currently the only Non-Euro Member of World Elite Scholars of the European Geogrid Experts
Panel, EGEP, alongside the other various esteemed memberships above. His approach to design
and engineering is unique and he has come up with revolutionary methods and techniques that
immensely assist Engineers in both design and construction supervision. For more than 28 years he
has worked on highways, bridges, airports, and many more large Civil Engineering Projects. His
skills in developing unique and innovative concepts and techniques for practical application in
Geotechnical Engineering, Materials Testing, Survey Methods, Analytical Approach, Perceptive
Scientific Tools, Systematic Approach Concepts, Engineering/Scientific Theories, Design Approach
and Methods of Construction as well as scientific and engineering research and specialized
construction supervision methods are, by any standards hardly quantifiable.
He studied in Japan for 13 years mastering the skills he mainly adopts in practice for various major
projects in the African Region and internationally. He attained a Ph.D Degree from The University
of Tokyo graduating among the top in his class consisting of international and Japanese students.
While in Japan, Dr. Mukabi participated in a number of large-scale projects and his substantial
research input culminated, partly, in the realization of the Ultra Futuristic 21st Century City - the
Minato Mirai 21 (MM21). This is a city in Yokohama City of Japan that incorporates all the modern
design elements including automated highways, high-tech information superhighway
infrastructure, high-tech smart buildings and amenity facilities constructed predominantly on land
![Page 5: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/5.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
that was reclaimed from the sea. He also possesses great qualities, knowledge and genius for civil
engineering construction of bridges, highways, and affordable housing for developing countries,
which result in appreciable cost savings.
Whilst at the University of Tokyo, Dr. Mukabi also had opportunities to conduct advanced joint
research with scholars from the Massachusetts Institute of Technology (MIT), Harvard University,
University of Cambridge, Imperial College, University of London, City University London,
University of Sydney, University of Beijing, University of Rome, University of Naples, Politecnico di
Torino, among others.
He also received research grants to undertake research for such institutions in Japan as, the Public
Works Research Institute, Ministry of Construction, Port and Harbor Research Institute, Ministry of
Transport, Kajima Corporation Research Institute, Technology Research Centre of Taisei
corporation, Obayashi Corporation Technical Research Institute, Central Research Institute of
Electric Power Industry, Tokyo Electric Company Research Institute, Ariake Bay Research Group,
Tokyo Bay Research Group, Kansai International Airport Research Group, Kandagawa Flood –
Control Research Group, Kansai Electric Company Research Institution, Railway Technical
Research Institute, Honshu Shikoku Bridge Authority, Minato Mirai 21 (MM 21)Development
Authority, Institute of Technology of Tokyu Construction Co. Ltd, Metropolitan Expressway Public
Corporation of Tokyo, Geo – Research Institute of Osaka, and Institute of Industrial Science of the
University of Tokyo, among others.
His Projects Oriented research work in Africa has also been mainly sponsored by the Japan Bank of
International Corporation (JBIC), Japan International Corporation Agency (JICA), Kajima
Corporation, Tokyo, Japan, Tensar International, London, UK, Construction Project Consultants,
Tokyo, Japan, Katahira and Engineers International Tokyo, Japan, Mitsui Corporation,
Johannesburg, South Africa, ConAid PTY Inc. Johannesburg, South Africa, Geo technologies,
Johannesburg, South Africa, Sumitomo Corporation, Nairobi, Kenya, Katahira and Engineers
International, Manila, Philippines and Urban Tone Corporation Co. Ltd, Bangkok, Thailand.
Dr. Mukabi has held key positions in international firms including Katahira & Engineers
International, Construction Project Consultants (CPC), Inc., and Kajima Corporation, among
others, where he has held such Senior and Executive positions as Chief Technical Advisor, General
Manager and Asst. Managing Director for the African Region. He is also the CEO and Chief
Consulting Engineer of Kensetsu Kaihatsu Consultants, Chairman of Createch Management
Consultants, Director and Chief Technical Advisor of numerous local and International
![Page 6: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/6.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Construction Firms, all organizations of which are deeply involved with projects in Developing
Countries all over the world. He has excellent and practical communication skills combined with a
great sense of humor and compassion, characters which make him easy to work with, and open to
ideas and discussions.
He has mainly worked within the African region for the past 14 years, mainly for Projects under
the International Aid Agencies such as The Japan International Cooperation Agency (JICA), World
Bank, Asian Development Bank (ADB), African Development Bank (AfDB) various NGOs and many
other organizations. He has played a major pivotal role in the success of various projects by
providing prompt and pragmatic engineering solutions to some of the most critical geotechnical
engineering problems and complex soils, besides developing VE (Value Engineering)
countermeasures for projects in areas suffering from a gross lack of suitable materials for road
and foundation design and construction. His engineering contribution has led to appreciably
enormous cost savings and reduction in terms of construction time of some major highway and
bridge projects particularly in Ethiopia, South Sudan, Tanzania, Uganda, Rwanda, Burundi, South
Africa, Mozambique, Kenya and the African and Asian Regions in general.
Dr. Mukabi strongly believes in the importance of fostering capacity building and technology
transfer for the benefit of upcoming Engineers and Professionals geared purposely for achieving
sustainable development. He has initiated and established various programmes to assist young
people and Engineers attain higher knowledge and expertise. He has also been a direct and distant
Supervisor and Examiner of Post Graduate Students in University of Nairobi, Jomo Kenyatta
University of Agriculture and Technology (JKUAT) and Addis Ababa University as well as various
universities in Asia and Europe. His research is founded on top global high technology and focused
on the African Continent with its type of materials and problems that face Engineers, Donors,
Politicians and in general, the people of Africa. He has worked extensively in Ethiopia, Southern
Sudan and Tanzania.
Currently, he is directly involved in civil engineering projects and restoration/restructuring of
public research institutes in Kenya, Southern Sudan, Ethiopia, Ghana, Egypt, Tanzania, Zambia,
South Africa, whilst offering distant advisory services in various other countries worldwide,
including mainly Germany, England, Italy, Hungary, Poland, Russia etc, whereby he always
encourages the enhancement of Research & Innovation for Sustainable Development (RISD),
advancement of Value Engineering Technologies, Technology Transfer, Capability and Capacity
Building as well as appropriate Training Programmes for Young Engineers and Scientists.
![Page 7: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/7.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Dr. Mukabi has been awarded more than 35 top international honours and cited in major
biographical references including The Contemporary Who’s Who of Professionals – 2005/2006,
American Hall of Fame, The Genius Elite, Great Minds of the 21ST
Century, The
Contemporary Who’s Who 2003/2004, American Biographical Institute (ABI) Contemporary
Hall of Fame, The 2003/2004 Leading Intellectuals of The World, The World Book of
Knowledge 2004, 2008 IBC Who’s Who, Ambassador of Africa in the World Forum of Science
and Culture, Oxford 2008, and many more. He has received more than 25 awards in Science,
Engineering and Technology including others such as ABI Man of The Year 2003, American
Medal of Honour Award 2004, ABI Noble Laureate, World laureate of the ABI 2004, Life
Achievement Award 2005, The Da Vinci Diamond Award 2006, Leader in Science Award 2007,
Achievement in Research Award 2007, ABI Fellow 2008, Great Minds of the 21st Century in
Science & Technology 2008, International Order of Merit Award 2009, Gold Medal for Kenya
in Science and Technology 2010, Hall of Fame for Distinguished Accomplishments in 2010,
among others.
EDUCATION
10. EDUCATION & SCHOLARSHIPS : Ph.D in Geotechnical Engineering, Post
Graduate School of Civil Engineering,
University of Tokyo, Japan - April 1991 ~
March 1995
: MSc. in Civil Engineering, Post Graduate
School of Civil Engineering, University of
Tokyo, Japan - April 1989 ~ March 1991
: BSc. (First Class Hons.) in Civil Engineering,
Department of Civil & Marine Engineering,
Yokohama National University, Japan - April
1985 ~ March 1989
![Page 8: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/8.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
SCHOLARSHIPS
: International Rotary Club
: Rotary Yoneyama, Japan
: Kajima Foundation, Japan
: Mombusho (Ministry of Education) Tuition
Scholarship, Japan
: United Nations Scholarship Candidate
![Page 9: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/9.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
11. RELEVANT SEMINARS, ENGINERING/SCIENTIFIC CONFERENCES, TRAINING, AND PUBLICATIONS:
1. Lectures offered by Dr. Mukabi
Dr. Mukabi has participated in many International Conferences, Symposiums, Seminars,
Workshops and Engineering Forums in which he has or is due to give the following Lectures,
including Keynote Addresses and Keynote Lectures:
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
The Advanced Role of OBRM in
Road Construction and the
Geo-environmental Mitigation
XXVTH World Road Congress Seoul, South Korea
WRC
Expected to
Lecture in
November, 2015
Recently Developed Value
Engineering Technologies for
Highway Design and
Construction in Africa
XXVTH World Road Congress Seoul, South Korea
WRC
Expected to
Lecture in
November, 2015
Application of Geoscientific
Methods Developed for
Analyzing the Behaviour of
Stabilized and
Geosynthetically Reinforced
Tropical Soils
16th African Regional
Conference on Soil
Mechanics and
Geotechnical
Tunis, Tunisia
ISSMGE
Expected to
Lecture in August,
2015
Soil-Structure Interaction
Mechanisms Based on the MCST
and CSSR Functions
16th African Regional
Conference on Soil
Mechanics and
Geotechnical
Tunis, Tunisia
ISSMGE
Expected to
Lecture in August,
2015
Change in Current Stress State-
Induced Anisotropy of Stiff
Pleistocene Clays Resulting
from Static and Dynamic
Loading Effects
16th African Regional
Conference on Soil
Mechanics and
Geotechnical
Tunis, Tunisia
ISSMGE
Expected to
Lecture in August,
2015
Some Vital Geotechnical
Engineering Elements for
Foundation Design and
Construction
Fourth TC-ISSMGE
International Conference
on New Developments in
Soil Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
ISSMGE
Expected to
Lecture in August,
2014
![Page 10: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/10.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Influence of Drainage
Conditions on Small Strain
Characteristics of Stiff
Pleistocene Clays
Fourth TC-ISSMGE
International Conference
on New Developments in
Soil Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
ISSMGE
Expected to
Lecture in August,
2014
Application of the Initial Yield
and CSSR Concepts in
Enhancing Vital Geotechnical
Engineering Parameters
Fourth TC-ISSMGE
International Conference
on New Developments in
Soil Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
ISSMGE
Expected to
Lecture in August,
2014
Static and Dynamic Loading
Effects on Drained and
Undrained Small Strain
Characteristics of Clayey
Geomaterials
Fourth TC-ISSMGE
International Conference
on New Developments in
Soil Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
ISSMGE
Expected to
Lecture in August,
2014
Simulation of Impact of
Seismic Loading on Degree of
Destructuration of Clayey
Geomaterials
Fourth TC-ISSMGE
International Conference
on New Developments in
Soil Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
ISSMGE
Expected to
Lecture in August,
2014
Some Vital Geotechnical
Engineering Elements for
Pavement Structural Design
and Construction
International Conference
of The Institution of
Engineers of Kenya
Nairobi, Kenya
IEK
Expected to
Lecture in April,
2014
Application of the Initial Yield
Strain Concept in Developing
the Failure Criteria for MEPD
Specifications
International Conference
of The Institution of
Engineers of Kenya
Nairobi, Kenya
IEK
Expected to
Lecture in April,
2014
Challenges and Innovations in
Geotechnics for African
Representative Soils
XVIII International
Conference on Soil
Mechanics and
Geotechnical Engineering
(ICSMGE )
Paris, France.
ISSMGE
Expected to
Lecture in
September 2013
![Page 11: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/11.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Influence of Varying
Consolidation Stress-strain
Histories on Small Strain
Behaviour of Stiff Geomaterials
XVIII International
Conference on Soil
Mechanics and
Geotechnical Engineering
(ICSMGE )
Paris, France.
ISSMGE
Expected to
Lecture in
September 2013
Introducing Intricate
Geomathematical Module
Functions for the OPMCS
Technology
15th Annual Conference of
The International
Association of
Mathematical Geosciences
Madrid, Spain
IAMG
Expected to
Lecture in
September 2013
Geoscientific Comparative
Analysis of the Interaction of
Geosynthetics with Natural and
Stabilized Tropical Soils
IEEE International
Geoscience and Remote
Sensing Symposium
(IGARSS)
Melbourne, Australia
IEEE & GRSS
Expected to
Lecture in July,
2013
Geoscientific Method of
Remote Field Data Acquisition
and Analysis for Civil
Engineering Application
IEEE International
Geoscience and Remote
Sensing Symposium
(IGARSS)
Melbourne, Australia
IEEE & GRSS
Expected to
Lecture in July,
2013
Some Recently Developed
Analytical Techniques for
Underground Construction in
Tropical Problematic Soils
International Conference
of The Institution of
Engineers of Kenya
Nairobi, Kenya
IEK
Expected to
Lecture in April,
2013
Advancing Innovative Ground
Improvement Technologies for
Founding Civil Engineering
Strucures
International Conference
of The Institution of
Engineers of Kenya
Nairobi, Kenya
IEK
Expected to
Lecture in April,
2013
Innovative Laboratory and In-
situ Methods of Testing in
Geotechnical Engineering
International Conference
of The Institution of
Engineers of Kenya
Nairobi, Kenya
IEK
Expected to
Lecture in April,
2013
A Geomathematical Method
for Quantitative Analysis of the
Impact of Sub-surface
Geoenvironmental Changes
International Conference
on Applied Physics and
Mathematics
ICASIT
Expected to
Lecture in April,
2013
![Page 12: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/12.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Application of OPMCS Strut
Micropiling Technique for
Foundation Ground and
Subgrade Improvement
ISM 11th International
Workshop on Micropiling
Rome, Italy
ISM, DFI & ADSC
Expected to
Lecture in
October, 2012
Some Recently Developed
Ground Improvement
Techniques for Tropical
Expansive Soils
The 4th International
Conference on Problematic
Soils
Wuhan, China
IAEGE & CSTAM
Expected to
Lecture in
September, 2012
Geoscientific Methods of
Remote Data Derivation for
Geotechnical Engineering
Applications
The 34th International
Geological Congress
Brisbane, Australia
IUGS & IAMG
Expected to
Lecture in
October, 2012
Proposed Quadruple Process
Model and Geomathematical
Functions Simulating Earth
Dynamic Processes
IEEE International
Geoscience and Remote
Sensing Symposium
(IGARSS
Munich, Germany
IEEE & GRSS
Expected to
Lecture in July,
2012
Integrated Geo-Probabilistic
and Geo-Statistical Module
Functions for the Proposed
Quadruple Process Model
IEEE International
Geoscience and Remote
Sensing Symposium
(IGARSS
Munich, Germany
IEEE & GRSS
Expected to
Lecture in July,
2012
Recent Developments of
Quantitative Determination of
Kinematic Hardening Sub-Yield
Surface Limits
Third International
Conference on New
Developments in Soil
Mechanics and
Geotechnical Engineering
North Cyprus, Turkey
TNCSMGE & NEU
Expected to
Lecture in June,
2012
Case Study Analysis of OPMC
Improved Foundation Ground,
Pavement and Other Geo-
structures Employing the
GECPRO Model
International Symposium
on Ground Improvement
(IS-GI)
Brussels, Belgium
ISSMGE-TC211 & BBRI
Expected to
Lecture in May,
2012
Application of High-Order
Spatial Cumulants Concept in
Developing Sophisticated
Analytical Methods and
Stochastic Simulation for
Stabilized Geomaterials
2nd International
Conference on Applied
Physics and Mathematics
(ICAPM)
Chennai, India
IACSIT
Expected to
Lecture in April,
2012
![Page 13: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/13.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
The Role of Research Oriented
Approach and Innovation in
Geotechnical Engineering for
Enhanced Technological
Development for Vision 2030
1st Regional Symposium on
drilling and Piling
Foundation
Nairobi, Kenya
The BAUER Group,
Germany
Expected to
Lecture in March,
2012
Characterization and Modelling
of Various Aspects of Pre-
failure Deformation of Clayey
Geomaterials – Fundamental
Theories and Analyses
KEYNOTE LECTURE
First International
Conference on
Geotechnique,
Construction Materials and
Environment
Mie, Japan
JGS, JSIDRE, JCK &
GI
November 2011
Characterization and Modelling
of Various Aspects of Pre-
failure Deformation of Clayey
Geomaterials – Application in
Modelling
KEYNOTE LECTURE
First International
Conference on
Geotechnique,
Construction Materials and
Environment
Mie, Japan
JGS, JSIDRE, JCK &
GI
November 2011
Derived Empirical Relations
and Models of Vital
Geotechnical Engineering
Parameters Based on
Geophysical and Mechanical
Methods of Testing
15th African Regional
Conference on Soil
Mechanics and
Geotechnical Engineering
Maputo, Mozambique
SSCE/ ISSMGE July 2011
Fundamental Theory of the
ReCap Technique and its’
Application in the Construction
of Pavement Structures within
Problematic Soils
15th African Regional
Conference on Soil
Mechanics and
Geotechnical Engineering
Maputo, Mozambique
SSCE/ ISSMGE July 2011
Case Study Analysis of a
Heavily Loaded Road Pavement
Structure Constructed on Black
Cotton Soil
15th African Regional
Conference on Soil
Mechanics and
Geotechnical Engineering
Maputo, Mozambique
SSCE/ ISSMGE July 2011
![Page 14: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/14.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
A Scientific Approach in
Determining Sustainable
Solutions to Slope Failures and
Landslides
2011 International Union
of Geodesy and
Geoscience – Earth on the
Edge: Science for a
Sustainable Planet
Melbourne, Australia June/July 2011
Some Recently Developed
Analytical Techniques for
Underground Construction in
Problematic Soils
The VIITH International
Symposium on
Geotechnical Aspects of
Underground Construction
in Soft Ground –
Underground Construction
in Soft Ground
Roma, Italy May 2011
Case Study Analysis of Scouring
Effects on Tropical Soils Slope
Formation
VTH International
Conference on Scour and
Erosion (ICSE-5)
San Francisco,
California, USA November 2010
Application of Lorentz
Transformations in Defining
Particulate Behaviour of
Tropical Geomaterials under
Dynamic Loading
International Conference
on Applied Mathematics,
Mechanics and Physics
Kyoto, Japan October 2010
Characterization of Black
Cotton Soil under Static and
Dynamic Loading – Testing and
Analyses
The International ICGE
Conference on
Geotechnical Engineering
Tunis, Tunisia
ISSMGE & TGS October 2010
Characterization of Black
Cotton Soil under Static and
Dynamic Loading – Discussions
and Analyses
The International ICGE
Conference on
Geotechnical Engineering
Tunis, Tunisia
ISSMGE & TGS October 2010
Some Advanced Aspects of the
Interaction of Geotechnical
Engineering and African
Geology
11th Congress of the
International Association
for Engineering Geology
Auckland, New
Zealand
New Zealand
Geotechnical Society
Inc. (NZGS)/IAEG
August 2010
![Page 15: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/15.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
A Mathematical Approach in
Determining the Influence of
Environmental Factors on
Geomaterials
The 14th Annual
Conference of the
International Association
for Mathematical
Geosciences
Budapest, Hungary
IAMG
August/September
2010
Proposed Theory of Soil
Particle Agglomeration and the
Profound Reciprocal Effects on
the Behaviour of Composite
Geomaterials
2010 IEEE International
Geoscience and Remote
Sensing Symposium
Hawaii, USA July 2010
Geotechnical challenges
underlying and circumscribing
Subsurface Development in
Nairobi
The International
Geotechnical Conference –
Geotechnical Challenges in
Megacities
Moscow, Russia
ISSMGE & RGS June 2010
Case Example of Design and
Construction within
Problematic Soils
The International
Geotechnical Conference –
Geotechnical Challenges in
Megacities
Moscow, Russia
ISSMGE & RGS June 2010
A Mathematical Introduction of
the Fundamental Theory of
GECS (Global Energy
Conservation Systems)
The 5th International
Conference of
Mathematics and
Engineering Physics
Cairo, Egypt
ISMEP May 2010
Mathematical Derivative of the
Modified Critical State Theory
and it’s Application in Soil
Mechanics
International Conference
on Applied Physics and
Mathematics
Kuala Lumpur,
Malaysia
IACSIT
May 2010
Pavement and Hydraulic
Structural Design Review Based
on the Value Engineering
Comprehensive Method of
Design (VE-CMD)
Technical Forum on
Improvement of Design
and Construction Aspects
for the Bomet Township
Roads and Storm Water
Hydraulic Structures
Nairobi, Kenya March 2010
![Page 16: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/16.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Pavement Structural Design
Review of the Songwe
International Airport Based on
the Value Engineering
Comprehensive Method of
Design (VE-CMD)
Technical Forum on Value
Engineering Aspects in
Pavement Structural
Design
Dubai, Emirates
BADEA/OPEC/TAA February 2010
Pavement Structural Design
Review Based on the Value
Engineering Comprehensive
Method of Design (VE-CMD)
Technical Forum on
Improvement of Design
and Construction Aspects
for the Gisambai ~ Mbale
Road
Nairobi, Kenya January 2010
Employing the CMD for the
Design of Bridge Foundations in
Juba Town
Workshop on the Juba
Urban Transport
Infrastructure (JUTI) and
Capacity Development
Study
Juba, Southern Sudan
JICA/GOSS December 2009
Application of OPMC
Technology in the Realization
of Affordable Housing
Research and Development
Forum on Affordable
Housing
Juba, Southern Sudan
USAID November 2009
Vital Engineering Elements in
the Design Review of the
Songwe International Airport
Pavement Structures
Engineering Workshop on
the Cost-effective
Enhancement of the
Structural Capacity of
Pavement Structures
Songwe, Tanzania
BADEA/OPEC/TAA October 2009
Recently Developed Suction
Stress, Moisture and Swell
Control Techniques Applied for
Ground Improvement
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Bibliotheca,
Alexandrina,
Alexandria, Egypt.
ISSMGE
September 2009
Application of CSSR Concepts
in the Prediction of Ground,
Pavement and Foundation
Behaviour
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Alexandria, Egypt.
ISSMGE September 2009
Design and Construction of
OPMC Stabilized Retaining
Walls
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Alexandria, Egypt.
ISSMGE
September 2009
![Page 17: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/17.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Strength and Deformation
Characteristics Derived from
the Interaction of Geogrids and
Tropical Geomaterials
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Alexandria, Egypt.
ISSMGE
September 2009
Some Geotechnical
Engineering Based Solutions to
Problems Related To Some
Tropical Problematic Soils
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Alexandria, Egypt.
ISSMGE
September 2009
Small Strain Behaviour of
Drained and Undrained
Pleistocene Clays under
Monotonic and Cyclic Loading
XVII International
Conference on Soil
Mechanics and
Geotechnical Engineering
Alexandria, Egypt.
ISSMGE
September 2009
Some Value Engineering
Perspectives of Pavement
Structural Design of the
Kaptama ~ Kapsokwony Road
Section
Technical Forum on the
Improvement of Some
Design Aspects of
Pavement Structures
Kitale, Kenya
MoR
June 2009
Some Recent Advances in Road
Design and Construction
Seminar on Recent
Advances in Road Design
and Construction
Khartoum, The Sudan
Eyat Oil Exploration
Co. Ltd
February, 2009
Employment of Value
Engineering in the Design of
Foundations for the MTC
Building Structures
Workshop on the Study and
Design of the Multi-
Training Centre Structures
Juba, Southern Sudan
JICA
January 2009
A Newly Proposed Approach in
the Pavement Structural
Design of the Lainya ~ Jambo
Road in Southern Sudan
Technical Workshop on
Latest Developments in
Pavement Design Methods
within the East and
Central African Region
Juba, Southern Sudan
GOSS
October 2008
Evaluation of the Technical
and Engineering Aspects for
the Comprehensive Design
Review of the Mbeya ~
Lwanjilo Trunk Road Project
Workshop on Appropriate
Value Engineering Design
for Roads and Bridges
Mbeya, Tanzania
TANROADS
August 2008
![Page 18: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/18.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Nairobi Underground City
Development Proposal
Nairobi Underground City
Development Proposal
Nairobi, Kenya.
Ministry of Local
Government (MoLG)
& Kensetsu Kaihatsu
Consultants
June 2008
The Role of Enhanced Research
in Geotechnical Engineering
for Pragmatic Infrastructure
Development within the Vision
2030
The Engineer and Vision
2030
Nairobi, Kenya.
Institute of Engineers
of Kenya, IEK
May 2008
The Challenges and Solutions
for Problematic Soils for
Infrastructure Development in
Kenya and the East Africa
Region.
The Engineer and Vision
2030
Nairobi, Kenya.
Institute of Engineers
of Kenya, IEK
May 2008
Newly Developed Technologies
for Roads and Bridges: An
example of Comprehensive
Design and Construction
Approach considering Tropical
Geomaterial Characteristics.
The Engineer and Vision
2030
Nairobi, Kenya.
Institute of Engineers
of Kenya, IEK
May 2008
Application of the Mechanics
of Tropical soils in
Geotechnical Engineering:
Some Recent Advances and
Introduction of Futuristic
Concepts on Geoscientific,
Global Energy Conservation
Systems GECS
The Engineer and Vision
2030
Nairobi, Kenya.
Institute of Engineers
of Kenya, IEK
May 2008
Pavement Structural Design
Review Based on the Value
Engineering Comprehensive
Method of Design (VE-CMD)
Transport Infrastructure
Development Seminar for
Juba Town
Juba, Southern Sudan
WB/GOSS April 2008
Practical Solutions for Soil
Reinforcements and Ground
Stabilization by Application of
Tensar Technology and OPMC
Interaction between US
and African Engineering
Consultants
Dares salaam,
Tanzania.
USAID/ Tensar Int.
March 2008
![Page 19: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/19.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Evaluation of the Structural
Performance of the Ntare ~
Ruhatsi Boulevard
Experimental Testing Trial
Sections
Workshop on the
Development of New
Design Approach
Bujumbura, Burundi
JICA February 2008
Strength and Deformation
Characteristics Derived from
the Interaction of Geogrids and
OPMC Stabilized Geomaterials
The Mechanisms of
Interaction of Geogrids
and Tropical Soils.
Hamburg, Germany.
European Geogrids
Experts Panel
December 2007
Pad Foundation Design for Oil
Drilling Rigs Based on Recently
Developed Ground
Improvement and Soil
Stabilization Technologies
Workshop on the Design of
Foundations and Pavement
Structures for the White
Nile Oil Exploration
Project
Nairobi, Kenya
WNOE November 2007
Application of Consolidation
and Shear Stress Ratio
Concepts in Foundation Design
and Construction
Soils of Africa
14th African Regional
Conference
Yaoundé, Cameroun
Comité National des
Géotechnhniciens du
Cameroun
ISSMGE
October 2007
Characterization of Expansive
Soils to Determine Appropriate
Highway and Foundation
Design – Construction Methods
Soils of Africa
14th African Regional
Conference
Yaoundé, Cameroun.
Comité National des
Géotechnhniciens du
Cameroun
ISSMGE
October 2007
A Comprehensive Method of
Analysis for Cost-Effective
Detailed Design of Pavement
Structures
Soils of Africa
14th African Regional
Conference
Yaoundé, Cameroun.
Comité National des
Géotechnhniciens du
Cameroun
ISSMGE
October 2007
![Page 20: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/20.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Employing Cost-effective
Countermeasures to Slope
Failure Based on Newly
Developed OPMC Stabilization
Concepts
Soils of Africa
14th African Regional
Conference
Yaoundé, Cameroun.
Comité National des
Géotechnhniciens du
Cameroun
ISSMGE
October 2007
Practical Solutions for Soil
Reinforcements and Ground
Stabilization through the
Application of Geosynthetic
and OPMCS Technologies
Technical Forum for
Application of Advanced
Geotechnologies
Dar Es Salaam,
Tanzania
AIAD/GEA/KKL
October 2007
Unique Methods of enhancing
Unique Properties of
Geomaterials
XXIII World Road Congress
Paris, France.
World Road Congress
PIARC
September 2007
Application of a New
Mechanical Stabilization and
Other Techniques in Reducing
the Cost and Impact of Rural
Road Construction
XXIII World Road Congress
Paris, France.
World Road Congress
PIARC
September 2007
Some Recent Advances in
Pavement Structural Design
and Methods of Construction
Workshop on “From
Reconstruction to
Development” – EMPS for
Basic Physical and Social
Infrastructure in Juba
Town and the Surrounding
Areas in Southern Sudan
Juba, Southern Sudan
JICA/GOSS August 2007
A Comprehensive Approach To
The Design of Flexible
Pavements In Tropical
Countries
10th Australia New Zealand
Conference on
Geomechanics
Brisbane, New
Zealand. August 2007
Some Engineering Based
Solutions To Problems Related
To Expansive Soils
10th Australia New Zealand
Conference on
Geomechanics
Brisbane, New
Zealand. August 2007
![Page 21: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/21.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Technical and Engineering
Challenges and Proposed
Countermeasures for the
Causeways along the Wau ~
Abyei Trunk Road
Seminar on Reconstruction
of Infrastructure Northern
States in Southern Sudan
Wau, Southern Sudan
UN-WFP July 2007
Geotechnologies for
Sustainable Infrastructure
Development
Developing Geotechnology
for Sustainable
Infrastructure
Development
Nairobi, Kenya.
Kensetsu Kaihatsu
Consultants
May 2007
The Dynamics of Sustainable
Highway Development within
the Juba Transport
Infrastructure Master Plan
Workshop on Transport
Infrastructure Master Plan
for Juba
Juba, Southern Sudan
JICA/GOSS August 2006
Technical Evaluation of the
Geotechnical Engineering
Challenges along the Kakuma ~
Lokichogio Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya June 2006
Technical Evaluation of the
Geotechnical Engineering
Challenges along the Lodwar ~
Kakuma Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya May 2006
Technical Evaluation of the
Geotechnical Engineering
Challenges along the Marich
Pass ~ Lodwar Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya April 2006
Transport Infrastructure
Development Study In The
Larger Juba Town
First Seminar on The
Emergency Study on The
Planning And Support For
Basic Physical And Social
Infrastructure In Juba
Town And The Surrounding
Areas
Juba, Southern
Sudan.
JICA
April 2006
![Page 22: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/22.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Technical Evaluation of the
Geotechnical Engineering
Challenges along the
Kapenguria ~ Marich Pass Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya March 2006
Technical Evaluation of the
Geotechnical Engineering
Challenges along the Baringo ~
Marich Pass Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya February 2006
Technical Evaluation of the
Geotechnical Engineering
Challenges along the Kabarak ~
Baringo Road
Seminar on EAC/NEPAD
Initiative for Regional
Integration
JICA/GoK
Nairobi, Kenya January 2006
Potential Geotechnical
Engineering Challenges Related
to Flyover(Suspended) Highway
Structures Development in
Nairobi
Workshop on the Nairobi
Metropolitan Urban
Transport Master Plan
Nairobi, Kenya
JICA/GoK October 2005
Geoscience Principles for
Engineering Design and
Application
31st International Congress
on Science, Culture and
Arts in the 21st Century
Hawaii, USA.
ABI/ IBC September 2005
“Developing A Scientific
Approach to Partial Solutions
of Geotechnical Engineering
Problems”
31st International Congress
on Science, Culture and
Arts in the 21st Century
Hawaii, USA.
ABI/ IBC September 2005
An Experimental and Analytical
Method Proposed for
Evaluating High Plasticity
Natural Geometrical
15th International Road
Federation (IRF)
Real Madrid, Spain.
IRF/ WRF August 2005
A unique VE Pavement Design
and Construction Approach
Adopted for Some Road
Projects in Kenya and Ethiopia
15th International Road
Federation (IRF)
Real Madrid, Spain.
IRF/ WRF August 2005
![Page 23: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/23.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Pavement Structure Design and
Construction Control
15th International Road
Federation (IRF)
Real Madrid, Spain.
IRF/ WRF August 2005
“Some Modified Methods for
Highway Design and
Construction”
15th International Road
Federation
Real Madrid, Spain.
IRF/ WRF August 2005
“Characterization of Tropical
Geomaterials Bearing Civil
Engineering Structures
Annual Conference of EACE
Addis Ababa,
Ethiopia
EACE/JICA/ERA
April 2005
“The CMM Systematic Approach
Concept for The Design of
Flexible Pavement Structures
in Developing Countries”
Special Engineering
Lecture
Addis Ababa, Ethiopia
EACE/AAU April 2005
A Value Engineering Design for
the Pavement Structures of
the Holeta ~ Muger Road
Special Engineering
Lecture
Addis Ababa, Ethiopia
ERA February 2005
Some State of the Art Design
Principles and Construction
Techniques
Young Engineers Seminar
on Road Engineering
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
EACE
December 2004
Some Recent Advances in
Highway and Bridge
Foundation Engineering
Capacity Building Seminar
in Engineering Design for
Counterpart Engineers of
Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
ERA
November 2004
Application of Value
Engineering Comprehensive
Design Concepts for the
Pavement Structural Design of
the Gimbothaya International
Airport Access Road
Seminar on Sustainable
Infrastructure
Development in Northern
Ethiopia
Bahir Dar, Ethiopia
Office of the Deputy
Prime Minister
September 2004
Application of Value
Engineering Comprehensive
Design Concepts for the
Pavement Structural Design of
the Bahir Dar University
Pedagological Access Road
Seminar on Sustainable
Infrastructure
Development in Northern
Ethiopia
Bahir Dar, Ethiopia
Office of the Deputy
Prime Minister
September 2004
![Page 24: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/24.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
A New Technique for The
Design and Construction of
Slope Protection Structures
Civil Engineering Seminar
Addis Ababa,
Ethiopia.
EACE/AAU/Kajima
Corporation
April 2004
“Some Recently Developed
Empirical Formulae For
Foundation Design
16th International
Congress on Science and
Culture
Dublin, Ireland.
ABI/IBC April 2004
The Enhancement of Structural
Capacity and Serviceability
Level of the Addis Ababa ~
Goha Tsion Trunk Road
Second 2003 Workshop on
Research Oriented Design
and Construction for Civil
Engineering Projects - II
Addis Ababa, Ethiopia
GoJ, JICA, MoFED &
ERA
April 2004
Recently Developed Civil
Engineering Countermeasures
to Slope, Embankment and
Pavement Structures
First 2003 Workshop on
Research Oriented Design
and Construction for Civil
Engineering Projects
Addis Ababa, Ethiopia
GoJ, JICA, MoFED &
ERA
March 2004
“Characterization of Tropical
Geomaterials Bearing Civil
Engineering Structures”
Consulting and Practicing
Engineers in Tropical
Countries
Addis Ababa,
Ethiopia.
EACE/AAU/Kajima
Corp
March 2004
“Comprehensive Design
Analysis of OV Type Based on
The Proposed CMD Design
Concept”
Evaluation of Design
Analysis in Africa
Ethiopia.
ERA, CPC, Kajima
Corp.
February 2004
Some State of the Art Design
Principles and Construction
Techniques
Young Engineers Seminar
on Road Engineering
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
EACE
December 2003
Some Recent Advances in
Materials Science and
Engineering
Capacity Building Seminar
in Engineering Design for
Counterpart Engineers of
Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
ERA
November 2003
![Page 25: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/25.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
“The Role of Enhanced
Research Oriented Highway
and Foundation Design for
Sustainable Development”
KEYNOTE LECTURE
International Workshop on
the Recent Trends in Civil
Engineering
Nairobi, Kenya.
Kyoto University
Obayashi Corporation
& JKUAT
August 2003
“Impact of Environmental
Factors on the Performance of
Highway Pavement Structures”
The International Civil
Engineering Seminar on
Sustainable Development
in the 21st Century.
Nairobi, Kenya.
International Civil
Engineering Society
August 2003
“Innovating Modified NDT/DT
Techniques for the Evaluation
of An Existing Pavement
Structure-Theoretical
Considerations and
Experimental Results”
The International Civil
Engineering Seminar on
Sustainable Development
in the 21st Century.
Nairobi, Kenya.
International Civil
Engineering Society
August 2003
“Innovating Modified NDT/DT
Techniques for the Evaluation
of An Existing Pavement
Structure-Method of Testing”
The International Civil
Engineering Seminar on
Sustainable Development
in the 21st Century.
Nairobi, Kenya.
International Civil
Engineering Society
August 2003
Some State of the Art Design
Principles and Construction
Techniques
Young Engineers Seminar
on Road Engineering
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
EACE
December 2002
Some Recent Advances in
Slope Stability Design
Capacity Building Seminar
in Engineering Design for
Counterpart Engineers of
Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
ERA
November 2002
Effects of some geological
aspects on the mechanical
performance of tropical road
construction geomaterials
9th International IAEG
Congress on “Engineering
Geology for Developing
Countries
Durban, South Africa.
IAEG September 2002
Some Recent Advances in
Highway and Bridge
Foundation Design
Evaluation of Japan ODA in
Africa
Ethiopia.
Japan ODA and ERA July 2002
![Page 26: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/26.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Proposed approach to
Determining Countermeasures
to Slope Failure at Sta.
9+310km ~ 9+346km
Annual Conference for
EACE
Addis Ababa,
Ethiopia.
EACE
May 2002
Some State of the Art Design
Principles and Construction
Techniques
Young Engineers Seminar
on Road Engineering
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
EACE
December 2001
Some Recent Advances in
Highway Pavement Structural
Design
Capacity Building Seminar
in Engineering Design for
Counterpart Engineers of
Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima,
ERA
November 2001
Computation of Capping Layer
Thickness with Reference to
Native Subgrade Bearing
Capacity
Young Engineers Capacity
Building Programme
Addis Ababa,
Ethiopia.
ERA/JICA
November 2001
“Evaluation of some Kenyan
geomaterial properties for
embankment design based on a
quasi-empirical approach”
15th International
Conference on Soil
Mechanics and
Geotechnical Engineering
(ICSMGE)
Istanbul, Turkey.
ISSMGE August 2001
“Derivation and application of
consolidation and shear stress
functions with reference to
Critical State analysis of N.C.
clays”
15th International
Conference on Soil
Mechanics and
Geotechnical Engineering
(ICSMGE)
Istanbul, Turkey.
ISSMGE August 2001
“Pragmatic method of
evaluation design parameters
adopting Kenyan tropical soils
for pavement structure”
14th IRF World Road
Congress
Paris, France.
IRF/ WRF June 2001
Strength and deformation
characteristics of mechanically
stabilized road construction
materials based on a new
batching ratio method
14th IRF World Road
Congress
Paris, France.
IRF/ WRF June 2001
![Page 27: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/27.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Theoretical and empirical basis
for a method of determining
and optimum batching ratio for
mechanical stabilization of
geomaterials
14th IRF World Road
Congress
Paris, France.
IRF/ WRF June 2001
Appropriate Design of Bridge
and Hydraulic Structures along
the Malindi ~ Garissa Trunk
Road
Technical Forum on Design
of Bridges and Hydraulic
Structures within the Tana
Basin Development Project
Malindi, Kenya
JBIC/GOK November 2000
Unique Design of Reinforced
Earth Structures and Slope
Protection Applying the Newly
Developed OBRM Technology
Technical Forum on Design
of Bridge Abutments
within the Tana Basin
Development Project
Malindi, Kenya
JBIC/GOK November 2000
Hydro-geological Aspects of
the Post El-Nino Flood Impact
Technical Forum on Design
of Hydraulic Structures
within the Tana Basin
Development Project
Mombasa, Kenya
JBIC/GOK May 2000
Geotechnical Engineering
Properties of the
Representative Soils in the
Western Region of Kenya
Workshop on the Study of
Rural Roads Improvement
in Western Kenya
Nairobi, Kenya
JICA/GOK October 1999
Behaviour of CON-AID Treated
Fine Grained Kenyan Soils
12th African Regional
Workshop on Geotechnics
for Developing Africa
Durban, South Africa.
ISSMGE, ARSGE October 1999
Influence of Reconsolidation
Stress History and Strain Rate
on The Behaviour of Kaolin
Over a Wide Range of Strain
12th African Regional
Workshop on Geotechnics
for Developing Africa
Durban, South Africa.
ISSMGE, ARSGE October 1999
Effects of Stress Path and
Aging in Reconsolidation on
Deformation Characteristics of
Stiff Clays
Second International
Symposium on Pre-Failure
Deformation of
Geomaterials
Torino, Italy.
ISSMGE September 1999
![Page 28: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/28.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Recent Advance in Highway
Design Principles and
Engineering
Workshop on the
Systematic and
Appropriate Study and
Design Approach for
Provincial and District
Engineers of the Ministry
of Roads and Public Works,
Kenya
Kakamega, Kenya
JICA) August 1999
Recent Advances in Highway
Design Principles and
Engineering
Workshop on the
Systematic and
Appropriate Study and
Design Approach for
Provincial and District
Engineers of the Ministry
of Roads and Public Works,
Kenya
Kisumu, Kenya
JICA August 1999
Recent Advance in Highway
Design Principles and
Engineering
Workshop on the
Systematic and
Appropriate Study and
Design Approach for
Provincial and District
Engineers of the Ministry
of Roads and Public Works,
Kenya
Nairobi, Kenya
JICA August 1999
Preliminary Research Oriented
Pavement Structural Design of
the Moi International Airport
Access Road
Technical Forum on the
Design of the Moi
International Airport
Access Road
Mombasa, Kenya
Mitsubishi/Takenaka
Corporations
November 1998
Comprehensive Analysis of the
Differential and Total
Settlement of Building
Structures at the Athi River
Cement Works
Technical Forum on the
Settlement Problem of the
Athi River Cement Works
Nairobi, Kenya
Sumitomo
Corporation
October 1998
Proposed Engineering
Mitigation Strategies in
Relation to El-Nino Damaged
Structures
Technical Forum on El-
Nino Mitigation Measures
Malindi, Kenya
JBIC/OP-GOK October 1998
![Page 29: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/29.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Some Recent Advances in
Materials Testing and Chemical
Stabilization Techniques
Workshop on Advanced
Geotechnical Testing for
Practicing Geotechnical
engineers.
Evaton, South Africa
CON AID Pty, Mitsui
corporation South
Africa
September 1998
Enhancement of Civil
Engineering Research &
Development Initiatives in
Kenya
Workshop on Advancing
Regional Civil Engineering
R&D Activities
Nairobi, Kenya
IDI, Japan August 1998
Some Recent Advances in
Materials Testing and Chemical
Stabilization Techniques
CON-AID Seminar for
Consulting and Practicing
Engineers
Nairobi, Kenya
CON-AID Pty, Mitsui
Corporation and CPC
July 1998
The Effects of Rapid
Development and Civil
Engineering Structures on Eco-
systems
Eco-training programme
for Japanese University
Students
Masai Mara, Kenya
Todo Press Inc. Japan April 1997
The Effects of Rapid
Development and Civil
Engineering Structures on Eco-
systems
Eco-training programme
for Japanese University
Students
Masai Mara, Kenya
Todo Press Inc. Japan May 1997
Enhancing Eco-tourism in
Developing Africa
Regional Seminar on Eco-
tourism
Nairobi, Kenya
Utalii College April 1996
Effects of Swelling and
Saturation of Unsaturated Clay
in Laboratory Testing
International Symposium
on Unsaturated Soils
Behaviour and Applications
Nairobi, Kenya.
University Of
Nairobi/
Saskatchewan
University,
Canada/CSCE
October 1995
Small Strain Behaviour of
Suginami Clay In Triaxial
Compression
50th Annual Conference of
JSCE
Kobe, Japan.
JSCE September 1995
![Page 30: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/30.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Proposed Ground Improvement
Methods for the Ariake Geo-
environment
Engineering Symposium on
the Design and
Construction of Rail Road
Systems in Ariake
Fukuoka, Japan
ARG April 1995
Geotechnical Engineering
Design Parameters of the OAP
Structures
Engineering Symposium on
the Design and
Construction of OAP
Skyscraper Buildings
Osaka, Japan
OCDA April 1995
Hi-tech Geo-Technical Testing
Techniques
Advanced Geotechnical
Engineering Methods of
Testing for Practicing
Engineers
Tokyo, Japan
JICA March 1995
Effects of Reconsolidation
Stress History and LTC on the
Behaviour of Stiff Clays at
Small Strains in Triaxial Tests
29th Japan National
Conference on SMFE
Wakayama, Japan.
JGS March 1995
Deformation Characteristics of
Reconstituted Ariake Clay
Technical Forum on the
Properties of Ariake Clay
under Seismic Loading
Fukuoka, Japan
ARG November 1994
Some Proposed Geotechnical
Engineering Design Elements of
the Soil Strata within the
Vicinity of the Flood Control
Shaft
Engineering Symposium on
the Design of the
Kandagawa Flood Control
Project
Tokyo, Japan
Taisei Corporation October 1994
Small Strain Stiffness of
Pleistocene Clays in Triaxial
Compression
First International
Symposium on Pre-failure
Deformation
Characteristics of
Geomaterials
Hokkaido, Japan.
JGS, ISSMGE September 1994
Strength and Deformation
Behaviour of Long Term
Consolidated Osaka Bay Clay
Symposium on the
Engineering Properties of
Osaka Bay Geomaterials
Osaka, Japan
PHRI, MoT August 1994
Hi-tech Geo-Technical Testing
Techniques
Advanced Geotechnical
Engineering Methods of
Testing for Practicing
Engineers
Tokyo, Japan
JICA July 1994
![Page 31: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/31.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Effects of Prestraining on the
Geotechnical Engineering
Characteristics of Hard
Suginami Clayey Sand
Engineering Symposium on
Enhanced Flood Control
Technologies
Tokyo, Japan
TSRC/Taisei
Corporation
May 1994
Small Strain Characteristics of
the Osaka Bay Clay under
Static and Dynamic Loading
Engineering Symposium on
the Dynamic Properties of
Osaka Bay Geomaterials
Osaka, Japan
PHRI, MoT April 1994
“Stiffness and Effects of
Sample Disturbance of Stiff
Clays By Triaxial Tests”
29th Japan National
Conference on SMFE,
Morioka, Japan.
JSSMFE March 1994
Impact of Loading Rate on the
Consolidation Properties of the
Osaka Bay Clay
Technical Symposium on
the Characteristics of
Osaka Bay Clay under
Dynamic Loading
Osaka, Japan
PHRI, MoT November 1993
Field and Laboratory
measurements of small strain
stiffness for Osaka Bay Clays
49th Annual Conference of
JSCE
Sendai Japan
JSCE September 1993
Some Geotechnical Engineering
Aspects of the Kandagawa
Flood Control Project
Engineering Symposium on
Enhanced Flood Control
Technologies
Tokyo, Japan
TSRC/Taisei
Corporation
September 1993
The Importance of
Mathematics and Science in
Civil Engineering
International Symposium
on Engineering
Mathematics and Science
for Graduate Engineers
Denver, USA.
ASCE August 1993
The Importance of
Mathematics and science in
civil Engineering
International Symposium
on Engineering
Mathematics and Science
for Graduate Engineers
Los Angeles, USA.
ASCE August 1993
Hi-tech Geo-Technical Testing
Techniques
Advanced Geotechnical
Engineering Methods of
Testing for Practicing
Engineers
Tokyo, Japan
JICA June 1993
Enhancing Geotechnical
Engineering Properties of Stiff
Pleistocene Clays
Engineering Symposium on
Properties of OAP Geo-
strata
Osaka, Japan
OCDA May 1993
![Page 32: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/32.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Long Term Consolidation
Effects on the Engineering
Properties of the Osaka Bay
Clay
Technical Forum on the
Consolidation Properties of
the Osaka Bay Soils
Osaka, Japan
PHRI, MoT April 1993
Local Verses external
measurements for axial Strain
for Clays
28th annual meeting of
JSSMFE
Kobe, Japan
JSSMFE March 1993
Small Strain Behaviour of Stiff
OAP Clays under Varying Modes
of Consolidation
Technical Symposium on
the Development of the
Osaka Amenity Park
Osaka, Japan
OCDA November 1992
Hi-tech Geo-Technical Testing
Techniques
Advanced Geotechnical
Engineering Methods of
Testing for Practicing
Engineers
Tokyo, Japan
JICA October 1992
Contributions of the Civil
Engineer in Realizing the
Minato Mirai 21 Mega-Project
International Symposium
on Futuristic Cities
Los Angeles, USA
LAUPD September 1992
A Conceptual Presentation of
the Main Futuristic
Components of the MM21
Development Projects
International Symposium
on Futuristic Cities
Los Angeles, USA
LAUPD September 1992
Introduction of Some State of
the Art Technologies Adapted
in MM21 Mega Project
International Symposium
on Futuristic Cities
Los Angeles, USA
LAUPD September 1992
Applying Spatial Concepts for
Urban Density and
Transportation Patterns
International Forum on
Advanced Transport
Infrastructure Planning
Perth, Australia
PCDA August 1992
Introducing Computerized
Noding Transport Network
Concepts
International Forum on
Advanced Transport
Infrastructure Planning
Perth, Australia
PCDA August 1992
Complex Permutation Matrices
Developed for Physical
Infrastructure Integration
International Forum on
Advanced Transport
Infrastructure Planning
Perth, Australia
PCDA August 1992
![Page 33: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/33.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Applying the Circumferential
Matrix Concept in Transport
Infrastructure Planning and
Development
International Forum on
Advanced Transport
Infrastructure Planning
Perth, Australia
PCDA August 1992
Introduction to Some
Advanced Civil Engineering
Technologies
International Symposium
on Advanced Civil
Engineering Technologies
Texas, USA.
SU July 1992
Introduction to Some
Advanced Civil Engineering
Technologies
Seminar on Some Recent
Advances Civil Engineering
Indianapolis, USA.
SU July 1992
Introduction to Some
Advanced Civil Engineering
Technologies
Regional Symposium on
Advanced Technologies
Hawaii, USA.
HU July 1992
Introduction to Some
Advanced Civil Engineering
Technologies
Symposium on Advances in
Civil Engineering Practice
Guam, USA.
GU July 1992
Urban Environmental
Deterioration and The Civil
Engineer
Challenges of The Future Yokohama Japan
MMDA June 1992
The Role of Civil Engineering in
the urban Environment
Planning and management
in the Developing world
Yokohama Japan
MMDA June 1992
Vital Geotechnical Engineering
Aspects for Ground Settlement
Control of the Osaka Bay Clay
Symposium on the
Engineering Properties of
Osaka Bay Geomaterials
Osaka, Japan
PHRI, MoT May 1992
Introduction to Some
Advanced Civil Engineering
Technologies
Regional Symposium on
Advanced Technologies
Perth, Australia.
PCDA April 1992
Effects of consolidation stress
ratio and strain rate on the
peak stress ratio of Kaolin
27th Annual meeting of the
JSSMFE
Kochi, Japan.
JSSMFE March 1992
An Engineering 3-D Model for
Analyzing Urban Rural
Integration Based on Civil
Engineering Concepts
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
![Page 34: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/34.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Proposed Methods for
Developing Appropriate Models
for Rural Planning and
Development
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
Pragmatic Application of the
Orthometric Quadra-Model for
Structural Analysis of Rural
Development Planning
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
Application of a Recently
Proposed Transformation
Matrix Model for Urban Cluster
Analysis
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
A Newly Proposed
Transformation Matrix Model
for Analyzing Models of Rural
Development
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
Spatial Modelling for Rural
Urban Matrix Integration
International Symposium
on New Concepts for
Systematic Urban and
Rural Development
Boston, USA.
GRC October 1991
Introducing some Basic
Concepts for an Engineering 3-
D Model for Analyzing
Urbanization Trends
International Symposium
on Analytical Methods for
Urban Planning and
Development
Manila, Philippines
DECM September 1991
The Role of Civil Engineering
in Urban Planning and
Development
Symposium on Futuristic
Cities
Seoul, South Korea.
Civil Engineering
Dept. of Seoul City
Authority
September 1991
Effects of Rapid Consolidation
on the Geotechnical
Engineering Properties of Man-
made Islands
Symposium on the
Research Aspects of the
Osaka Bay Land
Reclaimation
Osaka, Japan
PHRI, MoT September 1991
![Page 35: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/35.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Applying Statistical and
Probabilistic Methods in
Analyzing Major Impediments
of Systematic Urban
Development
International Symposium
on Analytical Methods for
Urban Planning and
Development
Manila, Philippines
DECM August 1991
The Role of Civil Engineering
in Urban Planning and
Development
Annual Symposium on
Minato Mirai MM21
Futuristic City Planning
Yokohama, Japan.
