Muhammad Zia-ur-Rehman - USAID SARI/Energy...
Transcript of Muhammad Zia-ur-Rehman - USAID SARI/Energy...
2
Muhammad Zia-ur-Rehman
G.M. (C&M) PEPCO
PAKISTAN POWER SECTORPAKISTAN POWER SECTOR
Kathmandu, 15 th November, 2011
33
Power Sector Overviewand Current Challenges
4
Pakistan Power Sector - Organization
IPPs
WAPDA PEPCO
PPIB SPPs/CPPs
KESC
GOVERNMENT OF PAKISTAN
Water Projects &
Dams
GENCOs(4)
DISCOs(9)
NTDC AEDB
Ministry of Water & Power
Pakistan Atomic EnergyCommission
NEPRAThe
Regulator
PrivateSector
CPPA
Kanupp & Chashnupp (C1 &C2)
POWER MARKET
Exist IPP
Exist Exist IPPIPP
WAPDA HYDEL
WAPDA WAPDA HYDELHYDEL
GENCOGENCOGENCO
NuclearNuclearNuclear
GENCOGENCOGENCOGENCOGENCOGENCO
Exist IPP
Exist Exist IPPIPPExist IPP
Exist Exist IPPIPP
New IPP
New New IPPIPPNew IPP
New New IPPIPPNew IPP
New New IPPIPP
WPPOWPPOWPPO
CPPA
CCPPPPAA
NTDC NTDC NTDC
DISCODISCODISCODISCODISCODISCODISCODISCODISCO
BSCBSCBSCBSCBSCBSCBSCBSCBSC
Exist IPP
Exist Exist IPPIPP
WAPDA HYDEL
WAPDA WAPDA HYDELHYDEL
GENCOGENCOGENCO
NuclearNuclearNuclear
GENCOGENCOGENCOGENCOGENCOGENCO
Exist IPP
Exist Exist IPPIPPExist IPP
Exist Exist IPPIPP
New IPP
New New IPPIPPNew IPP
New New IPPIPPNew IPP
New New IPPIPP
WPPOWPPOWPPO
CPPA
CCPPPPAA
NTDC NTDC NTDC
DISCODISCODISCODISCODISCODISCODISCODISCODISCO
BSCBSCBSCBSCBSCBSCBSCBSCBSC
Exist IPP
Exist Exist IPPIPP
WAPDA HYDEL
WAPDA WAPDA HYDELHYDEL
GENCOGENCOGENCO
NuclearNuclearNuclear
GENCOGENCOGENCOGENCOGENCOGENCO
Exist IPP
Exist Exist IPPIPPExist IPP
Exist Exist IPPIPP
New IPP
New New IPPIPPNew IPPNew New IPPIPPNew IPP
New New IPPIPP
WPPOWPPOWPPO
CPPA
CCPPPPAA
NTDC NTDC NTDC
DISCODISCODISCODISCODISCODISCODISCODISCODISCO
BSCBSCBSCBSCBSCBSCBSCBSCBSC
SOSO
Dispatch Dispatch
Availability
Availability
et others
et others
Contracts
Contracts
Demand
Demand
Least cost
operation
Exist IPP
Exist Exist IPPIPP
WAPDA HYDEL
WAPDA WAPDA HYDELHYDEL
GENCOGENCOGENCO
NuclearNuclearNuclear
GENCOGENCOGENCOGENCOGENCOGENCO
Exist IPP
Exist Exist IPPIPPExist IPP
Exist Exist IPPIPP
New IPP
New New IPPIPPNew IPPNew New IPPIPPNew IPP
New New IPPIPP
WPPOWPPOWPPO
CPPA
CCPPPPAA
NTDC NTDC NTDC
DISCODISCODISCODISCODISCODISCODISCODISCODISCO
BSCBSCBSCBSCBSCBSCBSCBSCBSC
SOSO
Dispatch Dispatch
Availability
Availability
et others
et others
Contracts
Contracts
Demand
Demand
Least cost
operation
Operational instructions given by the System Operator directly to
generators and DISCOS
Information for daily operation supplied by generators & DISCOs
directly to the System Operator
Supply Curve of national power market
6
0.51
1.253.12
10.21
11.1113.2
16.36
19.42
29.51
39.37
0
5
10
15
20
25
30
35
40
45
0 2000 4000 6000 8000 10000 12000 14000 16000
Pri
ce/
kW
h
Load (MW)
Whole sale price level in 2010-11
7
Wholesale average price during 2010-11
J A M M U &
S h a h i d M a h m o o d
M . W a s e e m Y o u n u s
A b d u l M a je e d M a l i k
D W N :
C . E
D . D
D I R :
G . M D R G # G M P P / G e o g / P A K . - 0 1 4 D A T E0 4 - 0 4 - 2 0 0 8
5 0 0 & 2 2 0 k V S Y S T E M
N T D C P L A N N I N G P O W E R
C H I N A
K A S H M I R
AFG
HA
NIS
TAN
S H I K A RP U R
I
N
D
I
A
M E P C OI N D U S RIV
E R
G E P C O
LES
CO
G I L G I T A G E N C Y
N E WD O U D K H E L
F E S C O
CH
EN
AB
RIV
ER
IND
US
RIV
ER
IND
US
R
IVE
R
P A K . G E N .