International Affairs
Division, Office of
the Mayor, City of
Yokohama
August 1991
The Role of Civil Engineering
in Urban Planning and
Development
Technical Forum on Kyoto
City Development Planning
Kyoto, Japan.
International Affairs
Division, Office of
the Mayor, City of
Kyoto
August 1991
The Role of Civil Engineering
in Urban Planning and
Development
Kagoshima City Planning
Seminar
Kagoshima, Japan.
International Affairs
Division, Office of
the Mayor, City of
Kagoshima.
July 1991
Alternative Energy Related
Research: It’s Contribution in
providing some Crucial
Solutions to Global Warming
International Symposium
on Global Environmental
Challenges
Texas, USA
UOTe June 1991
A strategic approach in
providing some Solutions to
Global Environmental Problems
International Symposium
on Global Environmental
Challenges
Texas, USA
UO Te June 1991
Advanced Methods of Design
and Construction of Civil
Engineering Structures within
Soft Clayey Soils
Annual Symposium on the
Geotechnical Engineering
Complexities and New
Technological
Development in Methods of
Tunneling
Tokyo, Japan May 1991
![Page 36: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/36.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Some Development
Perspectives for Rural-Urban
Migration in Developing
Countries
Conference for Spatial
Urban and Rural Planning
and Development
Niigata, Japan
OMCM October 1990
An Engineering Study on the
Impact of Urbanization on
Rural Planning and
Development
Conference for Spatial
Urban and Rural Planning
and Development
Niigata, Japan
OMCM October 1990
The Role of Enhancement
Transport Infrastructure
Development in Stimulating
Rural Economics
Conference for Spatial
Urban and Rural Planning
and Development
Niigata, Japan
OMCM October 1990
The Spiral Analytical Concept
in Analyzing Physical
Infrastructure Development of
Urban Centres
International Conference
on the Urban Planning and
the Environment
Hawaii, USA
OMCM September 1990
An Engineering Perspective of
the Comparative Analysis of
Urban Development Patterns
International Conference
on the Urban Planning and
the Environment
Hawaii, USA
OMCM September 1990
Challenges Emanating from
Rapid Urbanization
International Conference
on the Urban Planning and
the Environment
Hawaii, USA
OMCM September 1990
Some Proposed Pragmatic
Countermeasures for Design
and Construction of Civil
Engineering Structures within
Soft Clayey Soils
Annual Symposium on the
Geotechnical Engineering
Complexities and New
Technological
Development in Methods of
Tunneling
Tokyo, Japan July 1990
Challenges of Rapid
Enhancement of Transport
Infrastructure Development
Impact of Population
Explosion on the Urban
and Rural Environments
HongKong,HongKong
OMCH June 1990
Contribution of poor Transport
Infrastructure to Urbanization
Problems
International Conference
on Transport Infrastructure
Hong Kong,HongKong
OMCH June 1990
![Page 37: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/37.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Some Critical Impediments of
Urban Planning and
Development
International Urban
Planning and Development
Conference
Denver, USA
JUPRC April 1990
A Modelling Concept for
Systematic Urban Planning and
Development Based on some
Civil Engineering Concepts
International Urban
Planning and Development
Conference
Denver, USA
JUPRC April 1990
A Newly Proposed Civil
Engineering Orthometric
Quadra- Model Phasing for
Structural Analysis of Urban
Development
International Urban
Planning and Development
Conference
Denver, USA
JUPRC April 1990
A Proposed Civil Engineering
Model for Integrated Urban
Planning and Development
International Urban
Planning and Development
Conference
Denver, USA
JUPRC April 1990
Civil Engineering and Transport
Infrastructure
Modern Technologies for
Transport Infrastructure
Development
Seoul, South Korea
DCECS March 1990
The Importance of Strategic
Infrastructure Planning for
Urban Transport Development
Modern Technologies for
Transport Infrastructure
Development
Seoul, South Korea
DCECS March 1990
The Role of Geotechnical
Engineering in the Planning
and Development of Transport
Infrastructure
Modern Technologies for
Transport Infrastructure
Development
Seoul, South Korea
DCECS March 1990
The Role of Civil Engineering
in the Realization of MM21
Futuristic City – Environmental
Planning
Annual Symposium on
Minato Mirai MM21
Futuristic City Planning
Yokohama, Japan.
International Affairs
Division, Office of
the Mayor, City of
Yokohama
March 1990
![Page 38: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/38.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
Geotechnical Engineering
Complications in the Tunneling
of Soft Soil Strata in the Tokyo
Bay
Annual Symposium on the
Geotechnical Engineering
Complexities and New
Technological
Development in Methods of
Tunneling
Tokyo, Japan July 1989
The Role of Civil Engineering
in the Realization of MM21
Futuristic City – Physical
Planning
Annual Symposium on
Minato Mirai MM21
Futuristic City Planning
Yokohama, Japan.
International Affairs
Division, Office of
the Mayor, City of
Yokohama
June 1989
Recommendation of the
Adoption of Fly Ash as a Useful
Foundation and Land
Reclamation Geomaterial
Based on Comprehensive
Research Findings
International Conference
on the Use of Bi-materials
for Infrastructure
Development and
Environmental
Conservation
Osaka, Japan
Kansai Electric Power
Company
April 1989
The Role of Civil Engineering
in the Realization of MM21
Futuristic City – Transport
Infrastructure
Annual Symposium on
Minato Mirai MM21
Futuristic City Planning
Yokohama, Japan.
International Affairs
Division, Office of
the Mayor, City of
Yokohama
June 1988
The Role of Civil Engineering
in the Realization of MM21
Futuristic City – Geotechnical
Engineering Structures
Annual Symposium on
Minato Mirai MM21
Futuristic City Planning
Yokohama, Japan.
International Affairs
Division, Office of
the Mayor, City of
Yokohama
June 1987
Futuristic Perspectives of the
Civil Engineer in the 21st
Century
Journal of Technology and
the Future
Yokohama, Japan
international Affairs
Division, Office of
the Mayor, City of
Yokohama.
1987
![Page 39: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/39.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Title of Lecture
Title of
Conference/Symposium/
Seminar
Location and
Sponsor Date
A Proposal based on the
Fundamental Concept of Home
and Office Automation
Proposal of Futuristic
Cities of the 21st Century
Yokohama, Japan
international Affairs
Division, Office of
the Mayor, City of
Yokohama.
1985
Note*
AAU - Addis Ababa University IBC - International Biographical Centre
ABI - American Biological Institute IRF - International Roads Federation
ARSGE - African Regional Society of Geotechnical ISSMGE- International Society of Soil Mechanics Engineering and Geotechnical Engineering
JSSMFE - Japan Society of Soil Mechanics and Foundation Engineering.
ASCE - American Society of Civil Engineers
CSCE - Canadian Society of Civil Engineers JICA - Japan International Cooperation Agency
EACE - Ethiopian Society of Civil Engineers USAID - United States Agency for International Development
JCCE - Japan Society of Civil Engineers
ERA - Ethiopian Roads Authority WRF - World Road Federation
IAGE - International Association of Engineering Geology IRF - International Road Federation
AICE - Australian Institution of Civil Engineers SU - State University
HU - Hawaii University GU - Guam University
UoTe -University of Texas LAUPD-Los Angeles Urban Planning Department
UND - University of New Delhi PCDA-Perth City Development Authority
JCS -Japan Geotechnical Society MMDA – Minato Mirai 21 Development Authority
GRC – Globalization Research Centre
DECM – Department of Engineering, City of Nairobi
DCECS – Department of Civil Engineering, City of Seoul
![Page 40: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/40.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
2. Training offered by Dr. Mukabi
Dr. Mukabi has participated as a Guest Trainer/Keynote Lecturer in various Training
Forums/Seminars/Programmes
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Some Recent Advances in Road
Design and Construction
Khartoum, The Sudan
Eyat Oil Exploration Co. Ltd February, 2009 (2 days)
Innovative Road Construction
Development in Southern Sudan
Juba, Southern Sudan
Ministry of Transport & Roads,
GoSS
June, 2008 (3 days)
Capacity Building Programmes
and Lectures on Civil Engineering
for Young Engineers in Southern
Sudan
Central Equatorial State
JICA March 2008 (3 days)
Geotechnologies for Sustainable
Infrastructure Development
within the Kenya vision 2030
framework.
Nairobi, Kenya,
Tensar International London,
Geotechnologies South Africa and
Kensetsu Kaihatsu Consultants
May, 2007 (1 day)
Capacity Building Programmes
and Lectures on Civil Engineering
for Young Engineers in Southern
Sudan
Central Equatorial State
JICA April 2007 (3 days)
Introducing Some New Design
Methods for Problematic Soils in
Southern Sudan
Abyei, Southern Sudan
GoSS/ White Nile Oil Exploration
Co. Ltd
March, 2007 (3 days)
Design and Application of
Geogrids in the Mechanical
Stabilization of Soils in Africa
Johannesburg, South Africa
Tensar International February, 2007 (2 days)
Capacity Building Programmes
and Lectures on Civil Engineering
for Young Engineers in Southern
Sudan
Central Equatorial State
JICA March 2006 (3 days)
![Page 41: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/41.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Training on Design and
Construction Techniques for
Young Engineers
Addis Ababa, Ethiopia
JICA, CPC, Kajima, EACE
December, 2004
(3 days)
Capacity Building in Engineering
Design for Counterpart Engineers
of Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima, ERA
November 2004
(3 months)
Training on Design and
Construction Techniques for
Young Engineers
Addis Ababa, Ethiopia
JICA, CPC, Kajima, EACE
December, 2003
(3 days)
Capacity Building in Engineering
Design for Counterpart Engineers
of Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima, ERA
November 2003
(3 months)
Training on Design and
Construction Techniques for
Young Engineers
Addis Ababa, Ethiopia
JICA, CPC, Kajima, EACE
December, 2002
(3 days)
Capacity Building in Engineering
Design for Counterpart Engineers
of Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima, ERA
November 2002
(3 months)
Training on Design and
Construction Techniques for
Young Engineers
Addis Ababa, Ethiopia
JICA, CPC, Kajima, EACE
December, 2001
(3 days)
Capacity Building in Engineering
Design for Counterpart Engineers
of Ethiopian Roads Authority
Addis Ababa, Ethiopia
JICA, CPC, Kajima, ERA
November 2001
(3 months)
Workshop on advanced
geotechnical testing for
geotechnical engineers.
Evaton, South Africa CON AID
pty, Mitsui corporation South
Africa
September, 1999 (4 days)
Workshop on the Systematic and
Appropriate Study and Design
Approach for Provincial and
District Engineers of the Ministry
of Roads and Public Works, Kenya
Nairobi, Kenya
JICA August 3rd -8th 1999 (6 days)
![Page 42: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/42.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Workshop on the Systematic and
Appropriate Study and Design
Approach for Provincial and
District Engineers of the Ministry
of Roads and Public Works, Kenya
Kisumu, Kenya
JICA
August 10th -15th 1999(6
days)
Workshop on the Systematic and
Appropriate Study and Design
Approach for Provincial and
District Engineers of the Ministry
of Roads and Public Works, Kenya
Kakamega, Kenya
JICA
August 16th -21st 1999(6
days)
CON-AID Seminar for Consulting
and Practicing Engineers
Nairobi, Kenya
CON-AID Pty, Mitsui Corporation
and CPC
July, 1998 (2 Days)
Eco-training Programme for
Japanese University Students
Masai Mara, Kenya
Todo Press Inc. Japan April, 1997 (3 months)
Eco-training Programme for
Japanese University Students
Masai Mara, Kenya
Todo Press Inc. Japan May, 1996 (3 months)
Eco-training Programme for
Japanese University Students
Masai Mara, Kenya
Todo Press Inc. Japan April, 1995 (3 months)
Enhancing Eco-tourism in
Developing Africa
Nairobi, Kenya
Utalii College April 1996 (1 week)
Hi-tech Geo-Technical Testing
Techniques
Tokyo, Japan
JICA March, 1995 (5 days)
Hi-tech Geo-Technical Testing
Techniques
Tokyo, Japan
JICA July, 1994 (5 days)
Hi-tech Geo-Technical Testing
Techniques
Tokyo, Japan
JICA June 1993(5 days)
Hi-tech Geo-Technical Testing
Techniques
Tokyo, Japan
JICA Oct 1992 (5 days)
![Page 43: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/43.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Hi-tech Geo-Technical Testing
Techniques
New Delhi ,India
UND April 1994( 3 days)
Hi-tech Geo-Technical Testing
Techniques
Bombay ,India
UND April 1994( 3 days)
The Importance of Mathematics
and science in civil Engineering
Denver, USA.
ASCE August, 1993 (3 Days)
The Importance of Mathematics
and science in civil Engineering
Los Angeles, USA.
ASCE August, 1993 (3 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Texas, USA.
SU July 1992 (4 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Indianapolis, USA.
SU July 1992 (4 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Hawaii, USA.
HU July 1992 (4 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Guam, USA.
GU July 1992 (4 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Sydney, Australia.
PCDA April, 1992 (3 Days)
Introduction to Some Advanced
Civil Engineering Technologies
Perth, Australia.
PCDA April, 1992 (3 Days)
The Role of Civil Engineering in
Urban Planning and Development
Seoul, South Korea.
Civil Engineering Dept. of Seoul
City Authority
September 1991 (3 Days)
![Page 44: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/44.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
The Role of Civil Engineering in
Urban Planning and Development
Yokohama, Japan.
International Affairs Division,
Office of the Mayor, City of
Yokohama
August 1991 (4 Days)
The Role of Civil Engineering in
Urban Planning and Development
Kyoto, Japan.
International Affairs Division,
Office of the Mayor, City of Kyoto
August 1991 (4 Days)
The Role of Civil Engineering in
Urban Planning and Development
Kagoshima, Japan.
International Affairs Division,
Office of the Mayor, City of
Kagoshima.
July 1991 (4 Days)
The Role of Civil Engineering in
the Realization of MM21
Futuristic City
Yokohama, Japan.
International Affairs Division,
Office of the Mayor, City of
Yokohama
June 1990 (3 Days)
The Role of Civil Engineering in
the Realization of MM21
Futuristic City
Yokohama, Japan.
International Affairs Division,
Office of the Mayor, City of
Yokohama
June 1989 (3 Days)
The Role of Civil Engineering in
the Realization of MM21
Futuristic City
Yokohama, Japan.
International Affairs Division,
Office of the Mayor, City of
Yokohama
June 1988 ( 3 Days)
The Role of Civil Engineering in
the Realization of MM21
Futuristic City
Yokohama, Japan.
International Affairs Division,
Office of the Mayor, City of
Yokohama
June 1987 (3 Days)
![Page 45: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/45.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
3. Training Undertaken by Dr. Mukabi
During his studies abroad, Dr. Mukabi undertook training in various international Training
Forums/Seminars/Programmes in Asia and the United States of America mainly in his field of
expertise, Civil Engineering and Urban Planning.
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Project Development and Master Planning – Projecting The Yokohama Minato Mirai (MM21) 21st Century Futuristic City Development Project.
Yokohama, Japan
The Yokohama City Development Authority, Japan
August 1989 ~ August 1989
(1Month)
Developing Models for
Systematic Urban Planning and
Development.
Denver, USA
State Development Authority,
Denver
May 1989 ~ May 1989
(1Month)
Design & Construction Utilizing
New Materials in Civil
Engineering Adoption of Fly Ash
as a Land Reclamation Material.
Osaka, Japan
Kansai Electric Power
September 1989 ~
September 1989
(1Month)
Research & Development in
Shield Tunneling, Under Sea
Tunneling for the Tokyo Bay
Project.
Tokyo, Japan
The Trans-Tokyo Bay Highway
Corporation, Ministry of
Construction, Japan
March 1990 ~ April 1990
March 1990 ~ April 1990
(1.5 Months)
Transport Infrastructure and
Urbanization.
Hong Kong, Hong Kong
Hong Kong City Development
Authority
June 1990 ~ June 1990
(1Month)
Contract Administration and Project Management in Civil Engineering Practice.
Okayama, Japan
The Honshu Shikoku Bridge
Authority, Government of
Japan
June 1990 ~ September
1990.
(3.3 Months)
Research Orientation, Development and Benefits in Geotechnical Engineering.
Yokohama, Japan
The Port & Harbour Research
Institute, Ministry of Transport,
Japan
June 1991 ~ August 1991
(1.5 Months)
![Page 46: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/46.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Description/Title of Training
Forum/Seminar/Programme Location and Sponsor Time and Duration
Enhancing Research on the Development of Geotechnical Engineering Aspects of Man-made Islands and Land Reclamation of The New Kansai International Airport.
Kobe, Japan
The Port & Harbour Research Institute, Ministry of Transport,
Japan
July 1992 ~ August 1992
(1.5 Months)
Modeling Geotechnical Engineering and Geological Problems in Offshore Ground Settlement of The New Kansai International Airport.
Osaka, Japan
Osaka City Authority and The Port & Harbour Research
Institute, Ministry of Transport, Japan.
March 1993 ~ April 1993
(1.5 Months)
Flood Control within Urbanized Developments of The Kandagawa Flood Control Project.
Tokyo, Japan
Taisei Corporation, Japan.
July 1993 ~ July 1993
(1Month)
Developing Ground Improvement Aspects in Geotechnical Engineering for Railroad Ground Improvement in Ariake, Design and Construction.
Fukuoka, Japan
Ariake Geotechnical Research Group, Kyushuu Prefecture,
Japan.
March 1994 ~ April 1994
(1.5 Months)
Project Management Practice in Civil Engineering.
Tokyo, Japan
The Japan International
Cooperation Agency (JICA),
Government of Japan
June 1994 ~ August 1994
(2.5 Months)
Disaster Mitigation in Civil
Engineering, Reconstruction
Planning in Kobe City due the
Structural Damage caused by the
Great Kansai Earthquake.
Kobe, Japan
KOBENET, Kobe Prefectural
Government, Japan
March 1995 ~ March 1995
(1Month)
![Page 47: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/47.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
4. Publications as First Author
Dr. Mukabi has over 200 international publications as the First Author. Below are some of the most
relevant ones:
Science and Engineering Books under Publication by Mukabi J.N.
1. Advanced Mathematical Methods for Soil Mechanics and Geotechnical Engineering.
2. Geo-scientific Application for Civil Engineers.
3. Energy Solutions Based on GECS.
4. Advanced Engineering Geophysics.
Some Relevant Publications
[1] Mukabi J.N. (2015e). “The Advanced Role of OBRM in Road Construction and the Geo-environmental
Mitigation”, to be published in the Proceedings of the XXVTH World Road Congress, Seoul, South Korea.
[2] Mukabi J.N. (2015d). “Recently Developed Value Engineering Technologies for Highway Design and
Construction Applied in the East and Central African Region”, to be published in the Proceedings of
the XXVTH World Road Congress, Seoul, South Korea.
[3] Mukabi J.N. (2015c). “Application of Geoscientific Methods Developed for Analyzing the Behaviour
of Stabilized and Geosynthetically Reinforced Tropical Soils”, to be published in the Proceedings of
the 16th African Regional Conference on Soil Mechanics and Geotechnical Engineering (ARC on
SMGE), Tunis, Tunisia.
[4] Mukabi J.N. (2015b). “Soil-Structure Interaction Mechanisms Based on the MCST and CSSR
Functions”, to be published in the Proceedings of the 16th African Regional Conference on Soil
Mechanics and Geotechnical Engineering (ARC on SMGE), Tunis, Tunisia.
[5] Mukabi J.N. (2015a). “Change in Current Stress State-Induced Anisotropy of Stiff Pleistocene Clays
Resulting from Static and Dynamic Loading Effects”, to be published in the Proceedings of the 16th
African Regional Conference on Soil Mechanics and Geotechnical Engineering (ARC on SMGE), Tunis,
Tunisia.
[6] Mukabi J.N. (2014g). “Some Vital Geotechnical Engineering Elements for Foundation Design and
Construction”, to be published in the Proceedings of the Fourth TC-ISSMGE International
Conference on New Developments in Soil Mechanics and Geotechnical Engineering, North Cyprus,
Turkey.
[7] Mukabi J.N. (2014f). “Influence of Drainage Conditions on Small Strain Characteristics of Stiff
Pleistocene Clays”, to be published in the Proceedings of the Fourth TC-ISSMGE International
Conference on New Developments in Soil Mechanics and Geotechnical Engineering, North Cyprus,
Turkey.
![Page 48: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/48.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[8] Mukabi J.N. (2014e). “Application of the Initial Yield and CSSR Concepts in Enhancing Vital
Geotechnical Engineering Parameters”, to be published in the Proceedings of the Fourth TC-
ISSMGE International Conference on New Developments in Soil Mechanics and Geotechnical
Engineering, North Cyprus, Turkey.
[9] Mukabi J.N. (2014d). “Static and Dynamic Loading Effects on Drained and Undrained Small Strain
Characteristics of Clayey Geomaterials”, to be published in the Proceedings of the Fourth TC-
ISSMGE International Conference on New Developments in Soil Mechanics and Geotechnical
Engineering, North Cyprus, Turkey.
[10] Mukabi J.N. (2014c). “Simulation of Impact of Seismic Loading on Degree of Destructuration of
Clayey Geomaterials”, to be published in the Proceedings of the Fourth TC-ISSMGE International
Conference on New Developments in Soil Mechanics and Geotechnical Engineering, North Cyprus,
Turkey.
[11] Mukabi J.N. (2014b). “Some Vital Geotechnical Engineering Elements for Pavement Structural
Design and Construction”, to be published in the Proceedings of the International Conference of
the Institution of Engineers of Kenya, Nairobi, Kenya.
[12] Mukabi J.N. (2014a). “Application of the Initial Yield Strain Concept in Developing the Failure
Criteria for MEPD Specifications”, to be published in the Proceedings of the International
Conference of the Institution of Engineers of Kenya, Nairobi, Kenya.
[13] Mukabi J.N. (2013i). “Challenges and Innovations in Geotechnics for African Representative Soils”,
to be published in the Proceedings of the XVIII International Conference on Soil Mechanics and
Geotechnical Engineering (ICSMGE), Paris, France.
[14] Mukabi J.N. (2013h). “Influence of Varying Consolidation Stress-strain Histories on Small Strain
Behaviour of Stiff Geomaterials”, to be published in the Proceedings of the XVIII International
Conference on Soil Mechanics and Geotechnical Engineering (ICSMGE), Paris, France.
[15] Mukabi J.N. (2013g). “Introducing Intricate Geomathematical Module Functions for the OPMCS
Technology”, to be published in the Proceedings of the 15th Annual Conference of the
International Association of Mathematical Geosciences, Madrid, Spain.
[16] Mukabi J.N. (2013f). “Geoscientific Comparative Analysis of the Interaction of Geosynthetics with
Natural and Stabilized Tropical Soils”, to be published in the Proceedings of the IEEE International
Geoscience and Remote Sensing Symposium (IGARSS), Melborne, Australia.
[17] Mukabi J.N. (2013e). “Geoscientific Method of Remote Field Data Acquisition and Analysis for Civil
Engineering Application”, to be published in the Proceedings of the IEEE International Geoscience
and Remote Sensing Symposium (IGARSS), Melborne, Australia.
[18] Mukabi J.N. (2013d). “Some Recently Developed Analytical Techniques for Underground
Construction in Tropical Problematic Soils”, to be published in the Proceedings of the International
Conference of the Institution of Engineers of Kenya, Nairobi, Kenya.
[19] Mukabi J.N. (2013c). “Advancing Innovative Ground Improvement Technologies for Founding Civil
Engineering Structures”, to be published in the Proceedings of the International Conference of the
Institution of Engineers of Kenya, Nairobi, Kenya.
![Page 49: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/49.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[20] Mukabi J.N. (2013b). “Innovative Laboratory and In-situ Methods of Testing in Geotechnical
Engineering”, to be published in the Proceedings of the International Conference of the Institution
of Engineers of Kenya, Nairobi, Kenya.
[21] Mukabi J.N. (2013a). “A Geomathematical Method for Quantitative Analysis of the Impact of Sub-
surface Geoenvironmental Changes”, to be published in the Proceedings of the International
Conference on Applied Physics and Mathematics (ICAPM).
[22] Mukabi J.N. (2012i). “Application of OPMCS Strut Micropiling Technique for Foundation Ground and
Subgrade Improvement”, to be published in the Proceedings of the ISM 11th International Workshop
on Micropiling, Rome, Italy.
[23] Mukabi J.N. (2012h). “Some Recently Developed Ground Improvement Techniques for Tropical
Expansive Soils”, to be published in the Proceedings of the The 4th International Conference on
Problematic Soils, Wuhan, China.
[24] Mukabi J.N. (2012g). “Geoscientific Methods of Remote Data Derivation for Geotechnical
Engineering Applications”, to be published in the Proceedings of the 34th International Geological
Congress, Brisbane, Australia.
[25] Mukabi J.N. (2012f). “Proposed Quadruple Process Model and Geomathematical Functions
Simulating Earth Dynamic Processes”, to be published in the Proceedings of the IEEE International
Geoscience and Remote Sensing Symposium (IGARSS), Munich, Germany.
[26] Mukabi J.N. (2012e). “Integrated Geo-Probabilistic and Geo-Statistical Module Functions for the
Proposed Quadruple Process Model”, to be published in the Proceedings of the IEEE International
Geoscience and Remote Sensing Symposium (IGARSS), Munich, Germany.
[27] Mukabi J.N. (2012d). “Recent Developments of Quantitative Determination of Kinematic Hardening
Sub-Yield Surface Limits”, to be published in the Proceedings of the Fourth TC-ISSMGE
International Conference on New Developments in Soil Mechanics and Geotechnical Engineering,
North Cyprus, Turkey.
[28] Mukabi J.N. (2012c). “Case Study Analysis of OPMC Improved Foundation Ground, Pavement and
Other Geo-structures Employing the GECPRO Model”, to be published in the Proceedings of the
International Symposium on Ground Improvement, (ISSMGE-TC211), Brussels, Belgium.
[29] Mukabi J.N. (2012b). “Application of High-Order Spatial Cumulants Concept in Developing
Sophisticated Analytical Methods and Stochastic Simulation for Stabilized Geomaterials”, to be
published in the Proceedings of the International Conference on Applied Physics and Mathematics
(ICAPM), Chennai, India.
[30] Mukabi J.N. (2012a). “Promotion of Value Engineering Principles as Integral Means of Propulsion
Towards the Effective Achievement of Vision 2030”, East African Regional Symposium on Geotechnologies for Sustainable Socio-economic Development, Nairobi, Kenya.
[31] Mukabi, J.N. (2011g). “Characterization and modeling of various aspects of pre-failure deformation
of clayey geomaterials – Fundamental theories and analyses”. KEYNOTE LECTURE. Published in the
Proceedings, 1st International Conference on Geotechnique, Constrution Materials & Environment,
Vol. 1, pp. 30-39, Mie, Japan.
![Page 50: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/50.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[32] Mukabi, J.N. & Hossain Z. (2011f). “Characterization and modeling of various aspects of pre-failure
deformation of clayey Geomaterials – Application in Modeling”. KEYNOTE LECTURE. Published in
the Proceedings, 1st International Conference on Geotechnique, Constrution Materials &
Environment, Vol. 2, pp. 1-10, Mie, Japan.
[33] Mukabi J.N. (2011e). “Derived Empirical Relations and Models of Vital Geotechnical Engineering
Parameters Based on Geophysical and Mechanical Methods of Testing”, published in the
Proceedings of the 15th African Regional Conference on Soil Mechanics and Geotechnical
Engineering (ARC on SMGE), Maputo, Mozambique.
[34] Mukabi J.N. (2011d). “Fundamental Theory of the ReCap Technique and its’ Application in the
Construction of Pavement Structures within Problematic Soils”, published in the Proceedings of the
15th African Regional Conference on Soil Mechanics and Geotechnical Engineering (ARC on SMGE),
Maputo, Mozambique.
[35] Mukabi J.N. (2011c). “Case Study Analysis of a Heavily Loaded Road Pavement Structure
Constructed on Black Cotton Soil”, published in the Proceedings of the 15th African Regional
Conference on Soil Mechanics and Geotechnical Engineering (ARC on SMGE), Maputo, Mozambique.
[36] Mukabi J.N. (2011b). “A Scientific Approach in Determining Sustainable Solutions to Slope Failures
and Landslides”, Proceedings of the International Union of Geodesy and Geoscience – Earth on the
Edge: Science for a Sustainable Planet, Melbourne, Australia.
[37] Mukabi J.N. (2011a). “Some Recently Developed Analytical Techniques for Underground
Construction in Problematic Soils”, Proceedings of the The VIITH International Symposium on
Geotechnical Aspects of Underground Construction in Soft Ground – Underground Construction in
Soft Ground, Roma, Italy.
[38] Mukabi JN, Kimura Y, Murunga PA, Njoroge BN, Wambugu J, Sidai V, Onacha K., Kotheki S, Ngigi A,
“Case example of design and construction within problematic soils”, in Proc. Int. Geotec. Conf. on
Geotechnical Challenges in Megacities, Geomos, Moscow, 2010, vol. 2, pp 1172-1179.
[39] Mukabi JN, Kotheki S. (2010l). Geoscientific Methods of Analyzing the Modified Critical State
Theory. Proceedings of 2nd International Conference on Mathematics and Geosciences, Beijing,
China.
[40] Mukabi JN, Kotheki S. (2010k). “A Geo-mathematical model for quantitative analysis and
prediction of the impact of environmental changes on the characteristics of geomaterial
formation”, in Proceedings of 14th International Conference on Mathematical Geosciences, pp 382-
406. Budapest, Brussels.
[41] Mukabi J.N., Kotheki S., Ngigi A., Gono K., Njoroge B.N., Murunga P.A., Sidai V. (2010j) –
Characterization of Black Cotton Soil under static and dynamic loading – Testing and Analyses.
Published in Proceedings of the International Conference on Geotechnical Engineering (ICGE),
Tunis, Tunisia.
[42] Mukabi J.N., Kotheki S., Ngigi A., Gono K., Njoroge B.N., Murunga P.A., Sidai V. (2010i) –
Characterization of Black Cotton Soil under static and dynamic loading – Discussions and
![Page 51: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/51.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Applications. Published in Proceedings of the International Conference on Geotechnical
Engineering (ICGE), Tunis, Tunisia.
[43] Mukabi JN, Kotheki S. (2010h) “A Geo-mathematical model for quantitative analysis and prediction of the impact of environmental changes on the characteristics of geomaterial formation”, Proceedings of 14th Int. Conference on Mathematical Geosciences (ICMG), pp 382-406, Budapest, Brussels.
[44] Mukabi J.N, Murunga P, Sidai V, Kotheki S, Njoroge B.N. (2010g) Geotechnical Challenges
Underlying and Circumscribing Subsurface Development in Nairobi, to be published in the
Proceedings of the International Geotechnical Conference – Geotechnical Challenges in Megacities,
Moscow, Russia.
[45] Mukabi J.N & Kotheki S. (2010f). A Mathematical Introduction of the Fundamental Theory of GECS
(Global Energy Conservation Systems) , to be published in the Proceedings of the 5th International
Conference of Mathematics and Engineering Physics, Cairo, Egypt.
[46] Mukabi J.N. & Kotheki S. (2010e). Mathematical Derivative of the Modified Critical State Theory
and its Application in Soil Mechanics, published in the Proceedings of the 2nd International
Conference on Applied Physics and Mathematics (ICAPM), pp. 484-492, Kuala Lumpur, Malaysia.
[47] Mukabi J.N.(2010d) Some Advanced Aspects of the Interaction of Geotechnical Engineering and
African Geology, Proceedings of the 11th Congress of the International Association for Engineering
Geology Auckland, New Zealand.
[48] Mukabi J.N. (2010c). Pavement and Hydraulic Structural Design Review Based on the Value
Engineering Comprehensive Method of Design (VE-CMD), Technical Forum on Improvement of
Design and Construction Aspects for the Bomet Township Roads and Storm Water Hydraulic
Structures, Nairobi, Kenya.
[49] Mukabi J.N. (2010b). Pavement Structural Design Review of the Songwe International Airport Based
on the Value Engineering Comprehensive Method of Design (VE-CMD), Technical Forum on Value
Engineering Aspects in Pavement Structural Design, Submitted to Tanzania Airports Authority,
BADEA and OPEC, Dubai, Emirates.
[50] Mukabi J.N. (2010a). Pavement Structural Design Review Based on the Value Engineering
Comprehensive Method of Design (VE-CMD), Technical Forum on Improvement of Design and
Construction Aspects for the Gisambai ~ Mbale Road, Nairobi, Kenya.
[51] Mukabi J.N. (2009i). Employing the CMD for the Design of Bridge Foundations in Juba Town,
publication prepared for Workshop on the Juba Urban Transport Infrastructure (JUTI) and Capacity
Development Study Funded by the Japan International Cooperation Agency (JICA), Juba, Southern
Sudan.
[52] Mukabi J.N. (2009h). Application of OPMC Technology in the Realization of Affordable Housing,
publication prepared for Research and Development Forum on Affordable Housing Funded by
USAID, Juba, Southern Sudan.
![Page 52: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/52.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[53] Mukabi J.N. (2009g). Vital Engineering Elements in the Design Review of the Songwe International
Airport Pavement Structures, publication prepared for Engineering Workshop on the Cost-effective
Enhancement of the Structural Capacity of Pavement Structures Funded by BADEA, OPEC and
Tanzania Airports Authority, Songwe, Tanzania.
[54] Mukabi J.N. (2009f). Recently Developed Suction Stress, Moisture and Swell Control Techniques
Applied for Ground Improvement, Proceedings of the XVII International Conference on Soil
Mechanics and Geotechnical Engineering, Alexandria, Egypt.
[55] Mukabi J.N. (2009e). Strength and Deformation Characteristics Derived from the Interaction of Geogrids and Tropical Geomaterials, Proceedings of the XVII International Conference on Soil Mechanics and Geotechnical Engineering, Alexandria, Egypt.
[56] Mukabi J.N. (2009d). Small Strain Behaviour of Drained and Undrained Pleistocene Clays under Monotonic and Cyclic Loading, Proceedings of the XVII International Conference on Soil Mechanics and Geotechnical Engineering, Alexandria, Egypt.
[57] Mukabi J.N. (2009c). Some Value Engineering Perspectives of Pavement Structural Design of the Kaptama ~ Kapsokwony Road Section, Publication for the Technical Forum on the Improvement of Some Design Aspects of Pavement Structures, Kitale, Kenya.
[58] Mukabi J.N. (2009b). Some Recent Advances in Road Design and Construction, Publication for the Seminar on Recent Advances in Road Design and Construction, Khartoum, Sudan.
[59] Mukabi J.N. (2009a). Employment of Value Engineering in the Design of Foundations for the MTC Building Structures, publication prepared for Workshop on the Study and Design of the Multi-Training Centre Structures Funded by the Japan International Cooperation Agency (JICA), Juba, Southern Sudan.
[60] Mukabi J.N. (2008k). A Newly Proposed Approach in the Pavement Structural Design of the Lainya ~ Jambo Road in Southern Sudan, publication prepared for Technical Workshop on Latest Developments in Pavement Design Methods within the East and Central African Region, Juba, Southern Sudan.
[61] Mukabi J.N. (2008j). Evaluation of the Technical and Engineering Aspects for the Comprehensive
Design Review of the Mbeya ~ Lwanjilo Trunk Road Project, publication prepared for Workshop on Appropriate Value Engineering Design for Roads and Bridges, Juba, Southern Sudan.
[62] Mukabi J.N. (2008i). Nairobi Underground City Development Proposal, publication prepared for Workshop on Nairobi Underground City Development Proposal Sponsored by Ministry of Local Government, Nairobi, Kenya.
[63] Mukabi J.N (2008h) Geoscientific Analysis of the Mechanism of Interaction of geogrids and Geomaterials, to be published in the proceedings of the international conference for the European Geogrids Experts Panel, Edinburg, Scotland.
[64] Mukabi J.N. (2008g). The Role of Enhanced Research in Geotechnical Engineering for Pragmatic
Infrastructure Development within the Vision 2030 (Keynote Lecture), published in the Proceedings
of the IEK International Conference on ‘The Engineer and Vision 2030’, Nairobi, Kenya.
![Page 53: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/53.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[65] Mukabi J.N, Gono K, Njoroge B, Hatekayama R, Tesfaye A, Otwani J, Amoyo G, Murunga P, Ndemi
J, Okado J, Kotheki S. (2008f). The Challenges and Solutions for Problematic Soils for Infrastructure
Development in Kenya and the East Africa Region, published in the Proceedings of the IEK
International Conference on ‘The Engineer and Vision 2030’, Nairobi, Kenya.
[66] Mukabi J.N, Gono K, Ngare S, Nyang’aga F, Njoroge B, Hatekayama R, Tesfaye A, Feleke G,
Kotheki S. (2008e). Newly Developed Technologies for Roads and Bridges: An example of
Comprehensive Design and Construction Approach considering Tropical Geomaterial Characteristics,
published in the Proceedings of the IEK International Conference on ‘The Engineer and Vision
2030’, Nairobi, Kenya.
[67] Mukabi J.N. (2008d). Application of the Mechanics of Tropical soils in Geotechnical Engineering:
Some Recent Advances and Introduction of Futuristic Concepts on Geoscientific, Global Energy
Conservation Systems GECS, published in the Proceedings of the IEK International Conference on
‘The Engineer and Vision 2030’, Nairobi, Kenya.
[68] Mukabi J.N. (2008c). Pavement Structural Design Review Based on the Value Engineering
Comprehensive Method of Design (VE-CMD), Publication Prepared for the Transport Infrastructure
Development Seminar for Juba Town Sponsored by World Bank, Juba, Southern Sudan.
[69] Mukabi J.N. (2008b). Practical Solutions for Soil Reinforcements and Ground Stabilization by
Application of Tensar Technology and OPMC, Publication Prepared for the Interactive Forum for US
and African Engineering Consultants, Dar es Salaam, Tanzania.
[70] Mukabi J.N. (2008a). Evaluation of the Structural Performance of the Ntare ~ Ruhatsi Boulevard
Experimental Testing Trial Sections, Publication Prepared for the Workshop on the Development of
New Design Approach, Bujumbura, Burundi.
[71] Mukabi J.N. (2007s). Strength and Deformation Characteristics Derived from the Interaction of
Geogrids and OPMC Stabilized Geomaterials, International Symposium on The Mechanisms of
Interaction of Geogrids and Tropical Soils, Hamburg, Germany.
[72] Mukabi J.N. (2007r). Pad Foundation Design for Oil Drilling Rigs Based on Recently Developed
Ground Improvement and Soil Stabilization Technologies, Publication Prepared for the Workshop on
the Design of Foundations and Pavement Structures for the White Nile Oil Exploration Project,
Nairobi, Kenya.
[73] Mukabi J.N. (2007q). The Mechanism of Interaction of Geogrids and Soils, published in the
Proceedings of the European Geogrid Experts Panel, Hamburg, Germany.
[74] Mukabi J.N. (2007p). Practical Solutions for Soil Reinforcements and Ground Stabilization through
the Application of Geosynthetic and OPMCS Technologies, Publication submitted for the Technical
Forum for Application of Advanced Geotechnologies, Dar Es Salaam.
![Page 54: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/54.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[75] Mukabi J.N. (2007o): Mathematical Modeling of Some Recently Developed soil Mechanics and
Geotechnical Engineering Concepts, For Publication in the Proceedings of the 14th Regional
Conference on Geotechniques for Developing Africa, Yaoundé, Cameroon.
[76] Mukabi J.N. (2007n): Mathematical Examination of Some Recently Developed Concepts in
Geotechnical Engineering, For Publication in the Proceedings of the 14th Regional Conference on
Geotechniques for Developing Africa, Yaoundé, Cameroon.
[77] Mukabi J.N. (2007m). Application of Consolidation and Shear Stress Ratio Concepts in Foundation
Design and Construction, published in the Proceedings of the 14th African Regional Conference on
Soil Mechanics and Geotechnical Engineering, Yaoundé, Cameroon.
[78] Mukabi J.N. & Gono, K. (2007l). Characterization of Expansive Soils to Determine Appropriate
Highway and Foundation Design – Construction Methods, published in the Proceedings of the 14th
African Regional Conference on Soil Mechanics and Geotechnical Engineering, Yaoundé, Cameroon.
[79] Mukabi J.N., Hatakeyama, R. & Tesfaye, A. (2007k). A comprehensive Method of Analysis for Cost-
effective Detailed Design of Pavement Structures, published in the Proceedings of the 14th African
Regional Conference on Soil Mechanics and Geotechnical Engineering, Yaoundé, Cameroon.
[80] Mukabi J.N., Gono, K., Hatakeyama, R. & Tesfaye, A. (2007j). Employing Cost-effective
Countermeasures to Slope Failure Based on Newly Developed OPMC Stabilization Concepts,
published in the Proceedings of the 14th African Regional Conference on Soil Mechanics and
Geotechnical Engineering, Yaoundé, Cameroon.
[81] Mukabi J.N. (2007i). Some Recent Advances in Pavement Structural Design and Methods of
Construction, Publication submitted for the Workshop on “From Reconstruction to Development” –
EMPS for Basic Physical and Social Infrastructure in Juba Town and the Surrounding Areas in
Southern Sudan, Sponsored by Japan International Cooperation Agency (JICA), Southern Sudan.
[82] Mukabi J.N. (2007h). A Comprehensive Approach to the Design of Flexible Pavements in Tropical
Countries, published in the Proceedings of the 10th Australia New Zealand Conference on
Geomechanics, Brisbane, Australia.
[83] Mukabi J.N. & Gono, K. (2007g). Some Engineering Based Solutions to Problems Related to
Expansive Soils, published in the Proceedings of the 10th Australia New Zealand Conference on
Geomechanics, Brisbane, Australia.
[84] Mukabi J.N. (2007f). Technical and Engineering Challenges and Proposed Countermeasures for the
Causeways along the Wau ~ Abyei Trunk Road, Publication submitted for the Seminar on
Reconstruction of Infrastructure Northern States in Southern Sudan Sponsored by United Nations –
World Food Programme (UN-WFP), Wau, Southern Sudan.
[85] Mukabi J.N. (2007e). Geotechnologies for Sustainable Infrastructure Development, Publication
submitted for the Seminar on Developing Geotechnology for Sustainable Infrastructure
Development, Nairobi, Kenya.
![Page 55: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/55.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[86] Mukabi J.N. and Tatsuoka, F. (2007d): Pavement and Bridge Foundation Design Based on a Newly Proposed Consolidation and Shear Stress Ratio Concept, For Publication in the Geotechiques Journal.
[87] Mukabi J.N. and Tatsuoka, F. (2007c): Some Recently Developed Empirical Formulae for
Foundation Design, for Publication in the Journal of the American Society of Civil Engineers.
[88] Mukabi J.N., Toda, T. & Shimizu, N. (2007b): Application of a New Mechanical Stabilization
Technique in Reducing the Cost and Impact of Rural Road Construction, published in the
Proceedings of the 23rd World Road Congress, Paris, France.
[89] Mukabi J.N., Gono, K., Hatakeyama, R. & Tesfaye, A. (2007a): Unique Methods of Enhancing
Engineering Properties of Geomaterials for Slopes, Embankments and Pavement Structures,
published in the Proceedings of the 23rd World Road Congress, Paris, France.
[90] Mukabi J.N. (2006h): The Dynamics of Sustainable Highway Development within the Juba Transport
Infrastructure Master Plan, Publication submitted for the Workshop on Transport Infrastructure
Master Plan for Juba Sponsored by the Japan International Cooperation Agency (JICA), Juba,
Southern Sudan.
[91] Mukabi J.N. (2006g): Technical Evaluation of the Geotechnical Engineering Challenges along the
Kakuma ~ Lokkichogio Road, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
[92] Mukabi J.N. (2006f): Technical Evaluation of the Geotechnical Engineering Challenges along the
Lodwar ~ Kakuma Road, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
[93] Mukabi J.N. (2006e): Technical Evaluation of the Geotechnical Engineering Challenges along the
Marich Pass ~ Lodwar Road, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
[94] Mukabi J.N. (2006d): Technical Evaluation of the Geotechnical Engineering Challenges along the
Baringo ~ Marich Pass, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
[95] Mukabi J.N. (2006c): Transport Infrastructure Development Study In The Larger Juba Town, First
Seminar on The Emergency Study on The Planning And Support For Basic Physical And Social
Infrastructure In Juba Town And The Surrounding Areas, Juba, Southern Sudan.
[96] Mukabi J.N. (2006b): Technical Evaluation of the Geotechnical Engineering Challenges along the
Kapenguria ~ Marich Pass, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
![Page 56: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/56.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[97] Mukabi J.N. (2006a): Technical Evaluation of the Geotechnical Engineering Challenges along the
Kabarak ~ Baringo, Publication Prepared for Seminar on EAC/NEPAD Initiative on Regional
Integration, Nairobi, Kenya.
[98] Mukabi, J.N. (2005k): “Potential Geotechnical Engineering Challenges Related to
Flyover(Suspended) Highway Structures Development in Nairobi”, Publication submitted for the
Workshop on Nairobi Metropolitan Urban Transport (NUTRANS) Master Plan Sponsored by the
Japan International Cooperation Agency (JICA), Nairobi, Kenya.
[99] Mukabi, J.N. (2005j): Geoscience Principles for Engineering Design and Application, Publication in
the Proceedings of the 31st International Congress on Science, Culture and Arts in the 21st Century,
Hawaii, USA.
[100] Mukabi, J.N. (2005i): “Developing A Scientific Approach to Partial Solutions of Geotechnical
Engineering Problems”, Publication in the Proceedings of the 31st International Congress on
Science, Culture and Arts in the 21st Century, Hawaii, USA.
[101] Mukabi, J.N. Meselle, H. and Gono, K. (2005h): Characterization of Expansive Soil Under Static
and Dynamic Loading Conditions for Pavement Design, Publication in the Journal of civil
Engineering.
[102] Mukabi, J.N. Messelle, H. and Gono, K. (2005g): An Experimental and Analytical Method
Proposed for Evaluating High Plasticity Natural Geometrical, Publication in the Proceedings of the
15th International Road Federation (IRF), Real Madrid, Spain.
[103] Mukabi, J.N. Gono, K., and Hatakeyama, R. (2005f): A unique VE Pavement Design and
Construction Approach Adopted for Some Road Projects in Kenya and Ethiopia, Publication in the
Proceedings of the 15th International Road Federation (IRF), Real Madrid, Spain.
[104] Mukabi, J.N. (2005e): Pavement Structure Design and Construction Control, Publication in the
Proceedings of the 15th International Road Federation (IRF), Real Madrid, Spain.
[105] Mukabi, J.N. (2005d): Some Modified Methods for Highway Design and Construction,
Publication in the Proceedings of the 15th International Road Federation, Real Madrid, Spain.
[106] Mukabi, J.N. (2005c): “Characterization of Tropical Geomaterials Bearing Civil Engineering
Structures, Publication for Annual Conference of the Ethiopian Association of Civil Engineers,
Addis Ababa, Ethiopia.
[107] Mukabi, J. N. (2005b): The CMM Systematic Approach Concept For The Design of Flexible
Pavement Structures in Developing Countries, General Publication For Consulting and Practicing
Engineers in Developing Countries, Special Engineering Lecture.
![Page 57: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/57.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[108] Mukabi, J. N. (2005a): A Value Engineering Design for the Pavement Structures of the Holeta ~
Muger Road, Publication for Special Engineering Lecture for the Ethiopian Roads Authority, Addis
Ababa, Ethiopia.
[109] Mukabi, J. N. (2005a): Some State of the Art Design Principles and Construction Techniques,
Publication for Young Engineers Seminar on Road Engineering, Addis Ababa, Ethiopia.
[110] Mukabi, J. N. (2005a): Some Recent Advances in Highway and Bridge Foundation Engineering,
Capacity Building Seminar in Engineering Design for Counterpart Engineers of Ethiopian Roads
Authority, Addis Ababa, Ethiopia.
[111] Mukabi, J. N. (2005a): Application of Value Engineering Comprehensive Design Concepts for the
Pavement Structural Design of the Gimbothaya International Airport Access Road, Seminar on
Sustainable Infrastructure Development in Northern Ethiopia, Bahir Dar, Ethiopia.
[112] Mukabi, J. N. (2005a): Application of Value Engineering Comprehensive Design Concepts for the
Pavement Structural Design of the Bahir Dar University Pedagological Access Road, Seminar on
Sustainable Infrastructure Development in Northern Ethiopia, Bahir Dar, Ethiopia.
[113] Mukabi, J. N. (2005a): A New Technique for the Design and Construction of Slope Protection
Structures, Civil Engineering Seminar, Addis Ababa, Ethiopia.
[114] Mukabi, J. N. (2005a): Some Recently Developed Empirical Formulae For Foundation Design, 16th
International Congress on Science and Culture, Dublin, Ireland.
[115] Mukabi, J. N. (2005a): The Enhancement of Structural Capacity and Serviceability Level of the
Addis Ababa ~ Goha Tsion Trunk Road, Second 2003 Workshop on Research Oriented Design and
Construction for Civil Engineering Projects – II, Addis Ababa, Ethiopia.
[116] Mukabi, J. N. (2005a): Recently Developed Civil Engineering Countermeasures to Slope,
Embankment and Pavement Structures, First 2003 Workshop on Research Oriented Design and
Construction for Civil Engineering Projects – II, Addis Ababa, Ethiopia.
[117] Mukabi, J.N. (2004b): Characterization of Tropical Geomaterials Bearing Civil Engineering
Structures, (Publication for Consulting and Practicing Engineers in Tropical Countries)
[118] Mukabi, J. N. (2004a) : A Comprehensive Engineering Report Proposed Countermeasures to
Slope, Embankment and Pavement Structure Failure at Sta. 9+310 ~ 9+346km, Volume I.
Publication for Construction Project Consultants Inc. Ethiopian Roads Authority and Japan
International Cooperation Agency (JICA).
[119] Mukabi, J. N. (2003g): Some State of the Art Design Principles and Construction Techniques,
Publication for Young Engineers Seminar on Road Engineering, Addis Ababa, Ethiopia.
[120] Mukabi, J. N. (2003f): Some Recent Advances in Materials Science and Engineering, Publication
for Capacity Building Seminar in Engineering Design for Counterpart Engineers of Ethiopian Roads
![Page 58: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/58.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Authority, Addis Ababa, Ethiopia.
[121] Mukabi, J.N (2003e) Comprehensive Design Analysis of OV Type Based on The Proposed CMM
Design Concept, Publication for Ethiopian Roads Authority, Construction Project Consultants Inc;
and Kajima Corporation.
[122] Mukabi J.N, F. Tatsuoka, K.Gono, N. Shimizu, G. Feleke, R. Hatakeyama, W. Demoze, B. N.
Njoroge, A. Tesfaye. M. Tadele., (2003d). The Role of Enhanced Research Oriented Highway and
Foundation Design for Sustainable Development – Key Note Lecture, in proceedings of the
International Workshop on the Recent Trends in Civil Engineering.
[123] Mukabi, J.N., Feleke G., Demoze W., Zelalem A: (2003c). Impact of Environmental Factors on
the Performance of Highway Pavement Structures, in the proceedings of the International Civil
Engineering Conference on Sustainable development in the 21st Century. “Innovating Modified
NDT/DT Techniques for the Evaluation of an Existing Pavement Structure-Theoretical
Considerations and Experimental Results”, 2003.
[124] Mukabi, J.N., Gono K., Koishikawa K., Feleke G., Hatekayam R., Demoze W., Kunioka H.,
Zelalem A., (2003b). Innovating Modified NDT/DT Techniques for the Evaluation of An Existing
Pavement Structure-Theoretical Considerations and Experimental Results, in the proceedings of
the International Civil Engineering Conference on Sustainable development in the 21st Century.
[125] Mukabi, J.N., Gono, K., Koishikawa K., Feleke, G., Hatekayama, H., Demoze, W., Kunioka, R.,
Zelalem, A., (2003a). Innovating Modified NDT/DT Techniques for the Evaluation of An Existing
Pavement Structure-Method of Testing, in the proceedings of the International Civil Engineering
Conference on Sustainable development in the 21st Century.