S A T L U J R IVE R
N G P S
K A P C O
I ND
US
R
I VE
R
RI V
ER
I N
DU
S
C H A S N U P P
VEH
AR
I
R OU S C H
S R : R D
SU
TL E
J RIV
ER
S.N
AG
AR
R A VI R
IVER
SU
T LE J RIV
ER
B.R
D N E W
N . K . L P A T
RA
VI
RIV
ER
I S DIS P R
L U D E W A L A
B U R H AN
RIV
ER
IN
DU
S
R I V E R K A B U L
I E S C O
R I V E R C H E N A B
G/W
ALA
JHE
LUM
R
IVE
R
M A N G L A P / H
K .S.K
S I A L K O T
P E S C O
R I V E R K A B U L
M A R D A N
T H A HK O T
S E H R A
RIV
ER
IN
DU
S
H E S C OA R A B I A N S E A
G W A D A R 2 2 0 k V
I R A N
J A C K I G O R
Q E S C O
K E S C
N K I
L E G E N D
H Y D E L S T A T I O N
T H E R M A L S T A T I O N
5 0 0 k V
2 2 0 k V
E X I S T I N G P R O P O S E DL I N E SG R I D S G R I D S L I N E S
L A L P I R
K H W A R
N O W S H E R AN E W
J A G R A N H Y D E L
C H A BA H A R
5 0 .7 k m
D O Y I A N
B U N J I
B A S H A
D A S UP A T A N
K O H A L A
N E E L U M J H E L U M
B A H A W A LP U R N E W
7 0 .5 k m
PO
LAN
2 3 0 k V
75km
2 20 kV
K A R
N.A
BA
D
J R : R D
G A Z I R D .
P / H
S A B A
J A P A N
S E P C O L
F . K B R
KE
L I P P s
I P P s
I P P s
A E S
A E S
T H A R C O A L
N E WD A D U
H A L A R D
G U D D UP / H
U C HP / H
S I B B I
Q U E T T AI N D U S
K H U Z D A R
M U L T A N
M / G A R H
G A T T I
L A HO R E
N E WR E W A T
G / B R O T H AP E S H A W A R
P / H
T A R B E L AP / H
H Y D
B A N N UD O M A I L
H A B I B U L L A HI P P s
P / H
H U B C OP / H
S A H I W A L
I P P s
W A R S A K
230k
V
G/S
U N I V :
G H A K
M A N
A L L A I
S H O R OJ A M
N A T I O N A L G R I D
K D A - 3 3B A LD I A
S / B A G H
R O H R IN E W
E N G R O
D E H R K IC C P P
R . Y . K H A N5 0 0 k V
5 0 0 k V
C H I S H T I A N2 2 0 k V
2 2 0 k V
R A V I
S H A L I M A R
G U J R A TN E W
U C H - I I
C H A K W A L
S H O R OJ A M
J A M R U DI N D .
T A X I L A
C H I N T I N D .
J H A N G R D
F / A B A D I N D .