[126] Mukabi, J.N (2002h): Some State of the Art Design Principles and Construction Techniques,
Publication for Young Engineers Seminar on Road Engineering, Addis Ababa, Ethiopia.
[127] Mukabi, J.N (2002g): Some Recent Advances in Slope Stability Design, Publication for Capacity
Building Seminar in Engineering Design for Counterpart Engineers of Ethiopian Roads Authority,
Addis Ababa, Ethiopia.
[128] Mukabi, J.N (2002f) Proposed approach to Determining Countermeasures to Slope Failure at
Sta. 9+310km ~ 9+346km, Publication for Kajima Corporation and Ethiopian Roads Authority.
[129] Mukabi, J.N (2002e): Effects of some geological aspects on the mechanical performance of
tropical road construction geomaterials, for publication in the proceedings of the 12th
International Conference of the International Association of Engineering Geology, Durban, South
Africa
[130] Mukabi, J.N., Inamdar, W.A., and Chacha, C.G. (2002d): Environmental vs. socio-economic
![Page 59: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/59.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
impact of rural roads construction in Western Kenya with reference to geotechnical aspects, for
publication in the proceedings of the 4th International Congress on Environmental Geotechnics, Rio
de Janeiro, Brazil.
[131] Mukabi, J.N. (2002c): Some Recent Advances in Highway and Bridge Foundation Engineering.
(General Publication Incorporating Some New Design Concepts, Ideas, Approach and Engineering
Theories for Consulting and Research Engineers).
[132] Mukabi, J.N. (2002b): Vital Geotechnical Engineering Concepts on Determining
Countermeasures to Slope Failure, Publication for Annual Conference for EACE, Addis Ababa,
Ethiopia.
[133] Mukabi, J.N. (2002a): Limitations of foundation design codes predominantly based on the
conventional concept of critical state soil mechanics, for publication in the Proceedings of the
International Symposium on foundation design codes and soil investigation, Kamakura, Japan.
[134] Mukabi, J.N(2001l) A New Approach Proposed for the Evaluation and Analysis of the Structural
Capacity and Overlay Design of a Road Pavement Structure, for Japan International Cooperation
Agency and Ethiopian Roads Authority.
[135] Mukabi, J.N(2001k) Evaluation of Plasticity Characteristics and their Reciprocal Influence on
Vital Road engineering Parameter, for Japan International Cooperation Agency and Ethiopian
Roads Authority.
[136] Mukabi, J.N (2001j) Analysis and Evaluation of the Structural Capacity and Serviceability Level
of the Existing Road Pavement (PHASE III), for Japan International Cooperation Agency and
Ethiopian Roads Authority.
[137] Mukabi, J.N (2001i) Field Study and Status Quo Assessment on the Geotechnical Aspects of the
Addis Ababa~Debre Markos Trunk Road Project, for Construction Project Consultants and Ethiopian
Roads Authority.
[138] Mukabi, J.N (2001h) Computation of Capping Layer Thickness with Reference to Native
Subgrade Bearing Capacity (for Japan International Cooperation Agency and Ethiopian Roads
Authority.
[139] Mukabi. J.N., Njoroge, B.N. and Shimizu, N. (2001g): A unique method of mechanical
stabilization and construction adopted for a road project in Kenya; for publication in the
Proceedings of the Conference on Construction Technology, Sabah, Malaysia.
[140] Mukabi, J.N. Njoroge B.N., and Toda, T. (2001f): Behaviour of stabilized black cotton soil from
the Lake Basin of Kenya, for publication in the proceedings of the Symposium on Soil Behaviour
![Page 60: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/60.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
and Soft Ground Construction, Massachusetts, USA.
[141] Mukabi, J.N., Kimura, Y., Shimizu, N., Mwangi, S.N., Omollo, A., and Njoroge, B.N. (2001e):
Evaluation of some Kenyan geomaterial properties for embankment design based on a quasi-
empirical approach, in Proceedings of the International Conference of the ISSMGE, Istanbul,
Turkey.
[142] Mukabi, J.N. (2001d): Derivation and application of consolidation and shear stress functions
with reference to Critical State analysis of N.C. clays, in the proceedings of the International
Conference of the ISSMGE, Istanbul, Turkey.
[143] Mukabi, J.N., Njoroge, B.N., and Toda, T. (2001c): Pragmatic method of evaluation design
parameters adopting Kenyan tropical soils for pavement structure, in Proceedings of the 14th IRF
World Road Congress, Paris, France.
[144] Mukabi, J.N., and Shimizu, N. (2001b): Strength and deformation characteristics of
mechanically stabilized road construction materials based on a new batching ratio method, in
Proceedings of the 14th IRF Road World Congress, Paris France.
[145] Mukabi, J.N., (2001a): Theoretical and empirical basis for a method of determining and
optimum batching ratio for mechanical stabilization of geomaterials, in Proceedings of the 14th IRF
Road World Congress, Paris, France.
[146] Mukabi, J.N. (2000). The design and construction of Reinforced Earth Embankments. In Internal
Reports and Correspondence, the Terre Armee Method, 2000. CPC, Nairobi.
[147] Mukabi, J.N (1999d). The Study on Rural Roads Improvement in Western Kenya – Materials
Testing Analyses and Countermeasures for Design Purposes. In Internal Reports and
Correspondence, Japan International Cooperation Agency (JICA) & Ministry of Roads & Public
Works, Kenya
[148] Mukabi J.N & Tatsuoka, F. (1999c). Effects of stress path and ageing in reconsolidation on
deformation characteristics of stiff natural clays. Proc. 2nd I.S on pre-failure characteristic of
Geomaterials, Torino.
[149] Mukabi, J.N., Wambura, J.H. & Maina, J. P. Murunga (1999b): Behaviour of CON-AID Treated
Fine Grained Kenyan Soils, 12th African Regional Conference on Geotechnics for Developing Africa,
pp. 583-592, Durban, South Africa.
[150] Mukabi, J.N. & Tasuoka, F. (1999a): Influence of Reconsolidation Stress History and Strain Rate
on The Behaviour of Kaolin Over a Wide Range of Strain, 12th African Regional Conference on
Geotechnics for Developing African, pp. 365-377, Durban, South Africa.
![Page 61: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/61.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[151] Mukabi J.N & Tatsuoka, F. (1995b). Effects of swelling and saturation of Unsaturated Soil
Behaviour and Applications, Int. Symposium on the Behaviour of Unsaturated Soils, University of
Nairobi, Nairobi, Kenya.
[152] Mukabi, J.N & Tatsuoka, F. (1994c), Small strain behavior in triaxial compression of lightly
over-consolidated Kaolin. In Proc. 49th Annual Conf. of JSCE, III: 286-297.
[153] Mukabi J.N & Tatsuoka, F., Kohata, Y. & Akino, N. (1994b). Small strain stiffness of Pleistocene
clays. Proc. Int. Symp. On pre-failure Deformation Characteristics of Geomaterials, IS-Hokkaid.
‘94’ Balkema, Vol. 1, PP. 189-195
[154] Mukabi J.N. & Tatsuoka, F. (1994a); Small strain behavior in triaxial compression of lightly over
consolidated Kaolin, proc. 49th Annual Conf. Of JSCE, III, pp.296~297.
[155] Mukabi, J.N.Tatsuoka, F. and Tsuchida, T-(1993b).Field and Laboratory measurements of small
strain stiffness for Osaka Bay Clays.Proc.of 26th annual meeting of JSCE in Sendai, 111:46-47.
[156] Mukabi, J.N. Abe, H. and Tatsuoka, F (1993a).Local Verses external measurements for axial
Strain for Clays.Proc.of the 28th annual meeting of JSSMFE in Kobe, Vol.2, PP.655-658.
[157] Mukabi J.N and Richardson P.(1992m).Contributions of the Civil Engineer in Realizing the
Minato Mirai 21 Mega-Project, a Publication for the International Symposium on Futuristic Cities,
Los Angeles, USA
[158] Mukabi J.N and Richardson P.(1992l).A Conceptual Presentation of the Main Futuristic
Components of the MM21 Development Projects, a Publication for the International Symposium on
Futuristic Cities, Los Angeles, USA
[159] Mukabi J.N, Yasukawa H. and Okubo Y. (1992k).Introduction of Some State of the Art
Technologies Adapted in MM21 Mega Project, a Publication for the International Symposium on
Futuristic Cities, Los Angeles, USA
[160] Mukabi J.N, Yasufuku M. and Silvestre G.(1992j).Applying Spatial Concepts for Urban Density
and Transportation Patterns, a Publication for the International Forum on Advanced Transport
Infrastructure Planning, Perth, Australia
[161] Mukabi J.N, Yasufuku M. and Silvestre G. (1992i).Introducing Computerized Noding Transport
Network Concepts, a Publication for the International Forum on Advanced Transport Infrastructure
Planning, Perth, Australia
![Page 62: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/62.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[162] Mukabi J.N, Yasufuku M. and Silvestre G. (1992h).Complex Permutation Matrices Developed for
Physical Infrastructure Integration, a Publication for the International Forum on Advanced
Transport Infrastructure Planning, Perth, Australia
[163] Mukabi J.N, Yasufuku M. and Silvestre G.(1992g).Applying the Circumferential Matrix Concept
in Transport Infrastructure Planning and Development ,a Publication for the International Forum
on Advanced Transport Infrastructure Planning, Perth, Australia.
[164] Mukabi J.N. (1992f).Urban Environmental Deterioration and The Civil Engineering, a Publication
Drafted for Challenges of The Future.
[165] Mukabi J.N. (1992e).Overview of the Strategies and Policies of the Development and
Management Profile of Transport Infrastructure In Asia and The Pacific, a special Publication for
the Asian Development Bank (ADB).
[166] [Mukabi J.N. (1992d).Control of Rapid Urbanization based on a Technical and Engineering
Approach, a publication for World Urbanization Prospects.
[167] Mukabi J.N. (1992c). Pragmatic Application of Enhanced Civil Engineering Technologies in
Curbing Population Explosion, a Publication for World Urbanization Prospects.
[168] Mukabi J.N. (1992b). The Role of Civil Engineering in the urban Environment a publication for
Planning and management in the Developing world.
[169] Mukabi J.N & Tatsuoka, F. (1992a); Effects of consolidation stress ratio and strain rate on the
peak stress ratio of Kaolin, the 27th Annual meeting of the JSSMFE, Kochi, PP.655~6
[170] Mukabi, J.N. (1991k): Behavior of clays for a wide range of strain in triaxial compression, Msc.
Thesis, University of Tokyo.
[171] Mukabi J.N (1991j).An Engineering 3-D Model for Analyzing Urban Rural Integration Based on
Civil Engineering Concepts, a Publication for the International Symposium on New Concepts for
Systematic Urban and Rural Development, Boston, USA.
[172] Mukabi J.N, Rampello G and Clayton R.(1991i).Proposed Methods for Developing Appropriate
Models for Rural Planning and Development, a Publication for the International Symposium on New
Concepts for Systematic Urban and Rural Development, Boston, USA.
[173] Mukabi J.N, Rampello G and Clayton R.(1991h).Pragmatic Application of the Orthometric
Quadra-Model for Structural Analysis of Rural Development Planning, a Publication for the
International Symposium on New Concepts for Systematic Urban and Rural Development, Boston,
USA.
![Page 63: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/63.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[174] Mukabi J.N, Rampello G and Clayton R.(1991g).Application of a Recently Proposed
Transformation Matrix Model for Urban Cluster Analysis, a Publication for the International
Symposium on New Concepts for Systematic Urban and Rural Development, Boston, USA.
[175] Mukabi J.N, Rampello G and Clayton R. (1991f).A Newly Proposed Transformation Matrix Model
for Analyzing Models of Rural Development, a Publication for the International Symposium on New
Concepts for Systematic Urban and Rural Development, Boston, USA.
[176] Mukabi J.N (1991e). Spatial Modelling for Rural~Urban Matrix Integration, a Publication for the
International Symposium on New Concepts for Systematic Urban and Rural Development, Boston,
USA.
[177] Mukabi J.N and White F.J.(1991d).Introducing some Basic Concepts for an Engineering 3-D
Model for Analyzing Urbanization Trends, a Publication for the International Symposium on
Analytical Methods for Urban Planning and Development, Manilla, Phillipines.
[178] Mukabi J.N(1991c).Applying Statistical and Probabilistic Methods in Analyzing Major
Impediments of Systematic Urban Development, a Publication for the International Symposium on
Analytical Methods for Urban Planning and Development, Manilla, Phillipines.
[179] Mukabi J.N, Molner D. and Viggianni S. (1991b).Alternative Energy Related Research: It’s
Contribution in providing some Crucial Solutions to Global Warming, a Publication for the
International Symposium on Global Environmental Challenges, Texas, USA.
[180] Mukabi J.N and Viggiann S. (1991a). A strategic approach in providing some Solutions to Global
Environmental Problems, a Publication for the International Symposium on Global Environmental
Challenges, Texas, USA.
[181] Mukabi J.N and White L, (1990k).Some Development Perspectives for Rural-Urban Migration
[182] in Developing Countries, a Publication for the Conference for Spatial Urban and Rural
Planning and Development, Niigata, Japan
[183] Mukabi J.N and White L,(1990j).An Engineering Study on the Impact of Urbanization on Rural
Planning and Development, a Publication for the Conference for Spatial Urban and Rural Planning
and Development, Niigata, Japan
[184] Mukabi J.N and White L,(1990i).The Role of Enhanced Transport Infrastructure Development in
Stimulating Rural Economics, a Publication for the Conference for Spatial Urban and Rural
Planning and Development, Niigata, Japan
[185] Mukabi J.N. (1990h).The Spiral Analytical Concept in Analyzing Physical Infrastructure
Development of Urban Centres, a Publication for the International Conference on the Urban
Planning and the Environment, Hawaii, US.
![Page 64: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/64.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[186] Mukabi J.N. and Carlos S,(1990g) An Engineering Perspective of the Comparative Analysis of
Urban Development Patterns, a Publication for the International Conference on the Urban Planning
and the Environment, Hawaii, USA.
[187] Mukabi J.N, Torimitsu K and Carlos S,(1990f).Challenges Emanating from Rapid Urbanization,
a Publication for the International Conference on the Urban Planning and the Environment, Hawaii,
USA.
[188] Mukabi J.N and Scott J. (1990e).Challenges of Rapid Enhancement of Transport Infrastructure
Development, Impact of Population Explosion on the Urban and Rural Environments.
[189] Mukabi J.N and Scott J. (1990d) Mass Transit Systems: Their Importance In Regional and
National Development. Impact of Population Explosion on the Urban and Rural Environments
[190] Mukabi J.N, Fukushima I. and Scott J.(1990c),Contribution of poor Transport Infrastructure to
Urbanization Problems, a Publication for the International Conference on Transport Infrastructure,
Hong Kong.
[191] Mukabi J.N and Fukagawa H. (1990b).Impact of Population Explosion on the Urban and Rural
Environments, a Publication for the Environmental Science Journal.
[192] Mukabi J.N and Fukagawa H. (1990a) Adverse Effects of Rapid Urbanization on the Physical
Environment, a Publication for the Environmental Science Journal.
[193] Mukabi J.N and Sato F.,(1989l).Some Critical Impediments of Urban Planning and
Development,a publication for the International Urban Planning and Development Conference,
Denver, USA
[194] Mukabi J.N, Hosokawa T. and Hiroshi K. (1989k).A Modeling Concept for Systematic Urban
Planning and Development Based on some Civil Engineering Concepts. a Publication for the
International Urban Planning and Development Conference, Denver, USA
[195] Mukabi J.N, Hosokawa T. and Hiroshi K. (1989j).A Newly Proposed Civil Engineering
Orthometric Quadra- Model Phasing for Structural Analysis of Urban Development, a Publication for
the International Urban Planning and Development Conference, Denver, USA
[196] Mukabi J.N (1989h) .A Proposed Civil Engineering Model for Integrated Urban Planning and
Development, a Publication for the International Urban Planning and Development Conference,
Denver, USA
[197] Mukabi J.N (1989g).Civil Engineering and Transport Infrastructure, Publication for Modern
Technologies for Transport Infrastructure Development, Seoul, South Korea.
![Page 65: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/65.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
[198] Mukabi J.N and Katagira I.,(1989f).The Importance of Strategic Infrastructure Planning for
Urban Transport Development, Publication for Modern Technologies for Transport Infrastructure
Development, Seoul, South Korea.
[199] Mukabi J.N and Katagiri I.,(1989e).The Role of Geotechnical Engineering in the Planning and
Development of Transport Infrastructure, Publication for Modern Technologies for Transport
Infrastructure Development, Seoul, South Korea.
[200] Mukabi J.N and Yashimura H., (1989d).An Engineering Model of Analyzing some Global Warming
Effects. Pre-Kyoto Protocol Publication.
[201] Mukabi J.N and Nakamura K., (1989c).Impact of Civil Engineering Structures or the Marine
Environment, Pre-Kyoto Protocol Publication.
[202] Mukabi J.N, Sakai T and Fukagawa K., (1989b).An Engineering Approach to the Assessment of
Rural Area Environment. Pre-Kyoto Protocol Publication.
[203] Mukabi J.N, Sakai T and Fukagawa K., (1989a).Evaluation of the Modernized Urban Environment
from a Civil Engineering Perspective, Pre-Kyoto Protocol Publication.
[204] Mukabi J.N (1988): The Role of Enhanced Scientific and Technological Methods for Futuristic
Cities, a Publication for the Journal of Technology and the Future.
[205] Mukabi J.N (1987): Futuristic Perspectives of the Civil Engineer in the 21st Century, a
Publication for the Journal of Technology and the Future.
[206] Mukabi J.N (1985).A Proposal based on the Fundamental Concept of Home and Office
Automation, a Publication in the Proposal of Futuristic Cities of the 21st Century.
![Page 66: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/66.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
12. EMPLOYMENT RECORD BASED ON TYPE OF SERVICES
Position(s) Held/Designation Duration Employer Location & Client Types of Services
Rendered
Team Leader/Lead
Consultant/Lead
Researcher/Chief Technical
Advisor
March 2012
~
Materials Testing &
Research Department
Nairobi, Kenya
Ministry of Roads,
GoK
Research
Consultancy,
Technical Advisory
Services
Team Leader/External
Consultant
February
2011 ~
Comito & Associati
S.r.l Consulting
Services
Rome, Italy
European Union
Consultancy,
Technical Advisory
Services
Research & Development
Consultant/Chief Technical
Advisor
November
2010 ~
August 2011
Materials Testing &
Research Department
Nairobi, Kenya
Ministry of Roads,
GoK
Technical Advisory
Services on
Formulation and
Development of
Versatile and
Effective Research &
Innovation
Programme for
Sustainable
Infrastructure
Development
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
November
2010 ~ Roman Roads Limited
Abuja, Nigeria
GoRN
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2009 ~
Bill Engineering
Works Ltd.
Nairobi, Kenya
Bill Engineering
Works Ltd.
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
May 2009 ~
June 2010
Eyat Oilfield Services
Co. Ltd
Khartoum, The
Sudan
Eyat Oilfield
Services Co. Ltd
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Projects Director/Chief
Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2008 ~ April
2010
Eyat Roads & Bridges
Co. Ltd
Khartoum, The
Sudan
Eyat Oilfield
Services Co. Ltd
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Chief Technical Advisor/Lead October Eyat Mining & Khartoum, The Technical Advisory,
![Page 67: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/67.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Consultant/Lead
Researcher/Team Leader
2008 ~ May
2009
Exploration Co. Ltd Sudan
Eyat Oilfield
Services Co. Ltd
ADR, Management,
Engineering
Consultancy
Project Director/Chief
Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
July 2008 ~
April 2009
Japan International
Cooperation Agency
(JICA)
Khartoum, The
Sudan/Juba South
Sudan
JICA
Technical Advisory,
ADR, Management,
Engineering
Consultancy/Research
Director/Chief Technical
Advisor/Lead
Consultant/Lead Researcher
March 2008
~
BPC & Engineering
Services
Nairobi, Kenya
BPC & Engineering
Services
Technical Advisory,
ADR, Management,
Engineering
Consultancy/Research
Project Director/Chief
Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
August
2007~ July
2008
Payii Roads & Bridges
Co. Ltd
Juba, Southern
Sudan
Payii Roads &
Bridges Co. Ltd
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Project Director/Chief
Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2007 ~
March 2010
Kundan Singh
Construction Ltd.
Nairobi, Kenya/Dar
es Salaam/Mbeya,
Tanzania
Kundan Singh
Construction Ltd.
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Project Director &
Manager/Chief Technical
Advisor/Lead
Consultant/Lead
Researcher/Team Leader
March 2007 ~ April 2008
MoM-GoSS/White
Nile Oil Exploration
Co. Ltd
White Nile Oil
Exploration Co. Ltd
Juba, Southern
Sudan/Nairobi,
Kenya/Johannesburg
, South Africa
&London, England
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader August 2007
~
Geotechnologies East
Africa Ltd
Nairobi,
Kenya/Kampala,
Uganda/Juba,
Southern Sudan
Technical Advisory,
ADR, Management,
Engineering
Consultancy
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2007 ~ Tensar International London, England
Technical Advisory,
ADR, Engineering
Consultancy
Chief Technical Advisor/Lead
Consultant/Lead
September
2006 ~ July
2007
Geotechnologies
South Africa Pty.
Johannesburg, South
Africa
Geotechnologies
Technical Advisory,
ADR, Management,
Engineering
Consultancy
![Page 68: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/68.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Researcher/Team Leader South Africa Pty.
Project Director/Chief
Executive Officer/ Chief
Consulting Engineer/ Lead
Consultant/Lead Researcher/
Chief Technical Advisor
February
2004 ~
Kensetsu Kaihatsu
Consultants/Kensetsu
Kaihatsu Limited
Kenya (MoLG/ODPM,
MoR, MoPW),
Ethiopia, Tanzania,
South Africa,
Rwanda, Burundi,
Sudan (MOTR),
(CPC, Kajima, JBIC)
etc.
Executive, Technical
Advisory, ADR,
Management,
Engineering
Consultancy
Asst. Managing Director,
Africa Region/ Projects
Manager/Chief Technical
Advisor/
May 2005~
June 2007
Katahira & Engineers
International
African Region
JICA, JBIC, GoK,
MoR, GOSS etc.
Executive, Technical
Advisory, ADR,
Management,
Engineering
Consultancy
Chairman October
2003 ~ CMCC Kenya Executive
Chief Technical Advisor &
Representative Resident
Engineer
July 2001 ~
April 2004
CPC/Kajima
Corporation Ethiopia
Detailed Design, BD,
FS,PS
Geotechnical Engineer/Chief
Project Coordinator
Mar 99 ~ Dec
99
JICA (seconded by
CPC) Kenya FS
CEO & Chief Consulting
Engineer Dec 97 ~ Revtech Ltd. Kenya Advisory
Asst. General/Projects
Manager & Chief Technical
Advisor
Apr 98 ~ Apr
04 CPC East Africa
Engineering
Consultancy
Examiner Oct 03 ~ Addis Ababa
University
Ethiopia (Post
Graduate Sch.) Examine & Advisory
Executive
Consultant/Director May 98 ~ Mpata Inv. Ltd. Kenya, Japan
Executive for Real
Estate, Property Dev.
Board of Examiners Member Sep 98 ~ UoN, JKUAT,AAU Kenya (Post
Graduate) Examine
Lecturer, Environmental
Science on Global Internet Jun 96 NEC Japan Lecture
Special Representative Apr 95 ~ Dec
97 Mpata International Japan Executive
![Page 69: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/69.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Chief Programme Developer Apr 95 ~ Dec
97 Todo Press Inc.
Japan (Eco-Training
Programme)
Executive/Education,
ICT, Environment
Director May 95 ~ RECSSAD Kenya Executive
Director Jul 95 ~ KEIPET Kenya, Executive
Managing Director Dec 95 ~
Dec 97 Mpata Inv. Ltd. Kenya
Executive
Assistant Managing Director Jan 92 ~ Jan
94 Mpata International Japan Executive
Part-Time Lecturer Apr 91 ~ Apr
94 JICA
Japan, UoT
(Institute of
Industrial Science)
Lecture
Assistant Supervisor Jan 91 ~ Apr
95 Nihon University
Japan (Department
of CE) Advisory/Lecture
Technical Consultant Jan 90 ~ Apr
95 Skillman & Co. Japan
Advisory
Director 1985 ~ DI-M Technology
Systems USA Executive
Notes*
CPC - Construction Project Consultant Inc. JICA - Japan International Cooperation Agency
JBIC - Japan Bank of International Cooperation UON - University of Nairobi
CMC - Createch Management Consultants JKUAT - Jomo Kenyatta University of Agriculture
DD - Detail Design & Technology
TC - Technical Consultancy AAU - Addis Ababa University
BD - Basic Design RECSSAD - Regional Centre for Social Studies
FS - Feasibility Study & Development
PS - Preliminary Study UOT - University of Tokyo
MoR Ministry of Roads MoPW - Ministry of Public Works
MoLG – Ministry of Local Government ODPM - Office of the Deputy Prime Minister
![Page 70: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/70.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
13. EXPERIENCE RECORD
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Researcher &
Geotechnical Engineer
Dec. 2010 ~
March 2011
(3.3 Months)
Kenya Airports
Authority (KAA)
Ministry of
Transport,
Kenya
Detailed Investigations on
the Hydrogeological
Conditions of Isiolo
International Airport Site
for Design of Hydraulic
Structures
Geotechnical
Engineering &
Hydrological
Investigation,
Soils Analysis,
Environmental
Factors
Assessment
Research &
Development (R&D)
Consultant/Chief
Technical Advisor
Dec. 2010 ~
March 2011
(3.6 Months)
Materials
Testing &
Research
Department
(MT&RD)
Review of Sate of the Art
Scientific and Engineering
RISD and Case Study
Analysis on Geosynthetics
Technologies
Nairobi, Kenya
Ministry of Roads, GoK
Technical
Advisory
Services on
RISD
Lead Researcher &
Geotechnical Engineer
November
2010 ~
February
2011
(1.8 Months)
Kenya Airports
Authority (KAA)
Ministry of
Transport,
Kenya
Determination of
Degree/Performance Ratio
of Geosynthetic
Reinforcement within
Runway Pavements
Nairobi, Kenya
KAA, MoT
Geotechnical
Engineering/
Geoscientific
Analysis and
Technical
Advisory
Services
Research &
Development (R&D)
Consultant/Chief
Technical Advisor
November
2010 ~
August 2011
(8.7 Months)
Materials
Testing &
Research
Department
(MT&RD)
Formulation and
Development of Versatile
and Effective Research &
Innovation Programme for
Sustainable Infrastructure
Development (SID)
Nairobi, Kenya
Ministry of Roads, GoK
Technical
Advisory
Services on
R&D/SID
![Page 71: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/71.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief
Materials/Pavement &
Geotechnical/Research
Engineer
October
2010 ~
ongoing
Kenya Airports
Authority (KAA)
Ministry of
Transport,
Kenya
Restoration of Original
Pavements at Isiolo Airport
Isiolo, Kenya
Kenya Airports Authority
Engineering
Study and
Detailed
Design,
Construction
Supervision,
Technical
Assistance &
Capacity
Building
Lead Consultant/Lead
Researcher
October
2010 ~
March 2011
(4.7 Months)
Roman Roads
Limited
Development of Value
Engineering Technologies
Proposal
Nairobi, Kenya
Roman Roads Limited
R&D
Consultancy,
Technical
Advisory, ADR,
Engineering
Consultancy
Chief Technical
Advisor/Lead
Consultant/Lead
Researcher/Team
Leader
October
2010 ~
February
2011
(3.4 Months)
Geogrids East
Africa (GEA)
Research and Enhancement
of Geogrids Performance
within Composite Pavement
Layers
Nairobi, Kenya
GEA
R&D
Consultancy,
Technical
Advisory, ADR,
Engineering
Consultancy
Highway/ Geotechnical/
Materials Engineer &
Team Leader/Lead
Consultant
June 2010 ~
Sept. 2010
(3.8Months)
Office of the
Dep. Prime
Minister &
MoLG, Nairobi
City Council
Proposal for Subsurface
Development and
Implementation of
Flyovers/Interchanges at
Traffic Congested and
Problematic Areas in
Nairobi City
Nairobi, Kenya
Ministry of Local
Government
Pre-Feasibility
& Engineering
Study,
Investigation,
& Preliminary
Design
![Page 72: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/72.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Research &
Development (R&D)
Consultant
April 2010 ~
May 2010
(1.3 Months)
Kenya Rural
Roads Authority
(KeRRA)
Ministry of
Roads
Review of the KeRRA
Research Policy Formulation
Nationwide, Kenya
KeRRA
R&D
Consultancy,
Technical
Advisory
Services
Lead Consultant/Civil
Engineering Consultant
March 2010
~ May 2010
(2.7 Months)
Kamal Steels
Ltd., Kamal
Holdings
Proposal for Design and
Construction of Civil Works
at Kamal Steels Plant in
Tanzania
Assessment, Investigation,
and Detailed Engineering
Analyses and Design for
Zinga Industrial Estate Steel
Plant
Dar es Salaam, Tanzania
Kamal Steels Ltd./Kamal
Holdings
Civil
Engineering
Consultancy,
Geotechnical
Investigation,&
Engineering
Study
Lead Researcher &
Geotechnical Engineer
June 2009 ~
August 2009
(2.8 Months)
Tanzania
Airports
Authority (TAA),
GoT
Detailed Study on the
Characteristics of
Pozzolanic Geomaterials
within the Vicinity of the
Site of Songwe International
Airport
Songwe, Tanzania
TAA/KSC
Geotechnical
Engineering
Investigations,
Soils Mechanics
& Geological
Characteristics
Analysis
![Page 73: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/73.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Project Director/Lead
Consultant/Chief
Technical Advisor &
Chief Highway, Materials
& Pavement Engineer
June 2009 ~
Ongoing
Ministry of Local
Government and
Office of the
Deputy Prime
Minister,
Republic of
Kenya
Proposed
Rehabilitation/Reconstructi
on of Selected Roads, Storm
Water Drains and Erection
of Street Lighting
Bomet, Kenya
MoLG & ODPM
Contract
Administration
/Management,
Construction
Supervision,
and
Development
of Quality
Control
Programme &
Maintenance
System
Project Director/Lead
Consultant/Chief
Technical Advisor &
Chief Highway, Materials
& Pavement Engineer
May 2009 ~
February
2011
(22 Months)
Ministry of Local
Government and
Office of the
Deputy Prime
Minister,
Republic of
Kenya
Proposed
Rehabilitation/Reconstructi
on of the Gisambai-Mbale
Road in Vihiga District
Vihiga, Kenya
MoLG & ODPM
Contract
Administration
/Management,
Construction
Supervision,
and
Development
of Quality
Control
Programme &
Maintenance
System
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief
Materials/Pavement &
Geotechnical Engineer
April 2009 ~
August 2009
(4.2 Months)
Ministry of Local
Government and
Office of the
Deputy Prime
Minister,
Republic of
Kenya
Engineering Study and
Detailed Design Review for
the Rehabilitation and
Reconstruction of Selected
Roads, Storm Water Drains
and Erection of Street
Lighting
Bomet, Kenya
MoLG & ODPM
Engineering
Study and
Detailed Design
Review
![Page 74: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/74.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief
Materials/Pavement &
Geotechnical Engineer
March 2009
~ June 2009
(3.5 Months)
Ministry of Local
Government and
Office of the
Deputy Prime
Minister,
Republic of
Kenya
Engineering Study and
Detailed Design Review for
the Rehabilitation and
Reconstruction of Gisambai-
Mbale Road in Vihiga
District
Vihiga, Kenya
MoLG & ODPM
Engineering
Study and
Detailed Design
Review
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief
Materials/Pavement &
Geotechnical Engineer
February
2009 ~ April
2010
(14 Months)
Tanzania
Airports
Authority (TAA),
United Republic
of Tanzania
Construction of Pavements
and Buildings at Songwe
Airport in Mbeya Region
Mbeya, Tanzania
TAA/KSC
Engineering
Study and
Detailed
Design,
Construction
Supervision,
Technical
Assistance &
Capacity
Building
Lead Researcher/Chief
Technical Advisor
June 2009 ~
July 2009
(0.8 Months)
Geotechnologies
East Africa/
Tensar
International
Application of Triax Tensar
for Enhanced Mechanical
Stabilization of Roads in
Ghana
Selected Urban and Rural
Roads, Ghana
Geotechnologies East
Africa/ Tensar International
Research,
Technical
Advisory &
Engineering
Consultancy
Lead Researcher/Chief
Technical Advisor
April 2009 ~
June 2009
(2.7 Months)
MoR, KSC
Upgrading to Bitumen
Standards of the
Kamukuywa ~ Kaptama ~
Kapsokwony ~ Sirisia Road
Mt. Elgon, Kenya
MoR/KSC
Research,
Technical
Advisory &
Engineering
Consultancy
![Page 75: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/75.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Researcher/Chief
Technical Advisor
April 2009 ~
May 2009
(0.8 Months)
Geotechnologies
South Africa/
Tensar
International
Application of Triax Tensar
for Enhanced Mechanical
Stabilization of Roads in
Uganda
Selected Urban and Rural
Roads, Uganda
Geotechnologies East
Africa/ Tensar International
Research,
Technical
Advisory &
Engineering
Consultancy
Lead Researcher/Chief
Technical Advisor
March 2009
~ May 2009
(1.2 Months)
Geotechnologies
South Africa/
Tensar
International
Application of Triax Tensar
for Enhanced Mechanical
Stabilization of Access
Roads, Airstrips and Pad
Foundations for Oil Drilling
Rigs in Upper Delta Nigeria
Upper Delta, Nigeria
Geotechnologies East
Africa/ Tensar International
Research,
Technical
Advisory &
Engineering
Consultancy
Lead Researcher/Team
Leader/Chief Technical
Advisor
January
2009 ~ June
2009
(5.3 Months)
TANROADS
Kundan Singh
Construction
(KSC) Co.
Limited
Engineering Study on the
Soil Interaction and
Performance of Geogrids
with Some Mbeya Soils
Mbeya, Tanzania
TANROADS/KSC
Research,
Technical
Advisory &
Engineering
Consultancy
Project Director/Team
Leader/Chief
Highway/Pavement/Geo
technical/Materials
Engineer
October
2008 ~
October
2009
(12 Months)
Government of
South Sudan
(GoSS)
Emergency Rehabilitation
Works in Juba (ERWJ) –
Construction, Rehabilitation
and Upgrading of LOT1
Roads in Juba
Juba, South Sudan
GoSS/Eyat Roads & Bridges
Co. Ltd
Contract
Administration
/Management,
DR, DD, CSV,
Technical
Advisory,
Engineering
Consultancy
![Page 76: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/76.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Chief
Highway/Pavement/Geo
-technical/Materials &
Bridge Foundation
Engineer
September
2008 ~
March 2009
(6.5 Months)
JICA
Juba Urban Transport
Infrastructure and Capacity
Development Study in the
Southern Sudan (JUTI)
Juba, South Sudan
JICA/CTII
GEI, BD,
Technical
Advisory,
Engineering
Consultancy
Team Leader/ Chief
Highway/Pavement/Geo
-technical and Materials
Engineer
August 2008
~ Sept. 2008
(0.9 Months)
Ol Seki Mara
Camp
Proposed Design and
Construction of the Ol Seki
Airstrip
Ol Seki, Maasai Mara, Kenya
GEA/ Ol Seki Mara Camp
PF,SDR,BD,DD,
ADR
Team Leader/ Chief
Foundation/Geotechnica
l and Materials Engineer
July 2008 ~
April 2009
(9.3 Months)
JICA
Preliminary Study on
Strengthening Facilities and
Equipment of Multi-service
Training Center (MTC) in
Juba, South Sudan
Juba, South Sudan
JICA
GEI, BD, DD
Technical
Advisory,
Engineering
Consultancy
Team Leader/ Chief
Highway/Pavement/Geo
-technical and Materials
Engineer
June 2008 ~
August 2009
(2.4 Months)
MoR
Engineering Study on the
Performance of Tensar
Geogrids with Local Soils for
Outering Ring Road Project
Nairobi, Kenya
GEA/Tensar International
Research,
Technical
Advisory &
Engineering
Consultancy
Team Leader/Lead
Researcher & Chief
Geotechnical Engineer
May 2008 ~
May 2008
(0.7 Months)
Kenya Wildlife
Service
Engineering Study on the
performance of Tensar
Geogrids with local soils for
Kenya Wildlife Service
FS, PS,
Technical
Advisory
![Page 77: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/77.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Sr. Geotechnical
Engineer- Team Leader
April 2008 ~
May 2008
(1.3 Months)
Kenya Airports Authority
Engineering Study on the
performance of Tensar
Geogrids with local soils for
Kisumu Airport Expansion
Project.
Kisumu & Nairobi, Kenya
GEA/Tensar International
Technical
Advisory,
Engineering
Consultancy,
BD, DD
Team Leader/Chief
Highway/Pavement/Geo
technical/Materials
Engineer
April 2008 ~
May 2008
(1.2 Months)
MoR
Investigation of Pavement
Structural Capacity,
Strength and Deformation
Resistance of the Thogoto ~
Gikambura ~ Mutarakwa
Road
Central Province, Kenya
MoR/KSC
Technical
Advisory,
Engineering
Consultancy,
DR
Team Leader/Chief
Highway/Pavement/Geo
technical/Materials
Engineer
February
2008 ~ April
2008
(2.3 Months)
MoR
Engineering Study on the
performance of Tensar
Geogrids with Local Soils for
Mukurweini-Gakonya and
Rutune-Mahuani Roads
Project
Nyeri/Murang’a, Kenya
Tensor Intentional And
Geotechnologies South
Africa
BD, FS,
Technical
Advisory
Chief
Highway/Pavement/Geo
-technical and Materials
Engineer
January
2008 ~ May
2008
(4.6 Months)
TANROADS
Mbeya ~ Lwamjilo Road
Rehabilitation Project
Mbeya, Tanzania
TANROADS/KSC
DR, DD, CSV,
Technical
Advisory,
Engineering
Consultancy
![Page 78: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/78.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief
Highway/Pavement/Geo
-technical/Materials
Engineer
January
2008 ~
March 2008
(2.7 Months)
Governor’s Office/Ministry
of Physical Infrastructure and Planning
Transport Infrastructure
Development Study for
Malakal Town
Malakal, South Sudan
Governor’s Office/Ministry
of Physical Infrastructure
and Planning
PFS,
Engineering
Consultancy &
Technical
Advisory
Team Leader/ Chief
Materials &
Geotechnical Engineer
October
2007 ~
October
2007
(0.8 Months)
United Nations
World Food
Programme
(UN-WFP)
Evaluation of Contractor’s Contractual Claims for
Extension of Time for the Construction of the Wau ~ Abyei Trunk Road Project
Location Wau ~ Abyei, Southern Sudan
United Nations World Food Programme (UN-WFP)
Engineering
Consultancy &
Technical
Advisory
Project Director/Team
Leader/Chief
Highway/Pavement/Geo
technical/Materials
Engineer
September
2007 ~
November
2008
(14 Months)
Government of
South Sudan
(GoSS)
Gravel Road Rehabilitation
Works for Lainya ~ Jambo
Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Co. Ltd
DR, DD, CSV,
Technical
Advisory,
Engineering
Consultancy,
Contract
Administration
/Management
Lead Consultant/ Team
Leader/Lead Researcher
September
2007 ~
November
2007
(2.8 Months)
Government of
South Sudan
(GoSS)
Study on the Enhancement
of the Subgrade Structural
Performance for Lainya ~
Jambo Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Co. Ltd
Research,
Engineering
Consultancy &
Technical
Advisory
![Page 79: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/79.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Chief
Geotechnical Engineer
September
2007 ~
November
2007
(2.6 Months)
Government of
South Sudan
(GoSS)
Comprehensive
Hydrogeological Study for
Lainya ~ Jambo Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Co. Ltd
DR, DD,
Technical
Advisory,
Engineering
Consultancy
Team Leader/Chief Civil
Engineer
August 2007
~ May 2008
(8.5 Months)
Government of
South Sudan
(GoSS)
Detailed Scoping and Civil
Engineering Study of
Various Aspects of the
Lainya ~ Jambo Trunk Road
Government of South Sudan
(GoSS)
DS, PD,
Technical
Advisory,
Engineering
Consultancy
Team Leader/ Chief
Materials &
Geotechnical Engineer
August 2007
~ October
2007
(2.8 Months)
JICA
Ntare~Rushatsi Boulevard
Project for Pavement
Rehabilitation on City Roads
in Bujumbura
Bujumbura, Burundi
JICA
ADR, FS, BD,
DD
Lead Researcher/ Chief
Technical Advisor
August 2007
~ October
2007
(2.4 Months)
Geotechnologies East Africa
Research And Development
Study For Affordable
Housing For East And
Central Africa
Nairobi, Kenya
Juba, South Sudan
Geotechnologies East Africa
Research, FS,
PD, CS
Technical
Advisory
![Page 80: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/80.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief
Foundation/Pavement/
Geotechnical/Materials
Engineer
March 2007
~ November
2007
(8.7 Months)
White Nile Oil Exploration Co.
Ltd/GoSS
Engineering Design for Pad
Foundations for Oil Drilling
Rigs, Access Roads, Airstrip
and Base Camps for the
White Nile oil Exploration
Project in South Sudan
Jonglei, South Sudan
White Nile Oil Exploration
Co. Ltd/GoSS
BD, DD,
Engineering
Consultancy &
Technical
Advisory,
Contract
Administration
/Management
Lead Researcher/Team
Leader
March 2007
~ May 2007
(2.9 Months)
White Nile Oil Exploration Co.
Ltd/GoSS
Comprehensive
Geotechnical and
Hydrological Investigations
and R&D of Value
Engineering Technologies
for the White Nile oil
Exploration Project in South
Sudan
Jonglei, South Sudan
White Nile Oil Exploration
Co. Ltd/GoSS
Research,
Engineering
Consultancy &
Technical
Advisory
Lead Researcher/Team
Leader
March 2007
~ April 2007
(1.6 Months)
United Nations World Food
Programme (UN-WFP)
Technical and Engineering
Study for Determination of
Suitable and Pragmatic
Project Mitigation Measures
for the Cost-Time-Effective
Implementation of the Wau
~ Abyei Trunk Road Project
Wau ~ Abyei, Southern
Sudan
United Nations World Food Programme (UN-WFP)
Research,
Engineering
Consultancy &
Technical
Advisory
![Page 81: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/81.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief
Highway/Pavement/Geo
-technical/Materials
Engineer
February
2007 ~
August 2007
(6.8 Months)
Governor’s Office/Ministry
of Physical Infrastructure and Planning
Transport Infrastructure
Development Project
Leer~Adok Trunk Road and
Port Project
Bentiu, Unity State, South
Sudan
Governor’s Office/Ministry
of Physical Infrastructure
and Planning
PFS,
Engineering
Consultancy &
Technical
Advisory
Project Manager/Chief
Materials, Pavement &
Highway
Engineer/Research
Team Leader
November
2006 ~ July
2008
(21 Months)
GOSS/ World Food Programme
(WFP)
Consultancy Work
Supervision Of Emergency
Road Repairs In South Sudan
– Phase 3
Wau/Abyei, South sudan
GoSS/WFP
ADR, DD, FS,
Contract
Administration,
Project
Management
Lead Researcher/Team
Leader
November
2006 ~ July
2007
(9 Months)
United Nations World Food Programme (UN-WFP)
Comprehensive
Engineering and Geo-
materials Science
Research for the
Development of
Appropriate Value
Engineering Technologies
for the Wau ~ Abyei
Trunk Road Project
Wau ~ Abyei, Southern Sudan
United Nations World Food Programme (UN-WFP)
Research,
Engineering
Consultancy &
Technical
Advisory
![Page 82: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/82.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Project Manager/Lead
Consultant/Team
Leader/Chief Pavement
and Geotechnical
Engineer
October
2006 ~
September
2007
(11 Months)
JICA
Juba River Port Access Road
Detailed Engineering Design
and Construction
Supervision Project
Juba, South Sudan
JICA/Katahira & Engineers
International/Urban Tone
Corporation
ADR, DD, FS,
Contract
Administration,
Project
Management,
Engineering
Consultancy &
Technical
Advisory
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
July
2006 ~
December
2006
(5.8 Months)
JICA
Implementation of the Pilot
Projects in Juba Town
Juba, South Sudan
JICA/Katahira & Engineers
International
CSV,
Engineering
Consultancy &
Technical
Advisory
Lead Consultant
June
2006 ~ June
2006
(0.3 Months)
GoK/Mitsui Corporation
Preparation of Application
Form for Japan’s Grant Aid
for the Construction of the
Kapenguria ~ Marich Pass
Road Section Along A1
Kapenguria ~ Marich Pass,
Kenya
GoK/Mitsui Corporation
Engineering
Consultancy
Lead Consultant
July
2006 ~
December
2006
(5.8 Months)
GoK/Mitsui Corporation
Preparation of Application
Form for Japan’s Grant Aid
for the Construction of
Sebit and Wakor Bridges on
the Kapenguria ~ Marich
Pass Section Along A1
Kapenguria ~ Marich Pass,
Kenya
GoK/Mitsui Corporation
Engineering
Consultancy
![Page 83: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/83.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
May
2006 ~ June
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Kakuma ~
Lokkichogio Trunk Road
Section under the
EAC/NEPAD Initiative for
Regional Integration
Kakuma ~ Lokkichogio
JICA/GoK/Mitsui
Corporation
PFS, PEA
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
April
2006 ~ May
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Lodwar ~
Kakuma Trunk Road Section
under the EAC/NEPAD
Initiative for Regional
Integration
Lodwar ~ Kakuma
JICA/GoK/Mitsui
Corporation
PFS, PEA
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
March
2006 ~
February
2007
(12 Months)
JICA/GoSS
Comprehensive Evaluation
of the Engineering
Implementation of the
Emergency Study on
Planning and Support for
Basic Physical and Social
Infrastructure in Juba and
the surrounding areas in
Southern Sudan
Juba, Southern Sudan
JICA/GoSS
PFS, PD, CEE,
Engineering
Consultancy &
Technical
Advisory
![Page 84: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/84.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
March
2006 ~ April
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Marich
Pass ~ Lodwar Trunk Road
Section under the
EAC/NEPAD Initiative for
Regional Integration
Marich Pass ~ Lodwar
JICA/GoK/Mitsui
Corporation
PFS, PEA
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
February
2006 ~
March 2006
(0.5 Months)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the
Kapenguria ~ Marich Pass
Trunk Road Section under
the EAC/NEPAD Initiative
for Regional Integration
Kapenguria ~ Marich
JICA/GoK/Mitsui
Corporation
PFS, PEA
Chief Technical
advisor/Chief Project
Coordinator/Lead
Researcher/Chief.
Materials/Pavement &
Geotechnical Engineer
January
2006 ~
March 2007
(15 Months)
JICA
Emergency Study on The
Planning And Support For
Basic Physical And Social
Infrastructure In Juba Town
And The Surrounding Areas
Juba, South Sudan
JICA
FS, BD, R&D,
Engineering
Consultancy,
Technical
Advisory
![Page 85: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/85.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
January
2006 ~
February
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Baringo ~
Marich Pass Trunk Road
Section under the
EAC/NEPAD Initiative for
Regional Integration
Baringo ~ Marich Pass
JICA/GoK/Mitsui
Corporation
PFS, PEA
Lead Consultant/Team
Leader/Chief Highway
and Geotechnical
Engineer
December
2005 ~
January
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Kabarak
~ Baringo Trunk Road
Section under the
EAC/NEPAD Initiative for
Regional Integration
Kabarak ~ Baringo
JICA/GoK/Mitsui
Corporation
PFS, PEA
Deputy Project
Manager/Senior Highway
& Geotechnical Engineer
June
2005 ~
September
2005
(3.5 Months)
GoSS
Preliminary Study of
Southern Sudan Roads
Network and Capacity
Building
South Sudan
GoSS
FS, BD,
Contract
Administration,
Project
Management
Sr. Highway Engineer
and Team Leader
May
2005 ~
August 2005
(3.4 Months)
Ethiopia Roads Authority (ERA)/ Addis Ababa City Roads Authority
(AACRA)
Feasibility Study and
Preliminary Engineering
Design for the Addis Ababa
Urban Transport Network
Development
Addis Ababa, Ethiopia
ERA/AARA
FS, BD,
Technical
Advisory
![Page 86: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/86.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Chief Technical
Advisor/Senior Highway
& Geotechnical Engineer
May
2005 ~
October
2005
(6 Months)
JICA/ MoR/MoLG
The Study on Master Plan
for Urban Transport in the
Nairobi Metropolitan Area
Nairobi, Kenya
JICA/ MoR/MoLG
FS, BD,
Engineering
Consultancy,
Technical
Advisory
Sr. Highway Engineer
and Team Leader
April
2005 ~ May
2005
(1.8 Months)
ERA/AACRA
Feasibility Study and
Preliminary Engineering
Design for Mitigation
Measures against Traffic
Congestion and
Improvement Measures of
Traffic Safety in Addis
Ababa City
Addis Ababa, Ethiopia
ERA/AACRA
FS, Engineering
Consultancy,
Technical
Advisory
Sr. Highway Engineer
and Team Leader
January
2005 ~
January
2006
(12 Months)
JICA/ERA
Post-Construction Project
Evaluation and Preparation
of the Consultancy and
Contract Completion
Reports for the Addis
Ababa-Goha ~ Tsion
International Trunk Road
Project
Addis Ababa, Ethiopia
JICA/ERA/Kajima
Corporation
FS, BD, DD,
Engineering
Consultancy,
Technical
Advisory
![Page 87: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/87.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Engineering
Consultant/Chief
Technical Advisor/
Claims Engineer
June
2004 ~
December
2004
(6.5 Months)
Kajima Corporation
Evaluation assessment and
preparation of Contractual
Claims for the Addis Ababa-
Goha ~ Tsion International
Trunk Road Project
Addis Ababa, Ethiopia
Kajima Corporation
Claims
Assessment &
Evaluation,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Sr.
Geotechnical & Highway
Engineer
May
2004 ~
February
2005
(9.2 Months)
MoFED/ ERA / Kajima
Corporation
Feasibility Study and
Preliminary Engineering
Design of the Upgrading
Project of the Holeta~Muger
Road
Holeta ~ Muger, Ethiopia
MoFED/ ERA / Kajima
Corporation
FS, BD,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Project
Director/Sr.
Geotechnical & Highway
Engineer
May
2004 ~
September
2004
(3.8 Months)
ODPM/Bahir Dar Municipality
Feasibility Study and
Preliminary Engineering
Design Project for the
Upgrading and Expansion of
the Gimbothaya
International Airport and
Access Road in Bahir Dar
Bahir Dar, Ethiopia
ODPM/Bahir Dar
Municipality
FS, BD,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Project
Director/Sr.
Geotechnical & Highway
Engineer
May
2004 ~ July
2004
(2.5 Months)
ODPM/Bahir Dar Municipality
Feasibility Study and
Preliminary Engineering
Design of the Bahir Dar
University Road
Bahir Dar, Ethiopia
ODPM/Bahir Dar
Municipality
FS, BD,
Engineering
Consultancy,
Technical
Advisory
![Page 88: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/88.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader /Sr.
Highway & Geotechnical
Engineer/Lead
Researcher
March
2003 ~ April
2004
(12 Months)
MoFED/ ERA / Kajima
Corporation
Study for the Enhancement
of Structural Capacity and
Serviceability Level of the
Addis Ababa – Goha Tsion
Trunk Road.
Addis Ababa ~ Goha Tsion,
Ethiopia
MoFED/ ERA / Kajima
Corporation
FS, R&D,
Engineering
Consultancy,
Technical
Advisory
Dep. Project
Manager/Sr.
Geotechnical & Highway
Engineer/Lead
Researcher
December
2002 ~
March
2004
(15 Months)
JICA
Detailed Engineering Design
and Construction
Supervision of the Addis
Ababa~Goha Tsion Trunk
Road Project – Phase IV
Addis Ababa ~ Goha Tsion,
Ethiopia
JICA/ERA
BD, DD, DR,
R&D,
Engineering
Consultancy,
Technical
Advisory
Deputy Project
Manager/Resident
Geotechnical & Highway
Engineer/ Lead
Researcher
January
2002 ~
February
2003
(13 Months)
JICA
Detailed Engineering Design
and Construction
Supervision of the Addis
Ababa~Goha Tsion Trunk
Road Project – Phase III
Addis Ababa ~ Goha Tsion,
Ethiopia
JICA/ERA
BD, DD, DR,
R&D,
Contract
Administration,
Project
Management,
Engineering
Consultancy,
Technical
Advisory
![Page 89: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/89.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
External Consultant/Sr.
Geotechnical Engineer
June
2001 ~
March
2004
(33 Months)
JICA/Ministry of Roads and Transport,
Ghana
Detailed Design of the
Project for Construction of
Bridges , Ghana
Nationwide, Ghana
JICA/Ministry of Roads and
Transport, Ghana
FS, PS, BD,
Technical
Advisory
Team Leader/ Sr.
Highway & Geotechnical
Engineer/Lead
Researcher
October
2000 ~ April
2004
(43 Months)
JICA
Comprehensive Study and
Design Review of Road
Pavements and Related
Structures for the Addis
Ababa ~ Debre Markos Road
Development Project
Addis Ababa ~ Debre Markos
JICA/ERA
BD, DD, DR,
R&D,
Engineering
Consultancy,
Technical
Advisory
Claims Engineer
July, ‘00 ~
August, ‘00
(1.2 Months)
Japan Bank of International
Cooperation/Office of the President
Evaluation Contractor’s
Contractual Claims for
Variations and Extension of
Time for Sections B (Hola ~
Garsen) and C (Garsen ~
Malindi) of the Malindi ~
Garissa Trunk Road (B8) -
the Tana Basin
Development Project Phase
II
Hola ~ Garsen ~ Malindi,
Kenya
Japan Bank of International
Cooperation/Office of the
President
Engineering
Consultancy,
Technical
Advisory
![Page 90: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/90.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/ Sr.
Foundation &
Geotechnical
Engineer/Lead
Researcher
June
2000 ~
November
2000
(5.8 Months)
JBIC/Office of The President,
Kenya
Comprehensive Study and
Design Review of Bridge and
Hydraulic Structures for the
Tana Basin Road
Development Project
Malindi ~ Garsen ~Garissa,
Kenya
JBIC/ Office of The
President/MoRPW
DR, R&D,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Chief
Technical Advisor/ Sr.
Pavement/Geotechnical
& Materials
Engineer/Lead
Researcher
June
2000 ~
November
2000
(5.1 Months)
JBIC/Office of The President,
Kenya
Design of Reinforced Earth
Structures with Slope
Protection applying the
Terre Armee Method for the
Tana Basin Development
Project Phase II
Malindi ~ Garsen ~Garissa,
Kenya
JBIC/ Office of The
President/MoRPW
DR, R&D,
Engineering
Consultancy,
Technical
Advisory
Claims Engineer
May
2000 ~ May
2000
(0.6 Months)
Mpata International,
Japan
Evaluation and
Establishment of a Counter
Claim of Pioneer Plumbers
Contractual Claims for
Variations for the Mpata
Safari Club Project
Masai Mara, Kenya
Mpata International, Japan
Engineering
Consultancy,
Technical
Advisory
![Page 91: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/91.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Chief
Technical Advisor/Sr.
Geotechnical
January
2000 ~ May
2000
(4.3 Months)
JBIC/Office of The President,
Kenya
Review of Hydrological
Conditions and Chronology
for Redesigning Hydraulic
Structures for the Tana
Basin Development Project
Phase II
Malindi ~ Garsen ~Garissa,
Kenya
JBIC/ Office of The
President/MoRPW
DR,
Engineering
Consultancy,
Technical
Advisory
Deputy Project
Manager/Resident
Geotechnical & Highway
Engineer/ Lead
Researcher
December
1999 ~
March
2002
(27 Months)
JICA
Detailed Engineering Design
and Construction
Supervision of the Addis
Ababa~Goha Tsion Trunk
Road Project – Phase II
Addis Ababa ~ Goha Tsion,
Ethiopia
JICA/ERA
BD, DD, DR,
R&D,
Contract
Administration,
Project
Management,
Engineering
Consultancy,
Technical
Advisory
Chief Materials/
Geotechnical &
Pavement
Engineer/Chief Project
Coordinator & Advisor to
Team Leader
March
1999 ~
December
1999
(8.4 Months)
JICA
Study on Rural Roads
Improvement in Western
Kenya Considering Socio-
Economic Impact,
Environmental Impact
Assessment and Value
Engineering Based Design
JICA/MoF/MoRPW
FS, BD,
Engineering
Consultancy,
Technical
Advisory
![Page 92: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/92.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Sr. Civil
Engineer
Jan, 1999 ~
March, 1999
(2.4 Months)
Japan Bank of International Cooperation
(Fmr. OECF)/Office of the President
Report to the Japan Bank of
International Cooperation
(JBIC) Appraisal Mission for
The Additional Loan to the
Tana Basin Development
Road Project in The
Republic of Kenya
Malindi ~ Garissa, Kenya
Japan Bank of International
Cooperation (Fmr.
OECF)/Office of the
President
Engineering
Consultancy,
Technical
Advisory
Team Leader/Civil
Engineering Consultant
November
1998 ~
January
1999
(2.2 Months)
Mitsubishi and Takenaka
Corporations, Kenya
Socio-Economic &
Engineering Assessment and
Analysis of Viability of
Undertaking Rehabilitation
& Expansion of Mombasa
International Airport Access
Road (C110) and Part (A109)
Mombasa, Kenya
Mitsubishi Corporation/ Takenaka Corporation,
Japan
FS, Engineering
Consultancy,
Technical
Advisory
Civil Engineering
Consultant/Highway &
Geotechnical Engineer
September
1998 ~
February
1999
(5.8 Months)
IDI/GoK
Project Formulation Based
on Socio-economic and
Engineering Assessment of
the El-Nino Damaged
Approach Roads and Bridges
in Eastern and Coast
Provinces of Kenya
Eastern and Coast
Provinces, Kenya
IDI/GoK
PFS,
Engineering
Consultancy,
Technical
Advisory
![Page 93: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/93.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Sr. Civil
Engineering Consultant
September
1998 ~
December
1998
(3.6 Months)
Office of the President/ Ministry of
Public Works & Housing
Formulation and
Implementation of the Tana
Basin Road Flood Recovery
and Rehabilitation Project
Office of the
President/Ministry of Public
Works & Housing
PFS,
Engineering
Consultancy,
Technical
Advisory
Team
Leader/Geotechnical
Engineering
Consultant/Structural
Engineer
September
1998 ~
October
1998
(1.8 Months)
Sumitomo Construction
Company, Japan
Analysis of The Settlement
Problem at Athi River
Cement Works
Athi River, Kenya
Sumitomo Construction
Company, Japan
SA, DR,
Engineering
Consultancy,
Technical
Advisory
Team Leader/ Sr.
Highway & Geotechnical
Engineer
August
1998 ~
November
1998
(2.6 Months)
Mitsubishi Corporation,
Japan
Feasibility Study for Road
Improvement and
Preliminary Design for the
Moi International Airport,
Mombasa Access Road
Mombasa, Kenya
Mitsubishi Corporation/ Takenaka Corporation,
Japan
PFS, PD,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Research
Consultant
June
1998 ~
November
1998
(5.2 Months)
Con Aid, Mitsui & Co East
Africa. Con-Aid Pty SA
Research on the
Improvement and Adoption
of Liquid Chemical
Stabilizers for Rural Road
Development
Nairobi, Kenya
Johannesburg, South Africa
Con Aid, Mitsui & Co East
Africa. Con-Aid Pty SA
R&D,
Engineering
Consultancy,
Technical
Advisory
![Page 94: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/94.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Team Leader/Research
Consultant/Pavement &
Geotechnical Engineer
June
1998 ~
October
1998
(3.4 Months)
Con Aid, Mitsui & Co East
Africa. Con-Aid Pty SA
Study of Improved Methods
of Design, Environmental
and Socio-economic Aspects
for Evaton Municipal Roads
in Johannesburg
Nairobi, Kenya
Johannesburg, South Africa
Con Aid, Mitsui & Co East
Africa. Con-Aid Pty SA
R&D, BD, DD,
Engineering
Consultancy,
Technical
Advisory
Civil Engineering
Consultant/Highway &
Geotechnical Engineer
May
1998 ~ July
1998
(2.3 Months)
CPC/JICA
Socio-economic and
Engineering Assessment,
Analysis and Project
Formulation as a Mitigation
Strategy of the Impact of
El-Nino on the C70 Kangema
~ Gacharage Road & Bridges
Kangema ~ Gacharage,
Kenya
JICA/MoRPW
PFS,
Engineering
Consultancy,
Technical
Advisory
Research Team
Leader/Lead Researcher
April, 1998
~ October,
1998
(7.9 Months)
CON-AID Pty, South
Africa/Mitsui Corporation, South Africa/
Mitsui Corporation,
Kenya
CON-AID Research and
Development Proposal
Garsen ~ Hola, Kenya
CON-AID Pty, South
Africa/Mitsui Corporation,
South Africa/ Mitsui
Corporation, Kenya
R&D,
Engineering
Consultancy,
Technical
Advisory
![Page 95: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/95.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Lead Researcher/Civil
Engineering
Consultant/Team
Leader/Chief Projects
Coordinator
April
1998 ~
August
1998
(4.2 Months)
Industrial Development
Institute, Japan
Study on Effective Strategy
of Enhancing Research &
Development in Civil and
Structural Engineering in
Kenya
Countrywide, Kenya
Industrial Development
Institute, Japan
R&D,
Engineering
Consultancy,
Technical
Advisory
Deputy Project
Manager/Team
Leader/Research
Consultant/Pavement &
Geotechnical Engineer
March
1998 ~ April
2002
(49 Months)
JBIC/ Office of The President
Detailed Design and
Construction Supervision of
the Malindi ~ Garissa
International Trunk Road
under the Tana Basin
Development Project
Malindi ~ Garissa, Kenya
JBIC/ Office of The
President/MoRPW
BD, DD, DR,
R&D,
Contract
Administration,
Project
Management,
Engineering
Consultancy,
Technical
Advisory
Team Leader/Chief
Consulting & Research
Engineer
March
1998 ~ June
1998
(3.5 Months)
World Bank
Low & Medium Cost Housing
Development Projects in
Urban & Rural Areas (With
Particular Reference to
Material Science and
Construction Techniques
Development)
Nationwide, Kenya
World Bank
R&D, FS, PS,
PD,
Engineering
Consultancy,
Technical
Advisory
Deputy Team Leader/
Urban Planning & Civil
Engineering Consultant
January
1997 ~ July
1997
(6.2 Months)
MoT/ World Bank
Urban Traffic Control and
Planning for Major Cities in
Kenya
Urban Areas, Kenya
MoT/ World Bank
Engineering
Consultancy,
Technical
Advisory
![Page 96: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/96.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Deputy Team Leader/Sr. Geotechnical/Civil & Structural Engineer
August
1996 ~
November
1997
(15 Months)
African Development Bank (ADB)/ Ministry of
Health, Kenya
Rehabilitation of Health
Facilities in Western Kenya
Western Region of Kenya
ADB/MoH
FS, PDS, DR,
BD,
Engineering
Consultancy,
Technical
Advisory
Urban Planning & Civil
Engineering Consultant
July
1995 ~ June
1996
(12 Months)
World Bank/ UNECA
Sub-Sahara Africa Transport
Programme; NMT Urban
Transport Studies, East
Africa Region
East Africa Region
World Bank/ UNECA
Urban Planning
& Civil
Engineering
Consultancy
Civil Engineering
Consultant
June
1995 ~
August 1995
(2.7 Months)
USAID
An Evaluation of Private
Community Development
Projects, Kenya
Rural Areas in Kenya
USAID/GoK
PEA
Research/Civil &
Reconstruction
Engineering Consultant
February
1995 ~ April
1995
(2.3 Months)
Ministry of Infrastructure/ The Port And
Harbour Research Institute,
Ministry Of Transport,
Japan
KOBENET (Reconstruction
Activities Due to the
Damage Caused To
Structures In Kobe, Japan
by the Great Kansai
Earthquake), Kobe, Japan
(KOBENET)
Kobe, Japan
Ministry of Infrastructure/
The Port And Harbour
Research Institute, Ministry
Of Transport, Japan
R&D,
Engineering
Consultancy,
Technical
Advisory
![Page 97: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/97.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Associate Researcher
June
1994 ~
March 1995
(9.6 Months)
Ariake Geotechnical
Research Group
Ground Improvement in
Ariake, Kyushuu for Rail
Road Construction, Japan
Kyushuu Prefecture, Japan
Ariake Geotechnical
Research Group
R&D
Associate Researcher
April
1993 ~
March 1995
(24 Months)
Taisei Corporation
The Kandagawa Flood
Control Project in Suginami,
Tokyo
Tokyo, Japan
Taisei Corporation
R&D
Associate Researcher
April
1992 ~
March 1995
(36 Months)
Obayashi Construction
Company
The OAP (Osaka Amenity
Park) Project For Skyscraper
Buildings & Amenity Parks
in Osaka
Osaka, Japan
Obayashi Construction
Company
R&D
Associate Researcher
June
1994 ~
March 1995
(36 Months)
Port and Harbor Research Institute, Ministry of Transport,
Japan.
Waterfront Development,
Reclamation And Ground
Settlement-Associated
Problems of The New Kansai
International Airport.,
Osaka, Japan
The Port And Harbour
Research Institute, Ministry
of Transport, Japan
R&D
![Page 98: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/98.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Project Manager/Chief
Consultant/Chief
Coordinator and
Construction Supervision
Advisor
July
1991 ~ July
1993
(25 Months)
Mpata International Inc., Tokyo
Construction of Mpata
Safari Club in Maasai Mara,
Kenya
Maasai Mara, Kenya
Mpata International Inc.,
Tokyo
BD, DD, DR,
R&D,
Contract
Administration,
Project
Management,
Engineering
Consultancy,
Technical
Advisory
Associate Researcher
May
1989 ~
March 1991
(22Months)
Trans-Tokyo Bay Highway Corp.,
Ministry of Construction
Construction of Man-made
Islands, Bridges, Shield
Tunnels etc., Japan
Tokyo Bay, Japan
Trans-Tokyo Bay Highway
Corp., Ministry of
Construction
R&D
Research Associate
April
1988 ~
March 1989
(12 Months)
Kansai Electric Power Company
in Japan
A research project on the
adoption of Fly Ash as a
useful foundation and land
reclamation Geomaterial
Kansai, Japan
Kansai Electric Power
Company in Japan
R&D
Research Associate
October
1987 ~
March 1989
(18 Months)
Yokohama City Development
Authority, Japan
Yokohama Minato Mirai 21st
Century Project (MM21)
Yokohama, Japan.
Yokohama City
Development Authority,
Japan
R&D
![Page 99: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/99.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Associate Construction
Supervisor/Trainee In
Civil & Structural
Engineering Design &
Construction Supervision
June
1987 ~
September
1987
(3.5 Months)
The Honshu-Shikoku Bridge
Authority, Ministry of Transport,
Japan
Multi-Bridge Projects Across
The Seto Sea Islands, Japan
Kojima (Honshuu) ~ Sakaide
(Shikoku)
The Honshu-Shikoku Bridge
Authority, Ministry of
Transport, Japan
R&D, CSV
Project Manager/Team
Leader/Chief Consulting
Engineer
August
1987 ~ July
1989
(24 Months)
Mpata International, Tokyo, Japan
Mpata Safari Club Access
Road
Maasai Mara, Kenya
Mpata International, Tokyo,
Japan
BD, DD,
Contract
Administration,
Project
Management,
Engineering
Consultancy,
Technical
Advisory
![Page 100: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/100.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Position(s)
Held/Designation Duration
Name of
Employing
Organization
Project Name and Location
(Client)
Types of
Services
Rendered
Notes*
GoK - Government of Kenya GoJ - Government of Japan
GoSS - Government of South Sudan GoE - Government of Ethiopia
GoFRN - Government of The Federal Republic of Nigeria GoT - Government of Tanzania
JICA - Japan International Cooperation Agency ADB - African Development Bank
JBIC - Japan Bank of International Cooperation WB - World Bank
MoRPW - Ministry of Roads & Public Works, Kenya MoFED - Ministry of Finance & Economic Dev.
MoT - Ministry of Transport, Kenya ERA - Ethiopian Roads Authority
IDI - Industrial Development Institute, Japan AACRA – Addis Ababa City Roads Authority
CPC - Construction Project Consultant Inc. UoN - University of Nairobi
CCMC - Createch Construction & Management Consultants JKUAT - Jomo Kenyatta University of Agriculture
& Technology
DR - Design Review MoLG - Ministry of Local Government
DD - Detail Design TAA - Tanzania Airports Authority
PFS - Preliminary Feasibility Study KAA - Kenya Airports Authority
TA - Technical Advisory AAU - Addis Ababa University
BD - Basic Design RECSSAD - Regional Centre for Social Studies
& Development
RISD - Research & Innovation for Sustainable SID - Sustainable Infrastructure Development
Development MTR&D - Materials Testing & Research Department
FS - Feasibility Study MoR - Ministry of Roads (Kenya)
PDS - Preliminary Design Study UOT - University of Tokyo
CSA - Case Study Analysis MoH - Ministry of Health
R&D - Research & Development CSV - Construction Supervision
PEA - Project Evaluation & Analysis SA - Structural Analysis
![Page 101: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/101.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
14. PROJECT PARTICULARS AND POSITION
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
![Page 102: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/102.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
August ‘87 ~July’89
(24 Months)
Project Name: Design and Construction of Mpata Safari Club Access
Road
Client: Mpata International, Tokyo, Japan
Location: Maasai Mara, Kenya
Brief Project Particulars/Description
Mpata Safari Club is perched on the hilltop with breathtaking views of the Masai Mara Reserve. Its adventageous location and well designed programs offer guests a chance to experience the environmental beauty. The Clubs unique design is the brainchild of Edward Suzuki - a leading architect in Japan. Guests stay in individual cottages well spaced along the top of the escarpment offering paranomic views. There are 11 suites and 12 deluxe units in Mpata Safari Club, each with seperate bedroom, bathroom and verandah. With emphasis on comfort and a unique combination of interior design, the suites have a lounge, kitchenette but the best of all is an outdoor Jacuzzi with spectacular and breathtaking views of the Masai Marai Game Reserve. The Club has a Sunken Rock Bar that offers sensational views of the Mara River and the Sundowner Bar that is well located to enhance the view of the rising and setting sun. The project involved the Basic and detailed design and construction of
an approximately 10km long of the Mpata Safari Club Access Road
through very challenging terrain and acute gradients. As a consequence,
careful consideration had to be made, during the design studies, for the
cut and fill earth works, whilst ensuring minimal environmental
disturbance particularly due to the fact that the Club is located in one
of the most important conservation areas in this region.
Prior to, and during the implementation of the Project, serious
attention was made and care taken to ensure that the environmental
stipulations and requirements were upheld by undertaking periodically
consistent Environmental Impact Assessment and monitoring
programmes accordingly.
Position: Project Manager/Team Leader/Chief Consulting Engineer
The main tasks involved contract administration, Construction and
maintenance of Civil Works for civil and other works for the Mpata Club.
![Page 103: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/103.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June’87 ~ Sept.’87
(3.5 Months)
: Project Name: Bridge Projects Across The Seto Sea Islands, Japan
Client: The Honshu-Shikoku Bridge Authority, Government of Japan
Location: Kojima (Honshuu) ~ Sakaide (Shikoku), Japan
Brief Project Particulars/Description
Seto Great Bridge, Japanese Seto Ōhashi, is a series of suspension
bridges spanning the Inland Sea (Seto-naikai) between the islands of
Honshu and Shikoku, Japan. The double-tiered rail and vehicular
roadway is a network of six bridges, straddling a chain of five small
islands, and extends 5.6 miles (9 km) over water to link the towns of
Kojima, on Honshu, and Sakaide, on Shikoku. Its total length is 7.6 miles
(12.2 km), and it consists of three main suspensions—the longest being
the central span of Minami Bisan–Seto Bridge, at 3,667 feet (1,118 m).
The Seto Great Bridge took 10 years to build and was opened on April
10, 1988.
The Seto islands multi-billion dollar bridge project involved the long-
term rigorous research, study, design and massive construction of the
various types of bridges including suspension and cable stay over the
entire breath of sea connecting the main Honshu and the Shikoku islands
in the southern part of Japan.
Position: Associate Construction Supervisor/Trainee In Civil &
Structural Engineering Design & Construction Supervision
As a BSc. Student in the Department of Civil and Marine Engineering, Dr.
Mukabi undertook intensive training in Contract Administration and
Project Management in Civil Engineering Practice including planning,
design and construction implementation of mega projects.
The training also covered such technical aspects as:
Advances in Land Reclaimation Technologies
Deep Foundation Piling for Offshore Structures
Caisson Foundation Design and Construction
Geotechnical Engineering Design and Construction for Bridge
Foundations
Advances in the Application of the New Austrian Tunnelling
Method (This was applied for the construction of the Washuzan
Tunnel, an approach to the Seto Great Bridge from Honshuu).
![Page 104: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/104.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct ’87 ~ Mar ‘89
(18 Months)
: Project Name: Yokohama Minato Mirai 21st Century Project (MM21)
Futuristic Intelligent City.
Client: Yokohama City Development Authority, Japan
Location: Yokohama, Japan
Brief Project Particulars/Description
When Japan emerged from centuries of isolation in the mid-19th
century, Yokohama was a tiny seaside village, home to only 100 people
or so. But as the tide of internationalization rose, a port was established
and Yokohama began to grow as a gateway to Japan. Yokohama is now a
leading international trading port, the second largest city in Japan after
Tokyo. Situated just a short distance along the coast from the Japanese
capital, and within easy reach of Haneda Airport, Yokohama is now a
magnet for tourists not just from Japan but from every corner of the
world; it's a place everyone wants to visit.
The name "Minato Mirai 21" was one of many proposals submitted by
members of the public in response to an appeal. "Minato" means "port"
and "mirai" means "future." "Port Future 21" thus embodies the dream
that Yokohama will enjoy a bright future in the 21st century.
Minato Mirai 21 (MM21), first conceived as an Idea almost 3 decades
ago, was Yokohama's vision of the future. It was practically realized in
1997 once, only dockyards, the city is turning this harbour front area
into a world class business / recreation complex with one of the most
advanced information infrastructure. The main crown is the Landmark
Tower - at 296m, the tallest building in East Asia. It was meant to be
higher, but flight restrictions at the Haneda airport prevented it. It
boasts the latest in computerized anti-earthquake and anti-motion
equipment and the fastest elevator in the world ascending at a speed of
45km/hr (12.5m/s).
Intended to be a cultural cosmopolitan and information city of the 21st
Century with superior environment, the Intelligent City is a
manifestation of the success of Public and Private Sector joint
partnership.
![Page 105: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/105.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Oct ’87 ~ Mar ‘89
(18 Months)
Minato Mirai 21 is a modern urban development that was created, and
continues to evolve, on 186ha of land. A shipbuilding facility that used
to divide Yokohama's two main urban centers on Tokyo Bay was
relocated, and additional land was reclaimed from the sea. In 1989 an
exposition was held to mark the 100th anniversary of Yokohama's city
status and the 130th anniversary of the opening of Yokohama Port.
Following that event development gathered momentum, and now the
area boasts office blocks, commercial facilities, hotels, amusement
parks and convention facilities, as well as such cultural amenities as art
museums and concert halls. This, the new face of Yokohama, offers an
entire spectrum of urban functions and attracts more than 50 million
visitors every year.
Position: Research Associate
Dr. Mukabi participated in various Study Groups and Technical
Committees in charge of urban planning and design, home and office
automation, integrated communications systems and network, urban
transport planning, study and design as well as the study on the
performance of the reclaimed land and/or foundation bearing ground
under various loading conditions.
![Page 106: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/106.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Apr ’88 ~ Mar ‘89
(12 Months)
: Project Name: A Research Project on the Adoption of Fly Ash as a
Useful Foundation and Land Reclamation
Geomaterial.
Client: Kansai Electric Power Company, Japan
Location: Nationwide, Japan
Brief Project Particulars/Description
Fly ash has been used successfully in many projects to improve the strength characteristics of soils. Fly ash can be used to stabilize bases or subgrades, to stabilize backfill to reduce lateral earth pressures and to stabilize embankments to improve slope stability. Typical stabilized soil depths are 15 to 46 centimeters (6 to 18 inches). The primary reason fly ash is used in soil stabilization applications is to improve the compressive and shearing strength of soils. The compressive strength of fly ash treated soils is dependent on:
In-place soil properties
Delay time
Moisture content at time of compaction
Fly ash addition ratio Soil stabilization is the alteration of soil properties to improve the engineering performance of soils. The properties most often altered are density, water content, plasticity and strength. Modification of soil properties is the temporary enhancement of subgrade stability to expedite construction. Class C fly ash and Class F-lime product blends can be used in numerous geotechnical applications common with highway construction:
To enhance strength properties
Stabilize embankments
To control shrink swell properties of expansive soils
Drying agent to reduce soil moisture contents to permit compaction
Class C fly ash can be used as a stand-alone material because of its self-cementitious properties. Class F fly ash can be used in soil stabilization applications with the addition of a cementitious agent (lime, lime kiln dust, CKD, and cement). The self-cementitious behavior of fly ashes is determined by ASTM D 5239. This test provides a standard method for determining the compressive strength of cubes made with fly ash and water (water/fly ash weight ratio is 0.35), tested at seven days with standard moist curing. The self-cementitious characteristics are ranked as shown below:
![Page 107: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/107.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Apr ’88 ~ Mar ‘89
(12 Months)
Very self-cementing > 500 psi (3,400 kPa)
Moderately self-cementing 100 - 500 psi (700 - 3,400 kPa)
Non self-cementing < 100 psi (700 kPa)
In order to study into the possibility of adopting fly ash generated as a
by-product from geothermal power stations, as a cementatious
geomaterial for land reclamation and other geotechnical engineering
purposes by taking advantage of its pozzolanic reaction and nature, Dr.
Mukabi, through the Geotechnical Research Institute of the Yokohama
National University, was commissioned to carry out research for the
Research Institute of the Kansai Electric Company.
One of the basic objectives was to convert this environmentally
hazardous bi-product that is usually produced in bulk into a useful
construction material for Civil Engineering purposes. The shortcoming
however, had been developing a most cost-effective and
environmentally friendly mode of transporting this material to the
respective sites.
During the course of this Study, a method was designed to transform it
into slurry by applying admixtures (surface-active agents, surfactants)
and transporting it to site through high-pressurized piped pumping.
Nevertheless, this method was found to reduce the intrinsic strength
and affect other vital engineering properties of the material such as the
angle of internal friction. An intensive Study based on laboratory and
field testing was therefore set out to investigate, among other
engineering parameters and influencing factors, the effect of mode of
curing and period on the strength and deformation resistance
development.
Position: Research Associate
The tasks for Dr. Mukabi were to undertake research on the method of
enhancing the engineering properties of fly ash through the application
of admixtures and unique consolidation methods and propose optimum
methods of transporting the material to site and applying it practically
for purposes of land reclamation and construction of other geo-
structures.
![Page 108: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/108.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May’89 ~ Mar’91
(22 Months)
: Project Name: Construction of Man-made Islands, Bridges, Shield Tunnels etc., Japan
Client: Trans-Tokyo Bay Highway Corp., Ministry of Construction
Location: Tokyo Bay/Kawasaki/Chiba, Japan
Brief Project Particulars/Description
The Ministry of Construction started a feasibility survey in terms of economics and civil engineering technology in 1966. Several technical committees were organised August 1975. In August 1976, the Japan Highway Public Corporation took over the survey work. In May 1983, the Cabinet of the Japanese Government approved the construction of the highway. The Trans-Tokyo Bay Highway Corporation was established in October 1986. The actual construction started in May 1989. The ground improvement work by the sand compaction pile method and the deep mixing method (a sort of in-situ cement-mixing) started in August 1989 at several places along the route (i.e., the Ukishima Access and the Kawasaki and Kisarazu man-made islands). The construction of the foundations for the bridge started in October 1989. The construction was completed in December 1997 and the highway was opened to public on 18th December 1997. The Trans Tokyo Bay Highway, connecting Kawasaki City in Kanagawa Prefecture and Chiba City in Chiba Prefecture, Japan and traversing across the Central part of the Tokyo Bay Loop Road Network, was a project involving the construction of a 15.1 km highway initiated by the Trans-Tokyo Bay Highway Corporation under the Ministry of Construction, Japan. The main features included bridges, under sea shield tunnels, and man-made islands. The samples of the Tokyo Bay Clay, which is a relatively stiff clay of the Pleistocene Era were obtained from various locations of the constructions site at depths of between on 50 m below a 21.15 m deep sea bed.
The construction of the Trans-Tokyo Bay Highway became technically feasible only by employing several new construction techniques related to geotechnical engineering, including: 1) large scale improvement of existing soft clay deposits by in-situ cement-mixing, controlling the strength; 2) construction of large offshore embankments using a slurry of cement-mixed sand and a dry cement-mixed sand; 3) construction of shield tunnels with the world’s largest diameter in successive stiff cement-mixed soil and very soft clay at a very shallow depth and their underground connection with the help of the ground freezing technique; and
![Page 109: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/109.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
May’89 ~ Mar’91
(22 Months)
4) construction of a huge offshore diaphragm wall with the world’s largest dimensions of 98 m in internal diameter and 119 m in height with the bottom end at a depth of TP-114 m (i.e., a depth below the average sea level). The most difficult issue with respect to the structural form of the highway was how to safeguard extremely heavy shipping routes during construction and after completion. The shipping flow over the planned route of the highway that was measured inOctober 1990 was 1,400 vessels per day. Ninety percent of this traffic passes in the region of water between the Ukishima Access and the Kisarazu man-made island. The proposal that was investigated most seriously among those that were proposed at early stages of investigation. This plan was finally replaced by the final structural form. In this previous proposal, the highway comprised submerged tunnels (i.e., immersed tube tunnels) at the central part, two bridges on both sides and two embankment-type man-made islands between them. In 1985, this structural form was finally replaced for the following reasons (Uchida et al., 1993):
1) a bridge solution could not satisfy the required width of shipping route and cannot ensure the safety of the completed bridges; 2) a structure comprising submerged tunnels and bridges required the occupation of a large area of water for a long period during construction; and 3) it was technically difficult to keep to an acceptable level and to accurately predict the settlement of the embankment type Kawasaki man-made island, which was to be constructed on a very thick soft clay deposit, although the deposit was to be improved by a relevant method. The present structural form, comprising the Ukishima Access, the Kawasaki island, which is a steel and RC structure, and the Kisarazu man-made island, which is basically an embankment, and shield tunnels between them, was adopted for the following reasons (Uchida et al., 1993): 1) construction of such large-diameter shield tunnels with a long tunnel drive became technically feasible (n.b., the diameter of constructed shield tunnels had reached 11.2 m); 2) construction of such a large scale diaphragm wall as the main structure of the Kawasaki man-made island became technically feasible, after similar large diaphragm walls had been constructed along the sea shore of the Tokyo Bay;
![Page 110: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/110.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
May’89 ~ Mar’91
(22 Months)
3) the present structural form has several advantages over the previous plan, in particular in that shield tunnels do not occupy the sea surface both during construction and after completion, while the excavation of seabed, which is necessary for the construction of submerged tunnels and is not environmentally favourable, becomes unnecessary; and 4) it is feasible that two tunnels (n.b., the planned final number of tunnels is three) are first constructed, while the other is constructed in the future when it becomes necessary. This type of staged construction is not feasible with submerged tunnels. Four types of ground improvement techniques by cement-treatment were used. Among those investigated, three techniques were newly developed for the project. The total amount of cement-treated soils reached about 3.77 million m3. All of the ground treatment work was finished in February 1994. The deformation and strength properties of the cement-treated soils have been reported in detail by Tatsuoka et al. (1997). Before finally deciding to adopt the ground improvement techniques by in-situ cement-mixing and constructing fill embankments using cement-mixed soil, it was necessary to modify the conventional design method for cement-mixed soil, adapted to the large scale of the structures in this project, as described below. Position: Associate Researcher/Junior Construction Supervision Associate/Junior Associate Geotechnical Engineering Consultant As one of the Researchers, Construction Supervision Advisor and Consultant in Geotechnical Engineering, Dr. Mukabi was entrusted the responsibility of undertaking research that would determine not only the appropriate and suitable design parameters for various foundations but also to propose a method of enhancing the deformation resistance of the clay by developing unique testing procedures as well as proposing the most optimum soil improvement and construction techniques that would ensure the achievement of the quality required during construction.
![Page 111: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/111.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jul’91 ~ Jul’93
(25 Months)
: Project Name: Construction of Mpata Safari Club in Maasai Mara, Kenya
Client: Mpata International Inc., Tokyo
Location: Maasai Mara, Kenya
Brief Project Particulars/Description
A group of Japanese investors decided to develop a high class resort in Maasai Mara in Kenya and Serengeti in Tanzania. The Project involved undertaking feasibility studies, Basic Design, Detailed Design and Construction Supervision on the part of the Consultants who were a Consortium of Japanese, British Kenyans and Germans. Mpata Safari Club is perched on the hilltop with breathtaking views of the Masai Mara Reserve. Its adventageous location and well designed programs offer guests a chance to experience the environmental beauty. The Clubs unique design is the brainchild of Edward Suzuki - a leading architect in Japan. Guests stay in individual cottages well spaced along the top of the escarpment offering paranomic views. There are 11 suites and 12 deluxe units in Mpata Safari Club, each with seperate bedroom, bathroom and verandah. With emphasis on comfort and a unique combination of interior design, the suites have a lounge, kitchenette but the best of all is an outdoor Jacuzzi with spectacular and breathtaking views of the Masai Marai Game Reserve. The Club has a Sunken Rock Bar that offers sensational views of the Mara River and the Sundowner Bar that is well located to enhance the view of the rising and setting sun. The design and construction of Mpata Safari Club was to cater for all the facilities including staff residence, access roads and necessary infrastructure such as water supply and reticulation, power generation and such other amenities as a full football pitch, basketball court etc.Prior to, and during the implementation of the Project, serious attention was made and care taken to ensure that the environmental stipulations and requirements were upheld by undertaking periodically consistent Environmental Impact Assessment and monitoring programmes accordingly.
Position: Project Manager/Chief Consultant/Chief Coordinator and
Construction Supervision Advisor
During this undertaking, Dr. Mukabi was appointed the Chief Consultant, Coordinator and Construction Supervision Adviser charged with the responsibility of leading, advising and directing the Consortium of Consultants as well as contractors.
![Page 112: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/112.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jun’91 ~ Jun ‘94
(36 Months)
: Project Name: Waterfront Development, Reclamation And Ground Settlement-Associated Problems of The New Kansai International Airport.
Client: The Port And Harbour Research Institute, Ministry Of Transport
Location: Kansai, Japan
Brief Project Particulars/Description
The Kansai International Airport, which is located in Osaka Bay, 35km south of the centre of Osaka, Japan, opened in September 1994. Over 15 million passengers used the airport in the year 2008. Aircraft movements in the same year were 129,263. The port and Harbour Research Institute of the Ministry of Transport, Japan requested for a joint research with the Institute of Industrial Science of the University of Tokyo, to characterize as precisely as possible, the ground settlement at the site of the New Kansai International Airport as a result of reclamation activities. The Osaka Bay Clay adopted from experimental testing and research was sampled from depths of 98 –210 m below the seabed. A detailed and comprehensive Research Regime was designed for undertaking both field and laboratory testing applying State of the Art hi-tech automated tesing equipment with high resolution and precision levels and the versatile capability of measuring a variety of geaotechnical engineering parameters. Some of the main objectives that were for the research were to determine the effective countermeasures of simulating, modelling and controlling the settlement and developing geotechnical engineering technologies that would foster advanced Value Engineering. The Research Programme referred herein was mainly implemented between 1989 and 1994. The stratigraphy of the Osaka Bay is rather complex. It fromed the integral part of the subsurface investigation to evaluate the geological formation, design and undertake in-situ experimental testing for purposes of determining geotechnical engineering parameters for prediction and monitoring of the settlement of the 4km long man-made island filled with approximately 180,000,000m3 of rock mixed soil used for founding the Kansai International Airport as well as foundation design for the terminal buildings and runways pavement structures. KIA has already gained an important position as an international air traffic hub. In order to retain and further enhance its importance at a time when other large new airports are being built and opened throughout Asia, it is considered vital to proceed with the development.
![Page 113: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/113.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Jun’91 ~ Jun ‘94
(36 Months)
It is hoped the expansion will also increase economic and social activities and play a positive factor in improving the economy of Osaka and the greater Kansai region.
The Government of Japan estimates the total economic value produced by the second phase development of the project to be approximately $94.6bn and 190,000 new jobs nationwide, of which $85bn and 150,000 jobs will go to the Kinki region
The second phase includes the construction of a second main terminal building, located close to the first terminal building. The passenger area in the airport is planned to be wing shaped to accommodate future expansions. Cargo facilities are planned to be located south of the island, with sufficient space planned for aircraft parking apron along with a cargo warehouse at its side The airport previously operated on a single 3,500m runway and was capable of handling up to 160,000 departures and arrivals per year. With the addition of a second runway, this number is expected to rise to up to 230,000 departures and arrivals by 2011. The second runway was completed and opened on 2 August 2007, but the construction of the terminal was postponed. With the addition of a second 4,000m long runway, the airport is expected to handle up to 230,000 departures and arrivals by 2011.
Airport expansion project timescale
The seawall foundation improvement work started in 1999. Construction of the runway was started in 2003 and was ready for use in August 2007.
Land reclamation
The development will produce an additional 542ha of land projecting offshore from the current airport island. The new land will be the site for construction of a new 4,000m runway, a cargo complex and a supply management facility. The landfill is estimated to require 270 million cubic metres of earth, rock and sand.
This phase of construction is more difficult than the first as the work involves building over deeper water with softer ocean ground. Below the seabed lies a layer of moist, soft clay over 20m thick. Firstly, the water must be removed to strengthen the clay. Sea walls surrounding the island must be built to protect the airport island from the oceanic currents. When the sea walls are near completion, large vessels drop soil on the seabed.
![Page 114: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/114.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Jun’91 ~ Jun ‘94
(36 Months)
Seabed improvement
The method used for seabed improvement is the sand drain method. Prior to reclamation work, a number of sand piles are driven into the soft seabed clay. The weight of the soil used for reclamation causes the water in the clay beneath to move outward along the sand piles. The clay gradually becomes solidified in this way.
To measure precisely the subsidence, subsidence speed, subsidence behaviour and strength of the island's foundation, a large-scale measurement tower (33.5m in height from its foundation to its tower deck and 22m in deck area) was installed near the north end of the reclaimed land to be used for the project.
The tower will be used as a base for measuring the deformation of the seabed.
Eight large sand drain barges for deep-sea operations were used for the seabed improvement work. All the seabed improvement work was completed after the last sand drain barge departed from the construction area.
Position: Associate Researcher Dr. Mukabi developed various hi-tech testing techniques and procedures during this study that were effective in precisely determining the elastic and shear moduli, effect of reconsolidation procedure in relation to settlement, effects of rates of constructing overlaying reclamation layers, cyclic prestraining among others, whilst offering invaluable advise on the suitable techniques to be applied during the construction supervision stage.
![Page 115: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/115.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Apr’92 ~ Mar’95
(36 Months)
: Project Name: The OAP (Osaka Amenity Park) Project For Skyscraper
Buildings & Amenity Parks in Osaka, Japan
Client: Obayashi Construction Company, japan
Location: Osaka, Japan
Brief Project Particulars/Description
OAP stands for Osaka Amenity Park, a project that involved the
construction of high rise buildings and amenity facilities between Okawa
and Tanimachi in Osaka city. The project consisted of constructing a
176.25 m tall skyscraper office block, a 117.25 m tall hotel block both
founded on piles, several 30 floor residential blocks, hotel annexes,
parks and other socio-welfare amenities.
The Osaka Metropolitan Government, OAP Developers and the Implementation Consortium proposed a joint research with the Institute of Industrial Science of the University of Tokyo, to characterize as precisely as possible, the ground and in-situ material characteristics at the site for purposes of pile and pad foundation design and construction. The OAP geomaterial adopted for experimental testing and research was sampled from depths of 49 –80 m below the GL. A detailed and comprehensive Research Regime was designed for undertaking both field and laboratory testing applying State of the Art hi-tech automated tesing equipment with high resolution and precision levels and the versatile capability of measuring a variety of geaotechnical engineering parameters. Some of the main objectives that were for the research were to determine the effective countermeasures of simulating, modelling and controlling the settlement and developing geotechnical engineering technologies that would foster advanced Value Engineering. The Research Programme referred herein was mainly implemented between 1990 and 1995. Position: Associate Researcher
Dr. Mukabi was assigned to undertake comprehensive research to
determine suitable geotechnical parameters for foundation design,
characterize the geotechnical aspects for ground and foundation
simulation during construction and in the post-construction stage in case
of the prevalence of typhoons, wind effect, earthquakes etc and to
propose suitable countermeasures for deformation resistance as well as
offer advice for the proper methods for construction supervision.
![Page 116: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/116.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Apr’93 ~ Mar’95
(24 Months)
: Project Name: The Kandagawa Flood Control Project in Tokyo
Client: Taisei Corporation, Japan
Location: Kandagawa, Tokyo, Japan
Brief Project Particulars/Description
In the last decade, there have been many destructive floods in various parts of the world. Despite the extensive investment in flood control works, neither flood occurrences nor damages are decreasing. A possible consequence of climate change is an increased frequency of extreme meteorological events that may cause floods. The section of the Kandagawa River that flows through the Suginami Ward of Tokyo had become notorious for major floods disasters precipitated mainly by the overflooding of the River. As a civil engineering countermeasure and environmental mitigation measure, the Kandagawa Flood Control Project was initiated whereby a deep shaft with an internal diameter of 28.2m with a subsurface regulating reservoir was designed and constructed in Kandagawa within the vicinity of Kannana Highway, a Temple, Business Distric as well as residential and amenity areas. The shaft and reservoir were constructed within the Suginami Clay, which is a very stiff heavily overconsolidated Pleistocene clay. The samples for laboratory testing were obtaining by block sampling carved by hand from depths of between 29 ~ 60m below the ground surface. Most of the specimens were prepared from Geomaterial that had been sampled from the hole that had been prepared to take the shaft. A detailed and comprehensive Research Regime was designed for undertaking both field and laboratory testing applying State of the Art hi-tech automated tesing equipment with high resolution and precision levels and the versatile capability of measuring a variety of geaotechnical engineering parameters.
Position: Associate Researcher Due to the complications that may have prevailed in the geotechnical characteristic as a result of the flooding, Dr. Mukabi was assigned to study these effects under varying conditions. The research concerned mainly the experimental Study of the surrounding Suganami clay which was very stiff and heavily over consolidated Pleistocene in nature. The drained and undrained behaviour of the Suginami clay under intense static and dynamic cyclic loading was therefore studied. He was also assigned to assist in the supervision and ensure that the newly developed hi-tech civil engineering methods were effectively applied during the construction.
![Page 117: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/117.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June’ 94 ~ Mar ’95
(9.6 Months)
: Project Name: Ground Improvement in Ariake, Kyushu for Rail Road
Construction
Client: Ariake Geotechnical Research Group, Japan
Location: Kyushuu Prefecture, Japan
Brief Project Particulars/Description
Ariake is a region located in Kyushuu Prefecture, which is one of the
Islands in the Southern part of Japan.
The Ariake Clay is a very soft, sensitive and highly structured clay
underlying most of the Ariake area. Various physical and chemical
properties of this clay, including the plasticity index, unit weight,
specific density, voids ratio, natural water content etc, had been
investigated by Ariake Research Group since 1965. The soil profiles
depicted in the borelogging indicated that the overburden stress
increase virtually uniformly with depth derivatively implying that stress-
strain-time controlled consolidation techniques could also enhance the
vital geotechnical engineering properties. The project involved
undertaking research that would establish and develop ground
improvement methods that would realize higher strength, deformation
resistance and enhanced engineering properties so that the ground
would act as a foundation for railway construction.
A detailed and comprehensive Research Regime was designed for undertaking both field and laboratory testing applying State of the Art hi-tech automated tesing equipment with high resolution and precision levels and the versatile capability of measuring a variety of geaotechnical engineering parameters. Some of the main objectives that were for the research were to determine the effective countermeasures of simulating, modelling and controlling the settlement and developing geotechnical engineering technologies that would foster advanced Value Engineering. The Research Programme referred herein was mainly implemented between 1990 and 1995. Position: Associate Researcher
As one of the Associate Researchers of the Ariake Bay Research Group,
Dr. Mukabi undertook research related to the applications of
reconsolidation procedures in improving the ground foundation and also
partaking in the supervision of the construction.
![Page 118: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/118.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Feb ‘95 ~ Apr‘95
(2.3 Months)
: Project Name: KOBENET – Technical Committee on the
Reconstruction Strategy Due to the Damage
Caused To Structures In Kobe by the Great
Hanshin Earthquake
Client: Ministry of Construction, Government of Japan
Location: Kobe, Japan
Brief Project Particulars/Description
The Great Hanshin Earthquake or Kobe Earthquake which struck
Tuesday, January 17, 1995, at 05:46 JSTcaused death, injury and
colossal damage of most the civil engineering and architectural
structures in Kobe, Japan
It occurred in the southern part of Hyōgo Prefecture, Japan. It measured 6.8 on the moment magnitude scale (USGS) and Mj7.3 (adjusted from 7.2) on JMA magnitude scale. The tremors lasted for approximately 20 seconds. The focus of the earthquake was located 16 km beneath its epicenter, on the northern end of Awaji Island, 20 km away from the city of Kobe. Approximately 6,434 people lost their lives (final estimate as of December 22, 2005); about 4,600 of them were from Kobe. Among major cities, Kobe, with its population of 1.5 million, was the closest to the epicenter and hit by the strongest tremors. This was Japan's worst earthquake in the 20th century after the Great Kantō earthquake which occurred in 1923 claiming 140,000 lives. It caused approximately ten trillion yen ($100 billion) in damage, an amount that translates to 2.5% of Japan's GDP at the time
As a consequence, It was necessary to promptly establish various
technical committees that would undertake the design and
implementation of emergency mitigation measures and propose the
fastest methods of reconstruction since the city had practically been
almost totally destroyed.
Position: Research/Civil & Reconstruction Engineering Consultant
Dr. Mukabi was one of the Civil Engineering Consultants appointed on
the technical committee of the University of Tokyo to particularly
evaluate the post-destruction geotechnical and foundation conditions of
various structures including highways, bridges and skyscraper buildings
and supervise some of the emergency civil engineering works.
![Page 119: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/119.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June ’95 ~ Aug ‘95
(2.7 Months)
: Project Name: An Evaluation of Private Community Development
Projects in Kenya
Client: USAID
Location: Rural Areas in Kenya
Brief Project Particulars/Description
Sponsored by USAID, the study involved mainly the evaluation of the
socio-economic benefits of private community development projects in
Kenya and their contribution to poverty reduction.
Position: Civil Engineering Consultant
Dr. Mukabi’s role was mainly to advice on the technical aspects of such
projects, their feasibility and/or limitations accordingly.
July ’95 ~ June ‘96
(12 Months)
: Project Name: Sub-Sahara Africa Transport Programme; NMT Urban
Transport Studies, East Africa Region
Client: World Bank/ UNECA
Location: East Africa Region
Brief Project Particulars/Description
The studies involved the accurate determination of the existing traffic
conditions and proposal of future forecasts for purposes of designing
proper and suitable, and appropriate transport systems in sub-sahara
Africa.
Position: Urban Planning & Civil Engineering Consultant
Dr. Mukabi’s assignment was mainly to coordinate the urban transport
planning experts and evaluate and advise on the result of the studies.
![Page 120: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/120.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Aug ’96 ~ Nov ‘97
(15 Months)
: Project Name: Rehabilitation of Health Facilities in Western Kenya
Client: African Development Bank (ADB)/Government of Kenya
Location: Western Region of Kenya
Brief Project Particulars/Description
Kenya’s Nyanza and Western Provinces are densely populated. Both
Provinces have abundant fish and agricultural resources. The poor state
of health facilities however, have been one of the major obstacles to
socio-economic development hence the low standards of living in these
region. The region has a population of Approximately four million
people.
Fish and tea related industries are the most dominant in these areas
whereby the region’s fish products account for more than 95% of the
country’s total.
In 1995, upon the request of the Government of Kenya, the African
Development Bank, through the Ministry of Health, funded a study to
establish the appropriate design and methods of construction of all the
major health facilities in Western Kenya, which were in a decrepit
state.
The Study area covered the following parts in Western and Nyanza
Provinces (States) in the Western Region of Kenya.
All districts in Nyanza province with concentration in Kisii
District
All districts in Western province with concentration in
Kakamega District
Lake shore areas
Position: Deputy Team Leader/Sr. Geotechnical/Civil & Structural Engineer
As the Chief Civil and Structural Engineering Consultant Dr. Mukabi was
the Team Leader of the Civil and Structural Engineers entrusted with
the assignment of establishing the mode, rate and level of structural
deterioration, existing structural capacity, strength factors and
determining the appropriate countermeasures and effective methods of
rehabilitation.
![Page 121: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/121.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan. ’97 ~ July ‘97
(6.2 Months)
: Project Name: Urban Traffic Control & Planning for Major Cities in
Kenya
Client: The World Bank/Ministry of Transport
Location: Urban Areas, Kenya
Brief Project Particulars/Description
The present supply to transport is inadequate to meet the increase in
traffic demand in urban areas and major cities and in particular, the
Nairobi Metropolitan Area. Concentration of the Study was on Nairobi,
Mombasa, Kisumu, Nakuru and Nyeri.
The urgency and necessity for the development of road facilities and
traffic management measures are factors that are well appreciated by
the Government of Kenya.
With the objective of improving the traffic flow, alleviate traffic
congestion and improve the overall traffic characteristics, The World
Bank funded a Study for urban traffic control and planning for the major
cities in Kenya.
The Project involved formulation of a Master Plan for strategic
transportation system and conducting of feasibility studies and
recommending solution for selected priority projects with respect to
future transport demand. Traffic parameters of average speed and
congestion on the road networks, both within the urban centres and
peripheral areas were used to assess the road network and traffic flow
efficiency.
Preliminary Traffic Flow Improvement Plans for zones within the Central
Business Districts (CBDs) of Nairobi, Mombasa, Kisumu, Nakuru and Nyeri
were proposed mainly in consideration of: i) improvement of traffic flow
and circulation in the CBD; ii) improvement of traffic flow on major
arterials; iii) improvement of traffic flow in special commercial areas;
and, iv) improvement of parking systems in CBDs.
Position: Deputy Team Leader/ Urban Planning & Civil Engineering
Consultant
Dr. Mukabi’s task was to establish and advice on a sound technical
approach to the study vis a vis the prevailing conditions and problems in
fast growing cities in developing countries.
![Page 122: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/122.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Mar ’98 ~ June ‘98
(3.5 Months)
: Project Name: Low & Medium Cost Housing Development Projects
in Urban & Rural Areas With Particular Reference
to Material Science and Construction Techniques
Development
Client: African Development Bank (ADB)/Ministry of Public Works &
Housing, Government of Kenya
Location: Nationwide, Kenya
Brief Project Particulars/Description
The fact that housing has central importance to every human being’s
quality of life and health consolidated with considerable economic,
social, cultural and personal significance.
Despite the foregoing, the global trend seems to indicate an exponential
increase in slums or informal settlements as a result of population
explosion and dynamic rural-urban migration. Despite the fact that
considerable improvements and achievements have been made in
solving this problems in some countries, developing countries continue
to be the focus of increased slum developments.
The design of dwellings and neighbourhoods reflects and protects
important elements of values and culture. Further, the important role
of housing production in employment generation, particularly for
unskilled labour, cannot be overemphasized.
To ensure the initiation of effective programmes and decisive actions in
this regard, the Millennium Declaration of the UN-HABITAT endorsed the
“Cities Without Slums” goal of “improving the lives of at least 100
Million Slum Dwellers by the Year 2020”.
In this regard and With the increase demand of low to medium cost
housing, the ADB funded a Study to determine the feasibility of the
design and implementation of the findings from such studies with
particular reference to material science and construction techniques.
Position: Team Leader/Chief Consulting & Research Engineer
Dr. Mukabi was assigned to design the testing techniques, experimental
regime and the overall research methodology and programme aimed at
developing material science concepts and Value Engineering
technologies that can be applicable in the building construction industry
to facilitate for affordable housing as an integral component of poverty
eradication.
![Page 123: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/123.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Mar ’98 ~ April '02
(49 Months)
: Project Name: Detailed Design and Construction Supervision of the
Malindi ~ Garissa Trunk Road under the Tana Basin
Development Project
Client: Japan Bank of International Cooperation/Office of The
President
Location: Malindi ~ Garissa, Kenya
Brief Project Particulars/Description
In order to promote rapid socio-economic development and integration
to other regions, the Government of Kenya, within the scope of the
1997 ~ 2001 National Development Plan Policy that was set out to
achieve “Rapid Industrialization for Sustainable Development”, aimed at
completing the construction of the 327km Malindi ~ Garissa Trunk Road.
In 1992, the Government of Kenya initiated construction of 129km of
the road protion designated as Section A from Garissa to Hola through
the direct labour method by the National Youth Service (NYS).
In 1995, the Government of Kenya obtained loan No. KE-P16 from the
Government of Japan which was primarily to construct Sections A
(Garissa ~ Hola – 129km), Section B (Hola ~ Garsen – 94km) and Section
C (Garsen ~ Malindi – 104km). Part of the loadn was utilized to procure
machinery for Section A which was under NYS, whilst Sections B and C
were contracted, on 8th September 1995, to China Road & Bridge
Construction which was supervised by Construction Projects
Consultants, Japan.
The Tana Basin Development Project comprised of the rehabilitation
and construction of the Tana Basin Road Project connecting Malindi to
Garissa traversing 330 km and the construction of the Tana Basin
Irrigation Scheme. Both projects were undertaken under the funding by
Japan Bank of International Cooperation (JIBIC).
Position: Deputy Project Manager/Team Leader/Research
Consultant/Pavement & Geotechnical Engineer
Dr. Mukabi was appointed the Chief Technical Advisor and Deputy to the
General/Project Manager and was in charge of advising on technical
matters including study, research, design and construction supervision
of the Tana Basin Road Project.
![Page 124: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/124.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘98 ~ October, ‘98
(7.9 Months)
Project Name: CON-AID Research and Development Proposal
Client: CON-AID Pty, South Africa/Mitsui Corporation, South Africa/ Mitsui Corporation, Kenya
Location: Garsen ~ Hola, Kenya
Brief Project Background/Particulars/Description
CON-AID is fundamentally described as a chemical stabilizing agent
applied mainly for road construction. It is said to be totally dispersible
in water, non-flamable, non-hazardous, non-toxic and environmentally
friendly.
CON-AID is considered to be a surface agent which takes advantage of
the ION-exchange capacity of clay minerals to change a geomaterials
characteristics from the hydrophilic (water absorption) nature to a
hydrophobic (total water repellent). As clayey geomaterials consist of
many layers with a variety of loosely associated ions which attract
water molecules to enhance hydrophylicity (absorption) of clays, CON-
AID is said to be able to get rid of the adsorbed water leading to the
achievement of better compaction and permanent stabilization with
minimum mechanical effort through the direct contact of particles.
Capillaries existing in the compacted material also have their inner
walls coated with hydrophobic layers of CON-AID which is said to allow
free movement of water.
The assignment to provide justification on the feasibility of adopting
CON-AID was given to the Kenya Geotechnical Forum (currently known
as the Kenya Geotechnical Society) of which the Founder President is
Dr. John Mukabi. The assignment was supported by the Materials Testing
& Research Department of the Ministry of Public Works and Housing, the
University of Nairobi and Construction Projects Consultants.
The overall objectives were as follows.
1. To develop more technical and practical data base on CON-AID
in relation to what it’s physical and chemical properties are,
whether it really works, how it works and under what conditions
it works.
2. To scientifically determine and technically explain the effects
of sealing and the actual strength development of CON-AID with
time, as well as establish the optimum curing periods and
effective techniques that ensure optimum strength
development.
![Page 125: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/125.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
3. To simulate the life span and deterioration characteristics of CON-AID with time.
4. To determine design parameters and conditions for CON-AID treated geomaterials adopted for geotechnical engineering projects and subsequently develop a CON-AID Design Manual and Standard Specifications.
5. To quantify the effect of excess application of CON-AID in relation to engineering characteristics of soils.
6. To undertake comprehensive and detailed analyses of the effects of evaporation and migration of CON-AID prior to reaction with geomaterials and the variation of so doing in relation to the environmental factors such as climate, type of soils, drainage conditions, topography etc.
7. To establish methods of determination of optimum layer application, layer thickness and their reciprocal effective treatment quantities.
8. To develop an appropriate, comprehensive and detailed CON-AID Testing Manual.
9. To develop and propose a research base for enhanced Research & Development of CON-AID.
Field testing was undertaken on trial sections that were constructed along some sections of the Garsen ~ Hola portion of the Malindi ~ Garissa (B8) Trunk Road, while the problematic black cotton soils sampled from these sections were tested in the laboratory. The clays tested were essentially tropical products of physical and chemical in-situ weathering of igneous, sedimentary and metamorphic rocks under varying climatic conditions. The formation of such soils depends on a complex interaction of various variables such as weathering, erosion, climatic changes, type of original parent rock, local topography, drainage and cycle factors which have been known to strongly influence their engineering behavior. In general, the tropical clays researched and tested were of residual expansive nature formed from pyroclastic rocks. The Black Cotton Soils
tested were of very high swellability with dry densities (γd) greater than 16kN/m3, clay contents >55%, Liquid Limits (LL) >65%, Plasticity Indices (PI) >40%, Shrinkage Indices (Is) >60 and swell pressures >600kN/m2. Position: Research Team Leader/Lead Researcher Dr. Mukabi was charged with the overall responsibility of developing the
Research and Testing Regimes and leading the Research Team.
![Page 126: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/126.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Apr ’98 ~ Aug ‘98
(4.2 Months)
: Project Name: Study on Effective Strategy of Enhancing Research
& Development in Civil and Structural Engineering
in Kenya
Client: Industrial Development Institute, Japan
Location: Countrywide, Kenya
Brief Project Particulars/Description
In order for the Vision to be realized within the designated time-frame,
it is imperative that the targeted economic growth is achieved through
rapid industrialization, enhanced agricultural production and agro-
industry development, booming tourism, advanced education (science
and technology) among other factors. Such goals can only be achieved
through rapid infrastructure development based on innovative
techniques, methods and technologies as a primary driving factor.
This Proposal suggests and emphasizes on the utter need of enhancing
Research & Innovation for Sustainable Development (RISD) in
infrastructure as a top priority area which will form the integral
technological pillar and foundation for rapid industrialization leading to
the targeted socio-economic development.
Specifically, emphasis is made on the importance of designing and
implementing Research Regimes that concentrate on developing Value
Engineering (VE) technologies and materials science that would lead to
appreciable cost-time savings, whilst enhancing the structural and
serviceability levels as well as the overall performance of the
structures.
In order to enhance Research & Development as well as capacity
Building activities in Kenya discussions were held with the Industrial
Development Institute (IDI) of Tokyo, Japan. This would ultimately lead
to the development of design manuals and standard specification
tailored specifically for this region with the possibility of the
Government of Japan through the IDI, sponsoring these activities and
programmes depending on the mode of development.
Position: Lead Researcher/Civil Engineering Consultant/Team
Leader/Chief Projects Coordinator
Dr. Mukabi was appointed to spearhead, lead and coordinate these
activities and compile a preliminary report for submission to the IDI.
![Page 127: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/127.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May ‘98 ~ July ‘98
(2.3 Months)
: Project Name: Socio-Economic & Engineering Assessment, Analysis
and Project Formulation as a Mitigation Strategy of
the Impact of El-Nino on the C70 Kangema ~
Gacharage Road & Bridge for possible JICA funding
Client: Ministry of Public Works & Housing
Location: Kangema ~ Gacharage, Kenya
Brief Project Particulars/Description
Various Road Development Projects in Kenya were considerably
destroyed by flood disasters that occurred twice between 1997 and
1998. The first one was between April and July 1997, while the second
one caused by the El-Nino phenomenon was between September 1997
and January 1998.
As a result, extensive sections of the Kangema ~ Gacharage Road and
Bridges were over-flooded and several embankments washed away.
Colossal damage was rendered; particularly in areas with river crossings
due to the over-flooding of the rivers.
These disasters necessitated the undertaking of comprehensive
hydrogeological studies in order to determine suitable engineering
parameters that took into account, the change in environmental factors
and the scale of devastation, to ensure proper redesigning and
reconstruction of a number of sections of the road and hydraulic
structures as well as the carrying out of remedial works and repairs of
the damages with further additional works on protection and hydraulic
structures. Computation of cost implications and extension of time as a
result, including financial and economic analysis, were undertaken.
A preliminary socio-economic and engineering assessment was
undertaken for purposes of determining appropriate strategies for the
rehabilitation of the Kangema-Gacharage Road and Bridges and the
possibility of designing this section as a bypass of the Nairobi-Thika-
Nyeri Highway.
Position: Civil Engineering Consultant/Highway & Geotechnical
Engineer
Dr. Mukabi was assigned to lead the Study Team, undertake the study
and compile a Project Proposal to be submitted by the Government of
Kenya and to the Government of Japan for possible Grant Aid funding.
![Page 128: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/128.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June ’98 ~ Oct ‘98
(3.4 Months)
: Project Name: Study of Improved Methods of Design, Environmental
and Socio-economic Aspects for Evaton West
Municipal Roads in Johannesburg
Client: Evaton West Municipal Council, South Africa
Location: Johannesburg, South Africa
Brief Project Particulars/Description
In their latest Roads Infrastructure Development and maintenance Plan,
the Evaton West Municipal Council set out to embrace new engineering
concepts, design philosophies and technologies that could realize
substantial cost savings, minimum maintenance requirements and
maximum structural capacity and serviceability levels. The achievement
of these goals would enable the Council to:
1. Construct more roads within the Municipality.
2. Advance the development of the other sectors of infrastructure
from the proceeds of the acquisition savings.
3. Enhance integrated development of social institutions from the
cost savings realized from reduced maintenance requirements.
4. Improve the overall quality of physical infrastructure of the
Municipality in general.
In order to these goals, Evaton West Municipal Council sourced for
consultancy services from Consultants who could provide a baseline
proposal that would facilitate for the realization of this goal.
In the kick-off meeting held in Johannesburg, South Africa, dr. Mukabi
suggested that part of the Study be undertaken in Kenya while an
integral part of the field testing be carried out in South Africa to enable
comparative analysis between the geotechnical engineering properties
and characteristics of the Kenyan and South African Geomaterials. This
approach would ensure the enhancement of the precision levels of the
models to be developed for the required purposes.
Position: Team Leader/Lead Research Consultant/Pavement &
Geotechnical Engineer
Dr. Mukabi was appointed the Lead Research and Civil Engineering
Consultant to design the evaluation, study and approach that would be
effective in establishing suitable research, design and construction
methods.
![Page 129: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/129.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June ’98 ~ Nov ‘98
(5.2 Months)
: Project Name: Research on the Improvement and Adoption of
Liquid Chemical Stabilizers for Rural Road
Development South Africa
Client: Mitsui & Co East Africa/ Con-Aid Pty SA
Location: Nairobi, Kenya/Johannesburg, South Africa
Brief Project Particulars/Description
Based on the request of various Municipalities and local governments in
South Africa, Con Aid Pty SA embarked on research that could improve
the stabilization effect of Con Aid Liquid Chemical to enhance the
strength and mechanical properties of fine-grained and expansive soils.
CON-AID is considered to be a surface agent which takes advantage of
the ION-exchange capacity of clay minerals to change a geomaterials
characteristics from the hydrophilic (water absorption) nature to a
hydrophobic (total water repellent). As clayey geomaterials consist of
many layers with a variety of loosely associated ions which attract
water molecules to enhance hydrophylicity (absorption) of clays, CON-
AID is said to be able to get rid of the adsorbed water leading to the
achievement of better compaction and permanent stabilization with
minimum mechanical effort through the direct contact of particles.
Capillaries existing in the compacted material also have their inner
walls coated with hydrophobic layers of CON-AID which is said to allow
free movement of water.
Position: Team Leader/Research Consultant
Having previously undertaken extensive research on problematic soils,
Dr. Mukabi’s services were then required and he was appointed Chief
Research Consultant and Team Leader of the Research groups in Kenya
and South Africa. His main tasks included:
Design an effective Experimental and Research regime in order to realize the goals accordingly.
Appoint, organize, lead and advise the Research teams on the approach, testing and analytical methodology.
Direct the Research Teams on various aspects of the research objectives including the realization of an enhanced yet cost-effective product.
Compile and disseminate the results accordingly.
![Page 130: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/130.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
August, ‘98 ~ November, ‘98
(2.6 Months)
Project Name: Feasibility Study for Road Improvement and
Preliminary Design for the Moi International
Airport, Mombasa Access Road
Client: Mitsubishi Corporation/Takenaka Corporation, Japan Location: Mombasa, Kenya
Brief Project Particulars/Description
Upon successful construction and completion of the Moi International
Airport, Mombasa, which had been undertaken by Takenaka Corporation
and Mitsubishi Corporation of Japan, as a Grant Aid funded project by
the Government of Japan, it was further proposed that a Pre-feasibility
study encompassing socio-economic and engineering analysis be
undertaken to establish the viability of implementing the rehabilitation,
improvement and expansion of the International Airport Access Road.
This road is part of the C110 that also forms part of the A109 Main
Mombasa ~ Nairobi Highway.
A Preliminary Reconnaissance Study was initially undertaken mainly for
purposes of assessing and evaluating the following factors.
1. Traffic Volume and loading intensity particularly in
consideration of the trailer trucks that transport heavy
commercial goods from the Kilindini Port through the Access
Road towards Nairobi using the A109 International Trunk Road.
2. Traffic mode and characteristics.
3. Predominant socio-economic activities within the immediate
vicinity as well the extended zones.
4. Road condition survey.
5. Pavement structural state.
6. Existing and prevailing environmental factors and conditions.
7. Road expansion impediments.
8. Hydrogeological conditions and land use patterns.
9. General circumscribing integrated environment.
Position: Team Leader/ Sr. Highway & Geotechnical Engineer
His tasks included: Geotechnical Engineering Investigation; Pavement
Structural Design; Bridges Design Proposal; Proposal of appropriate
Environmental Mitigation Measures in reference to the existing
Causeway; Materials Investigation and Characterization.
![Page 131: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/131.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept ’98 ~ Oct ‘98
(1.8 Months)
: Project Name: Analysis of The Settlement Problem at Athi River
Cement Works
Client: Sumitomo Construction Co. Ltd, Japan
Location: Athi River, Kenya
Brief Project Particulars/Description
Gross settlement started occurring a few months after the new Athi
River cement factory had been constructed. Having realized the
settlement was progressive, the contractor, Sumitomo Construction Co.
Ltd., wished to determine whether it was a design or construction
problem.
In order to determine the engineering parameters that would be useful
in carrying out the necessary analysis, the following factors were
evaluated and/or carried out.
1. Comprehensive review of Engineering Reports, Design Study
Reports, Detailed Design Drawings, Materials Report, As-built
Drawings, Quality Control Programmes and corresponding Test
Data, Quality Assurance Certificates etc.
2. Assessment of the physical environment.
3. Hydrogeological conditions.
4. The overall structural condition of the building structures.
5. Soils profiles and existing conditions.
6. Structural elements of the foundation and foundation ground.
7. Concrete elements of the building structures.
8. Structural sufficiency of reinforcing elements.
Essentially, the Study arrived at the following overall conclusions.
1. The building structures were structurally sound.
2. The differential settlement was mainly caused by moisture-
suction variation within the underlying layers of problematic
soils, a factor of which had not been taken into account.
Position: Team Leader/Geotechnical & Structural Engineering
Consultant
Dr Mukabi was requested to undertake the assessment, evaluation and
analysis of the settlement problem, determine the cause and history as
well as the appropriate and suitable countermeasures.
![Page 132: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/132.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept ’98 ~ Feb ‘99
(5.8 Months)
: Project Name: Project Formulation Based on Socio-Economic &
Engineering Assessment of the El~Nino Damaged
Approach Roads & Bridges in Eastern & Coast
Provinces of Kenya
Client: Industrial Development Institute, Japan/Government of Kenya
Location: Eastern and Coast Provinces in Kenya
Brief Project Particulars/Description
Due to the occurrence of El Nino, various roads and bridges were
damaged all over the country in Kenya.
Various Road Development Projects in Kenya were considerably
destroyed by flood disasters that occurred twice between 1997 and
1998. The first one was between April and July 1997, while the second
one caused by the El-Nino phenomenon was between September 1997
and January 1998.
As a result, extensive sections of Approach Roads and Bridges were
over-flooded and several embankments washed away in both Eastern
and Coast Provinces. Colossal damage was rendered; particularly in
areas with river crossings due to the over-flooding of the rivers.
These disasters necessitated the undertaking of comprehensive
hydrogeological studies in order to determine suitable engineering
parameters that took into account, the change in environmental factors
and the scale of devastation, to ensure proper redesigning and
reconstruction of a number of sections of the road and hydraulic
structures as well as the carrying out of remedial works and repairs of
the damages with further additional works on protection and hydraulic
structures. Computation of cost implications and extension of time due
to these works, as well as financial and economic analysis had to be
undertaken.
Upon the request of the Government of Kenya, the Government of
Japan decided to send a mission from the Industrial Development
Institute (IDI) to undertake a reconnaissance study of the bridges and
approach sections of the roads and bridges that had been damaged and
determine the appropriate emergency as well as long term mitigation
measures.
![Page 133: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/133.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Sept ’98 ~ Feb ‘99
(5.8 Months)
A preliminary socio-economic and engineering assessment was
undertaken for purposes of determining appropriate strategies for the
rehabilitation of this Region and evaluating the possibility of redesigning
the pavement structures of the bridge approaches as well as the bridge
and other hydraulic structures.
The findings and outputs were compiled into a Study Report by the
Study Mission and submitted to the Government of Kenya and the
Government of Japan through the Ministry of Public Works and Housing
and the Japan Industrial Development Institute respectively.
Position: Civil Engineering Consultant/Highway & Geotechnical
Engineer
Dr. Mukabi participated as part of the Study Mission and was in charge
of coordinating the Study Mission and Public Officials, analyzing the
structural capacity of the existing roads and bridges and determining
the essential parameters that would formulate the main basis of the
preliminary structural designs.
![Page 134: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/134.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept, ‘98 ~ Dec, ‘98
(3.6 Months)
Project Name Formulation and Implementation of the Tana Basin
Road Flood Recovery and Rehabilitation Project
Client: Japan Bank of International Cooperation (Fmr. OECF)/Office of the President
Location: Malindi ~ Garissa, Tana District, Kenya
Brief Project Background/Particulars/Description
According to the Tana River District Development Plan, one of the major
constraints to industrial development in this region is the lack of basic
infrastructure. The whole district had only 918 kilometers of motorable
roads representing only 0.015% of the total national road network and
one of the lowest relative demand factors of 0.04% based on the traffic
generation and attraction.
In order to promote rapid socio-economic development and integration
to other regions, the Government of Kenya, within the scope of the
1997 ~ 2001 National Development Plan Policy that was set out to
achieve “Rapid Industrialization for Sustainable Development”, aimed at
completing the construction of the 327km Malindi ~ Garissa Trunk Road.
In 1992, the Government of Kenya initiated construction of 129km of
the road protion designated as Section A from Garissa to Hola through
the direct labour method by the National Youth Service (NYS).
In 1995, the Government of Kenya obtained loan No. KE-P16 from the
Government of Japan which was primarily to construct Sections A
(Garissa ~ Hola – 129km), Section B (Hola ~ Garsen – 94km) and Section
C (Garsen ~ Malindi – 104km). Part of the loadn was utilized to procure
machinery for Section A which was under NYS, whilst Sections B and C
were contracted, on 8th September 1995, to China Road & Bridge
Construction which was supervised by Construction Projects
Consultants, Japan.
Unfortunately, during the construction, the Tana Basin Road
Development Project was devastated twice by flood disasters. The first
one was between April and July 1997, while the second one caused by
the El-Nino phenomenon was between September 1997 and January
1998. As a result, extensive sections of the road were over flooded and
several embankments washed away. Colossal damage was rendered;
particularly in areas such as Tulu along Section B and Laga Buna on
Section C due to the over-flooding of the Tana River.
![Page 135: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/135.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Sept, ‘98 ~ Dec, ‘98
(3.6 Months)
These disasters necessitated the redesigning and reconstruction of a
number of sections of the road as well as carrying out remedial works
and repairs of the damages with further additional works on protection
and hydraulic structures. Consequently, cost implications due to these
works and extension of time were oriented towards escalation.
In order to achieve the successful completion and consequent socio-
economic viability of the Project, additional funds were certainly
necessary.
To realize this goal therefore, the Government of Kenya, through the
Office of the President and the Ministry of Public Works & Housing,
commissioned the Consultants to formulate and undertake the “Tana
Basin Road Flood Recovery and Rehabilitation Project” whose main
objective was to carry out a technical evaluation to determine the
extent of structural damage and financial cost implications thereof.
The Consultants undertook a comprehensive and detailed technical and
financial evaluation and conclusively determined that an additional
KShs 2,024 Million (Kenya Shillings Two Billion and Twenty Four
Million (Approximately US$ 30 Million or JY 3,074 Million) was
required.
Based on these findings, the Government of Kenya sent a request for
additional funding to the Government of Japan, through the Overseas
Economic Cooperation Fund (OECF), currently known as the Japan Bank
of International Cooperation (JBIC).
Position: Team Leader/Sr. Civil Engineer Dr. Mukabi was charged with the overall responsibility of contractually
evaluating the Contractor’s Claims and providing the necessary
recommendations accordingly.
![Page 136: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/136.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘99 ~ March, ‘99
(2.4 Months)
Project Name: Report to the Japan Bank of International
Cooperation (JBIC) Appraisal Mission for The
Additional Loan to the Tana Basin Development
Road Project in The Republic of Kenya
Client: Japan Bank of International Cooperation (Fmr. OECF)/Office of the President
Location: Malindi ~ Garissa, Kenya
Brief Project Background/Particulars/Description
The Government of Kenya, within the scope of the 1997 ~ 2001 National
Development Plan Policy that was set out to achieve “Rapid
Industrialization for Sustainable Development”, aimed at completing the
construction of the Malindi ~ Garissa Trunk Road under the Phase II of
the Tana Basin Development Project which had been designated as a
top priority Project within this region.
On the other hand, the Tana Basin Road Development Project had, in
the past, been devastated twice by flood disasters. The first one was
between April and July 1997, while the second one caused by the El-
Nino phenomenon was between September 1997 and January 1998. As a
result, extensive sections of the road were over flooded and several
embankments washed away. Colossal damage was rendered; particularly
in areas such as Tulu along Section B and Laga Buna on Section C due to
the over-flooding of the Tana River.
These disasters necessitated the redesigning and reconstruction of a
number of sections of the road as well as carrying out remedial works
and repairs of the damages with further additional works on protection
and hydraulic structures. Consequently, cost implications due to these
works and extension of time were oriented towards escalation.
In order to achieve the successful completion and consequent socio-
economic viability of the Project, additional funds were certainly
necessary.
In order to realize this goal therefore, the Government of Kenya
recognized the importance of undertaking the Tana Basin Road Flood
Recovery and Rehabilitation Project which determined an additional
requirement of KShs 2,024 Million (Kenya Shillings Two Billion and
Twenty Four Million (Approximately US$ 30 Million or JY 3,074 Million).
![Page 137: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/137.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Jan, ‘99 ~ March, ‘99
(2.4 Months)
Upon the request of the Government of Kenya therefore, that the
Government of Japan, through the Overseas Economic Cooperation Fund
(OECF), currently known as the Japan Bank of International Cooperation
(JBIC), grants it a loan extension of JY 3,148 Million (Japanese Yen
Three Billion One Hundred Forty Eight Million) constituting 85% of the
additional Project cost, the Government of Japan, through the OECF,
sent a comprehensive “Technical Questionnaire on the Additional
Loan to Tana Basin Road Project” that necessitated urgent appraisal of
the Project. An OECF Appraisal Team was subsequently sent to Kenya
from Japan for detailed Technical and Financial Appraisal and Project
Evaluation.
In this regard therefore, the Construction Project Consultants were
commissioned by the Office of the President to undertake the appraisal
and evaluation of the Status Quo of the Road Project.
A detailed assessment, evaluation, review and analysis of the Project
and compiled and a Report covering the following as the main topics.
1. National Development Plan
2. The Road Sector in General
3. Status Quo of the Tana Basin Development Project
4. The Detail of The Project
5. Cost of the Project
6. Implementation Schedule
7. Procurement Method
8. Right-of-way Acquisition and Resettlement
9. Environmental Assesment
10. Implementation Scheme
11. Maintenance Scheme
12. Economic and Financial Analysis
Based on the foregoing justification, the Consultants recommended and
the Government of Japan approved the loan extension accordingly.
Position: Team Leader/Sr. Civil Engineer Dr. Mukabi was charged with the overall responsibility of contractually
evaluating the Contractor’s Claims and providing the necessary
recommendations accordingly.
![Page 138: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/138.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Mar’99 ~ Dec ‘99
(8.6 Months)
: Project Name: Study on Rural Roads Improvement in Western
Kenya Considering Socio-Economic Impact,
Environmental Impact Assessment and Value
Engineering Based Design, (Japan International
Cooperation Agency, Ministry of Finance, Ministry
Of Roads & Public Works Kenya)
Location: Mombasa, Kenya
Brief Project Particulars/Description
The Government of Kenya through the Ministry of Finance and the
Ministry of Roads and Public Works requested the Government of Japan
to finance an elaborate and extensive feasibility study of the rural roads
in the whole of Western Kenya covering over 5,000 km of the Nyanza
and Western Provinces for purposes of improving the roads and road
network in that region. A JICA Study Team comprising of consultants
from Pacific Consultants International and Construction Project
Consultants was formed to undertake the study and determine the top
priority 100 km out of the 5,000 km. as the initial phase of
implementation.
Position: Chief Materials/ Geotechnical & Pavement Engineer/Chief
Project Coordinator & Advisor to Team Leader
During the study, Dr. Mukabi’s responsibilities included:
Coordinating the JICA Study Team, Ministry of Roads and Public Works and other Government of Kenya officials in all matters pertaining to the project.
Advising the consultants, in particular, the Highway Engineer and Environmental Specialist to ensure a correlated, coordinated and integrated design.
Organizing and coordinating capacity building and training sessions, seminars and technical forums for the engineers from the Ministry of Roads and Public Works.
Organising and coordinating seminars to disseminate the research and study findings.
Spearheading the research section of the study.
Characterization of geomaterials for engineering and construction purposes.
![Page 139: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/139.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec, ‘99 ~ Mar, ‘02
(27 Months)
Project Name: Detailed Engineering Design and Construction
Supervision of the Addis Ababa~Goha Tsion
Trunk Road Project – Phase II
Client: Japan International Cooperation Agency/Ethiopian Roads
Authority
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
The North-Western Corridor (Addis Ababa ~ Debre Markos ~ Gondar ~
Eritrean border) is one of the most important trunk road. It traverses
the northwestern part of Oromia, Amhara and Tigre Regions, the highest
agricultural producing areas of the country. Forty-six percent of major
crops and 45% of livestock (number of head) of the country are
produced in the area of influence of this corridor. This entire Corridor is
programmed for rehabilitation or upgrading under RSDP-1, particularly
Addis Ababa Goha Tsion forming a principal section of this corridor is
placed as the highest priority
The overall length of the Project is 182.5 km and is divided into four
phases. Phase 1 was the first 2 km (Sta. 3.5~5.5Km) within the
metropolises Addis Ababa and Phase II was the next 89.5km
(Sta.5.5~95.0Km), while Phase III was 16Km (Sta.95.0~111.0Km) and
Phase IV makes up the remaining 75Km (Sta. 111.0~186.0Km) km upto
Goha Tsion.
The pavement structural design was based on a Research Oriented Design Approach based on the “Comprehensive Study and Design Review of Road Pavements and Related Structures for the Addis Ababa ~ Debre Markos Road Development Project” that was undertaken concurrently with the construction was on-going. Position: Deputy Project Manager/Resident Geotechnical & Highway
Engineer/ Lead Researcher
Tasks included: Overall Project Management; Pavement Structural
Design; Development of appropriate Quality Control Systems and
effective Methods of Construction; Preparation of Detailed Engineering
Design Report for the 89.5Km (Phase II); Preparation of Tender
Documents for the 89.5Km (Phase II); and, Construction Supervision of
the 89.5Km (Phase II).
![Page 140: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/140.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec, ‘99 ~ Mar, ‘02
(27 Months)
Project Name: Detailed Engineering Design and Construction Supervision of the Addis Ababa~Goha Tsion Trunk Road Project – Phase II
Client: Japan International Cooperation Agency/Ethiopian Roads
Authority
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
By 1996, the Government of Ethiopia had identified the North-Western Corridor constituting the Addis Ababa ~ Debre Markos ~ Gondar Trunk Road as the top priority corridor to connect the main city Addis Ababa, not only to the North, but also as an international corridor through to Sudan and Eritrea. Having realized the importance, and urgency of rehabilitating this corridor, the Government of Ethiopia prepared a detailed design for the Addis Ababa ~ Debre Markos section in 1996. Subsequently, the Government of Ethiopia made an official request to the Government of Japan for Grant Aid to facilitate the implementation of the Project. In response to the request from the Government of the Federal Democratic Republic of Ethiopia, and having realized the urgency, the Government of Japan decided to conduct a Basic Design Study on the Project for Rehabilitation of the Addis Ababa ~ Goha Tsion Trunk Road under the Japan International Cooperation Agency (JICA). The JICA Study Team was then sent to Ethiopia from November 23rd to December 28th, 1997. Although the original request from the Government of Ethiopia covered the section between Addis Ababa ~ Debre Markos, a distance of approximately 300km, single phase implementation was not feasible mainly due to the Grant Aid system of the Government of Japan. The JICA Study Team therefore recommended that the construction be implemented in phases especially in view of the fact that the implementation schedule for the Debre Markos ~ Gondar section was programmed to start in 1998 through IDA funding. The North-Western Corridor (Addis Ababa ~ Debre Markos ~ Gondar ~ Eritrean border) is one of the most important trunk road. It traverses the northwestern part of Oromia, Amhara and Tigre Regions, the highest agricultural producing areas of the country. Forty-six percent of major crops and 45% of livestock (number of head) of the country are produced in the area of influence of this corridor. This entire Corridor is programmed for rehabilitation or upgrading under RSDP-1, particularly Addis Ababa Goha Tsion forming a principal section of this corridor is placed as the highest priority.
![Page 141: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/141.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Dec, ‘99 ~ Mar, ‘02
(27 Months)
Basic Design Concept
Sub Sections Sub-sections were determined by area (city, urban or rural) and topography (rolling or mountainous) along the targeted road of Addis Ababa ~ Goha Tsion between the start point at Km 3.5 to the end point at Km 186.
Geometry Since the alignment of the existing road was basically in accordance with the standards adopted i.e. ASHTO or TRL Road Note No. 6, it was recommended that the alignment be maintained as much as possible.
Road Width During the basic design study and prior to the preparation of the Geometric Design Manual, 2001, ERA (Ethiopian Road Authority) used to adopt a 7.0m cam agency and 1.5m of shoulder on both sides for the major trunk roads. The basic design therefore adopted the same criteria except for the mountainous sections where a 6.5m carriage way and a 1.0m shoulder were adopted. However, for the section km 5.0 ~ Km 10.0 (mountainous and urban area) a 3.0m shoulder on the hill side was adopted.
Pavement Structure The pavement structural design was based on a Research Oriented Design Approach based on the “Comprehensive Study and Design Review of Road Pavements and Related Structures for the Addis Ababa ~ Debre Markos Road Development Project” that was undertaken concurrently with the construction was on-going.
Position: Deputy Project Manager/Resident Geotechnical & Highway Engineer/ Lead Researcher
Tasks included: Overall Project Management; Pavement Structural Design; Development of appropriate Quality Control Systems and effective Methods of Construction; Preparation of Detailed Engineering Design Report for the 89.5Km (Phase II); Preparation of Tender Documents for the 89.5Km (Phase II); and, Construction Supervision of the 89.5Km (Phase II).
![Page 142: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/142.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘00 ~ May, ‘00
(0.6 Months)
Project Name: Evaluation and Establishment of a Counter Claim of
Pioneer Plumbers Contractual Claims for Variations
for the Mpata Safari Club Project
Client: Mpata International, Japan
Location: Masai Mara/Nairobi, Kenya
Brief Project Background/Particulars/Description
A group of Japanese investors decided to develop a high class resort in Maasai Mara in Kenya and Serengeti in Tanzania. The Project involved undertaking feasibility studies, Basic Design, Detailed Design and Construction Supervision of the Mpata Safari Club on the part of the Consultants who were a Consortium of Japanese, British Kenyans and Germans.
Mpata Safari Club is perched on the hilltop with breathtaking views of the Masai Mara Reserve. Its adventageous location and well designed programs offer guests a chance to experience the environmental beauty. The Clubs unique design is the brainchild of Edward Suzuki - a leading architect in Japan. Guests stay in individual cottages well spaced along the top of the escarpment offering paranomic views. There are 11 suites and 12 deluxe units in Mpata Safari Club, each with seperate bedroom, bathroom and verandah. With emphasis on comfort and a unique combination of interior design, the suites have a lounge, kitchenette but the best of all is an outdoor Jacuzzi with spectacular and breathtaking views of the Masai Marai Game Reserve. The Club has a Sunken Rock Bar that offers sensational views of the Mara River and the Sundowner Bar that is well located to enhance the view of the rising and setting sun. Due to its location on top of the escarpment, the water had to be pumped through a distance of more than 3km at a most critical gradient from the Mara River. These conditions led to complications in the plumbing works that were undertaken by Pioneer Plumbers who were Sub-Contractors. This culminated in the delay in the implementation of the works. Due to this, the Sub-Contractor submitted claims for variations in the works citing that complications had arisen from the topographical nature and site conditions which he had not envisaged well nor taken into account during his bid. Based on the Terms and Conditions of the Contract that had been entered into and signed between the Client and the Sub-Contractor, a
![Page 143: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/143.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
May, ‘00 ~ May, ‘00
(0.6 Months)
detailed assessment, evaluation, review and analysis of the Contractor’s
Claims was undertaken.
During this exercise, various factors were considered partially by the
Consultants, including the complexity of undertaking the works against
the fair Tender Price that had been quoted by the Contractor.
In their findings, the Consultants determined that, mainly due to the
delay in handing over and commissioning the works, the Client was
actually entitled to a Counter Claim.
Nevertheless, in view of the complexity of the works and the prudent
pricing of the Sub-Contractor, the Consultants recommended that he be
awarded 36% of the Claims.
Both the Client and the Sub-Contractor mutually agreed and consented
to the Consultants recommendations and the matter was settled
amicably.
Position: Claims Engineer Dr. Mukabi was charged with the overall responsibility of contractually
evaluating the Contractor’s Claims and providing the necessary
recommendations accordingly.
![Page 144: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/144.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June ’00 ~ Nov ‘00
(5.1 Months)
Project Name: Design of Reinforced Earth Structures with Slope
Protection applying the Terre Armee Method for
the Tana Basin Development Project Phase II
Client: Japan Bank of International Cooperation, Ministry of Roads &
Public Works, Kenya
Location: Malindi ~ Garissa, Kenya
Brief Project Particulars/Description
During the construction, the Tana Basin Road Development Project was
devastated twice by flood disasters. The first one was between April
and July 1997, while the second one caused by the El-Nino phenomenon
was between September 1997 and January 1998. As a result, extensive
sections of the road were over flooded and several embankments
washed away. Colossal damage was rendered; particularly in areas such
as Tulu along Section B and Laga Buna on Section C (Garsen ~ Malindi)
due to the over-flooding of the Tana River.
Due to the colossal damage that had been caused by the El Nino, the
Ministry of Roads and Public Works of Kenya requested the Consultant
(CPC) to come up with Value Engineering based solutions for the major
lagas along the 330km long Malindi – Garissa road. Since lack of suitable
geomaterials also posed a problem, it became necessary to develop
methods of improving the material quality besides advising on the
overall supervision.
Position: Team Leader/Chief Technical Advisor/ Sr. Pavement,
Geotechnical & Materials Engineer/Lead Researcher
Dr. Mukabi was assigned the tasks of formulating a Technical Committee
under his chairmanship to undertake studies, evaluation and research
for purposes of ensuring appropriate engineering decisions leading to an
optimum design were realized. It is during this assignment that he
innovated the new Optimum Batching Ratio Method (OBRM) that greatly
enhanced the mechanical stability of relatively inferior geomaterials
and the reciprocal appropriate Method of Construction. He was
therefore also charged with the responsibility of supervising the
practical construction adopting the newly developed techniques. As a
consequence, more than 40% cost savings were realized on practically
pavement layers and other geostructures, including bridge abuttments.
![Page 145: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/145.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June ’00 ~ Nov ‘00
(5.8 Months)
Project Name: Comprehensive Study and Design Review of Bridge and Hydraulic Structures for the Tana Basin Road Development Project
Client: Japan Bank of International Cooperation/Office of the President/ Ministry of Roads & Public Works, Kenya
Location: Malindi ~ Garissa, Kenya
Brief Project Particulars/Description
The section has a total length of 130Km connecting Garissa (Provincial headquarters, North Eastern Province) and Hola (District headquarters) Tana River District in the Coast province. Garissa is a vital base for camps for the UN, WFP and other NGO’s.The Construction of section A was undertaken by (OOP)office of the president, through direct labour by National Youth Service and supervision by the Ministry of Public Works and Housing. The works involved the construction of 130Km of road and 2 bridges, 7 box culverts and over 300 pipe culvert lines. A total 103Km of paved road and 110Km earth works were completed by October 1997.
The El-Nino floods caused massive damage to the earthworks already constructed at Km218 ~ 221, in the process, forming a deep gulleys of about 30 ~ 60m wide and 2 ~ 3m deep.
These disasters necessitated the undertaking of comprehensive
hydrogeological studies in order to determine suitable engineering
parameters that took into account, the change in environmental factors
and the scale of devastation, to ensure proper redesigning and
reconstruction of a number of sections of the road and hydraulic
structures as well as the carrying out of remedial works and repairs of
the damages with further additional works on protection and hydraulic
structures. Computation of cost implications and extension of time due
to these works, as well as financial and economic analysis had to be
undertaken.
Position: Team Leader/ Sr. Foundation & Geotechnical Engineer/Lead Researcher
His main tasks included Flood damage control and remedial works; Road restoration works including restoration of embankments and pavement layers as well as the corresponding structural elements.
![Page 146: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/146.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
July, ‘00 ~ August, ‘00
(1.2 Months)
Project Name: Evaluation Contractor’s Contractual Claims for
Variations and Extension of Time for Sections B
(Hola ~ Garsen) and C (Garsen ~ Malindi) of the
Malindi ~ Garissa Trunk Road (B8) - the Tana Basin
Development Project Phase II
Client: Japan Bank of International Cooperation/Office of the President
Location: Malindi ~ Garissa, Kenya
Brief Project Background/Particulars/Description
During the construction, the Tana Basin Road Development Project was
devastated twice by flood disasters. The first one was between April
and July 1997, while the second one caused by the El-Nino phenomenon
was between September 1997 and January 1998. As a result, extensive
sections of the road were over flooded and several embankments
washed away. Colossal damage was rendered; particularly in areas such
as Tulu along Section B and Laga Buna on Section C (Garsen ~ Malindi)
due to the over-flooding of the Tana River.
These disasters necessitated the redesigning and reconstruction of a
number of sections of the road as well as carrying out remedial works
and repairs of the damages with further additional works on protection
and hydraulic structures. Consequently, cost implications due to these
works and extension of time were oriented towards escalation.
Due to the damage caused by these disasters, the Government of Kenya,
through the Office of the President and the Ministry of Public Works &
Housing, commissioned the Consultants to formulate and undertake the
“Tana Basin Road Flood Recovery and Rehabilitation Project” whose
main objective was to carry out a technical evaluation to determine the
extent of structural damage and financial cost implications thereof. This
assignment was carried out between September and December 1999. ,
whilst the Project Appraisal was carried out by the Consultants between
January and March 2000.
For purposes of accurate and consistent cost calculations, the
Consultant divided the works into “Certified and Remaining Works as at
November 1998”. All the Works that had been revised, completed and
certified as at November 1998 were measured and quantified accurately
on site. The quantities were then subtracted from the total workload,
![Page 147: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/147.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
July, ‘00 ~ August, ‘00
(1.2 Months)
which had also been measured and quantified, to form the remaining
works.
The remaining works included all components affected by design change
before prevalence of the El-Nino for Section C as well as the flood
damage and improvement prompted by the El-Nino for both Sections B
and C. One of the major factors that contributed to increase in costs
was the realignment in Section C from PK 92+000 to PK 96+404 and from
PK 217+500 to 222+893 in Section B, both of whose criteria had been
well defined. Rasing of embankments and redesign of bridge approaches
were other major factors that contributed to cost escalation.
Due to these developments, the Contractor submitted Contractual
Claims for Variations and Extension of Time.
Based on the Terms and Conditions of the Contract that had been
entered into and signed between the Client and the Contractor, a
detailed assessment, evaluation, review and analysis of the Contractor’s
Claims was undertaken.
During this exercise, various factors were partially, ethically and
prudently considered by the Consultants.
In their findings, the Consultants determined that the Contractor was
entitled to 83% of his claims against variations and 74% of claims for the
extension of time.
The Consultants recommended these awards to which both the Client
and the Contractor mutually agreed and consented and the matter was
settled amicably.
Position: Claims Engineer Dr. Mukabi was charged with the overall responsibility of contractually
evaluating the Contractor’s Claims and providing the necessary
recommendations accordingly.
![Page 148: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/148.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct., ‘00 ~ Apr., ‘04
(43 Months)
: Project Name: Comprehensive Study and Design Review of Road
Pavements and Related Structures for the Addis
Ababa ~ Debre Markos Road Development Project
Client: Japan International Cooperation Agency/Ethiopian Roads
Authority
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
Through the request of the Government of Ethiopia, the Government of Japan offered Grant Aid for the rehabilitation of a 182.5 km highway including 19 bridges from Addis Ababa to Goha Tsion and Road Project Development through the Abay Gorge, Blue Nile to Debre Markos, which forms part of the vital International rans African Highway. The necessity and justification to carry out a comprehensive Study and Design Review of this Project is mainly attributed to the following facts.
1. Implementation of the Construction was effected when 25% of the Design Life had elapsed (since the Detailed Design had been completed). It was therefore considered that such vital design parameters as structural capacity, pavement performance index and serviceability levels would certainly have varied over that period of time.
2. Prolonged traffic loading had culminated in increased damaging effect.
3. The pavement structure had deteriorated with the progression of time.
4. The Design Criteria and Project Specifications did not seem to synchronize.
5. The existence of problematic soils, in particular, Black Cotoon Soils had not been taken into account in existing Detailed Design.
6. Slope instability was prevalent in a number of sections along the Road corridor.
7. General assessment and evaluation of the site conditions, alignment soils, nature of subgrade in most sections and Material sources indicated that there could be the necessity to improve the subgrade and mechanically and/or chemically stabilize subbase materials sourced from certain borrow pits.
8. Pavement structural configuration seemd insufficient in certain cases and overdesigned in others possibly due to the fact that the environmental factors and problematic subgrade soils had not been comprehensively analyzed during the stage of the Detailed Design Study.
9.
![Page 149: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/149.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Oct., ‘00 ~ Apr., ‘04
(43 Months)
In order to confirm the facts itemized above, a Preliminary Study was undertaken under emergency status since the Project was already under implementation. The findings of this Study carried out by the Consultants, which confirmed all the above facts, were presented to, and discussed with the Client (both Japan International Cooperation Agency and Ethiopian Roads Authority). In their Engineering Report, the Consultants proposed, and the Client consented, that the Project be implemented on the basis of Research Oriented Design. A Study Team was constituted and the assignment undertaken accordingly. Due to the Research Oriented Design Approach, approximately 40% direct cost savings and 60% time savings were realized against the construction of the pavement structures. As a consequence, the Project was completed 3 years ahead of schedule. Position: Team Leader/Lead Consultant/ Lead Researcher /Chief
Highway/Pavements & Geotechnical Engineer The work carried out by Dr. Mukabi included:
Overall management and supervision of the Study
Providing due guidance to each Expert of the Study Team
Designing and developing the Research Regime, unique Testing Programmes and necessary analytical tools
Providing guidelines for the Detailed Design and Studies
Innovating unique engineering solutions for problematic soils
Developing research based methods to foster Value Engineering concepts (Enhanced pavement structural performance at reduced costs)
Development of pragmatically applicable Value Engineering Technologies
Undertaking capacity building and training programmes for young Ethiopian Engineers
Developing new and advanced Methods of Construction and Quality Control Systems.
![Page 150: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/150.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘01 –Mar, ‘04
(33 Months)
Project Name: Detailed Design of the Project for Construction of
Bridges
Client: Japan International Cooperation Agency
Location: Nationwide, Ghana
Brief Project Particulars/Description
In most rural areas in Africa, economic and social activities associated
with socio-economic development have been constrained due to poor
infrastructure facilities and inaccessibility resulting from lack of bridges
and other hydraulic structures that facilitate for crossings over water
bodies. This is particularly the case along most of the feeder roads.
The project for the Detailed Design Study of the selected bridges
covered Soil/Materials, Geotechnical Investigation and Testing Regimes;
Hydrological Survey and Analysis; Comparative Study of Bridge Type and
Basic Design of Bridges; Detailed Design of Bridge Foundations and
Approach Roads; Construction Planning, Cost Estimate and Preparation
of Tender Documents. The Project was intended not only to improve on
the existing conditions but also support and spur socio-economic
development for the entire of country, more particularly the project
influence area, and to upgrade the living standards of the rural people
within as wide an area as possible.
Position: External Consultant/Sr. Geotechnical Engineer
Dr. Mukabi was tasked with: Developing Soil/Materials, Geotechnical
Investigation and Testing Regimes; Designing the Hydrological Survey
and Analysis; Establishing guidelines for Comparative Study of Bridge
Type and Basic Design of Bridges; Advising on the Detailed Design of
Bridge Foundations and Approach Roads; Providing Technical Advisory
Services regarding Construction Planning, Cost Estimate and Preparation
of Tender Documents
![Page 151: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/151.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘02 ~ Feb, ‘03
(13 Months)
Project Name: Detailed Engineering Design and Construction Supervision of the Addis Ababa~Goha Tsion Trunk Road Project – Phase III
Client: Japan International Cooperation Agency/Ethiopian Roads
Authority
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
The North-Western Corridor constituting the Addis Ababa ~ Debre Markos ~ Gondar Trunk Road as the top priority corridor to connect the main city Addis Ababa, not only to the North, but also as an international corridor through to Sudan and Eritrea. Having realized the importance, and urgency of rehabilitating this corridor, the Government of Ethiopia prepared a detailed design for the Addis Ababa ~ Debre Markos section in 1996. Subsequently, the Government of Ethiopia made an official request to the Government of Japan for Grant Aid to facilitate the implementation of the Project. In response to the request from the Government of the Federal Democratic Republic of Ethiopia, and having realized the urgency, the Government of Japan decided to conduct a Basic Design Study on the Project for Rehabilitation of the Addis Ababa ~ Goha Tsion Trunk Road under the Japan International Cooperation Agency (JICA). The JICA Study Team was then sent to Ethiopia from November 23rd to December 28th, 1997. Although the original request from the Government of Ethiopia covered the section between Addis Ababa ~ Debre Markos, a distance of approximately 300km, single phase implementation was not feasible mainly due to the Grant Aid system of the Government of Japan. The JICA Study Team therefore recommended that the construction be implemented in phases especially in view of the fact that the implementation schedule for the Debre Markos ~ Gondar section was programmed to start in 1998 through IDA funding. The North-Western Corridor (Addis Ababa ~ Debre Markos ~ Gondar ~ Eritrean border) is one of the most important trunk road. It traverses the northwestern part of Oromia, Amhara and Tigre Regions, the highest agricultural producing areas of the country. Forty-six percent of major crops and 45% of livestock (number of head) of the country are produced in the area of influence of this corridor. This entire Corridor is programmed for rehabilitation or upgrading under RSDP-1, particularly Addis Ababa Goha Tsion forming a principal section of this corridor is placed as the highest priority.
![Page 152: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/152.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Jan, ‘02 ~ Feb, ‘03
(13 Months)
Basic Design Concept
Sub Sections Sub-sections were determined by area (city, urban or rural) and topography (rolling or mountainous) along the targeted road of Addis Ababa ~ Goha Tsion between the start point at Km 3.5 to the end point at Km 186.
Geometry Since the alignment of the existing road was basically in accordance with the standards adopted i.e. ASHTO or TRL Road Note No. 6, it was recommended that the alignment be maintained as much as possible.
Road Width During the basic design study and prior to the preparation of the Geometric Design Manual, 2001, ERA (Ethiopian Road Authority) used to adopt a 7.0m cam agency and 1.5m of shoulder on both sides for the major trunk roads. The basic design therefore adopted the same criteria except for the mountainous sections where a 6.5m carriage way and a 1.0m shoulder were adopted. However, for the section km 5.0 ~ Km 10.0 (mountainous and urban area) a 3.0m shoulder on the hill side was adopted.
Pavement Structure The pavement structural design was based on a Research Oriented Design Approach based on the “Comprehensive Study and Design Review of Road Pavements and Related Structures for the Addis Ababa ~ Debre Markos Road Development Project” that was undertaken concurrently with the construction was on-going.
Position: Deputy Project Manager/Resident Geotechnical & Highway Engineer/ Lead Researcher
Tasks included: Overall Project Management; Pavement Structural Design; Development of appropriate Quality Control Systems and effective Methods of Construction; Preparation of Detailed Engineering Design Report for the 16Km (Phase III); Preparation of Tender Documents for the 16Km (Phase III); and, Construction Supervision of the 16Km (Phase III).
![Page 153: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/153.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec, ‘02 ~ March, ‘04
(15 Months)
: Project Name: Detailed Engineering Design and Construction Supervision of the Addis Ababa~Goha Tsion Trunk Road Project – Phase IV
Client: Japan International Cooperation Agency/Ethiopian Roads
Authority
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
The Addis Ababa ~ Goha Tsion road leads from the capital, Addis Ababa towards the in North West direction to Bahirdar, the capital of the Amhara Region. The overall length of the Project is 182.5 km and is divided into four phases. Phase 1 was the first 2 km (Sta. 3.5~5.5Km) within the metropolises Addis Ababa and Phase II was the next 89.5km (Sta.5.5~95.0Km), while Phase III was 16Km (Sta.95.0~111.0Km) and Phase IV makes up the remaining 75Km (Sta. 111.0~186.0Km) km upto Goha Tsion. Some of the main towns through which the road traverses are Chancho, Debretsige, Fiche and Gebre Guracha. The scope of the work was to rehabilitate the existing road with some upgrading to improve ride ability bearing capacity, strength deformation resistance and Road safety. The final road width in all the sections of this Phase IV from Km 111.0 to Km 186.0 will then have a two lane typical carriageway of 7m width and 1.5m shoulder width on both sides but varying pavement structural configuration due to the subgrade soils, terrain and topographic characteristics that vary with the sections of Phases I ~ III. In addition to a 50mm AC wearing course, there is a variable aggregate base course layer in the over lay portion overlain by a variable layer of subbase for the areas to be extended at the edges of the existing road way. The Basic Design Concept adopted for this Phase was fundamentally similar to the one that was adopted for Phases I ~ III. After completion of this Study, a Preliminary Geotechnical Engineering Study was carried out through the Abay Gorge, across the Blue Nile through the landslide prone areas to Debre ~ Markos> Position: Deputy Project Manager/Resident Geotechnical & Highway
Engineer/ Lead Researcher
Tasks included: Overall Project Management; Pavement Structural Design; Development of appropriate Quality Control Systems and effective Methods of Construction; Preparation of Detailed Engineering Design Report for the 75Km (Phase IV); Preparation of Tender Documents for the 75Km (Phase IV); and, Construction Supervision of the 75Km (Phase IV).
![Page 154: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/154.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Mar,’03~ April, ‘04
(12 Months)
Project Name: Study for the Enhancement of Structural Capacity and Serviceability Level of the Addis Ababa – Goha Tsion Trunk Road
Client: Kajima Coporation/Japan International Cooperation Agency/Ethiopian Roads Authority
Location: North Western Corridor (Branching to Sudan and Eritrean border), Ethiopia
Brief Project Particulars/Description
The Government of the Federal Democratic Republic of Ethiopia (GOE) did, within the Road Sector Development Programme (RSDP), set out to achieve Rapid Infrastructure Development aimed principally at Poverty Reduction and Sustainable Socio-economic Development.
In order to realize the above stated goals for the Oromia, Amhara and Tigray regions, which produce approx. 46% of the total crops and 45% of the total livestock of the entire nation, and foster enhanced Regional and International Trade and Relations.
However, following the rehabilitation and widening reconstruction of the Ababa ~ Goha Tsion International Trunk Road, exceedingly exponential increase in Traffic Volume (the traffic volume for cargo and trailer trucks had doubled in a span of just 2 years between 2002 and 2004, for example) and loading intensity was experienced, mainly as a result of heavy trucks transporting commercial goods to Sudan and oil tankers that ferry petroleum products imported from Sudan to Ethiopia. The necessity to implement the project to enhance the structural capacity and serviceability level had been identified by July, 2001. Technical discussions were then undertaken between the Client, Consultant and Contractor whereby an agreement was reached that a Technical Committee, and a Research and Study Team be established. Subsequently, the Research and Study Team embarked on a project to investigate the structural capacity and serviceability level of the existing road at that time (July, 2001) and propose technical measures for appropriate engineering solutions. An internal report of the results obtained from the study was then
compiled into an engineering report entitled "Analysis and Evaluation
of the Structural Capacity and Serviceability Level of the Existing
Road Pavement''.
![Page 155: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/155.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Mar,’03~ April, ‘04
(12 Months)
Based on this report, continuous research, evaluation, analysis and
technical discussions were organized and the results disseminated
accordingly. Consequently, it became increasingly evident that, as a
result of the drastic increase in traffic volume and corresponding axle
loading, it would be necessary to strengthen the existing pavement
structure.
Consequently, the GoE commissioned the Consultants, with the full cooperation and support of the Contractor, to undertake “Study for the Enhancement of Structural Capacity and Serviceability Level of the Addis Ababa – Goha Tsion Trunk Road”.
In view of the prevailing circumstances, the Client, Ethiopian Roads Authority (ERA) requested that a Research and Study Team, be engaged in compiling a proposal that would incorporate technical aspects that can justify the requirement of the enhancement of the structural capacity and serviceability level of the Addis Ababa ~ Goha Tsion Trunk Road. Based on the Monitoring Programme of the transport and pavement structural characteristics initiated by the Research and Study Team, the GoE was advised of the need to source funds for the expeditious enhancement of the Structural Capacity and Serviceability Level of the Addis Ababa ~ Goha Tsion International Trunk Road. The fundamental objective of the project, therefore, was to undertake a detailed and comprehensive study for the enhancement of the serviceability, safety and structural capacity levels of the Addis Ababa-Goha Tsion Trunk Road in order to foster further poverty reduction and increased socio-economic development through connections to Sudan and Eritrea. It is the humble request therefore, of the Government of the Federal Democratic Republic of Ethiopia to the Government of Japan to kindly approve the utilization of Ethiopian Birr 128 Million (One Hundred Twenty Eight Million Birr) from the Counterpart Fund for the initial Term 1 construction of 60km double surfacing as part of the total 341 Million (Three Hundred Fourty One Million Birr) required for the strengthening of the 180.5km from Addis Ababa to Goha Tsion. This initiative is crucial in pragmatically achieving the goals stated in (1) above. Position: Team Leader /Sr. Highway & Geotechnical Engineer/Lead
Researcher Dr. Mukabi undertook Comprehensive and detailed studies/ investigations undertaken for a period of 2 years for the enhancement of structural capacity and serviceability level, Project concept planning and pre-feasibility study phase, Feasibility and EIA studies.
![Page 156: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/156.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘04 ~ July, ‘04
(2.5 Months)
Project Name: Pre-Feasibility Study and Preliminary Engineering
Design of the Bahir Dar University Road
Client: Office of the Deputy Prime Minister/Bahir Dar Municipality
Location: Bahir Dar , Ethiopia
Brief Project Particulars/Description
The Bahir Dar University has several campuses all located within the
Bahir Dar City. Perching on the shores of Lake Tana, the city is
approximately 550km north of Addis Ababa and is one of the major
cities in the northern part of Ethiopia. The Study area was for the
Access Road, an integral part of the Bahir Dar City Highway Network
within the planned Ring Road, leading to the Faculty of Education and
Business Administration (Pedagogical) Campus. The terrain is generally
flat in nature resulting in resulting in critical ponding and drainage
problems
After carrying out an Initial Assessment of the site conditions, it was
concluded that, in order to provide possible Value Engineering based
solutions that would be cost-effective, it was imperative to implement
the “Pre-Feasibility Study and Preliminary Engineering Design of the
Bahir Dar University Road”.
Upon these recommendations, the Office of the Deputy Prime
Minister/Bahir Dar Municipality commissioned the Consultants to
undertake the Study as a matter of urgency.
The basic objective of the Project was to facilitate for the proper and
precise Design and Construction of the Bahir Dar University Access Road
that would realize a VE (Value Engineering) based cost-effective
product.
Position: Team Leader/Project Director/Sr. Geotechnical & Highway
Engineer
He undertook preliminary investigations for the enhancement of
structural capacity and serviceability level, Project concept planning
and pre-feasibility study phase, including the Initial Environmental
Examination.
![Page 157: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/157.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May ,’04 ~ Sept, ’04
(3.8 Months)
Project Name: Pre-Feasibility Study and Preliminary Engineering
Design Project for the Upgrading and Expansion of
the Gimbothaya International Airport and Access
Road in Bahir Dar
Client: Office of the Deputy Prime Minister/Bahir Dar Municipality
Location: Bahir Dar, Ethiopia
Brief Project Particulars/Description
The Gimbothaya (Bahir Dar) International Airport University has several
campuses all located within the Bahir Dar City which is located on the
shores of Lake Tana, approximately 550km north of Addis Ababa and is
one of the major cities in the northern part of Ethiopia. The Study area
covered the zones within te vicinity of the planned highway to the
Airport, an integral part of the Bahir Dar City Highway Network. At the
time of undertaking this Study, it was still a gravel road.
The project Scope of Works was basically to undertake a pre-feasibility
study and preliminary engineering design for the improvement of the
Gimbothaya (Bahir Dar) International Airport infrastructure and the
4.5km Access Road.In general, the gravel road was in good ridable
condition and was not characterized by serious drainage problems. It
was assessed that the hilly terrain that is offset from the Road at an
appreciable distance would not pose any technical, drainage,
environmental and/or construction problems.
The following are some of the conclusions that were deduced from the
Preliminary Study.
1. In order to realize a cost-effective Value Engineering based
design and method of construction, further surveys,
investigations and studies based on both in-situ and laboratory
testing and detailed analysis.
2. For the initial phase of improvement, the existing gravel
pavement may be sufficient to serve as a foundationof a
leveling course of OBRM stabilized crusher-run aggregate and a
5cm Asphalt Concrete (AC) surface layer for faster and more
comfortable accessibility from the airport to the city of Bahir
Dar and vice versa.
3. Despite the gravel loss observed, the rate is not drastic hence
the fairly good roadbed condition.
![Page 158: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/158.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
May ,’04 ~ Sept, ’04
(3.8 Months)
4. Given the low traffic volume (AADT≤100 vehicles one way) at
the time, the existing 7m carriageway was considered sufficient
for the initial phase.
5. Given the state of the existing vertical and horizontal
alignments of the road, it would be advisable to maintain the
existing alignment.
6. In order to arrive at an economical pavement structural design,
a design traffic volume of 100< AADT ≤ 250 for the initial phase.
7. Since congestion of the road and frequent breakdown of
vehicles is not envisaged, provision of shoulders should be
considered as a mimum requirement.
Position: Team Leader/Project Director/Sr. Geotechnical & Highway
Engineer
He was charged with the responsibilities of Formulation of study
concept and approach; Engineering study, research and analysis;
Capacity building; Geotechnical and material surveys and investigations;
Topographic, geological and hydrological survey/ study; Evaluation of
existing structural capacity of road pavements and bridge structures;
amongst other tasks.
![Page 159: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/159.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘04 ~ Feb, ‘05
(9.2 Months)
Project Name: Feasibility Study and Preliminary Engineering Design of the Upgrading Project of the Holeta~Muger Road
Location: Nekemta ~ Ambo, Ethiopia
Brief Project Particulars/Description
The Holeta~Muger road Project is located in West Shoa Zone of Oromiya Regional State. The road branches off at Holeta, located about 45km from Addis Ababa along the Addis-Nekemt-Ambo main highway. The road traverses two main towns namely Inchini, located at 35kms from Holeta and Muger Reiji located at 52kms from the same. The road is mainly utilized by heavy trucks in transporting cement, raw materials and fuel for the Muger Cement Factory. The Project entailed undertaking a Pre-feasibility study and preliminary Engineering Design for the Holeta~Muger Road comprising of a total length of 56.8km.
Position: Team Leader/Project Director/Sr. Geotechnical & Highway Engineer
Undertaking Project concept planning and pre-feasibility study phase, and organizing a 6-month training programme of young Ethiopian engineers through the Ethiopian Association of Civil Engineers under a similar framework.
June, ‘04 ~ Dec, ‘04
(6.5 Months)
Project Name: Evaluation, Assessment and Preparation of
Contractual Claims
Client: Kajima Corporation, Japan
Location: Addis Ababa, Ethiopia
Brief Project Particulars/Description
The main assignment involved a comprehensive evaluation, assessment
and preparation of the contractual claims pertaining to the acquisition
savings realized by the Consultant and the Contractor during the
rehabilitation/construction of the Addis Ababa ~ Goha Tsion including
tax refund claims.
Position: Claims Engineer
The main tasks included the comprehensive assessment and evaluation
of contractual claims for the project.
![Page 160: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/160.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘05 ~ Jan, ‘06
(12 Months)
Project Name: Post-Construction Project Evaluation and Preparation of the Consultancy and Contract Completion Reports for the Addis Ababa-Goha Tsion Trunk Road Project
Location: Addis Ababa ~ Goha Tsion, Ethiopia
Brief Project Particulars/Description
This Terms of Reference for this assignment was to undertake Post-Construction Project Evaluation and Preparation of the Consultancy and Contract Completion Reports North-Western Corridor (Addis Ababa ~ Debre Markos ~ Gondar ~ Eritrean border), one of the most important trunk road that traverses the northwestern part of Oromia, Amhara and Tigre Regions, the highest agricultural producing areas of the country.
The main goals and objectives of carrying out these tasks is to as much
as possible, try to compile completion reports that would not only form
major reference material for the client but that would also be unique to
the pragmatic application of the engineering and technical theories,
concepts as well as design and construction principles and techniques.
The research oriented design and construction techniques developed and presented in these reports are generally tailored for developing countries with particular reference to the East and Central Africa region. The purposes of innovating such techniques and the practical application of the results emanating thereof is to realize structures in regard to cost-effectiveness, performance and environmental considerations. This is extremely important in the face of the facts that developing countries are constrained by lack of sufficient or necessary financial resources and technical capability. In the final remarks, the Consultant stated that It was his hope and
ultimate goal that the Consultancy and Contract Completion Reports
would form integral reference material for the development, review
and/or advancement of any future Standard Specifications and/or
Design Manuals to be considered by the client.
Position: Sr. Highway Engineer and Team Leader
Dr. Mukabi was part of the Team that made the final evaluation and compiled the Road Condition Inventory, which was included in the Reports making recommendations on the appropriate mode and time based maintenance requirements quantified in progressive terms.
![Page 161: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/161.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘05 ~ May, ‘05
(1.8 Months)
Project Name: Pre-Feasibility Study and Preliminary Engineering
Design for Mitigation Measures against Traffic
Congestion and Improvement Measures of Traffic
Safety in Addis Ababa City
Client: Addis Ababa City Roads Authority
Location: Addis Ababa, Ethiopia
Brief Project Particulars/Description
As any other major city in developing countries, Addis Ababa suffers its
share of traffic congestion, traffic management and traffic institution
accordingly.
Cognizant of the importance of the development of transport network in
Addis Ababa City, the Government of Ethiopia decided to conduct the
World Bank assisted “Urban Transport Study and Preparation of Pilot
Project for Addis Ababa”. The said Study proposes medium to long-
range urban transport development projects such as road improvement,
establishment of bus rapid transit system, construction of light rail
transit, etc., which require sizeable investments.
In this preliminary Study, the concentration was allotted to the physical
elements of the road transport infrastructure.
This Study was undertaken for purposes of securing finnce to facilitate
for a more comprehensive Study on Master Plan for the Addis Ababa
Metropolitan Urban Transport Network.
Some of the main components whose recommendations for
incorporation in the main Study were as follows.
1. Clear formulation of relevant objectives, plan components and
project cost analysis.
2. Plan evaluation addressing technical, economic and
environmental matters.
3. Implementation of Pre-Feasibility Studies for each of the main
components, simulation pilot projects and physical
infrastructure pilot projects.
Position: Sr. Highway Engineer and Team Leader
He led the Team in undertaking the study on the existing Road Network
of Addis Ababa, Current conditions of Bridge and Hydraulic Structures
and Initial Environmental Examination (IEE).
![Page 162: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/162.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ’05 ~ Oct,’05
(6 Months)
Project Name: The Study on Master Plan for Urban Transport in the Nairobi Metropolitan Area
Client: Japan International Cooperation Agency/Ministry of Roads & Public Works/Ministry of Local Government
Location: Nairobi, Kenya
Brief Project Particulars/Description
As most developing cities, Nairobi, the Capital city of Kenya and transportation hub for the East and Central African Region is also indeed faced with Urban Transportation problems mainly associated with population explosion, rapid increase in vehicle traffic and chronic congestion. In order to substantially alleviate some of these problems, and having recognized the transport sector as a facilitator of rapid economic growth, reconstruction, poverty eradication and wealth creation for the country, the Government of Kenya requested the Government of Japan for grant aid through the Japan International Cooperation Agency for purposes of undertaking comprehensive studies that would formulate an urban transport Master Plan for the Nairobi Metropolitan Area. The project mainly entailed the proposal of pragmatic solutions for the long-term period up to the Year 2025 as well as implementing Pre-Feasibility Studies (PFS) and Pilot Projects (PP) for the priority projects comprising predominantly of the construction of missing links and Non-Motorized Traffic (NMT) facilities, CBD traffic circulation plan and reciprocal improvement as well as the introduction a reform system for the Bus-Matatu Public transport, whilst carrying out technology transfer to Kenyan Counterpart Personnel during the course of the Study. The Master Plan, in its’ plan components and project costs, identified a number of projects and measures covering the transport sectors of road development, public transport, traffic management and traffic institution, and classified their urgency into Short, Medium and Long Term Strategic Implementation with the following main components: i) implementation of previously planned projects; ii) formulation of radial and circumferential road network (R/C Road Networks); iii) upgrading of existing rail road and network; and, improvement of Uhuru Highway.
Position: Chief Technical Advisor/Senior Highway & Geotechnical Engineer
Dr. Mukabi was assigned with the task of evaluating and reviewing the technical aspects of the Study and advising the JICA Study Team and Team Leader accordingly as well as managing the construction supervision of the pilot projects.
![Page 163: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/163.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘05 ~ August, ‘05
(3.4 Months)
Project Name: Feasibility Study and Preliminary Engineering Design for the Addis Ababa Urban Transport Network Development
Client: JICA/ERA/Addis Ababa City Roads Authority
Location: Addis Ababa, Ethiopia
Brief Project Particulars/Description
The Addis Ababa Urban Transport Network Development Study was urgently required to study and investigate the present condition of traffic and transport network and to establish short, medium and long-term plans for development of transport network including maintenance, rehabilitation and new construction projects based on the urban socio-economic development plans and the future traffic demand.
Position: Sr. Highway Engineer and Team Leader
Undertook the following studies among others: Road network of Addis Ababa, Current conditions of Bridge and Hydraulic Structures and Initial Environmental Examination, review of financial and economic analysis, cost estimates and preparation of Tender Documents.
June, ‘05 ~ Sept, ‘05
(3.5 Months)
Project Name: Preliminary Study of Southern Sudan Roads Network and Capacity Building
Client: Government of Southern Sudan (GoSS)
Location: Entire Southern Sudan
Brief Project Particulars/Description
The Study aimed to identify and formulate road network improvement
to be requested for development study and grant aid scheme under
Japan Official Development Assistance in the Southern Sudan.
Position: Deputy Project Manager/Senior Highway & Geotechnical
Engineer
Responsible for conducting present condition survey and data
collection, road and bridge inventory survey, evaluation of present road
network, formulation of future road network plan, preparation of road
maintenance and road construction plan, and formulation of the project
candidates, and preparation of TOR.
![Page 164: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/164.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec, ‘05 ~ Jan, ‘06
(1Month)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Mogotio ~ Marigat ~ Loruk (B4)
Trunk Road Section (92Km) under the EAC/NEPAD
Initiative for Regional Integration
Client: JICA/GoK/Mitsui Corporation
Location: Mogotio ~ Marigat ~ Loruk, Kenya
Brief Project Background/Particulars/Description
In consistency with the vision and development of Africa’s development
blueprint in the New Partnership of Africa’s Development (NEPAD), the
East African Community (EAC) Development Strategy 2001-2005
published in April 2001, states in part that “the vision of regional
integration is to create wealth, raise the standards of living of all
people of East Africa and enhance competitiveness through increased
production, trade and investments. Furthermore, having played a major
role in the peace negotiations between Northern and Southern Sudan,
the Government of Kenya recognized and understood the essence of
taking concrete action to harvest the dividends of peace through
regional cooperation and trade with South Sudan. It is in this light that
it initiated this Study with the cooperation of JICA and Mistui
Corporation to establish an alternative transit route to Southern Sudan
that would also contribute significantly to poverty eradication within
the impoverished areas on the Kenyan side.
The main objective of the Study was therefore:-
(i) To establish preliminary, existing road conditions of the alternative routes connecting to the Southern Sudan.
(ii) Undertake a basic comparative analysis of the existing traffic characteristics of the routes.
(iii) Undertake a basic socio-economic comparative analysis based on the existing and projected trends for areas through which these routes traverse.
(iv) Determine the fundamental needs associated with the road improvement as may be anticipated by the local communities.
(v) Determine the global contribution of an enhanced regional network in basic terms.
The Fundamental goals in realizing such objectives
and undertaking would be:-
(a) Enhance transportation infrastructure and
![Page 165: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/165.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Dec, ‘05 ~ Jan, ‘06
(1Month)
The Fundamental goals in realizing such objectives and
undertaking would be:-
(a) Enhance transportation infrastructure and services on the Kenyan side for purposes of promoting trade between Kenya and Southern Sudan.
(b) Guarantee enhanced security within the two countries and along their borders culminating in the automatic promotion of trade, tourism and regional socio-economic interaction between the peoples.
(c) Promote Socio-economic development within the areas through which the road traverses.
(d) Attract and promote the interaction of the regional people in order to foster trade and cultural exchange with the aim of realizing enhanced peace, stability and sustainable economic growth.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present road network, formulation of future road network plan, preparation of road maintenance and road construction plan, formulation of the top priority project candidates, and preparation of the Application Form for Japan’s Grant Aid.
![Page 166: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/166.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘06 ~ Feb, ‘06
(1.5 Months)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Loruk ~ Tot ~ Marich Pass Trunk
(B4) Road Section (149Km) under the EAC/NEPAD
Initiative for Regional Integration
Client: JICA/GoK/Mitsui Corporation
Location: Loruk ~ Tot ~ Marich Pass, Kenya
Brief Project Background/Particulars/Description
The project background, particulars and description are similar to those
presented for the Mogotio ~ Marigat ~ Loruk Trunk Road Section.
Nevertheless, due to the general complexity of the Cherangani Hills and
the associated acute gradients (the altitude between Loruk and Tot, for
example, increased from 1200m a.s.l to 2400 a.s.l over a distance of
94Km), topography and hydrogeological features, more concentration on
the geometric alignment, geotechnical engineering and hydrological
study had to be made.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present road network, formulation of future road network plan, preparation of road maintenance and road construction plan, formulation of the top priority project candidates, and preparation of the Application Form for Japan’s Grant Aid. He was also given the responsibility of giving the Economic Experts technical and engineering guidance in determining the most cost-effective options which included the consideration of tunneling through the Cherangani Hills. However, the tunneling option was considered to be non-viable.
![Page 167: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/167.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘06 ~ March, ‘07
(15 Months)
Project Name: Emergency Study on The Planning And Support For Basic Physical And Social Infrastructure In Juba Town And The Surrounding Areas
Client: JICA/GoSS
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
The Study, which had three components of Pilot Projects (Infrastructure, Water Supply and Community Based Development) aims at mainly reviewing the present condition of the Study Area, preparing a simplified map, establishing Juba Town Development Strategy establishing a socio-economic framework, planning the distribution of urban functions zoning map, public facilities development plan, Ian use plan, planning of urgent rehabilitation/development projects preparation of design and bidding documents for the pilot projects, implementation and supervision of the pilot projects and preparation of a maintenance plan for the facilities constructed in the three Pilot Projects.
The summarized scope of the Pilot Project in the Infrastructure Sector (Juba River Port) mainly included:
Construction of a Berthing Facility on piled piers
Provision of a Cargo Handling Yard
Installation of a pier Facility and Overhead Rail crane
Installation of a Mooring Facility consisting of four bollards
Construction of a Storage Facility fully furnished with fuel, equipment, spare parts, tools storage and provision for miscellaneous items
Construction of a 590m long all weather access road with ample pavement structural capacity and drainage/hydraulic facilities, leading from the cargo handling yard to the arterial road network.
On the other hand, the summarized scope of the Pilot Project in the Water Supply Sector (Munuki Water Supply) mainly included:
Drilling of a minimum of 2 deep wells fully facilitated with submersible pumps to supply water to 2,300 people at the capacity of 13 ~ 20 liters per person per day
Installation of water reticulation pipes of a minimum total length of 1,330m
Installation of 8 public hydrants with a minimum of three tapping zones each
![Page 168: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/168.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Jan, ‘06 ~ March, ‘07
(15 Months)
The summarized scope of the Pilot Project for the Community Based
Development (Urban Livelihood Improvement) mainly included:
The establishment of two Executive Bodies that would
effectively administer skills Training Programmes
The establishment of two Training Centers mainly for carpentry,
masonry, plumbing, electrical wiring, motor vehicle
maintenance and repair, mechanical works, electrical
appliances repairs, woodwork, welding etc.
The establishment of appropriate Training Programmes
Ensuring the smooth and successful implementation of the
initial Training Programmes
Position: Chief Technical advisor/Chief Project Coordinator/Lead Researcher/Chief. Materials/Pavement & Geotechnical Engineer
Dr. Mukabi was mainly responsible for advising and assisting the Team Leader on the formulation of the Master Plan and Design, Implementation and Construction Supervision of the Pilot Projects and coordinating the Experts, GoSS officials, logistics, overall planning and integration of the various Sectors.
![Page 169: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/169.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Feb, ‘06 ~ March, ‘06
(0.5 Months)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Kapenguria ~ Marich Pass Trunk
(A1) Road Section (63Km) under the EAC/NEPAD
Initiative for Regional Integration
Client: JICA/GoK/Mitsui Corporation
Location: Kapenguria ~ Marich Pass, Kenya
Brief Project Background/Particulars/Description
The project background, particulars and description are similar to those
presented for the Mogotio ~ Marigat ~ Loruk Trunk Road Section.
Due to the frequent washout of the Sebit and Wakor Bridges as well
other hydraulic structures along this route mainly due to the Muruny
River, the study concentrated more on the technical aspects of river
crossings, geometric alignment, geotechnical engineering and
hydrology.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present road network, formulation of future road network plan, preparation of road maintenance and road construction plan, formulation of the top priority project candidates, and preparation of the Application Form for Japan’s Grant Aid. He was also given the responsibility of giving the Economic Experts technical and engineering guidance in determining the most cost-effective options of dealing with the geotechnical aspects of the river crossing section and recommended option of the bridge foundation designs.
![Page 170: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/170.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘06 ~ April, ‘06
(1.2 Months)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Marich Pass ~ Lokichar ~ Lodwar
Trunk (A1) Road Section (196Km) under the
EAC/NEPAD Initiative for Regional Integration
Client: JICA/GoK/Mitsui Corporation
Location: Marich Pass ~ Lokichar ~ Lodwar, Kenya
Brief Project Background/Particulars/Description
The project background, particulars and description are similar to those
presented for the Mogotio ~ Marigat ~ Loruk Trunk Road Section.
This section of the road is frequently interrupted with the crossing of
Lagas which are predominant in this area whose soils are mostly sandy
in nature. As a consequence, the study concentrated on topography and
hydrogeological features, the geometric alignment, geotechnical
engineering as well hydrological assessment, evaluation and analysis.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present road network, formulation of future road network plan, preparation of road maintenance and road construction plan, formulation of the top priority project candidates, and preparation of the Application Form for Japan’s Grant Aid. He was also given the responsibility of giving the Economic Experts technical and engineering guidance in determining the most cost-effective options which included the consideration of the laga crossings, soil stabilization and appropriate Value Engineering technologies for geomaterial stabilization and enhancement of pavement structural performance.
![Page 171: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/171.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘06 ~ Feb, ‘07
(12 Months)
Project Name: Comprehensive Evaluation of the Engineering
Implementation of the Emergency Study on
Planning and Support for Basic Physical and
Social Infrastructure in Juba and the
surrounding areas in Southern Sudan
Client: JICA/GoSS
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
The project involved analysis of the present and future conditions and
demand in physical and social infrastructure in Juba town and the
surrounding areas culminating in a Master Plan from reconstruction/
rehabilitation to the development of Juba town and the surrounding
areas.
A Pre-Feasibility Study (PFS) of a Juba Urban Transport Master Plan was
also undertaken this Study. Based on a preliminary Traffic Survey
conducted under this Study, the traffic evaluation and analysis took
into account the rapid increase in traffic volume and loading intensity
and the impact thereof and incorporated these parameters into the
proposed Transport Infrastructure Framework and predictive simulations
whilst identifying a number of projects and measures covering the
transport sectors of road development, public transport, traffic
management and traffic institution, and classified their urgency into
Short, Medium and Long Term Strategic Implementation with the
following main components: i) implementation of previously planned
projects; ii) formulation of radial and circumferential road network
(R/C Road Networks); iii) upgrading of existing Juba Town road
network; and, improvement of traffic flow and bottleneck areas.
Implementation of pilot projects in transport infrastructure, water
supply and community based development sectors were also carried out
as pilot projects.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi’s tasks mainly involved projection of Development Plan for
Juba town urban transport, evaluation of bridges and hydraulic
structures, and technical advisory on proposals for Feasibility Studies.
![Page 172: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/172.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘06 ~ May, ‘06
(0.8 Months)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Lodwar ~ Kakuma Trunk (A1)
Road Section (120Km)
Client: JICA/GoK/Mitsui Corporation
Location: Lodwar ~ Kakuma, Kenya
Brief Project Background/Particulars/Description
The project background, particulars and description are similar to those
presented for the Mogotio ~ Marigat ~ Loruk Trunk Road Section.
This section of the road had just been rehabilitated hence it was in an
appreciably good state. The study therefore concentrated on the
assessment, evaluation and analysis of the structural capacity and
serviceability level of the existing pavement structure.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present structural capacity and serviceability level.
![Page 173: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/173.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘06 ~ June, ‘06
(0.6 Months)
Project Name: Pre-Feasibility Study and Geotechnical Engineering
Assessment of the Kakuma ~ Lokichoggio Trunk
(A1) Road Section (95Km)
Client: JICA/GoK/Mitsui Corporation
Location Kakuma ~ Lokichoggio, Kenya
Brief Project Background/Particulars/Description
The project background, particulars and description are similar to those
presented for the Mogotio ~ Marigat ~ Loruk Trunk Road Section.
This section of the road had just been rehabilitated hence it was in an
appreciably good state. The study therefore concentrated on the
assessment, evaluation and analysis of the structural capacity and
serviceability level of the existing pavement structure.
Position: Lead Consultant/Team Leader/Chief Highway and
Geotechnical Engineer
Dr. Mukabi led the Study Team in establishing and designing present condition survey and data collection, road and bridge inventory survey, evaluation of present structural capacity and serviceability level.
June, ‘06 ~ June, ‘06
(0.3 Months)
Project Name: Preparation of Application Form for Japan’s Grant
Aid for the Construction of Sebit and Wakor Bridges
on the Kapenguria ~ Marich Pass Section Along A1
Client: GoK/Mitsui Corporation
Location Kapenguria ~ Marich Pass A1 Road Section, Kenya
Brief Project Background/Particulars/Description
The assignment involved the compilation of a justification Report and
Preparation of Application Form, on behalf of the Government of Kenya
(GoK), for possible Grant Aid funding from Japan for the Construction
of Sebit and Wakor Bridges on the Kapenguria ~ Marich Pass Section of
the A1 Road that traverses through Lodwar to Lokkichogio.
Position: Lead Consultant
Dr. Mukabi led the Study Team in the preparation of the stated Report and Application Form.
![Page 174: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/174.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘06 ~ June, ‘06
(0.3 Months)
Project Name: Preparation of Application Form for Japan’s Grant
Aid for the Construction of the Kapenguria ~ Marich
Pass Road Section Along A1
Client: GoK/Mitsui Corporation
Location Kapenguria ~ Marich Pass A1 Road Section, Kenya
Brief Project Background/Particulars/Description
The assignment involved the compilation of a justification Report and
Preparation of Application Form, on behalf of the Government of Kenya
(GoK), for possible Grant Aid funding from Japan for the Construction
of the Kapenguria ~ Marich Pass Section of the A1 Road that traverses
through Lodwar to Lokkichogio.
This was considered a vital initiative under the East Africa Road
Network Programme since the Kapenguria ~ Marich Pass ~ Lodwar ~
Kakuma ~ Lokichoggio is the only link to South Sudan via Torit to Juba.
Position: Lead Consultant
Dr. Mukabi led the Study Team in the preparation of the stated Report and Application Form.
July, ‘06 ~ Dec, ‘06
(5.8 Months)
Project Name: Implementation of the Pilot Projects in Juba Town
Client: JICA/GoSS
Location Juba, Southern Sudan
Brief Project Background/Particulars/Description
The project involved implementation of the Pilot Projects under the
Emergency Study on Planning and Support for Basic Physical and
Social Infrastructure in Juba and the surrounding areas in Southern
Sudan.
Position: Projects Manager/Chief Highway and Geotechnical Engineer
Dr. Mukabi was assigned to oversee the Implementation of pilot projects
in transport, water supply and community based development.
![Page 175: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/175.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘06 ~ Sept, ‘07
(11 Months)
Project Name: Juba River Port Access Road Detailed Engineering Design and Construction Supervision Project
Client: JICA/GoSS
Location Juba, Southern Sudan
Brief Project Background/Particulars/Description
Due to the gross lack of suitable pavement construction material, the project involved comprehensive research to develop appropriate and suitable Value Engineering Technologies, Basic Design Study, Detailed Design Study rehabilitation of the existing road, in part and construction of new sections of the access road that serves the port of Juba. Subsequently, a versatile research report and a comprehensive engineering report on the overall study, design study and method of construction of the project road was compiling, including innovative methods of construction through the application of value engineering and state of the art standards.
Position: Project Manager/Lead Consultant & Researcher/Team Leader/Chief Pavement and Geotechnical Engineer
The tasks undertaken by Dr. Mukabi included design of the Research and Development (R&D) Regime, Detailed Engineering Design; Capacity building in terms of training of manpower in general, lab technicians on testing methods and quality control; and Inspectors for Construction Supervision.
![Page 176: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/176.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Nov, ‘06 ~ July, ‘07
(9 Months)
Project Name: Comprehensive Engineering and Geo-materials
Science Research for the Development of
Appropriate Value Engineering Technologies for
the Wau ~ Abyei Trunk Road Project
Client: United Nations World Food Programme (UN-WFP)
Location: Wau ~ Abyei, Southern Sudan
Brief Project Background/Particulars/Description
This Project was formulated, designed and implemented as the preparatory Phase of the “Consultancy Work Supervision Of Emergency Road Repairs In South Sudan – Phase 3” WFP required basic road infrastructure to facilitate efficient delivery of
requisite goods and services to target such populations. It is against this
background that UN-WFP is implementing Emergency Road Repair Works
in the Western Corridor of Southern Sudan. Several road links have been
targeted for improvement including the trunk road from Wau to Abyei.
This phase of the Project basically involved comprehensive geotechnical and hydrological investigations, research and development of appropriate Value Engineering Technologies, designs, systematic-time-effective methods of construction and advanced QC Programmes. Furthermore, due to the fact that the main Project would be implemented as a research based design comprehensive monitoring systems that would consistently confirm achievement of the required results were also developed during this Study.
Position: Lead Researcher/Team Leader The specific tasks assigned to Dr. Mukabi included:
Overall management and coordination of the research programme
Innovation of unique engineering solutions for problematic soils and countermeasures for lack of suitable road and foundation construction material
Developing research based methods to foster Value Engineering that would achieve and enhanced pavement and foundation structures at fostering effectiveness in costs and construction time
Developing new and advanced Quality Control methods
Developing appropriate maintenance programmes and systems
Simulating depreciation in structural capacity under the influence of varying environmental conditions and prolonged and intensified loading.
![Page 177: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/177.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Nov, ‘06 ~ July, ‘08
(21 Months)
Project Name: Consultancy Work Supervision Of Emergency Road Repairs In South Sudan – Phase 3
Client: United Nations World Food Programme (UN-WFP)
Location Wau ~ Abyei, Southern Sudan
Brief Project Background/Particulars/Description
The Project, which basically involved an emergency components for food, medicine and other supplies besides opening up trading and other social links for the 237Km Wau ~ Abyei Trunk Road, entailed various tasks partially including Feasibility Studies, Research & Development in order to identify suitable Value Engineering Technologies that would be cost-effective and easy to apply, Basic Design Studies, Detailed Design Studies as well as Project Formulation and Construction Supervision. The basic idea was to establish accessibility whilst designing and constructing a road pavement structure that could form a stable and strong foundation for future upgrading to bitumen standards. The Geotechnical and Hydrological conditions were extremely challenging given the existence of large flood plains hence the need for the design of long stretches of causeways totaling to more than 60Km. This could only be solved through rigorous Research, Surveys and thorough investigations which were undertaken and appropriate countermeasures developed accordingly.
Position: Project Manager/Senior Materials, Pavement & Highway Engineer/Research Team Leader for:
Overall project management and supervision
Detailed Design Study and Construction Supervision
Implementing the unique engineering solutions developed in the initial phase for problematic soils and countermeasures for lack of suitable road construction material
Implementing the research based methods developed in the initial phase to foster Value Engineering that would achieve and Enhanced Pavement Structure at Reduced Costs and Construction Time
Undertaking Capacity building and Training Programmes for young Southern Sudanese Engineers and other Personnel
Applying the newly Developed unique and advanced Quality Control methods
Applying the appropriate maintenance programmes and systems
Developing appropriate and suitable monitoring systems and programmes based on practical as-built technical factors that would ensure the sustenance of the required standards.
![Page 178: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/178.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Feb, ‘07 ~ Aug, ‘07
(6.8 Months)
Project Name: Transport Infrastructure Development Project - Leer~Adok Trunk Road and Port Project
Client: Governor’s Office/Ministry of Physical Infrastructure and Planning
Location: Bentiu, Unity State, Southern Sudan
Brief Project Background/Particulars/Description
The Leer~ Adok Trunk Road is Located in the oil rich Unity State and traverses South-easterly From Leer to Adok through Flood-prone areas characterized by problematic soils and swampy zones. The road is approximately60km in length connecting the hinterland to the White Nile, which is an important waterway for transporting goods and persons to Khartoum and Juba. The State of Unity, being faced with major logistical and transport problems, required solutions that are Value Enfineering based, i.e., structurally sound yet cost-time-effective. Considering that the country is still rehabilitating and reconstructing, no formal transport routes are available that are economically viable fore importing the much needed and lacking goods. It was established that the alternative for importing such essential goods as cement, construction materials, and other necessities, was to use the Nile river after the goods are delivered in Juba from Kenya. In his case, the cost of goods would translate to more than 300% of the cost in Kenya. The logistical alternative of using the river would cut down the cost drastically. Once the goods arrive at Adok port, they would need a good road to transport to Bentiu, the main town and thus the project to develop the Leer~Adok Trunk Road connecting to the Main Trunk Road to Bentiu and the Adok River Port. Fundamentally, the project involved a Pre-Feasibility Study, within comprehensive geotechnical and hydrogeological investigations as well as preliminary design studies and basic topographic survey mainly for preliminarily determing suitable and proper horizontal and vertical alignment. Preliminary Proposals for Standard Penetration Testing regimes, sounding and geophysical investigations for the design of the Adok River Port foundation design and construction were within this Study.
Position: Lead Consultant/ Team Leader/Chief Highway/Pavement/Geotechnical/Materials Engineer
Dr. Mukabi was assigned to oversee the Geotechnical Investigation; Geological Study; Soil and Ground Survey; Topographical Survey; Pre-Feasibility Study; and Material Testing in the project area.
![Page 179: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/179.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘07 ~ April, ‘07
(1.6 Months)
Project Name: Technical and Engineering Study for Determination
of Suitable and Pragmatic Project Mitigation
Measures for the Cost-Time-Effective
Implementation of the Wau ~ Abyei Trunk Road
Project
Client: United Nations World Food Programme (UN-WFP)
Location Wau ~ Abyei, Southern Sudan
Brief Project Background/Particulars/Description
The Wau ~ Abyei Trunk Road is characterized by various and complicated technical and engineering challenges. The existence of long stretches of flood areas and causeways totaling to more than 60Km coupled with the lack of suitable construction materials and predominance of problematic subgrade materials necessitated the review of the prevailing conditions in order to determine suitable and pragmatic mitigation measures that would realize the expeditious and cost-time effective implementation of the Project. Due to the foregoing, this Study was designed and implemented under “Urgency Status” whereby the following main conclusions were drawn.
1. Lack of suitable construction geomaterials, geological and hydrological complexities and stringent environmental constraints were practically evident.
2. Due to lack of suitable construction geomaterials, the Contractor had been forced to haul materials over long distances as far as 31 ~ 35Km culminating in exorbitant unit costs and overly slow construction progress.
3. In the absence of the expeditious providence of appropriate technical and engineering solutions, the Contractor would be justified to submit claims for variation in price and Extension of Time (EoT), which would continue to escalate and prolong respectively.
Based on the foregoing conclusions, the Study recommended that a research based materials investigation and geotechnical engineering study be undertaken to improve the engineering properties and performance of the readily available geomaterials within 5Km Haulage.
Position: Lead Researcher/Team Leader Dr. Mukabi was charged with the responsibility of designing and developing a unique research regime and investigation and testing programmes that could be implemented immediately to realize applicable results within the shortest period possible.
![Page 180: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/180.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘07 ~ May, ‘07
(2.9 Months)
Project Name: Comprehensive Geotechnical and Hydrological
Investigations and R&D of Value Engineering
Technologies for the White Nile oil Exploration
Project in South Sudan
Client: White Nile Oil Exploration Co./GoSS
Location: Jonglei Flood Plains, Southern Sudan
Brief Project Background/Particulars/Description
This Project was formulated, designed and implemented under the
“Project for Engineering Design for Pad Foundations for Oil Drilling Rigs,
Access Roads, Airstrip and Base Camps for the White Nile oil Exploration
Project in South Sudan
Due to its logistical and contractual urgency, lack of suitable construction materials, complex ground conditions, existence of thick layers of problematic soils (Black Cotton Soils) and the daily losses of
approximately £120,000 (One Hundred and Twenty Thousand Pounds), it was imperative that the Project be implemented expeditiously. This phase of the Project basically involved comprehensive geotechnical and hydrological investigations, research and development of appropriate Value Engineering Technologies, designs, systematic-time-effective methods of construction and advanced QC Programmes. Furthermore, due to the fact that the main Project would be implemented as a research based design comprehensive monitoring systems that would consistently confirm achievement of the required results were also developed during this Study.
Position: Lead Researcher/Team Leader The specific tasks assigned to Dr. Mukabi included:
Overall management and coordination of the research programme
Innovation of unique engineering solutions for problematic soils and countermeasures for lack of suitable road and foundation construction material
Developing research based methods to foster Value Engineering that would achieve and enhanced pavement and foundation structures at fostering effectiveness in costs and construction time
Developing new and advanced Quality Control methods
Developing appropriate maintenance programmes and systems
Simulating depreciation in structural capacity under the influence of varying environmental conditions and prolonged and intensified loading.
![Page 181: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/181.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘07 ~ Nov, ‘07
(8.7 Months)
Project Name: Engineering Design for Pad Foundations for Oil
Drilling Rigs, Access Roads, Airstrip and Base
Camps for the White Nile oil Exploration Project
in South Sudan
Client: White Nile Oil Exploration Co. Ltd./GoSS
Location: Sudd Flood Plains in Jonglei, Jale, Southern Sudan
Brief Project Background/Particulars/Description
The flagship project was the 67,000sq km Block Ba located in the
Jonglei Flood Plains of Southern Sudan, an area equivalent to
approximately 28 UK North Sea blocks or 11 UK North Sea quadrants.
White Nile in partnership with the Government of Southern Sudan had
planned an ongoing exploration and development programme for Block
Ba, which included drilling a minimum of two exploration wells in 2007
during the dry season. The services of the engineering consultancy in
this phase of the Project included design and construction supervision of
airstrips, access roads, additional pads and general civil engineering
structures. The main objective was to provide expeditious engineering
solutions to the problematic soils related Pad Foundation Design for the
drilling rig which was set for mounting in Jale, geographically located in
the Sudd Flood Plains of Southern Sudan. The urgency of this Project
required that quick impact engineering solutions be provided to
determine cost-effective measures. Based on some recently developed
enhanced scientific theories and engineering concepts, comprehensive
testing and analysis were carried out with as much precision as possible
and a remarkably stable pad foundation and related structures were
designed and constructed expeditiously realizing more than 40% cost
savings, 220% time savings whilst the bearing capacity, strength,
deformation resistance were enhanced by more than 1.8 times.
Position: Chief Technical Advisor
Overall project management and supervision
Detailed Design Study and Construction Supervision
Undertaking Capacity building and Training Programmes for young Southern Sudanese Engineers and other Personnel
Developing new and advanced Quality Control methods
Developing appropriate maintenance programmes and systems
Simulation of the structural capacity under the influence of varying
environmental conditions and prolonged and intensified loading.
![Page 182: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/182.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
July, ‘07 ~ Sept, ‘09
(2.4 Months)
Project Name: Research And Development Study For Affordable Housing For East And Central Africa
Client: Geotechnologies East Africa
Location: Juba, Southern Sudan/Nairobi, Kenya
Brief Project Background/Particulars/Description
Through the application of a combination of Tensar geo-products OBRM AND OPMC VE technologies which are research oriented applying material science, structural and geotechnical engineering concepts, and other Innovative technologies, the project was designed to realize cost-effective and Value Engineering based building construction materials and appropriate foundation engineering techniques for problematic soil conditions such as black cotton soils. The research and development (R&D) study regime was also designed to develop technologies that reduce the use of cement and size of concrete structural elements.
Position: Lead Researcher/ Chief Technical Advisor Main tasks included Undertaking Project Conceptualization; designing mode of Project implementation; determining necessary outputs; and, Developing Enhanced Structural Engineering Technology.
Aug, ‘07 ~ Oct, ‘07
(2.8 Months)
Project Name: Ntare~Rushatsi Boulevard Project for Pavement Rehabilitation on City Roads, Bujumbura
Client: JICA/Government of Burundi
Location: Bujumbura, Burundi
Brief Project Background/Particulars/Description
The project involved conducting a study in the works of NR 7 rehabilitation (NTARE RUSHATSI Boulevard). A detailed geotechnical investigation study was conducted with materials testing conducted at the National Laboratory of Building and Public Works “L.N.B.T.P” various tests including Dynamic Penetrometer , Granulometric analysis, among other innovative and standard tests. The main purpose was to determine the correct ratios for application of the Optimum Batching Ratio Method (OBRM) and OPMC VE technologies.
Position: Team Leader/ Chief Materials & Geotechnical Engineer Mainly responsible for designing the innovative testing and geotechnical investigation regimes and approving the OBRM and OPMC.
![Page 183: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/183.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Aug, ‘07 ~ May, ‘08
(8.5 Months)
Project Name: Detailed Scoping and Civil Engineering Study of
Various Aspects of the Lainya ~ Jambo Trunk Road
Client: Ministry of Transport & Roads (MoTR), Government of South Sudan (GoSS)
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
For purposes of determining technical impediments and geotechnical
engineering, topographic and environmental complexities, in order to
make it passable through spot and false repairs, a Detailed Scoping and
Civil Engineering Study along the 110Km Lainya ~ Jambo Trunk Road
which was otherwise in extremely poor conditions rendering it
dangerous and impassable to all kinds of traffic.
The scoping and engineering study entailed various tasks including compilation of a comprehensive scoping inventory of the road bed conditions, type of soils, environmental and climatic factors, vegetation, water bodies and the corresponding characteristics, missing links, types, conditions and sizes of bridge and other hydraulic structures, condition of approaches, soil profiles, gradients, road width, and other pertinent and relevant factors.
Detailed Scoping and Preliminary Engineering Reports were compiled at every 5Km intervals from the connection to the Yei ~ Juba International Trunk Road at Lainya to the vital Juba ~ Mundri Trunk Road at Jambo, enabling detailed reviews to be carried out and improvements made prior to proceeding to the next section.
Young Southern Sudanese Engineers, Surveyors, Inspectors and other Personnel were involved in this assignment as part of Capacity Building and Technical Transfer initiatives.
Position: Team Leader/Civil Engineer Dr. Mukabi was charged with the responsibility of developing the guidelines, Terms of Reference and Scope of Works of the Detailed Scoping and Civil Engineering Study, leading the Study Team through the tasks and providing guidance for various other technical and related aspects including reporting.
![Page 184: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/184.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept, ‘07 ~ Nov, ‘07
(2.6 Months)
Project Name: Comprehensive Hydrogeological Study for Lainya ~
Jambo Trunk Road
Client: MoTR, Government of South Sudan (GoSS)
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
The Lainya ~ Jambo Trunk Road traverses two States, namely; Central
Equatoria and Western Equatoria. The climate of this region is
equatorial with an annual average precipitation level of 1500mm and
temperatures of between 26°C and 36°C. The vegetation is still
predominantly virgin densely populated with indigenous trees, thick
bushes, bamboo forest and mainly tall reedy trees grass. The soils along
the corridor mainly consist of a combination of Ferralsols-Nitisols,
Phaeozems and Flurisols and are eutric all along the corridor, gleyic-
umbric with ferric from Lainya to Wonduruba and rhodic-ferric with
gleyic-umbric for the rest of the stretch up to Jambo. The whole road
corridor is interspersed with Lithic soil sections.
This Study basically involved comprehensive geotechnical and hydrological investigations as well as preliminary Initial Environmental Examination (IEE), including collection, collation, gathering and recording of data and information to facilitate evaluation and/or analysis of parameters related to flow rates, water level variations within water courses, channels, rivers and other water bodies, debri lines, precise catchment sizes, type of soils, land use and characteristics as well as other relevant data and information. During the Study, intensive scoping, soils testing, in-situ measurements and evaluation as well as other field surveys were undertaken.
This Study formed the basis of the design of Bridges and other hydraulic structures along with some basic recommendations derived from the preliminary IEE which had been undertaken.
Position: Team Leader/Chief Geotechnical Engineer Dr. Mukabi’s main task was to design the investigation regime and programme and provide guidance to the Study Team accordingly.
![Page 185: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/185.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept, ‘07 ~ Nov, ‘07
(2.8 Months)
Project Name: Study on the Enhancement of the Subgrade Structural
Performance for Lainya ~ Jambo Trunk Road
Client: MoTR, Government of South Sudan (GoSS)
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
Due to the existence of poor soils, problematic geomaterials, the gross
deteriorated road bed conditions, missing links and non-existence of
road pavement in long stretches of sections of the road based on the
results from the “Detailed Scoping and Civil Engineering Study of
Various Aspects of the Lainya ~ Jambo Trunk Road”, it was decided
that a “Study on the Enhancement of the Subgrade Structural
Performance for Lainya ~ Jambo Trunk Road” be undertaken
expeditiously.
This Study basically involved comprehensive geotechnical and soils investigations. Sampling of alignment and road bed soils was carried out to an average depth of 1m and in-situ dynamic penetration tests undertaken at the sampling locations which were designated at 200m intervals staggered between RHS/CL/LHS along the entire 110Km of the Road corridor. During the Study, intensive scoping, soils testing, in-situ measurements and evaluation as well as other field surveys were also undertaken in areas that were considered complex and problematic.
This Study formed an integral basis of the pavement structural design. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining Value Engineering Ground Improvement (GI) techniques.
Employment of these technologies realized average cost savings of approximately 56% in the earth works depending on the existing road and soil conditions, topography and hydrogelogical factors.
Position: Lead Consultant/ Team Leader/Lead Researcher Dr. Mukabi’s main task was to design and develop the detailed components of the Study and providing guidance to the Study Team and establishing the Particular Specifications and Guidelines for the innovative Ground Improvement (GI) techniques.
.
![Page 186: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/186.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept, ‘07 ~ Nov, ‘08
(14 Months)
Project Name: Gravel Road Rehabilitation Works for Lainya ~ Jambo
Trunk Road
Client: MoTR, Government of South Sudan (GoSS)
Location: Juba, Southern Sudan
Brief Project Background/Particulars/Description
The Lainya ~ Jambo is a 110Km Trunk Road that traverses two States
that have enormous potential of agriculture and the development of
various agro-industries. Most of the areas within the two States,
namely; Central Equatoria and Western Equatoria are also densely
forested with indigenous trees. These States can certainly be developed
into a food basket for the East and Central African Region and are
therefore set to contribute immensely to the socio-economic
development of the country.
The Project Road, which connects to the Yei ~ Juba International Trunk
Road at Lainya to the vital Juba ~ Mundri Trunk Road at Jambo, was also
a lifeline for the SPLA during the 21 years of conflict enabling them to
transport goods, personnel and other necessities to the Western and
Northern parts of Southern Sudan including Rumbek, which was then the
headquarters of the SPLM/SPLA. As a consequence, it was designated as
one of the top most priority roads for development within the
Infrastructure Development Programme of the GoSS.
The Project entailed various tasks including comprehensive scoping, preliminary Feasibility Studies, Research & Development in order to identify suitable Value Engineering Technologies that would be cost-effective and easy to apply, Basic Design Studies, Detailed Design Studies and Construction Supervision.
Position: Project Director/Team Leader/Chief Highway/Pavement/ Materials /Geotechnical Engineer
Dr. Mukabi’s main tasks for this Project involved:
Overall project management and supervision
Providing guidance for Detailed Design Study, Quality Control, Construction Supervision, Maintenance and Technology Transfer
Providing guidance for the application of the unique engineering solutions developed in the initial phase for problematic soils and countermeasures for lack of suitable road construction material
Implementing the research based methods developed in the initial phase to achieve Value Engineering Pavement Structures.
![Page 187: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/187.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘07 ~ Oct, ‘07
(0.8 Months)
Project Name: Evaluation of Contractor’s Contractual Claims for
Extension of Time for the Construction of the Wau ~
Abyei Trunk Road Project
Client: United Nations World Food Programme (UN-WFP)
Location: Wau ~ Abyei, Southern Sudan
Brief Project Background/Particulars/Description
Wau – Abyei Road Project falls under Phase 3 of the Emergency Road
Repairs in South Sudan. The Contract was awarded to Civicon Limited as
the Contractor and Katahira and Engineers International as the
Consultant. Both teams have henceforth embarked on the ground to
facilitate the completion of the project within the limited contract
duration.
However, the project had been faced with various engineering and
physical factors which offer major challenges to this important road
link. Nevertheless, the Contractor continued to carry out works despite
the fewer daily tipper trips which were being realised as a result of the
increased hauling distance. By the end of July 2007, haulage distance
had reached 31 kilometers and is expected to stop at km 35 (Gogrial
town from Junction to Civicon Base Camp at Kuajok). As a
countermeasure, the Contractor on his part had mobilized additional
dumping trucks and by the end of the month, a total of nineteen
tippers were operational. This effort notwithstanding, the project was
behind schedule with only 41.2% of the Value of works executed against an
anticipated 86.8% as at the end of July 2007.
A detailed Assessment, review and analysis of the Contractor’s Claims
was undertaken based on the Terms and Conditions of Contract entered
into and signed on the 21st day of September 2006 between the Client
(United Nations World Food Programme) and the Contractor (Civicon
Limited) is undertaken and the results reported herein accordingly.
The Consultants have recommended an award of 114 days Extension of
Time to the Contract period.
Position: Claims Engineer Dr. Mukabi was charged with the overall responsibility of contractually evaluating the Contractor’s Claims and providing the necessary recommendations accordingly.
![Page 188: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/188.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘08 ~ March, ‘08
(2.7 Months)
Project Name: Preliminary Transport Infrastructure Development
Study for Malakal Town
Client: Governor’s Office/Ministry of Physical Infrastructure and Planning
Location: Malakal Town, Upper Nile State, Southern Sudan
Brief Project Background/Particulars/Description
Malakal is one of the major towns located along the White Nile within
the Upper Nile State. As is the case with most of the towns in Southern
Sudan, Malakal was utterly destroyed and progressively dilapidated
during the 21 year conflict with the North.
The assignment involved preliminary assessment and evaluation of the
present conditions and hypothetical projection of future conditions and
demand in physical and social infrastructure in Malakal town and the
surrounding areas.
A very basic and provisional White paper Master Plan Proposal was
derived delineating the fundamental processes of reconstruction/
rehabilitation to the progressive development of Malakal town and the
vicinity. No detailed studies were undertaken.
Preliminarilly, the project involved a very basic Pre-Feasibility Study, geotechnical and hydrogeological investigations as well as preliminary design studies for selected areas and sections of roads.
Preliminary Proposals for Standard Penetration Testing regimes, sounding and geophysical investigations for the design of a River Port foundation were also part of the Terms of Reference of this Study.
However, not all components of the Study were carried out due to lack of sufficient funding.
Position: Lead Consultant/Team Leader/Chief Highway /Pavement/Geo-technical/Materials Engineer
Dr. Mukabi was assigned to oversee and lead the Study Team in developing the preliminary Master Plan, and undertaking the Pre-Feasibility Study, Geotechnical Investigation, Geological Study, Soil and Ground Survey, Topographical Survey, and Material Testing within the designated project area.
![Page 189: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/189.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Feb, ‘08 ~ April, ‘08
(2.3 Months)
Project Name: Engineering Study on the performance of Tensar
Geogrids with Local Soils for Mukurweini-Gakonya
and Rutune-Mahuani Roads Project
Client: Ministry of Roads
Location: Nyeri/ Murang’a Districts, Central Province, Kenya
Brief Project Background/Particulars/Description
The Mukurweini-Gakonya road consists of roads D429 and E559 and starts
at Mukurweini Market, and ends at Gakonya Junction with Murang’a-
Sagana road (C73). This project road transverses in a north easterly
direction towards Nyeri town and have a total length of 26Km. Rutune
Bridge (Mboiro Bridge) – Mahuani road (E554) transverses in north
westerly direction and has a length of 40Km. the total length of the
Project Roads is approximately 31Km and located in Murang’a and Nyeri
Districts of the Central Province.
The main objectives of this Study were to: i) determine the engineering
performance of the Geogrid reinforcement within pavements of varying
layer configurations; ii) characterize the combined performance of the
OBRM, OPMC and Geogrid reinforcement technologies ii) determine the
cost-time effectiveness through the application of these technologies;
and, iii) determine the degree of enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings. Position: Lead Researcher/Team Leader/Chief Geotechnical and
Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 190: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/190.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘08 ~ April, ‘08
(0.7 Months)
Project Name: Evaluation of Contractor’s Contractual Claims for the Construction of the Gravel Road Rehabilitation Works for Lainya ~ Jambo Trunk Road
Client: MoTR, Government of South Sudan (GoSS)
Location: Lainya ~ Jambo, Southern Sudan
Brief Project Background/Particulars/Description
The 110Km Lainya ~ Jambo Trunk Road traverses rolling to hilly country
with numerous seasonal streams and lagas. Notification of the award
was conveyed to the Contractor, Payii Roads & Bridges Company, by the
Ministry of Transport & Roads of the GoSS on 29th May 2007, signed on
the 8th of August 2007 and awarded on the 18th of August 2007. The
Contractor mobilized expeditiously within two days and commenced
works on 20th August 2007.
The Road Project was basically a Design & Build Contract whose
pavement structure was to be designed and constructed to a structural
capacity whereby it could be upgraded to bitumen standards with
minimal additional costs.
One of the main problems with this Project is that no studies
whatsoever had been undertaken to determine its feasibility, design and
construction Bills of Quantities (BoQs) or any other requirements. A
variation in the Scope of Works, quantities and construction time had
therefore been anticipated.
In view of this status, Kensetsu Kaihatsu Limited were appointed the
Consultants by the MoTR and seconded by the Contractor on the basis of
their vast experience in similar contracts in Southern sudan.
Based on the foregoing facts, the Consultants, within 3 days of
commencement of works, embarked on Comprehensive Scoping and
emergency Topographic Survey mainly of the vertical and horizontal
alignments as priorities. This field exercise, which started from PK
0+000 in Lainya Town at the junction of Juba ~ Yei and Lainya ~ Jambo
Trunk Roads and ended in Jambo Town at the junction of the Lainya ~
Jambo and Juba ~ Mundri Trunk Roads, was completed within 1.4
Months on 8th October 2007.
![Page 191: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/191.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
April, ‘08 ~ April, ‘08
(0.7 Months)
The assignment basically entailed the following as the main tasks.
Multi-component GPS Measurements
Geometric and Topographic Condition Survey
Land/Mapping Survey
Road Condition Survey
Geotechnical/Soils Condition Survey
Hydrological Conditions Survey
Hydraulic Structures Survey
Assessment and Evaluation of the existing Pavement Structure
Preliminary Initial Environmental Examination
Subsequently, an “Engineering Justification Report on Revision of Bill
of Quantities and Program Scheduling” was compiled and submitted to
the Client within four days of completion of the field exercise on 12th
October 2007. After detailed analysis and evaluation of the data,
information and results of the comprehensive scoping and surveys, the
“First Scoping and Engineering Report Based on the Scoping Inspection
and Revision of Bills of Quantities” was compiled and submitted to the
Client on 2nd November 2007.
This Study identified the following issues which constituted the main
components of the Contractor’s Contractual Claims.
1. The sources of clean surface water to be used for construction
purposes were very scarce particularly due to the drying up of
the streams and lagas during the dry season.
2. Accessibility to material sources was rather distant and complex
due to lack of existing tracks.
3. The width of the design Road carriageway of 9m was insufficient
for almost 55% of the entire road length.
4. The bush clearing and grubbing works would increase by
approximately 43%.
5. The quantities of the earth works would increase by about 58%
due to additional volume of the increased elevation of
embankments above the abutting land particularly through flood
plains and river valleys.
6. Increase in quantities and sizes of hydraulic structures.
7. Increased drainage works due to the rehabilitation of bridges,
construction of box culvers, excavation of mitre drains, slope
protection, stone pitching and installation of gabions.
![Page 192: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/192.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
April, ‘08 ~ April, ‘08
(0.7 Months)
Upon presentation of the matter to the Client by the Consultant, it was
mutually agreed that the Contractor compiles and submits a Contractual
Claims Report for the various claims components including Extension of
Time (EoT).
A detailed Assessment, review and analysis of the Contractor’s Claims
was undertaken based on the Terms and Conditions of Contract entered
into and signed on the 8th day of August 2007 between the Client and
the Contractor) was undertaken and the results reported to the Client
accordingly.
The Consultants made the appropriate recommendations and the Client
consented to an award of the claimed components and Extension of
Time to the Contract period in favor of the Contractor.
Position: Claims Engineer Dr. Mukabi was charged with the overall responsibility of advising both
the Client and the Contractor, contractually evaluating the Contractor’s
Claims and providing the necessary recommendations accordingly.
![Page 193: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/193.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘08 ~ May, ‘08
(1.2 Months)
Project Name: Investigation of Pavement Structural Capacity,
Strength and Deformation Resistance of the
Thogoto ~ Gikambura ~ Mutarakwa Road
Client: Ministry of Roads
Location: Central Province, Kenya
Brief Project Background/Particulars/Description
The Thogoto-Kamangu-Mutarakwa (D411) road lies to the North West of
Nairobi in the Central Province of the Republic of Kenya. The road lies
in Kiambu District. The start of the road is at the junction with the
Nairobi-Kikuyu Road just before the Kikuyu Campus of the University of
Nairobi. It continues westwards through Thogoto, Gikambura Lusigeti,
Kamangu market centres and ends at Mutarakwa market off B3 (Nairobi-
Mai Mahiu) road.
The overall objective of the Study was to establish the actual existing
geotechnical problems including slope stability, the hydrogeological
conditions and engineering impediments that could culminate in slow
progress and cost in-effectiveness rendering the Contract non-viable.
The specific objectives of the Study were:
1) To undertake a Comprehensive geotechnical soil and
materials study of the Thogoto~Gikambura~Mutarakwa
Road.
2) To comprehensively review the original design in relation to
the soils, materials and geotechnical engineering aspects.
3) To determine the ground stability through comparative
analysis of cut and fill areas along the Project Road.
Kensetsu Kaihatsu Consultants were commissioned to undertake an
investigation to determine the pavement structural capacity, strength
and deformation resistance of the newly constructed Subbase course as
well as that of the composite structure of the
Thogoto~Gikambura~Mutarakwa Road.The assignment mainly included
the following tasks:
i) Undertake Site Surveys and Investigations.
ii) Analysis and assessment of the test data carried out in
Kenya.
iii) Carry out material investigation, sampling and testing
for the proposed 600m long road alignment.
![Page 194: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/194.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
April, ‘08 ~ May, ‘08
(1.2 Months)
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Team Leader/Chief Highway/ Pavement/Geotechnical/Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study
Team, develop the Testing and Investigation Regime, establish and
provide Guidelines for unique and innovative Geotechnical
Investigation, Geological Study, Soil and Ground Survey, and Material
Testing from which he was to derive Special Specifications.
![Page 195: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/195.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘08 ~ May, ‘08
(1.3 Months)
Project Name: Engineering Study on the performance of Tensar
Geogrids with local soils for Kisumu Airport
Expansion Project.
Client: GEA/Tensar International, England/ Kenya Airports Authority
Location: Kisumu, Kenya
Brief Project Background/Particulars/Description
The site is located at Kisumu Airport on the shores of Lake Victoria in Western Kenya. Kisumu is located approximately 300Km northwest of Nairobi, on the eastern shore of L. Victoria. The airport is located 5Km to the west of Kisumu town along the Kisumu-Busia road. At the time, the airport handled domestic traffic, which operated up to 6 domestic flights only per day and served the western Kenya region, covering Nyanza, Western and Central Rift Valley Provinces. The major civil works included:
i) Extension of the runway by approximately 1,000m × 45m (45,000m2) comprising of granular and cement treated pavement layerworks and asphalt concrete wearing course
ii) Construction of new 42,000m2 Portland Cement Concrete Turnpads
iii) Reconstruction and widening of the existing 2000m (90,000m2) Runway
iv) Construction of 45,000m2 of a new Parking Apron in 105,000m2 of Asphalt Concrete and 70,000m2 of Portland Cement Concrete
v) Construction of a new 5,000m2 taxiway in granular pavement layerworks and asphalt concrete
vi) Bulk earthworks for the establishment of the platform formation for a new 3,000m2 one storey terminal buiding
vii) Construction of a new 3,500m2 grade vehicle parking viii) Construction of a Passenger Terminal Access Road from the
main road ix) Rehabilitation of the existing CFR road, including the re-use
of recycled asphalt product x) Installation of a 10,000m perimeter high security chain link
fence and gates around the airport xi) All drainage works including an oil separator drain, and
other associated infrastructure for the above xii) Bulk wet services, including bulk water supply and fire
reticulation (1,500m uPVC and HDPE), sewer gravity mains (2,1600m uPVC) and sewer rising mains of 630m HDPE
![Page 196: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/196.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
April, ‘08 ~ May, ‘08
(1.3 Months)
xiii) Installation of mechanical-electrical equipment associated with the bulk wet services, including submersible pumps, and MCC’s
xiv) Two elevated water storage tanks (150m3 and 50m3), and associated pipework.
Approximately 150,000m2 of Geogrid was required for the whole Project. The assignment mainly included the following tasks:
i) Undertake Site Surveys and Investigations.
ii) Analysis and assessment of the existing test data.
iii) Carry out materials investigation, sampling and testing for
the proposed runway.
Undertake comprehensive analysis particularly for the soils-geogrids interaction. The main objectives of this Study were to: i) determine the engineering performance of the Geogrid reinforcement within pavements of varying layer configurations; ii) characterize the combined performance of the OBRM, OPMC and Geogrid reinforcement technologies ii) determine the cost-time effectiveness through the application of these technologies; and, iii) determine the degree of enhanced geotechnical properties. Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Geotechnical and Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study
Team, develop the Testing and Investigation Regime for Geogrids
(geosynthetics)-Soils interaction, establish and provide Guidelines for
unique and innovative Geotechnical Investigation, Geological Study,
Soil and Ground Survey, and Material Testing from which he was to
derive Special Specifications.
![Page 197: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/197.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘08 ~ May, ‘08
(0.7 Months)
Project Name: Engineering Study on the performance of Tensar
Geogrids with local soils for Kenya Wildlife Service
Client: Kenya Wildlife Service (KWS), Ministry of Tourism
Location: Nairobi National Park, Kenya
Brief Project Background/Particulars/Description
The project area is located within the Nairobi National Park, and
entailed the upgrading of the access roads to all weather roads. In their
current state, the existing roads were highly characterized by failure
during the wet season per seasonal cycle.
The main objectives of this Study were to: i) determine the engineering
performance of the Geogrid reinforcement within pavements of varying
layer configurations; ii) characterize the combined performance of the
OBRM, OPMC and Geogrid reinforcement technologies ii) determine the
cost-time effectiveness through the application of these technologies;
and, iii) determine the degree of enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Geotechnical and Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 198: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/198.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘08 ~ Aug, ‘08
(2.4 Months)
Project Name: Engineering Study on the Performance of Tensar
Geogrids with Local Soils for Outering Ring Road
Client: Ministry of Roads
Location: Outering – Nairobi, Kenya
Brief Project Background/Particulars/Description
New housing areas are developing along the trunk road in a radial
pattern with little attention to roads for commuting; trips originated
from those areas have a characteristic of long distance trip beyond
walking. Consequently, transport demand for motorized traffic is
generated to concentrate on radial arteries. The project area is outside
the Central area of Nairobi, 7Km radius from the CBD and is surrounded
by Karura Forest to the north, and King’ara road to the West.
The main aim of the Project was to ensure the soils along the Outering
Ring Road could withstand the heavy traffic (mostly trucks) cutting
across it on their odyssey to join Mombasa Road to the South.
The specific objectives of this Study were to: i) determine the
engineering performance of the Geogrid reinforcement within
pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMC and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings. Position: Lead Researcher/Team Leader/Chief Geotechnical and
Materials Engineer Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 199: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/199.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
July, ‘08 ~ April, ‘08
(9.3 Months)
Project Name: Preliminary Study on the Project on Strengthening
Facilities and Equipment of Multi-Service Training
Center (MTC) in Juba, South Sudan.
Client: JICA/GoSS
Location: Juba, Central Equatoria State, South Sudan
Brief Project Background/Particulars/Description
In response to the request of the Government of Sudan, the Government
of Japan (GoJ), through its Implementing Agency, the Japan
International Cooperation Agency (JICA), decided to conduct the above
titled Study.
Under the Study, it had been established that the undertaking of a Soil
(Geotechnical) Investigation Survey, was an important component for
purposes of determining suitable and appropriate recommendations for
the Foundation Design of 1 and 2 stories RC buildings for classrooms and
workshops at the MTC.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of foundation ground characteristics, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering methods that would enhance the foundation ground performance whilst realizing significant cost and construction time savings.
Position: Team Leader/ Chief Foundation/Geotechnical and Materials Engineer
The tasks assigned to Dr. Mukabi and his Team included: Geotechnical Investigation; Hydrogeological Survey/ Study; Preliminary evaluation and assessment of the six Borehole Sites; Design of appropriate and suitable testing methods and regimes; Carry out material investigation, sampling and testing for the six Borehole Sites; Undertake in-situ tests; Perform laboratory tests on the geomaterials sampled from the boreholes during drilling at the MTC sites; Carry out Geophysical Survey; Prepare and compile a Geotechnical Investigation Report that were useful for Preliminary/Basic Foundation Design purposes.
![Page 200: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/200.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Aug, ‘08 ~ Sept, ‘08
(0.9 Months)
Project Name: Proposed Design and Construction of the Ol Seki
Airstrip
Client: Ol Seki Mara Camp
Location: Masai Mara, Kenya
Brief Project Background/Particulars/Description
The Client, Ol Seki Mara Camp, intended to build an airstrip, 30m by
1400m on black cotton soil using Optimum Batching Ratio Method
(OBRM), Optimum Mechanical and Chemical Stabilization (OPMCS) and
Tensar Geogrids reinforcement technologies.
Reconnaissance was undertaken, soil samples collected and transported
to Nairobi for testing and analysis.
Essentially therefore, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Geotechnical and Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 201: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/201.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Sept, ‘08 ~ March, ‘09
(6.5 Months)
Project Name: Juba Urban Transport Infrastructure and Capacity
Development Study in the Southern Sudan (JUTI).
Client: JICA/GoSS
Location: Juba, Central Equatoria State, South Sudan
Brief Project Background/Particulars/Description
In response to the request of the Government of Sudan, the Government of Japan (GoJ), through its Implementing Agency, the Japan International Cooperation Agency (JICA), decided to conduct the above titled Study. Under the Study, it had been established that the undertaking of a Soil (Geotechnical) Investigation Survey, was an important component for purposes of determining suitable and appropriate Basic Design parameters and recommendations for Bridge Foundation Design. The Four Components of the Study included:
1. Topographic Survey for Roads 2. Traffic Survey for Roads 3. Topographic Survey for Bridges 4. Geotechnical Investigation for Bridges
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of foundation ground characteristics, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering methods that would enhance the pavements and foundation ground performance whilst significant cost and construction time savings.
Position: Team Leader/Chief Highway/Pavement/Geo-technical/Materials & Bridge Foundation Engineer
The tasks assigned to Dr. Mukabi and his Team included: Geotechnical Investigation; Preliminary evaluation and assessment of the four Borehole Sites; Design of appropriate and suitable testing methods and regimes; Carry out material investigation, sampling and testing for the four Borehole Sites; Undertake in-situ tests as set out in the Technical Specifications; Perform laboratory tests on the geomaterials sampled from the boreholes during drilling at the designated four Bridge Sites; Carry out Geophysical Survey; Prepare and compile a Geotechnical Investigation Report that can be useful for Preliminary/Basic Bridge Foundation Design purposes.
![Page 202: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/202.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘08 ~ Oct, ‘09
(12 Months)
Project Name: Emergency Rehabilitation Works in Juba (ERWJ) –
Construction, Rehabilitation and Upgrading of
LOT1 Roads in Juba, South Sudan
Client: Multi Donor Trust Fund/Government of South Sudan (GoSS)
Location: Juba, Central Equatoria State, South Sudan
Brief Project Background/Particulars/Description
In its efforts to rehabilitate and reconstruct Southern Sudan after the devastating War that rendered practically all the infrastructure damaged, dilapidated and obsolete, GoSS is implementing various projects around the country in a fast track mode to establish a foundation for future development and create an enabling environment for the population of Juba and Southern Sudan in General. Various Projects are underway to achieve this goal and it is within this arrangement that the roads in Juba are being rehabilitated and constructed. More than 35 roads are slotted for rehabilitation under LOT1. The previous Study of Juba Town and Surrounding Areas had established the emergency works and roads to be rehabilitated. Kensetsu Kaihatsu Ltd has been contracted by EYAT Oilfield Services Co. Ltd under the auspices of GoSS to contribute to several projects top of which was the LOT1 roads under ERWJ. The works started with Road M that starts from the Junction (roundabout) at the road to Munuki (km 0+000) and ends at the junction to Road A1 (km 3+090) that is approximately 500M from the Juba International Airport. Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. Position: Project Director/Team Leader/Chief
Highway/Pavement/Geotechnical/Materials Engineer Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications. He was also required to be in-charge of: i) Coordinating overall project management and supervision; ii) Providing guidance for the application of the unique engineering solutions developed; iii) Implementing the research based methods developed in the initial phase to achieve Value Engineering Pavement Structures.
![Page 203: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/203.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Jan, ‘09 ~ June, ‘09
(5.3 Months)
Project Name: Engineering Study on the Soil Interaction and
performance of Geogrids with Tanzanian Soils.
Client: TANROADS/Kundan Singh Construction (KSC) Co. Limited
Location: Mbeya ~ Lwanjilo ~ Makongolosi, Tanzania
Brief Project Background/Particulars/Description
The above study was conducted along the Mbeya ~ Lwanjilo ~
Makongolosi road which is being upgraded to Bitumen standards by the
Government of Tanzania through the Ministry of Works (MoW), and the
Tanzania National Roads Agency (TANROADS).
The main objectives of the Study were set as: i) determine the
engineering performance of the Geogrid reinforcement within
pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Geotechnical and Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 204: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/204.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘09 ~ May, ‘09
(1.2 Months)
Project Name: Application of Triax Tensar for Enhanced Mechanical
Stabilization of Access Roads , Airstrips and Pad
Foundations for Oil Drilling Rigs in Niger Delta
Client: Geotechnologies East Africa/ Tensar International
Location: Niger Delta, Nigeria
Brief Project Background/Particulars/Description
Tensar International in collaboration with the Government of the
Nigeria through the various relevant Ministries is undertaking a research
programme on enhancing the engineering properties of ground and
foundation stability, strength and deformation resistance for purposes
of realizing sustainability, cost effective and savings in maintenance.
The consultants were commissioned to undertake a comprehensive
geotechnical engineering analysis and review of the original design by
employing Value Engineering and set up State-of-the-Art standards
fostering engineering and scientific concepts that can be tailored and
applicable in Nigeria.
The assignment included the following tasks:-
i) Review comprehensively, the original design documents.
ii) Study the Nigerian Pavement and Materials Design Manual –
1999, Standard Specifications and any other relevant
documents.
iii) Undertake comprehensive Site Surveys and Investigations.
iv) Analysis and assessment of the test data carried out in
Tanzania and Kenya.
v) Assessment of the laboratory equipment and capability of
the same to carry out material acceptance and pavement
control testing.
vi) Carry out material investigation, sampling and testing for
the proposed 600m long road alignment. Perform tests on
any other suitable material sites for aggregate sources,
later to be utilized in the construction of the access road.
vii) Carry out Geo-material improvement, mechanical,&
chemical stabilization and testing for all non-compliance
materials.
viii) Build capacity in terms of training manpower, laboratory
Technicians on test methods and quality control.
![Page 205: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/205.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
March, ‘09 ~ May, ‘09
(1.2 Months)
Essentially therefore, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Technical Advisor
Dr. Mukabi was assigned to administer the Study and lead the Study
Team, develop the Testing and Investigation Regime, establish and
provide Guidelines for unique and innovative Geotechnical
Investigation, Geological Study, Soil and Ground Survey, and Material
Testing from which he was to derive Special Specifications.
![Page 206: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/206.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘09 ~ May, ‘09
(0.8 Months)
Project Name: Application of Triax Tensar for Enhanced Mechanical
Stabilization of Roads in Uganda
Client: Geotechnologies East Africa/ Tensar International
Location: Selected Urban and Rural Roads, Uganda
Brief Project Background/Particulars/Description
Tensar International in collaboration with the Government of the
Uganda through the various relevant Ministries is undertaking a research
programme on enhancing the engineering properties of ground and
foundation stability, strength and deformation resistance for purposes
of realizing sustainability, cost effective and savings in maintenance.
The consultants were commissioned to undertake a comprehensive
geotechnical engineering analysis and review of the original design by
employing Value Engineering and set up State-of-the-Art standards
fostering engineering and scientific concepts that can be tailored and
applicable in Nigeria.
The assignment included the following tasks:-
i) Review comprehensively, the original design documents.
ii) Study the Nigerian Pavement and Materials Design Manual –
1999, Standard Specifications and any other relevant
documents.
iii) Undertake comprehensive Site Surveys and Investigations.
iv) Analysis and assessment of the test data carried out in
Tanzania and Kenya.
v) Assessment of the laboratory equipment and capability of
the same to carry out material acceptance and pavement
control testing.
vi) Carry out material investigation, sampling and testing for
the proposed 600m long road alignment. Perform tests on
any other suitable material sites for aggregate sources,
later to be utilized in the construction of the access road.
vii) Carry out Geo-material improvement, mechanical,&
chemical stabilization and testing for all non-compliance
materials.
viii) Build capacity in terms of training manpower, laboratory
Technicians on test methods and quality control.
![Page 207: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/207.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
April, ‘09 ~ May, ‘09
(0.8 Months)
Essentially therefore, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Technical Advisor
Dr. Mukabi was assigned to administer the Study and lead the Study
Team, develop the Testing and Investigation Regime, establish and
provide Guidelines for unique and innovative Geotechnical
Investigation, Geological Study, Soil and Ground Survey, and Material
Testing from which he was to derive Special Specifications.
![Page 208: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/208.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘09 ~ June, ‘09
(2.7 Months)
Project Name: Upgrading to Bitumen Standards of the Kamukuywa-Kaptama-Kapsokwony-Sirisia Road
Client: Ministry of Roads/Kundan Singh Construction Co. Ltd
Location: Mt. Elgon, Kenya
Brief Project Background/Particulars/Description
The Government of the Republic of Kenya (GoK) through the Ministry of Roads (MoR) is undertaking the upgrading of the Kamukuywa-Kaptama-Kapsokwony-Sirisia road to tarmac grade. The proposed project is located in Mt. Elgon in the Western Region of Kenya, about 550km from Nairobi City. The Project road is about 92km long and lies between 08025’00 – 08053’36”S and 33000’48” – 34007’12”E. The altitude for the Project road ranges from 2200 to 2450 metres above sea level (m.a.s.l). The project road traverses some of the highest points of trunk roads in Kenya.
The consultants were commissioned to undertake a comprehensive geotechnical engineering analysis and review of the original design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Kenya.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Geotechnical and Materials Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 209: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/209.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘09 ~ July, ‘09
(0.8 Months)
Project Name: Application of Triax Tensar for Enhanced Mechanical
Stabilization of Roads in Ghana
Client: Geotechnologies East Africa/ Tensar International
Location: Selected Urban and Rural Roads, Ghana
Brief Project Background/Particulars/Description
Tensar International in collaboration with the Government of the Ghana
through the various relevant Ministries is undertaking a research
programme on enhancing the engineering properties of ground and
foundation stability, strength and deformation resistance for purposes
of realizing sustainability, cost effective and savings in maintenance.
The consultants were commissioned to undertake a comprehensive
geotechnical engineering analysis and review of the original design by
employing Value Engineering and set up State-of-the-Art standards
fostering engineering and scientific concepts that can be tailored and
applicable in Nigeria.
The assignment included the following tasks:-
i) Review comprehensively, the original design documents.
ii) Study the Nigerian Pavement and Materials Design Manual –
1999, Standard Specifications and any other relevant
documents.
iii) Undertake comprehensive Site Surveys and Investigations.
iv) Analysis and assessment of the test data carried out in
Tanzania and Kenya.
v) Assessment of the laboratory equipment and capability of
the same to carry out material acceptance and pavement
control testing.
vi) Carry out material investigation, sampling and testing for
the proposed 600m long road alignment. Perform tests on
any other suitable material sites for aggregate sources,
later to be utilized in the construction of the access road.
vii) Carry out Geo-material improvement, mechanical,&
chemical stabilization and testing for all non-compliance
materials.
viii) Build capacity in terms of training manpower, laboratory
Technicians on test methods and quality control.
![Page 210: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/210.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
June, ‘09 ~ July, ‘09
(0.8 Months)
Essentially therefore, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that would enhance the composite pavement structural performance whilst realizing significant cost and construction time savings.
Position: Lead Researcher/Team Leader/Chief Technical Advisor
Dr. Mukabi was assigned to administer the Study and lead the Study
Team, develop the Testing and Investigation Regime, establish and
provide Guidelines for unique and innovative Geotechnical
Investigation, Geological Study, Soil and Ground Survey, and Material
Testing from which he was to derive Special Specifications.
![Page 211: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/211.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Feb, ‘09 ~ April, ‘09
(14 Months)
Project Name: Construction of Pavements and Buildings at Songwe Airport in Mbeya Region
Client: Tanzania Airports Authority
Location: Songwe, Mbeya, Tanzania
Brief Project Background/Particulars/Description
The Tanzania Airport Authority (TAA) received loans from BADEA and
the OPEC Fund for the construction of a new airport at Songwe in the
Mbeya Region. The idea of construction of a new airport in Mbeya was
first conceived in 1977, which was followed up in 1987. The Feasibility
Study (F/S) recommended locating the new airport outside the city due
to the extent of development in the downtown area.
The initial design was to cater for a Fokker F50 as the design aircraft
with provision for future expansion to accommodate a Boeing 737. In
May 2004, however, a redesign of the runway, taxiway and aprons was
undertaken in order to facilitate for B737 operations.
The consultants were commissioned to undertake a comprehensive geotechnical engineering analysis and review of the original design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Tanzania. Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that were applied in drastically enhancing the composite pavement structural performance whilst realizing significant cost savings of more than 46%, construction time savings of almost 200%, and immense reduction in the Maintenance Requirement Ratio.
Position: Lead Consultant/Team Leader/Chief Technical Advisor/Chief Materials/Pavement & Geotechnical Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 212: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/212.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘09 ~ June, ‘09
(3.5 Months)
Project Name: Engineering Study and Detailed Design Review for
the Rehabilitation and Reconstruction of Gisambai-
Mbale Road in Vihiga District
Client: Ministry of Local Government and Office of the Deputy Prime Minister, Republic of Kenya
Location: Vihiga, Kenya
Brief Project Background/Particulars/Description
The Government of the Republic of Kenya through the Office of the Deputy Prime Minister and Ministry of Local Government is undertaking the Project of Rehabilitation/Reconstruction of Gisambai ~ Mbale Road in Vihiga District. The consultancy services included aspects of undertaking a comprehensive geotechnical engineering analysis and review of the original design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Kenya. On the other hand, the construction is designated to employ the recently developed methods and techniques of construction that are tailored for the East African Region taking into account, the complexity of the tropical soils.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that were applied in drastically enhancing the composite pavement structural performance whilst realizing significant cost savings, construction time savings, and immense reduction in the Maintenance Requirement Ratio.
Position: Lead Consultant/Team Leader/Chief Technical Advisor/Chief Materials/Pavement & Geotechnical Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 213: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/213.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘09 ~ August, ‘09
(4.2 Months)
Project Name: Engineering Study and Detailed Design Review for
the Rehabilitation and Reconstruction of Selected
Roads, Storm Water Drains and Erection of Street
Lighting
Client: Ministry of Local Government and Office of the Deputy Prime Minister, Republic of Kenya
Location: Bomet, Kenya
Brief Project Background/Particulars/Description
The Government of the Republic of Kenya through the Office of the Deputy Prime Minister and Ministry of Local Government is undertaking the Project of Rehabilitation/Reconstruction of selected Roads, Storm Drains And Erection of Street Lighting in Bomet Township. The consultancy services included aspects of undertaking a comprehensive geotechnical engineering analysis and review of the original design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Kenya. On the other hand, the construction is designated to employ the recently developed methods and techniques of construction that are tailored for the East African Region taking into account, the complexity of the tropical soils. Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that were applied in drastically enhancing the composite pavement structural performance whilst realizing significant cost savings construction time savings and immense reduction in the Maintenance Requirement Ratio.
Position: Lead Consultant/Team Leader/Chief Technical Advisor/Chief Materials/Pavement & Geotechnical Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 214: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/214.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
May, ‘09 ~ February, ‘11
(22 Months)
Project Name: Proposed Rehabilitation and Reconstruction of
Gisambai-Mbale Road in Vihiga District
Client: Ministry of Local Government and Office of the Deputy Prime Minister, Republic of Kenya
Location: Vihiga, Kenya
Brief Project Background/Particulars/Description
The project road starts at Gisambai and Slopes Slightly in a north-
westerly direction to Mbale where it ends at Kisumu Kakamega
Junction. From Mbale, It traverses Various Schools and Churches
supporting various economic activities along the Project Road.
The Project was initiated by the Government of Kenya through its
Internal Funds for the purposes of Construction and Completion of
Outstanding Works and new Projects.
The effort is supported by Office of the Deputy Prime Minister, Ministry
of Local Government and Ministry of Roads and Public Works.
Various scoping activities undertaken by the Consultant were reported
accordingly.
The Project basically involved overall Construction Supervision featuring mainly Contract Administration, Project Management, field and laboratory Quality Control testing, strict monitoring of Designs and Specifications implementation, providing guidelines for systematic-time-effective methods of construction and advanced QC Programmes. Position: Project Director/Lead Consultant/Chief Technical Advisor &
Chief Highway, Materials & Pavement Engineer
The specific tasks assigned to Dr. Mukabi included:
Overall management and coordination of the Project
Innovation of unique engineering solutions for problematic soils and countermeasures for lack of suitable road and foundation construction material
Developing research based methods to foster Value Engineering that would achieve and enhanced pavement and foundation structures at fostering effectiveness in costs and construction time
Developing new and advanced Quality Control methods
Developing appropriate maintenance programmes and systems
Simulating depreciation in structural capacity under the influence of varying environmental conditions and prolonged and intensified loading.
![Page 215: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/215.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘09 ~ Ongoing
Project Name: Proposed Rehabilitation/Reconstruction of Selected
Roads, Storm Water Drains and Erection of Street
Lighting
Client: Ministry of Local Government and Office of the Deputy Prime Minister, Republic of Kenya
Location: Bomet, Kenya
Brief Project Background/Particulars/Description
The project is located within the Bomet Townsip. The existing roads are
predominantly of earth surface. Due to prolonged periods of non
maintenance most of the road surfaces and structures in many sections
had been deteriorated by the combined effect of vehicular traffic and
uncontrolled storm-water runoff. This rendered the roads dangerous
and impassable to all kinds of traffic, especially during the rainy
seasons.
The rehabilitation/reconstruction is being undertaken for selected roads
and storm water drains in Bomet County. The contract includes the
repair of the dilapidated road link and hydraulic structures to enable all
weather passage. The Project basically involved overall Construction
Supervision featuring mainly Contract Administration, Project
Management, field and laboratory Quality Control testing, strict
monitoring of Designs and Specifications implementation, providing
guidelines for systematic-time-effective methods of construction and
advanced QC Programmes.
Position: Project Director/Lead Consultant/Chief Technical Advisor & Chief Highway, Materials & Pavement Engineer
The specific tasks assigned to Dr. Mukabi included:
Overall management and coordination of the Project
Innovation of unique engineering solutions for problematic soils and countermeasures for lack of suitable road and foundation construction material
Developing research based methods to foster Value Engineering that would achieve and enhanced pavement and foundation structures at fostering effectiveness in costs and construction time
Developing new and advanced Quality Control methods
Developing appropriate maintenance programmes and systems
Simulating depreciation in structural capacity under the influence of varying environmental conditions and prolonged and intensified loading.
![Page 216: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/216.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘09 ~ Aug, ‘09
(2.8 Months)
Project Name: Detailed Study on the Characteristics of Pozzolanic
Geomaterials within the Vicinity of the Site of
Songwe International Airport
Client: Tanzania Airports Authority
Location: Songwe, Mbeya, Tanzania
Brief Project Background/Particulars/Description
In order to confirm, more precisely, the engineering properties of the
existing soils as well as the behavior of the existing ground and
pavement structure, monitoring, technical evaluation and geotechnical
engineering investigations were undertaken. The preliminary results
indicated that the existing ground and pavement structure exhibited
much higher bearing capacity and strength responses in comparison to
the values that may have been considered in the existing design. As a
consequence, the Tanzania Airports Authority (TAA) made a decision to
embark on further and more detailed laboratory and in-situ
experimental testing, technical evaluation, geotechnical engineering
investigations and analyses. This was also in consideration of the fact
that it was most likely that the existing design did not take into account
the pozzolanic cementetious nature of the natural geomaterial in
existence and its immediate response to compaction and the effects of
time related consolidation, thixotropy and creep (secondary
consolidation).
The Study concludes that the naturally existing pozzolanic geomaterial exhibits extremely high geotechnical engineering properties in terms of bearing capacity, strength and deformation resistance and that addition of minimal factory produced Pozzolanic Portland Cement (PPC) astronomically enhances these properties . The Structural Capacity Depreciation (SCDR) Model indicates that, by utilizing this material with only a 2% PPC treatment, the Maintenance Requirement Ratio (MRR) is tremendously reduced to a minimum and that the Runway Pavement Structure will still be intact over the Design Life of 20 years provided that minimal maintenance is undertaken accordingly. Position: Lead Researcher & Geotechnical Engineer Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 217: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/217.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
March, ‘10 ~ May, ‘10
(2.7 Months)
Project Name: Proposal for Design and Construction of Civil Works at
Kamal Steels Plant in Tanzania
Assessment, Investigation, and Detailed Engineering
Analyses and Design for Zinga Industrial Estate Steel
Plant
Client: Kamal Steels Ltd., Kamal Holdings
Location: EPZ, Bagamoyo/Dar es Salaam, Tanzania
Brief Project Background/Particulars/Description
Kamal Steel was incorporated in Tanzania (East Africa) in 2004, through Tanzania Investment Center (TIC) under the foreign investment scheme and is mainly involved in manufacturing Integrated Steel, High Tensile Deformed Bars (Grade 460) and Mild Steel Deformed and Round Bars.
Kamal Steel is one of a group of companies including Kamal Alloys Ltd which has developed Kamal Industrial Estate an Export Processing Zone, that is first of its kind in Tanzania. The Company is also engaged in developing the Steel Plant of capacity of 5,00,000 tons per year.
Kamal Steels believes in continues growth and have thus set targets and have planned for the coming years.
To set up an additional rolling mill.
Kamal Steel is presently covering the neighboring countries like Zambia, Burundi, Congo, Kenya , Malawi. We plan to make our dealer network wide and deep in the East and Central Africa.
Targeting to increase manufacturing capacity twice as that of present, in duration of 2 years.
With its increasing horizon Kamal Steel is now planning to enter a new domain that of Industrial and Medical Gases.
To focus on strengthening “Engineering and Technical” aspects. The consultants proposed to undertake a comprehensive geotechnical engineering analysis and review of the original design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Tanzania.
![Page 218: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/218.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
March, ‘10 ~ May, ‘10
(2.7 Months)
The Proposal recommended the undertaking of comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that would be obtained from this Study would then be comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that were applied in drastically enhancing the composite pavement structural performance whilst realizing significant cost savings, construction time savings, and immense reduction in the Maintenance Requirement Ratio.
Position: Lead Consultant/Civil Engineering Consultant
Dr. Mukabi was assigned to administer the Study and lead the Study Team, propose the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, Material Testing from which he was to derive Special Specifications.
Furthermore, he was to propose appropriate Geotechnical Investigations for Foundation Design for Building Structures and other civil works, and advize on any other Technical and Civil Engineering matters as may be required.
![Page 219: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/219.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
April, ‘10 ~ May, ‘10
(1.3 Months)
Project Name: Review of the Kenya Rural Roads Authority (KeRRA)
Research Policy Formulation
Client: Kenya Rural Roads Authority (KeRRA), Ministry of Roads
Location: Nationwide, Kenya
Brief Project Background/Particulars/Description
The Government of the Republic of Kenya mandates the Kenya Rural
Roads Authority (KeRRA) to construct, maintain and manage a rural
roads network comprising of more than 130,000 kms. This gives KeRRA’s
Research Unit an excellent chance to exploit this opportunity in
developing and excelling to become one of the leading Research
Institutions in Infrastructure Development in the continent.
The Review Report emphasized the need for formulation of Research
Policies for any Agency, Institution or organization at any given scale be
normally propelled and guided by unique needs fostering enhanced rate
and level of development vis a vis available natural and human
resources. This calls for research to be appropriate, dynamic and
commensurate to the prevailing dynamics of time~space related events,
disasters, rate of development/destruction and fundamental changes in
the socio-economic and physical environment.
The Review Report further stated that it is therefore important that the
Research Policy is explicit on its goals, objectives and direction so that
it provides clear guidelines within which research can be undertaken
professionally, ethically and with due diligence for the sole purposes of
introducing, advancing and/or adopting newly developed Value
Engineering (VE) based innovative scientific and engineering theories,
concepts, techniques, technologies, analytical tools, design principles
and methods of construction. Such research should ultimately provide
pragmatic solutions for sustainable infrastructure at the various scopes
of implementation including; emergency, immediate, short-term,
medium-term and long-term within the respective time frames as to be
defined by the Research Policy. Various recommendations were made.
Position: Research & Development (R&D) Consultant
Dr. Mukabi was assigned to Review and give comments and Recommendations based on his experience of having professionally participated in other international RISD formulation.
![Page 220: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/220.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
June, ‘10 ~ Sept, ‘10
(3.8 Months)
Project Name: Engineering Proposal for Subsurface Development and
Implementation of Flyovers/Interchanges at Traffic
Congested and Problematic Areas in Nairobi City
Client: Office of the Deputy Prime Minister and Ministry of Local Government, Republic of Kenya
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
Population explosion from 350,000 people in 1963 to 5 Million currently has transformed Nairobi into a candidate mega city. On the other hand, an inadequate supply of the road capacity, road structure and traffic management measures have been causing exceedingly heavy traffic congestion and traffic accidents. Accordingly therefore, based on some of the recommendations made in the Nairobi Urban Transport (NUTRANS) Master Plan coupled with the recognition by the Government of Kenya, the Office of the Deputy Prime Minister and Ministry of Local Government is reviewing the necessary policies, whilst the Government of the Republic of Kenya has established the Ministry of Nairobi Metropolitan Development mainly to ensure the realisation of the Nairobi Metro 2030 Vision. Within this vision, Nairobi is to be transformed into a world class metropolis with a robust, internationally competitive, and dynamic economy. Through this Office, the Consultants were requested to submit an Engineering Proposal for Subsurface Development and Implementation of Flyovers/Interchanges at Traffic Congested and Problematic Areas in Nairobi City in order to progressively solve some of these problems ranging from immediate, short, medium to long term periods. In this Proposal, the Consultants recommended that Research & Development (R&D) for underground city development that will include modern subsurface mass transit systems, parking bays, shopping malls, amenity parks, be initiated as part of long term programmes, whilst implementation of flyovers/interchanges be considered as short to medium term countermeasures. In this Proposal, some of the major challenges facing such an undertaking are introduced. A preamble is also given on some technologies and concepts that may be further developed to solve some of the geotechnical engineering problems. The importance of advancing comprehensive investigations, testing and analysis in relation to enhanced R&D is also briefly discussed. Position: Highway/ Geotechnical/ Materials Engineer & Team
Leader/Lead Consultant Dr. Mukabi was responsible of formulating the fundamental concepts.
![Page 221: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/221.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘10 ~ Feb, ‘10
(3.4 Months)
Project Name: Research and Enhancement of Geogrids
Performance within Composite Pavement
Layers
Client: Geogrids East Africa (GEA)
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
Performance-Based Design (PBD) fundamentally entails that, deformation in ground, pavement materials and structures soils along with the reciprocal structural deformation and stress states be comprehensively analyzed by adopting sophisticated methods, particularly for structures with high exposure to seismic action. In performance-based design, the acceptable level of drainage, i.e. the damage criteria, should be specified in engineering terms such as displacements, limit stress state and ductility/ strain limit based on the function as well dynamic loading and/ or seismic response of the structure. Consequently, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively
analyzed applying advanced and sophisticated analytical tools and
models and employed in quantitatively determining the objectives.
Scientific and engineering comparative analyses were also undertaken.
Position: Chief Technical Advisor/Lead Consultant/Lead Researcher/Team Leader
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 222: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/222.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘10 ~ March, ‘11
(4.7 Months)
Project Name: Development of Value Engineering Technologies
Proposal
Client: Roman Roads Limited
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
This Proposal suggests and emphasizes on the utter need of enhancing
Research & Innovation for Sustainable Development (RISD) in
infrastructure as a top priority area which will form the integral
technological pillar and foundation for rapid industrialization leading to
the targeted socio-economic development.
Specifically, emphasis is made on the importance of designing and
implementing Research Regimes that concentrate on developing Value
Engineering (VE) technologies and materials science that would lead to
appreciable cost-time savings, whilst enhancing the structural and
serviceability levels as well as the overall performance of the
structures.
Examples of some of the VE technologies that have been recently
developed and effectively applied on roads and runway pavements,
airports construction, pad foundations for oil exploration and drilling
rigs, subgrade ground improvement for pavement structures, foundation
ground improvement for bridges, jetties and other port facilities as well
as slope stabilization and structural enhancement of retaining walls are
presented and their areas of application outlined.
Various recommendations for enhancing Research & Innovation for
Sustainable Development (RISD) are provided and the advantages of so
doing discussed from a pragmatic perspective.
Position: Lead Consultant/Lead Researcher Dr. Mukabi was assigned the responsibility of developing the Proposal regarding the most effective research regimes approach, methodology and work plan in developing Value Engineering technologies.
![Page 223: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/223.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Oct, ‘10 ~ Ongoing
Project Name: Restoration of Original Pavements at Isiolo Airport
Client: Kenya Airports Authority, Ministry of Transport
Location: Isiolo and Meru Counties, Eastern Province, Kenya
Brief Project Background/Particulars/Description
As part of Vision 2030 the Government of the Republic Kenya has
embarked on an elaborate and ambitious project known as LAPSSET
(Lamu Port - Southern Sudan - Ethiopia Transport Corridor) which entails
linking Kenya's coast to its northern neighbours through the Eastern and
Northern Frontiers of Isiolo, Turkana and Moyale. The $16 Billion mega
project will have the construction of three berhs with associated
infrastructure at Manada Bay, Lamu as the first phase. The corridor
though Isiolo is one of the flagship projects identified under the
country’s long-term economic development programme.
Isiolo Airprt is one of three airports to be constructed to International Standards within this mega project. The as the first phase project, consists mainly of the following components:
Lamu Port and Manda Bay
Standard gauge railway line to Juba
Road network
Oil pipelines (Southern Sudan and Ethiopia)
Oil refinery at Lamu
Three Airports
Three resort cities (Lamu, Isiolo and Lake Turkana shores)
The transport corridor is expected to serve an estimated population of 85 million Ethiopians and another 15 million from Southern Sudan. Once completed, LAPSSET is intended to increase business opportunities in tourism, agriculture and manufacturing. The development, expansion of, and transformation of Isiolo into a green city of the Northern frontier and upgrading Isiolo Airport to international status is an integral component of LAPSSET.
The consultants were commissioned to undertake a comprehensive geotechnical engineering analysis and design by employing Value Engineering and set up State-of-the-Art standards fostering engineering and scientific concepts that can be tailored and applicable in Tropical Regions.
![Page 224: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/224.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
Oct, ‘10 ~ Ongoing
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of roadbed and subgrade characteristics, pavement structural capacity, bearing capacity, strength and deformation resistance. The results that were obtained from this Study were comprehensively analyzed applying advanced and sophisticated analytical tools and models and employed in determining appropriate Value Engineering techniques that were applied in drastically enhancing the composite pavement structural performance whilst significant cost savings of more than 60%, construction time savings of almost 200%, and immense reduction in the Maintenance Requirement Ratio are to be realized.
This Project, which is on-going, is a manifestation of the most recent
application of the Optimum Mechanical and Chemical Stabilization
(OPMCS) in the design and construction of the runway pavements, taxi
way, aprons and parking bays of the Isiolo International Airport located
in the Eastern State of Kenya.
The OPMCS is one of the Value Engineering Technologies developed by
Mukabi.
The results from the laboratory tests indicated that: a) the UCS was significantly enhanced as the soil particles agglomerate progressively with time particularly for the cemented geomaterial; b) soil particle agglomeration is dependent on the mode of stabilization; c) the effects of geogrid reinforcement are more noticeable with increased agglomeration possibly due to the influence of confinement in increasing the degree of interlocking of particles culminating in reduction of voids ratio, and d) the degree of soil particle agglomeration is higher under OPMC stabilization in comparison to geogrid reinforcement thus confirming the theory that, in comparison to other influencing factors, cementation processes have greater impact on agglomeration mechanisms.
The site location of this project is predominated by Black Cotton Soils
(BCSs), which are highly problematic and expansive in nature.
Consequently, Ground Improvement (GI) was undertaken by adopting
the Moisture Control Sand Column (MCSC) method proposed by Mukabi
et al, 2010b. Both laboratory and field experimental testing results
indicate that, on the average, this method typically enhances the
bearing capacity, strength and deformation resistance of BCS subgrades
by more than five - fold.
![Page 225: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/225.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
Oct, ‘10 ~ Ongoing
The uniqueness of this design includes the: 1) combination of OPMCS and geosynthetics; 2) use of geotextile as a separation, filtration and stress mobilization interface; 3) use of geogrid as a reinforcement and tensile stress control component, and 4) realization of high composite structural enhancement factor.
Position: Lead Consultant/Team Leader/Chief Technical Advisor/Chief Materials/Pavement & Geotechnical Engineer
Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 226: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/226.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Nov, ‘10 ~ Aug, ‘11
(8.7 Months)
Project Name: Formulation and Development of Versatile and
Effective Research & Innovation Programme for
Sustainable Infrastructure Development (SID)
Client: Materials Testing & Research Department (MT&RD)
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
In order for the Kenya Vision 2030 to be realized within the designated
time-frame, it is imperative that the targeted economic growth is
achieved through rapid industrialization, enhanced agricultural
production and agro-industry development, booming tourism, advanced
education (science and technology) among other factors. Such goals can
only be achieved through rapid infrastructure development based on
innovative techniques, methods and technologies as a primary driving
factor.
Innovative methods that can realize the practical achievements of such
advancement are discussed in this Proposal in terms of cost-
effectiveness, performance and environmental considerations. In order
to achieve these fundamental goals, the paper also emphasizes the
need to enhance capacity building programmes through the pragmatic
development of strong Young Engineers Programmes (YEPs) for public,
private and academic institutions through technology transfer, technical
training and Research & Development activities.
This Proposal suggests and emphasizes on the utter need of enhancing
Research & Innovation for Sustainable Development (RISD) in
infrastructure as a top priority area which will form the integral
technological pillar and foundation for rapid industrialization leading to
the targeted socio-economic development.
Specifically, emphasis is made on the importance of designing and
implementing Research Regimes that concentrate on developing Value
Engineering (VE) technologies and materials science that would lead to
appreciable cost-time savings, whilst enhancing the structural and
serviceability levels as well as the overall performance of the
structures.
![Page 227: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/227.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
Nov, ‘10 ~ Aug, ‘11
(8.7 Months)
Examples of some of the VE technologies that have been recently
developed and effectively applied on roads and runway pavements,
airports construction, pad foundations for oil exploration and drilling
rigs, subgrade ground improvement for pavement structures, foundation
ground improvement for bridges, jetties and other port facilities as well
as slope stabilization and structural enhancement of retaining walls are
presented and their areas of application outlined.
Various recommendations for enhancing Research & Innovation for
Sustainable Development (RISD) are provided and the advantages of so
doing discussed from a pragmatic perspective.
Some of the main conclusions derived and recommendations made are:
Conclusions
1. Infrastructure is an absolutely integral priority area of
research.
2. Enhancement of Research & Development Programmes,
capacity building and increased funding in the advancing of
Value Engineering (VE) technologies and materials science is
certainly integral in the achievement of rapid socio-economic
development in line with the Kenya Vision 2030.
3. The Case Examples and Analyses of the VE Technologies
introduced in Chapter 3 of this Proposal clearly demonstrate
the:
a) importance of enhanced R&D;
b) enormous cost-time savings realized through the
application of these technologies;
c) enhanced structural performance and serviceability levels
achieved;
d) versatility of technologies in their applications; and,
e) technologies can immensely contribute to the rapid
achievement of integrated and socio-economic
development.
![Page 228: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/228.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continued)
Nov, ‘10 ~ Aug, ‘11
(8.7 Months)
Recommendations
1. Infrastructure be taken into account and considered as a
topmost priority area of research.
2. Funding for research in this area be exponentially increased in
order to undertake comprehensive and extensive research for
purposes of achieving rapid and useful results.
3. Policies be established to the effect that a percentage of say
3 ~ 5% be levied on every infrastructure project for purposes
of research funding in this field.
4. Policies be established to make it mandatory that
infrastructure projects only be awarded to consulting and
contracting firms that foster, develop and apply Value
Engineering Technologies as is demonstrated in sections of the
Proposal, which outline some policy and contractual aspects
of Value Engineering.
Position: Research & Development (R&D) Consultant/Chief Technical
Advisor Dr. Mukabi was assigned the responsibility of developing the Proposal
regarding the most effective research regimes approach, methodology
and work plan in developing Value Engineering technologies.
![Page 229: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/229.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Nov, ‘10 ~ Feb, ‘11
(1.8 Months)
Project Name: Determination of Degree/Performance Ratio of
Geosynthetic Reinforcement within Runway
Pavements of the Isiolo International Airport
Client: Kenya Airports Authority, Ministry of Transport, Kenya
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
In performance-based design, the acceptable level of the damage criteria, should be specified in engineering terms such as displacements, limit stress state and ductility/ strain limit based on the function as well dynamic loading and/ or seismic response of the structure. The Designs of the Isiolo International Airport were predominantly based on a research based approach. A versatile, comprehensive and detailed Research Regime was therefore designed to investigate various scientific and engineering factors. A preliminary determination of degree/performance ratio of geosynthetic reinforcement within Runway Pavements was made by varying the pavement layer configurations, quality and properties. Consequently, the main objectives of the Study were set as: i)
determine the engineering performance of the Geogrid reinforcement
within pavements of varying layer configurations; ii) characterize the
combined performance of the OBRM, OPMCS and Geogrid reinforcement
technologies ii) determine the cost-time effectiveness through the
application of these technologies; and, iii) determine the degree of
enhanced geotechnical properties.
Comprehensive innovative as well as standard field and laboratory tests were conducted to determine various vital geotechnical engineering parameters and soil properties relevant for the detailed analysis of of the varying the pavement layer configurations, quality and properties. The results that were obtained from this Study were comprehensively
analyzed applying advanced and sophisticated analytical tools and
models and employed in quantitatively determining the objectives.
Scientific and engineering comparative analyses were also undertaken.
Position: Lead Researcher & Geotechnical Engineer Dr. Mukabi was assigned to administer the Study and lead the Study Team, develop the Testing and Investigation Regime, establish and provide Guidelines for unique and innovative Geotechnical Investigation, Geological Study, Soil and Ground Survey, and Material Testing from which he was to derive Special Specifications.
![Page 230: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/230.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec, ‘10 ~ March, ‘11
(3.6 Months)
Project Name: Review of Sate of the Art Scientific and Engineering
RISD and Case Study Analysis on Geosynthetics
Technologies
Client: Materials Testing & Research Department (MT&RD)
Location: Nairobi, Kenya
Brief Project Background/Particulars/Description
Geosynthetics have been widely used for geotechnical and environmental applications globally for the past four decades. New products and applications are routinely developed globally to provide solutions to routine and critical problems. Over the years, these products have helped Design Engineers to solve various types of engineering challenges where the use of conventional materials would be restricted or considerably more expensive. There is a significant number of Geosynthetic types and applications, common types of Geosynthetics used for soil reinforcement include geotextiles, Geogrids and Geocells. A wide variety of Geosynthetic products can be used in environmental protection including Geomembranes, Geomats, Geonets, Geocomposites and Geopipes. Geocomposites are Geosynthetics made from a combination of two or more Geosynthetic types. Examples include: geotextile – Geonet; Geotextile – Geogrid; Geonet – Geomembrane; or a Geosynthetic clay line (GCL). Geopipes are perforated or solid-wall polymeric pipes used for drainage of liquids or gas. Geosynthetics are also used to mitigate: erosion, slope failure, poor bearing capacity, etc. Construction of Geosynthetic-reinforced soil retaining walls (GRS RW’s) and Geosynthetic-reinforced steep slopes of embankments has become popular in Asia (e.g., Japan, Korea, China, Taiwan, Vietnam, Thailand, Singapore, Malaysia and India), following pioneering works in Europe and North America. Among the technologies used to construct these numerous Geosynthetic-reinforced soil structures in Asia, a couple of unique ones that were developed in this region are reported herein. In this Study, literature review on the State of the Art publications, Case Studies, Scientific and Engineering Analyses were comprehensively undertaken.
Position: Research & Development (R&D) Consultant/Chief Technical Advisor
Dr. Mukabi gave guidance on the approach and methodology of this
Study.
![Page 231: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/231.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Dec., ‘10 ~ March, ‘10
(3.3 Months)
Project Name: Detailed Investigations on the Hydrogeological
Conditions of Isiolo International Airport Site for
Design of Hydraulic Structures
Client: Kenya Airports Authority, Ministry of Transport, Kenya
Location: Isiolo, Kenya
Brief Project Background/Particulars/Description
Isiolo is located in the Upper Eastern sub-region some 285Km north of
Nairobi, the capital of Kenya. It is characterized by three climatic
zones, namely: i) Semi-arid Zone IV covering 5% of the total area with
precipitation levels of 250 ~ 650mm per annum; ii) Arid zone covering
30% of the total area with precipitation levels of 300 ~ 350mm per
annum; and, iii) Extremely Arid zone covering 65% of the total area with
precipitation levels of 150 ~ 250mm per annum. The average range of
ambient temperatures is between 13 and 29°C. The soils on site and
within its vicinity are predominantly very thick layers of problematic
and expansive Black Cotton Soils. It is practically flat with low lying
plains that rise gradually from an altitude of 200m a.s.l at Lorian Swamp
in the North to about 300m a.s.l at Merti Plateau.
This Study basically involved comprehensive geotechnical and hydrological investigations as well as preliminary Initial Environmental Examination (IEE), including collection, collation, gathering and recording of data and information to facilitate evaluation and/or analysis of parameters related to flow rates, water level variations within water courses, channels, rivers and other water bodies, debri lines, precise catchment sizes, type of soils, land use and characteristics as well as other relevant data and information. During the Study, intensive scoping, soils testing, in-situ measurements and evaluation as well as other field surveys were undertaken.
This Study was to form the basis of the design of Bridges and other hydraulic structures along with some basic recommendations derived from the preliminary IEE which had been undertaken.
Position: Lead Researcher & Geotechnical Engineer Dr. Mukabi’s main task was to design the investigation regime and programme and provide guidance to the Study Team accordingly.
![Page 232: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/232.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Project Name: Studies on Geosynthetics Reinforced Materials for
Road Embankments and Pavements
Client: Materials Testing and Research Department, Ministry of Roads
Location: Selected Urban & Rural Roads Countrywide, Kenya
Brief Project Background/Particulars/Description
On 7th December 2011, Kensetsu Kaihatsu Limited, submitted Technical
and Financial Proposals to the Materials Testing and Research
Department (MTRD) for research consultancy services for some priority
areas within the Ministry of Roads regarding the introduction and
application of research based advanced technologies.
Essentially, the Request for Proposal (RFP) required the design of a research regime that is primarily aimed at developing construction and performance Specifications for Geosynthetics reinforced Geomaterials for road embankments and pavement structures in particular, including design procedures and quality control systems as well as evaluation regimes and procedures for evaluating the performance of existing geo-structures and retaining walls.
From a global perspective the methods of design, construction, quality control systems and performance specifications should ensure that the procedures and techniques are pragmatically applicable and;
1. Cost and time effective predominated with a Value Engineering (VE) component.
2. State of the Art so that they are applicable to inclusion in the Road Design Manual (K) and Standard Specifications.
3. Are particularly tailored for tropical environmental conditions within the East and Central Africa Region.
4. Satisfactorily innovative enough to provide a useful basis for developing alternative and more effective stabilization techniques for Geomaterials, new engineering products, more cost-effective concepts, methods of design and construction techniques which are also environmentally friendly.
5. Provide engineering indicators for quality control, monitoring and evaluation of performance of Geo-structures.
![Page 233: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/233.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Expected
In general, the Consultant’s interpretation of the main objectives is the Client’s wishes to determine the effectiveness and degree of performance and/or contribution of Geosynthetics in flexible pavements in order to determine its benefits mainly for purposes of developing specifications and guidelines for Design Manuals. In this regard therefore, it is an important objective of this Study to quantify this effectiveness and provide a better understanding of the Geosynthetic mechanisms in pavements and other Geo-structures.
Performance-Based Design (PBD) fundamentally entails that, deformation in ground, pavement materials and structures soils along with the reciprocal structural deformation and stress states be comprehensively analyzed by adopting sophisticated methods, particularly for structures with high exposure to seismic action. In performance-based design, the acceptable level of drainage, i.e. the damage criteria, should be specified in engineering terms such as displacements, limit stress state and ductility/ strain limit based on the function as well dynamic loading and/ or seismic response of the structure.
In his Proposal, the Consultant defined the term “performance based” to mean “the contribution of the Geogrid in enhancing the mechanical stability, strength, bearing capacity, deformation resistance, structural capacity, durability, stress distribution characteristics, and secondary consolidation properties of the composite pavement structure that can specifically define its qualitative properties in quantitative terms”. The Consultant further suggested that performance engineering properties of the Geogrids shall be determined based on the scientific and engineering concepts, and unique methods of testing and that the enhancement of the following engineering properties of the pavement structure shall be construed to form the performance based specification of Geogrids in general.
1. Tensile Strength 2. Compressive Strength 3. Modulus of Elasticity 4. Structural Capacity 5. Degree of Interlocking 6. Durability 7. Stress Distribution mode 8. Secondary Consolidation (Creep) rate 9. Reduction of Structural Thickness
![Page 234: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/234.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Expected
Based on the Study objectives, the fundamental definition of Performance-Based Design defined in above and the Consultant’s experience, an example of the ultimate output expected by the Client in terms of Performance-Based Specifications for Geosynthetically reinforced pavements and Geo-structures, developed and hypothetically proposed by the Consultant was presented in the Technical Proposal.
Position: Team Leader/Lead Consultant/Lead Researcher &
Geotechnical Engineer In this Study, Dr. Mukabi’s main tasks would be to design the Research, Geotechnical Investigations well as field and laboratory testing regimes and programmes besides leading and provide guidance to the Study Team. In particular he would be charged with the following tasks.
Management of all Tasks in general; and,
Liaison with Chief Engineer (Materials)
Advancing Research in Geomaterials, Geosynthetics & RE
Geostructures
Design of Research & Testing Regimes
Design of Trial sections
Development of Evaluation and Monitoring Procedures, Systems
and Programmes
Development of Appropriate and Unique Design Procedures,
Methods of Construction and Quality Control Systems
Development of Special Specifications
Overall Technical Approach, Coordination and Implementation
Methodology
Overall Organization of Study
Overall Presentation and Reporting
![Page 235: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/235.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Project Name: Performance Evaluation of Reinforced Earth Retaining
Walls (Re-Walls) Along Thika Road (A2)
Client: Materials Testing and Research Department, Ministry of Roads
Location: Nairobi ~ Thika Highway, Kenya
Brief Project Background/Particulars/Description
In their Request For Proposal (RFP). the Materials Testing and Research
Department (MTRD) of the Ministry of Roads requires research
consultancy services for some priority areas within regarding the
introduction and application of research based advanced technologies.
As one of the major objectives, the Request for Proposal mainly required the design of evaluation and monitoring regimes and procedures for effectively evaluating the performance of existing geo-structures and retaining walls. The assignment would therefore entail the development of procedures for testing and evaluation of completed works which should include assessment of settlement on embankments and stability of RE-Walls. The Procedures developed in the preceding paragraph would then be applied in evaluating the performance of the RE Geo-structures and Retaining Walls constructed along Nairobi ~ Thika Road (A2) vis a vis the design assumptions in the following locations of the highway.
i) City Arterial Connectors [Lot 1]; Three (3) Structures; ii) Muthaiga Roundabout ~ Kenyatta University [Lot 2]: Two
(2) Structures; and, iii) Kenyatta ~ Thika [Lot 3]: Two (2) Structures.
The Scope of Works for this assignment also covers the design of a monitoring programme to inform development of Standard Construction Specifications for RE Geostructures and Retaining Walls.
In regard to this assignment, the Consultant made the following proposals, among others.
1. Evaluation and Monitoring of RE Geostructures
Evaluation and monitoring of the Reinforced Earth (RE) Geostructures will be undertaken on the basis of the Consultant’s experience of a similar nature presented in Tool 14 of Volume III, Section 3.2 of Chapter 3 of this Technical Proposal and partly introduced in Attachment A7.
![Page 236: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/236.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
(Continuation)
Expected
2. Evaluation and Monitoring of Retaining Walls
Tool 16 provides detailed discussions regarding this case whereby the Consultant provided effective Value Engineering (VE) countermeasures and engineering employing research oriented technologies that he developed for purposes of that assignment after designing trial sections and undertaking monitoring and evaluation over a period of three years (36 months) through varying seasonal changes and moisture-suction variations.
3. Comprehensive Analysis and Characterization of RE-Retaining Walls Interaction
During the proposed assignment, the Consultant intends to apply the state of the art engineering principles and concepts as well as recently developed scientific theories and geo-mathematical models to undertake comprehensive analysis and characterization of the RE-Retaining Walls interaction for the geo-structures to be investigated along Thika Road.
4. Consultant’s Relevant Experience in Developing Monitoring
and Evaluation Systems & Programmes
An example of monitoring and evaluation systems developed by the
Consultant is provided under Attachment A8 of the Technical
Proposal.
Position: Team Leader/Lead Consultant/Lead Researcher & Geotechnical Engineer
In this Study, Dr. Mukabi’s main tasks would be to design the evaluation and monitoring regimes and programmes besides leading and providing guidance to the Study Team. In particular he would be charged with the following tasks.
Liaison with Chief Engineer (Materials)
Advancing Research in & RE Geo-structures
Design of Research & Monitoring Regimes
Development of Evaluation and Monitoring Procedures, Systems
and Programmes
Development of Special Specifications
Overall Technical Approach, Coordination and Implementation
Methodology
Overall Organization of Study
Overall Presentation and Reporting
![Page 237: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/237.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Project Name: Condition Surveys Including Structural Evaluation on the Geosynthetics Trial Sections Constructed in Kenya
Client: Materials Testing and Research Department, Ministry of Roads
Location: Countrywide, Kenya
Brief Project Background/Particulars/Description
Geosynthetics have been widely used for geotechnical and environmental applications globally for the past four decades. New products and applications are routinely developed globally to provide solutions to routine and critical problems. Over the years, these products have helped Design Engineers to solve various types of engineering challenges where the use of conventional materials would be restricted or considerably more expensive.
Between 1987 and 2011, geosynthetically reinforced Experimental Trial Sections have been constructed on the following roads in Kenya.
i. Garsen ~ Lamu Road (B8/C112) and Garsen Bridge; ii. Upgrading to dual carriageway of Thika ~ Makutano
Road (A2); iii. Reconstruction of Eldoret ~ Burnt Forest Road (A104);
and, iv. Reconstruction of Webuye ~ Malaba Road (A104).
The assignment would therefore entail the development of appropriate procedures for in-situ testing and evaluation of existing pavement structures. Based on the agreed principles and findings from this asssignment, the SoW requires the development of design procedures, preliminary construction specifications and quality control systems including recommendation on appropriate testing equipment for geosynthetics reinforcement. Position: Team Leader/Lead Consultant/Lead Researcher &
Geotechnical Engineer In this Study, Dr. Mukabi’s main tasks would be to design research, testing, evaluation and monitoring regimes and programmes besides leading and providing guidance to the Study Team. He would also be in-charge of the overall organization of the Study including the technical approach, coordination and implementation methodology.
![Page 238: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/238.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Project Name: Development of Special Specifications for Further Trials on Geosynthetics Reinforced Embankments
Client: Materials Testing and Research Department, Ministry of Roads
Location: Countrywide, Kenya
Brief Project Background/Particulars/Description
Under this assignment, the main objective is to develop Special
Specifications for carrying out further trials on geosynthetically
reinforced embankments.
In particular, the ToR stipulates the following requirements.
a) Develop special specifications for further trials on geosynthetics reinforced embankments on the following roads:
i) Masalani bridge approaches; ii) Likoni ~ Shelly beach; iii) Kiserian ~ Isinya Road (D523); and, iv) Sigalagala ~ Butere Road (D260).
b) Develop special specifications for further trials on geosynthetic
reinforced DBM/AC on the following roads: i) Rehabilitation of Eldoret ~ Timboroa Road (A104); ii) Rehabilitation of Eldoret ~ Webuye Road (A104); iii) Rehabilitation of Webuye ~ Malaba Road (A104); and, iv) Rehabilitation of Uplands ~ Kimende Road (A104)
c) Develop programmes for monitoring and evaluation of the trials
under a) and b) The assignment would therefore entail the development of appropriate procedures for in-situ testing and evaluation of existing pavement structures.
Position: Team Leader/Lead Consultant/Lead Researcher & Geotechnical Engineer
In this Study, Dr. Mukabi’s main tasks would be to design research, testing, evaluation and monitoring regimes and programmes besides leading and providing guidance to the Study Team. He would also be in-charge of the overall organization of the Study including the technical approach, coordination and implementation methodology.
![Page 239: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/239.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Research Associate: Bamburi Cement – Lafarge Group Materials
Research Innovation & Sustainable Development
Location: East Africaand Central Africa
Proposed Project:
Bamburi Cement Limited (BCL) operates in East Africa mainly Kenya &
Uganda and the company is managed as one enterprise. The principal
activities are in the manufacture and sale of cement & cement related
products. BC also own and manage a world class nature and
environmental park developed from rehabilitated quarries. Bamburi
Cement is the largest cement manufacturing company in the region and
it's Mombasa plant is the second largest cement plant in sub-Saharan
Africa.
BSP - Bamburi Special Product’s Research and Development department
have been instrumental in expanding its existing range of products. BSP
is a wholly owned subsidiary of Bamburi Cement Limited, which is a
subsidiary of Lafarge - the largest building material manufacturer in the
World.
World leader in building materials, Lafarge extracts resources from the
heart of the earth to make materials to bring to the heart of life.
Present in 78 countries, the Group responds to the world’s demand for
housing and infrastructure. Lafarge is driven by the needs of its
customers, shareholders, local communities and architects. The Group
creates high value-added solutions which encourage creativity whilst
leaving a lighter trace on the world.
Sustainable construction, from Lafarge's perspective, involves reducing
a building's impact on the environment as much as possible while
preserving aesthetics and comfort. Numerous partnerships, research and
development of innovative products are all advantages and actions
which make Lafarge a major player in sustainable construction. To
develop value-added products for the whole of the building sector; to
remain a step ahead of the competition by increasing research activity;
to provide new solutions for sustainable construction: these are
Lafarge's innovation and research ambitions.
Proposed Position: Lead Consultant/Lead Researcher/Team
Leader/Chief Highway/Geotechnical/Civil Engineer
![Page 240: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/240.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
LEGEND
COMPLETED PROJECTS
ON GOING PROJECTS
EXPECTED PROJECTS
DATE PROJECT PARTICULARS AND POSITION
Expected
Collaborating Associate: Comito & Associati S.r.l. Consulting Services,
Italy and Others
Location: Italy and Worldwide
Assignment:
Dr. Mukabi has been invited to propose collaboration/team with Comito & Associati S.r.l. an Italian consulting firm specialised since 1978 in the strategic due diligence, monitoring & evaluation of projects and feasibility studies in developing, transitional and emerging countries, focusing mainly on economic, financial, engineering and environmental aspects. For over 30 years Comito & Associati S.r.l. has focused its activities in the following sectors: Transport infrastructures (roads, airports, ports, railways, multimodal) and logistics; Urban/Regional planning and development; Tourism and Leisure development; Environment, water and waste management; Institutional capacity building and strengthening, know-how transfer, Training; Macro economy, public finances, trade and business development. Services offered include: Transport planning, economics and engineering; Economic and financial feasibility studies, cost benefit-analysis; Support for investment-financing decisions, Project Financing, Public Private Partnership (PPP) and privatizations; • Environmental Impact Assessment; Socio-economic analysis; Rural development and poverty reduction strategies; Policy analysis, reform of national and local administrations; Legislative and regulatory frameworks analysis; Project Monitoring & Evaluation; Tender preparation and selection Comito & Associati has a database of 2.500 international English, French, Spanish, Portuguese, Arabic and Russian speaking consultants (Business Development Managers, Environmental experts, Economists/Financial analysts, Infrastructures engineers etc.) active in different sectors and geographical areas. Comito & Associati S.r.l. has successfully carried out projects world-wide in more than 50 countries in enlarged Europe, Africa, Mediterranean and Middle East, Central and South America, Asia, North America.
![Page 241: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/241.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
15. SUMMARY OF EXPERIENCE:
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Detailed Investigations on the
Hydrogeological Conditions of
Isiolo International Airport
Site for Design of Hydraulic
Structures
Lead Researcher & Geotechnical
Engineer
Dec. 2010 ~
March 2011
(3.3 Months)
Kenya Airports Authority
(KAA)
Ministry of Transport,
Kenya
Review of Sate of the Art
Scientific and Engineering
RISD and Case Study Analysis
on Geosynthetics
Technologies
Research & Development (R&D)
Consultant/Chief Technical
Advisor
Dec. 2010 ~
March 2011
(3.6 Months)
Materials Testing &
Research Department
(MT&RD)
Determination of
Degree/Performance Ratio of
Geosynthetic Reinforcement
within Runway Pavements
Lead Researcher & Geotechnical
Engineer
November
2010 ~
February
2011
(1.8 Months)
Kenya Airports Authority
(KAA)
Ministry of Transport,
Kenya
Formulation and Development
of Versatile and Effective
Research & Innovation
Programme for Sustainable
Infrastructure Development
(SID)
Research & Development (R&D)
Consultant/Chief Technical
Advisor
November
2010 ~
August 2011
(8.7 Months)
Materials Testing &
Research Department
(MT&RD)
Restoration of Original
Pavements at Isiolo Airport
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief Materials/Pavement
& Geotechnical/Research
Engineer
October
2010 ~
ongoing
Kenya Airports Authority
(KAA)
Ministry of Transport,
Kenya
Preliminary Study on
Appropriate Infrastructure
Development Employing Value
Engineering Concepts and
Technologies
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2010 ~
ongoing
Roman Roads Limited
Development of Value
Engineering Technologies Lead Consultant/Lead Researcher October
2010 ~ Roman Roads Limited
![Page 242: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/242.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Proposal
March 2011
(4.7 Months)
Research and Enhancement of
Geogrids Performance within
Composite Pavement Layers
Chief Technical Advisor/Lead
Consultant/Lead
Researcher/Team Leader
October
2010 ~
February
2011
(3.4 Months)
Geogrids East Africa
(GEA)
Proposal for Subsurface
Development and
Implementation of
Flyovers/Interchanges at
Traffic Congested and
Problematic Areas in Nairobi
City
Highway/ Geotechnical/ Materials
Engineer & Team Leader/Lead
Consultant
June 2010 ~
Sept. 2010
(3.8 Months)
Office of the Dep. Prime
Minister & Ministry of
Local
Government/Nairobi City
Council
Review of the KeRRA Research
Policy Formulation
Research & Development (R&D)
Consultant
April 2010 ~
May 2010
(1.3 Months)
Kenya Rural Roads
Authority (KeRRA)
Ministry of Roads
Proposal for Design and
Construction of Civil Works at
Kamal Steels Plant in
Tanzania
Assessment, Investigation,
and Detailed Engineering
Analyses and Design for Zinga
Industrial Estate Steel Plant
Lead Consultant/Civil Engineering
Consultant
March 2010
~ May 2010
(2.7 Months)
Kamal Steels Ltd., Kamal
Holdings
Detailed Study on the
Characteristics of Pozzolanic
Geomaterials within the
Vicinity of the Site of Songwe
International Airport
Lead Researcher & Geotechnical
Engineer
June 2009 ~
August 2009
(2.8 Months)
Tanzania Airports
Authority (TAA)
Proposed
Rehabilitation/Reconstruction
of Selected Roads, Storm
Water Drains and Erection of
Project Director/Lead
Consultant/Chief Technical
Advisor & Chief Highway,
June 2009 ~
Ongoing
Office of the Deputy
Prime Minister and
Ministry of Local
Government, Republic of
![Page 243: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/243.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Street Lighting
Materials & Pavement Engineer Kenya
Proposed
Rehabilitation/Reconstruction
of the Gisambai-Mbale Road in
Vihiga District
Project Director/Lead
Consultant/Chief Technical
Advisor & Chief Highway,
Materials & Pavement Engineer
May 2009 ~
February
2011
(22 Months)
Office of the Deputy
Prime Minister and
Ministry of Local
Government, Republic of
Kenya
Engineering Study and
Detailed Design Review for
the Rehabilitation and
Reconstruction of Selected
Roads, Storm Water Drains
and Erection of Street
Lighting
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief Materials/Pavement
& Geotechnical Engineer
April 2009 ~
August 2009
(4.2 Months)
Office of the Deputy
Prime Minister and
Ministry of Local
Government, Republic of
Kenya
Engineering Study and
Detailed Design Review for
the Rehabilitation and
Reconstruction of Gisambai-
Mbale Road in Vihiga District
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief Materials/Pavement
& Geotechnical Engineer
March 2009
~ June 2009
(3.5 Months)
Office of the Deputy
Prime Minister and
Ministry of Local
Government, Republic of
Kenya
Construction of Pavements
and Buildings at Songwe
Airport in Mbeya Region
Lead Consultant/Team
Leader/Chief Technical
Advisor/Chief Materials/Pavement
& Geotechnical Engineer
February
2009 ~ April
2010
(14 Months)
Tanzania Airports
Authority (TAA), United
Republic of Tanzania
Application of Triax Tensar for
Enhanced Mechanical
Stabilization of Roads in
Ghana
Lead Researcher/Chief Technical
Advisor
June 2009 ~
July 2009
(0.8 Months)
Geotechnologies East
Africa/ Tensar
International
Upgrading to Bitumen
Standards of the Kamukuywa
~ Kaptama ~ Kapsokwony ~
Sirisia Road
Lead Researcher/Chief Technical
April 2009 ~
June 2009
MoR, KSC
![Page 244: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/244.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Advisor (2.7 Months)
Application of Triax Tensar for
Enhanced Mechanical
Stabilization of Roads in
Uganda
Selected Urban and Rural
Roads, Uganda
Geotechnologies East Africa/
Tensar International
Lead Researcher/Chief Technical
Advisor
April 2009 ~
May 2009
(0.8 Months)
Geotechnologies South
Africa/ Tensar
International
Application of Triax Tensar for
Enhanced Mechanical
Stabilization of Access Roads,
Airstrips and Pad Foundations
for Oil Drilling Rigs in Upper
Delta Nigeria
Upper Delta, Nigeria
Geotechnologies East Africa/
Tensar International
Lead Researcher/Chief Technical
Advisor
March 2009
~ May 2009
(1.2 Months)
Geotechnologies South
Africa/ Tensar
International
Engineering Study on the Soil
Interaction and Performance
of Geogrids with Some Mbeya
Soils
Mbeya, Tanzania
TANROADS/KSC
Lead Researcher/Team
Leader/Chief Technical Advisor
January
2009 ~ June
2009
(5.3 Months)
TANROADS
Kundan Singh
Construction (KSC) Co.
Limited
Emergency Rehabilitation
Works in Juba (ERWJ) –
Construction, Rehabilitation
and Upgrading of LOT1 Roads
in Juba
Project Director/Team
Leader/Chief
Highway/Pavement/Geotechnical
/Materials Engineer
October
2008 ~
October
2009
(12 Months)
Government of South
Sudan (GoSS)
Juba Urban Transport
Infrastructure and Capacity
Team Leader/Chief
Highway/Pavement/Geo-
September
2008 ~ JICA
![Page 245: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/245.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Development Study in the
Southern Sudan (JUTI)
technical/Materials & Bridge
Foundation Engineer
March 2009
(6.5Months)
Proposed Design and
Construction of the Ol Seki
Airstrip
Team Leader/ Chief
Highway/Pavement/Geo-technical
and Materials Engineer
August 2008
~ Sept. 2008
(0.9 Months)
Ol Seki Mara Camp
Preliminary Study on
Strengthening Facilities and
Equipment of Multi-service
Training Center (MTC) in
Juba, South Sudan
Team Leader/ Chief
Foundation/Geotechnical and
Materials Engineer
July 2008 ~
April 2009
(9.3 Months)
JICA
Engineering Study on the
Performance of Tensar
Geogrids with Local Soils for
Outering Ring Road Project
Team Leader/ Chief
Highway/Pavement/Geo-technical
and Materials Engineer
June 2008 ~
August 2009
(2.4 Months)
MoR
Engineering Study on the
performance of Tensar
Geogrids with local soils for
Kenya Wildlife Service
Team Leader/Lead Researcher &
Chief Geotechnical Engineer
May 2008 ~
May 2008
(0.7 Months)
Kenya Wildlife Service
Engineering Study on the
performance of Tensar
Geogrids with local soils for
Kisumu Airport Expansion
Project.
Sr. Geotechnical Engineer- Team
Leader
April 2008 ~
May 2008
(1.3 Months)
Kenya Airports Authority
Investigation of Pavement
Structural Capacity, Strength
and Deformation Resistance of
the Thogoto ~ Gikambura ~
Mutarakwa Road
Team Leader/Chief
Highway/Pavement/Geotechnical
/Materials Engineer
April 2008 ~
May 2008
(1.2 Months)
MoR
Evaluation of Contractor’s Contractual Claims for the Construction of the Gravel
Road Rehabilitation Works for Lainya ~ Jambo Trunk Road
Claims Engineer
April, 2008
~ April,
2008
(0.7 Months)
GoSS
![Page 246: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/246.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Engineering Study on the
performance of Tensar
Geogrids with Local Soils for
Mukurweini-Gakonya and
Rutune-Mahuani Roads Project
Team Leader/Chief
Highway/Pavement/Geotechnical
/Materials Engineer
February
2008 ~ April
2008
(2.3 Months)
MoR
Mbeya ~ Lwamjilo Road
Rehabilitation Project
Chief Highway/Pavement/Geo-
technical and Materials Engineer
January
2008 ~ May
2008
(4.6 Months)
TANROADS
Transport Infrastructure
Development Study for
Malakal Town
Lead Consultant/Team
Leader/Chief
Highway/Pavement/Geo-
technical/Materials Engineer
January
2008 ~
March 2008
(2.7 Months)
Governor’s Office/Ministry of
Physical Infrastructure and Planning
Evaluation of Contractor’s Contractual Claims for
Extension of Time for the Construction of the Wau ~ Abyei Trunk Road Project
Claims Engineer
October
2007 ~
October
2007
(0.8 Months)
United Nations World
Food Programme
(UN-WFP)
Gravel Road Rehabilitation
Works for Lainya ~ Jambo
Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Co. Ltd
Project Director/Team
Leader/Chief
Highway/Pavement/Geotechnical
/Materials Engineer
September
2007 ~
November
2008
(14 Months)
Government of South
Sudan (GoSS)
Study on the Enhancement of
the Subgrade Structural
Performance for Lainya ~
Jambo Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Lead Consultant/ Team
Leader/Lead Researcher
September
2007 ~
November
2007
(2.8 Months)
Government of South
Sudan (GoSS)
![Page 247: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/247.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Co. Ltd
Comprehensive
Hydrogeological Study for
Lainya ~ Jambo Trunk Road
Juba, South Sudan
GoSS/Payii Roads & Bridges
Co. Ltd
Team Leader/Chief Geotechnical
Engineer
September
2007 ~
November
2007
(2.6 Months)
Government of South
Sudan (GoSS)
Detailed Scoping and Civil
Engineering Study of Various
Aspects of the Lainya ~
Jambo Trunk Road
Government of South Sudan
(GoSS)
Team Leader/Chief Civil Engineer
August 2007
~ May 2008
(8.5 Months)
Government of South
Sudan (GoSS)
Ntare~Rushatsi Boulevard
Project for Pavement
Rehabilitation on City Roads
in Bujumbura
Team Leader/Chief Technical
advisor/Chief Project
Coordinator/Sr.
Materials/Pavement &
Geotechnical Engineer
September
2007 ~
November
2007
(2.8 Months)
JICA
Research And Development
Study For Affordable Housing
For East And Central Africa
Lead Researcher/ Chief Technical
Advisor
August 2007
~ October
2007
(2.4 Months)
Geotechnologies East Africa
Engineering Design for Pad
Foundations for Oil Drilling
Rigs, Access Roads, Airstrip
and Base Camps for the White
Nile oil Exploration Project in
South Sudan
Lead Consultant/Team
Leader/Chief
Foundation/Pavement/Geotechnic
al/Materials Engineer
March 2007
~ November
2007
(8.7 Months)
White Nile Oil Exploration Co. Ltd/GoSS
Comprehensive Geotechnical
and Hydrological
Investigations and R&D of
Lead Researcher/Team Leader
March 2007
White Nile Oil Exploration Co. Ltd/GoSS
![Page 248: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/248.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Value Engineering
Technologies for the White
Nile oil Exploration Project in
South Sudan
~ May 2007
(2.9 Months)
Technical and Engineering
Study for Determination of
Suitable and Pragmatic
Project Mitigation Measures
for the Cost-Time-Effective
Implementation of the Wau ~
Abyei Trunk Road Project
Lead Researcher/Team Leader
March 2007
~ April 2007
(1.6 Months)
United Nations World Food Programme (UN-
WFP)
Transport Infrastructure
Development Project
Leer~Adok Trunk Road and
Port Project
Lead Consultant/Team
Leader/Chief
Highway/Pavement/Geo-
technical/Materials Engineer
February
2007 ~
August 2007
(6.8 Months)
Governor’s Office/Ministry of
Physical Infrastructure and Planning
Consultancy Work Supervision
Of Emergency Road Repairs
In South Sudan – Phase 3
Project Manager/Chief Materials,
Pavement & Highway
Engineer/Research Team Leader
November
2006 ~ July
2008
(21 Months)
GOSS/ World Food Programme (WFP)
Comprehensive Engineering
and Geo-materials Science
Research for the
Development of
Appropriate Value
Engineering Technologies
for the Wau ~ Abyei Trunk
Road Project
Lead Researcher/Team Leader
November
2006 ~ July
2007
(9 Months)
United Nations World Food Programme
(UN-WFP)
Juba River Port Access Road
Detailed Engineering Design
and Construction Supervision
Project
Project Manager/Lead
Consultant/Team Leader/Chief
Pavement and Geotechnical
Engineer
October
2006 ~
September
2007
JICA
![Page 249: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/249.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
(11 Months)
Feasibility Study on The Urban
Infrastructure Development of
Juba Town
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
July
2006 ~
December
2006
(5.8 Months)
JICA
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Kakuma ~
Lokkichogio Trunk Road
Section under the EAC/NEPAD
Initiative for Regional
Integration
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
May
2006 ~ June
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Lodwar ~
Kakuma Trunk Road Section
under the EAC/NEPAD
Initiative for Regional
Integration
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
April
2006 ~ May
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Comprehensive Evaluation of
the Engineering
Implementation of the
Emergency Study on Planning
and Support for Basic Physical
and Social Infrastructure in
Juba and the surrounding
areas in Southern Sudan
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
March
2006 ~
February
2007
(12 Months)
JICA/GoSS
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Marich Pass
~ Lodwar Trunk Road Section
under the EAC/NEPAD
Initiative for Regional
Integration
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
March
2006 ~ April
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Lead Consultant/Team
Leader/Chief Highway and
February
2006 ~ JICA/GoK/Mitsui
Corporation
![Page 250: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/250.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Assessment of the Kapenguria
~ Marich Pass Trunk Road
Section under the EAC/NEPAD
Initiative for Regional
Integration
Geotechnical Engineer March 2006
(0.5 Months)
Emergency Study on The
Planning And Support For
Basic Physical And Social
Infrastructure In Juba Town
And The Surrounding Areas
Chief Technical advisor/Chief
Project Coordinator/Lead
Researcher/Chief.
Materials/Pavement &
Geotechnical Engineer
January
2006 ~
March 2007
(15 Months)
JICA
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Baringo ~
Marich Pass Trunk Road
Section under the EAC/NEPAD
Initiative for Regional
Integration
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
January
2006 ~
February
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Pre-Feasibility Study and
Geotechnical Engineering
Assessment of the Kabarak ~
Baringo Trunk Road Section
under the EAC/NEPAD
Initiative for Regional
Integration
Lead Consultant/Team
Leader/Chief Highway and
Geotechnical Engineer
December
2005 ~
January
2006
(1 Month)
JICA/GoK/Mitsui Corporation
Preliminary Study of Southern
Sudan Roads Network and
Capacity Building
Deputy Project Manager/Senior
Highway & Geotechnical Engineer
June
2005 ~
September
2005
(3.5 Months)
GoSS
Feasibility Study and
Preliminary Engineering
Design for the Addis Ababa
Urban Transport Network
Sr. Highway Engineer and Team
Leader
May
2005 ~
Ethiopia Roads Authority (ERA)/ Addis Ababa City Roads Authority (AACRA)
![Page 251: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/251.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Development August 2005
(3.4 Months)
The Study on Master Plan for
Urban Transport in the Nairobi
Metropolitan Area
Chief Technical Advisor/Senior
Highway & Geotechnical Engineer
May
2005 ~
October
2005
(6 Months)
JICA/ MoR/MoLG
Feasibility Study and
Preliminary Engineering
Design for Mitigation Measures
against Traffic Congestion and
Improvement Measures of
Traffic Safety in Addis Ababa
City
Sr. Highway Engineer and Team
Leader
April
2005 ~ May
2005
(1.8 Months)
ERA/AACRA
Post-Construction Project
Evaluation and Preparation of
the Consultancy and Contract
Completion Reports for the
Addis Ababa-Goha ~ Tsion
International Trunk Road
Project
Sr. Highway Engineer and Team
Leader
January
2005 ~
January
2006
(12 Months)
JICA/ERA
Evaluation assessment and
preparation of Contractual
Claims for the Addis Ababa-
Goha ~ Tsion International
Trunk Road Project
Engineering Consultant/Chief
Technical Advisor/ Claims
Engineer
June
2004 ~
December
2004
(6.5 Months)
Kajima Corporation
Feasibility Study and
Preliminary Engineering
Design of the Upgrading
Team Leader/Sr. Geotechnical &
Highway Engineer
May
2004 ~
February
MoFED/ ERA / Kajima Corporation
![Page 252: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/252.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Project of the Holeta~Muger
Road
2005
(9.2 Months)
Feasibility Study and
Preliminary Engineering
Design Project for the
Upgrading and Expansion of
the Gimbothaya International
Airport and Access Road in
Bahir Dar
Team Leader/Project Director/Sr.
Geotechnical & Highway Engineer
May
2004 ~
September
2004
(3.8 Months)
ODPM/Bahir Dar Municipality
Feasibility Study and
Preliminary Engineering
Design of the Bahir Dar
University Road
Team Leader/Project Director/Sr.
Geotechnical & Highway Engineer
May
2004 ~ July
2004
(2.5 Months)
ODPM/Bahir Dar Municipality
Study for the Enhancement of
Structural Capacity and
Serviceability Level of the
Addis Ababa – Goha Tsion
Trunk Road.
Team Leader /Sr. Highway &
Geotechnical Engineer/Lead
Researcher
March
2003 ~ April
2004
(12 Months)
MoFED/ ERA / Kajima Corporation
Detailed Engineering Design
and Construction Supervision
of the Addis Ababa~Goha
Tsion Trunk Road Project –
Phase IV
Dep. Project Manager/Sr.
Geotechnical & Highway
Engineer/Lead Researcher
December
2002 ~
March
2004
(15 Months)
JICA
Detailed Engineering Design
and Construction Supervision
of the Addis Ababa~Goha
Tsion Trunk Road Project –
Deputy Project Manager/Resident
Geotechnical & Highway
Engineer/ Lead Researcher
January
2002 ~
February
JICA
![Page 253: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/253.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Phase III 2003
(13 Months)
Detailed Design of the Project
for Construction of Bridges ,
Ghana
External Consultant/Sr.
Geotechnical Engineer
June
2001 ~
March
2004
(33 Months)
JICA/Ministry of Roads and Transport, Ghana
Comprehensive Study and
Design Review of Bridge and
Hydraulic Structures for the
Tana Basin Road Development
Project
Team Leader/ Sr. Highway &
Geotechnical Engineer/Lead
Researcher
October
2000 ~ April
2004
(43 Months)
JBIC/Office of The President, Kenya
Evaluation Contractor’s
Contractual Claims for
Variations and Extension of
Time for Sections B (Hola ~
Garsen) and C (Garsen ~
Malindi) of the Malindi ~
Garissa Trunk Road (B8) - the
Tana Basin Development
Project Phase II
Claims Engineer
July, ‘00 ~
August, ‘00
(1.2 Months)
Japan Bank of International
Cooperation/Office of the President
Comprehensive Study and
Design Review of Bridge and
Hydraulic Structures for the
Tana Basin Road Development
Project
Team Leader/ Sr. Foundation &
Geotechnical Engineer/Lead
Researcher
June
2000 ~
November
2000
(5.8 Months)
JBIC/Office of The President, Kenya
Design of Reinforced Earth
Structures with Slope
Protection applying the Terre
Armee Method for the Tana
Basin Development Project
Phase II
Team Leader/Chief Technical
Advisor/ Sr.
Pavement/Geotechnical &
Materials Engineer/Lead
Researcher
June
2000 ~
November
2000
JBIC/Office of The President, Kenya
![Page 254: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/254.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
(5.1 Months)
Evaluation and Establishment
of a Counter Claim of Pioneer
Plumbers Contractual Claims
for Variations for the Mpata
Safari Club Project
Claims Engineer
May
2000 ~ May
2000
(0.6 Months)
Mpata International, Japan
Review of Hydrological
Conditions and Chronology for
of Redesigning Hydraulic
Structures for the Tana Basin
Development Project Phase II
Team Leader/Chief Technical
Advisor/Sr. Geotechnical
January
2000 ~ May
2000
(4.3 Months)
JBIC/Office of The President, Kenya
Detailed Engineering Design
and Construction Supervision
of the Addis Ababa~Goha
Tsion Trunk Road Project –
Phase II
Deputy Project Manager/Resident
Geotechnical & Highway
Engineer/ Lead Researcher
December
1999 ~
March
2002
(27 Months)
JICA
Study on Rural Roads
Improvement in Western
Kenya Considering Socio-
Economic Impact,
Environmental Impact
Assessment and Value
Engineering Based Design
Chief Materials/ Geotechnical &
Pavement Engineer/Chief Project
Coordinator & Advisor to Team
Leader
March
1999 ~
December
1999
(8.4 Months)
JICA
Report to the Japan Bank of
International Cooperation
(JBIC) Appraisal Mission for
The Additional Loan to the
Tana Basin Development Road
Project in The Republic of
Kenya
Team Leader/Sr. Civil Engineer
Jan, 1999 ~
March, 1999
(2.4 Months)
Japan Bank of International
Cooperation (Fmr. OECF)/Office of the
President
Socio-Economic & Engineering
Assessment and Analysis of
Team Leader/Civil Engineering
Consultant
November
Mitsubishi and Takenaka Corporations, Kenya
![Page 255: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/255.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Viability of Undertaking
Rehabilitation & Expansion of
Mombasa International Airport
Access Road (C110) and Part
(A109)
1998 ~
January
1999
(2.2 Months)
Project Formulation Based on
Socio-economic and
Engineering Assessment of the
El-Nino Damaged Approach
Roads and Bridges in Eastern
and Coast Provinces of Kenya
Civil Engineering
Consultant/Highway &
Geotechnical Engineer
September
1998 ~
February
1999
(5.8Months)
IDI/GoK
Formulation and
Implementation of the Tana
Basin Road Flood Recovery
and Rehabilitation Project
Team Leader/Sr. Civil Engineering
Consultant
September
1998 ~
December
1998
(3.6 Months)
Office of the President/ Ministry of Public Works
& Housing
Analysis of The Settlement
Problem at Athi River Cement
Works
Team Leader/Geotechnical
Engineering Consultant/Structural
Engineer
September
1998 ~
October
1998
(1.8 Months)
Sumitomo Construction Company, Japan
Feasibility Study for Road
Improvement and Preliminary
Design for the Moi
International Airport,
Mombasa Access Road
Team Leader/ Sr. Highway &
Geotechnical Engineer
August
1998 ~
November
1998
(2.6 Months)
Mitsubishi Corporation, Japan
Research on the Improvement
and Adoption of Liquid
Chemical Stabilizers for Rural
Road Development
Team Leader/Research Consultant
June
1998 ~
November
1998
Con Aid, Mitsui & Co East Africa. Con-Aid Pty SA
![Page 256: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/256.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
(5.2 Months)
Study of Improved Methods of
Design, Environmental and
Socio-economic Aspects for
Evaton Municipal Roads in
Johannesburg
Team Leader/Research
Consultant/Pavement &
Geotechnical Engineer
June
1998 ~
October
1998
(3.4 Months)
Con Aid, Mitsui & Co East Africa. Con-Aid Pty SA
Socio-economic and
Engineering Assessment,
Analysis and Project
Formulation as a Mitigation
Strategy of the Impact of El-
Nino on the C70 Kangema ~
Gacharage Road & Bridges
Civil Engineering
Consultant/Highway &
Geotechnical Engineer
May
1998 ~ July
1998
(2.3 Months)
CPC/JICA
CON-AID Research and
Development Proposal
Research Team Leader/Lead
Researcher
April, 1998
~ October,
1998
(7.9 Months)
CON-AID Pty, South Africa/Mitsui
Corporation, South Africa/ Mitsui
Corporation, Kenya
Study on Effective Strategy of
Enhancing Research &
Development in Civil and
Structural Engineering in
Kenya
Lead Researcher/Civil Engineering
Consultant/Team Leader/Chief
Projects Coordinator
April
1998 ~
August
1998
(4.2 Months)
Industrial Development Institute, Japan
Detailed Design and
Construction Supervision of
the Malindi ~ Garissa
International Trunk Road
under the Tana Basin
Development Project
Deputy Project Manager/Team
Leader/Research
Consultant/Pavement &
Geotechnical Engineer
March
1998 ~ April
2002
(49 Months)
JBIC/ Office of The President
Low & Medium Cost Housing
Development Projects in
Urban & Rural Areas (With
Particular Reference to
Team Leader/Chief Consulting &
Research Engineer
March
1998 ~ June
1998
World Bank
![Page 257: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/257.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Material Science and
Construction Techniques
Development)
(3.5 Months)
Urban Traffic Control and
Planning for Major Cities in
Kenya
Deputy Team Leader/ Urban
Planning & Civil Engineering
Consultant
January
1997 ~ July
1997
(6.2 Months)
MoT/ World Bank
Rehabilitation of Health
Facilities in Western Kenya
Deputy Team Leader/Sr. Geotechnical/Civil & Structural Engineer
August
1996 ~
November
1997
(15 Months)
African Development Bank (ADB)/ Ministry of
Health, Kenya
Sub-Sahara Africa Transport
Programme; NMT Urban
Transport Studies, East Africa
Region
Urban Planning & Civil Engineering
Consultant
July
1995 ~ June
1996
(12 Months)
World Bank/ UNECA
An Evaluation of Private
Community Development
Projects, Kenya
Civil Engineering Consultant
June
1995 ~
August 1995
(2.7 Months)
USAID
KOBENET (Reconstruction
Activities Due to the Damage
Caused To Structures In Kobe,
Japan by the Great Kansai
Earthquake), Kobe, Japan
(KOBENET)
Research/Civil & Reconstruction
Engineering Consultant
February
1995 ~ April
1995
(2.3 Months)
Ministry of Infrastructure/ The Port And Harbour Research Institute, Ministry Of
Transport, Japan
Ground Improvement in
Ariake, Kyushuu for Rail Road
Construction, Japan
Associate Researcher
June
1994 ~
March 1995
(9.6 Months)
Ariake Geotechnical Research Group
![Page 258: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/258.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
The Kandagawa Flood Control
Project in Suginami, Tokyo Associate Researcher
April
1993 ~
March 1995
(24 Months)
Taisei Corporation
The OAP (Osaka Amenity Park)
Project For Skyscraper
Buildings & Amenity Parks in
Osaka
Associate Researcher
April
1992 ~
March 1995
(36 Months)
Obayashi Construction Company
Waterfront Development,
Reclamation And Ground
Settlement-Associated
Problems of The New Kansai
International Airport., Osaka,
Japan
Associate Researcher
June
1994 ~
March 1995
(36 Months)
Port and Harbor Research Institute, Ministry of Transport, Japan.
Construction of Mpata Safari
Club in Maasai Mara, Kenya
Project Manager/Chief
Consultant/Chief Coordinator and
Construction Supervision Advisor
July
1991 ~ July
1993
(25 Months)
Mpata International Inc., Tokyo
Construction of Man-made
Islands, Bridges, Shield
Tunnels etc., Japan
Associate Researcher
May
1989 ~
March 1991
(22 Months)
Trans-Tokyo Bay Highway Corp., Ministry of
Construction
A research project on the
adoption of Fly Ash as a useful
foundation and land
reclamation Geomaterial
Research Associate
April
1988 ~
March 1989
(12 Months)
Kansai Electric Power Company in Japan
Yokohama Minato Mirai 21st
Century Futuristic Intelligent
City Project (MM21)
Research Associate
October
1987 ~
March 1989
(18 Months)
Yokohama City Development Authority,
Japan
![Page 259: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/259.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
Experience as Project Director/Project Manager/Team Leader/Lead Researcher/Sr. Position
Project Position Duration
(Yrs) Financier
Bridge Projects Across The
Seto Sea Islands, Japan
Associate Construction
Supervisor/Trainee In Civil &
Structural Engineering Design &
Construction Supervision
June
1987 ~
September
1987
(3.5 Months)
The Honshu-Shikoku Bridge Authority,
Ministry of Transport, Japan
Mpata Safari Club Access Road Project Manager/Team
Leader/Chief Consulting Engineer
August
1987 ~ July
1989
(24 Months)
Mpata International, Tokyo, Japan
![Page 260: Mukabi Jn (Ph.d)_cv_edited Jan2012](https://reader036.fdocuments.us/reader036/viewer/2022081801/5536f0a14a795967228b4ba9/html5/thumbnails/260.jpg)
JN Mukabi (Ph.D) Curriculum Vitae 2012
16. MAIN LANGUAGES AND DEGREE OF PROFICIENCY
Reading Writing Speaking
English Excellent Excellent Excellent
Japanese Excellent Excellent Excellent
Swahili Excellent Excellent Excellent
CERTIFICATION
I, the undersigned, certify that to the best of my knowledge and belief, the curriculum vitae
correctly describes me, my qualifications, and my experience accordingly.
_____________________________________________________
18/January/2012
(Signature) Day/Month/Year
Full name: JOHN NGAYA MUKABI