M O R O5 0 0 k V
T A N D O J A M 7 6 5 / 5 0 0 k V
L O R A L A I
D.G
.KH
AN
5 0 0 k V S T A T I O N S1 - P e s h a w a r
2 - T a r b e l a3 - G h a z i B r o t h a4 - R e w a t N e w5 - L a h o r e6 - G a t t i
R O U S C H ( I P P )
7 - Y o u s a f w a l a8 - M u l t a n9 - M u z a f f a r G a r h
1 0 - G u d d u
1 1 - D a d u N e w1 2 - J a m s h o r o
H U B C O ( I P P )
I P P s
1 - K A P C O 1 6 3 82 - H U B C O 1 2 9 23 - A E S P A K G E N 3 6 5
5 - K E L 1 3 14 - A E S L A L P I R 3 6 2
6 - S E P C O 1 1 7
7 - H C P C 1 4 0
9 - R O U S C H 4 1 21 0 - S A B A 1 3 4
8 - F A U J I K A B I R W A L A 1 5 7
1 1 - J A P A N P O W E R 1 3 5
1 3 - U C H 5 8 6
1 5 - A L T E R N 1 11 4 - J A G R A N H Y D E L 3 0
1 6 - L I B E R T Y P O W E R 2 3 5
1 2 - C H A S H N U P P 3 2 5
I N S T A L L E DC A P A C I T Y I N M W
I M P O R T E D C O A L
A E S
M I S
AC
/DC
LIN
ES
TO L
HR
/ IS
D N
EW
(CO
NS
UL
TAN
T)
5 0 0 k V
5 0 0 k V
M u h a m m a d A k h t a r
K A R A C H I( G A D A N I )
N O O R IA B A D
C A V A L I E R 5 0 0 M W I P P
P R O G A S 3 4 5 M W I P P
A L - T U W A R I Q I S T E E L M I L L
Domestic
43%
Commercial
6%
Industrial
25%
Bulk
3%
Agri
12%
AJK
2%
KESC
8%
Others
1%
Other
11%
Consumption Mix
10
Historic Demand & Supply Position
Fiscal Year Computed Peak Demand* Corresponding SupplySurplus/ Shortfall
2007-08 17398 12442 -4956
2008-09 17852 13637 -4215
2009-10 18583 13413 -5170
2010-11 19230 13163 -5581
(All Figures in MW)
11
GENERATION - EXISTING CAPACITY (Excluding KESC)
Type of GenerationInstalled Capacity (MW)
De-rated/Dependable
Capacity (MW)
Availability(MW)
WAPDA Hydro* 6,516 6,516 4,500
GENCOs 4,764 3,580 2,000
IPPs (incl. Nuclear) 9,085 8,295 7,600
Rental 393 393 200
Total 20,823 18,784 14,300
12
Hydel
35%
Furnace Oil
35%
Gas
25%Nuclear
3%
Coal 2%
Other
5%
13
Fuel-wise Generation Mix (2010 -2011)
Reasons for Current Power Deficit / Load Shedding
Activity No.Increase in
Demand (MW)
Villages electrified
Population benefitted: 7 m +47,076 188
Connections given (2008-2011) excluding
tube-well connections3,062,215 190
Agriculture tube-wells Connection 40,577 100
Load addition due to installation of air-
conditioners1 Million 2,500
Total 2,978
Quantum jump in power demand during 2008-2011 due to:
� Increase in load as under:
� Non-availability of fuel oil for power plants
� Shortage of Gas Supply to Power Sector 14
AVERAGE GAS REQUIREMENT VS. ACTUAL GAS SUPPLIED TO GENCOS POWER STATIONS
DESCRIP
TIONRequired
Gas (GENCOs)
Gas Available
(GENCOs)
Gap(GENCOs)
Required
Gas
(IPPs)
Gas
Available
(IPPs)
Gap
(IPPs)
Total Gap
(GENCOs +
IPPs)
Availability
(%age)
2005-06 735 583 152 671 524 147 299 79%
2006-07 735 451 284 671 523 148 432 69%
2007-08 735 438 297 671 491 180 477 66%
2008-09 735 405 330 671 408 263 593 58%
2009-10 735 361 374 671 391 280 654 53%
2010-11 735 267 468 671 358 313 781 44%
15
(MMCFD)
• Period : July and July• KESC supply (182 MMCFD) not included
AVERAGE FURNACE OIL RECEIVEDDURING THE YEAR - 2011
16
Average non-Availability of Generation due to Oil & Gas (201 1)� Oil 1800 MW
� Gas 750 MW
15294 15324
18850
15293
17387
20696
17730
31600
30000
28000
26700
31000 31000
32000
0
5000
10000
15000
20000
25000
30000
35000
January February March April May June July
Fuel Oil Supply Vs Demand
Supplied
Required
DisCos Tariff Determined and Notified
17
Tariff Effective Determined
Tariff Rs./kWh
Notified Tariff
Rs./kWh
Difference Rs./kWh
24-02-2007 5.13 4.25 0.88
01-03-2008 5.58 4.78 0.80
05-09-2008 8.35 5.58 2.77
25-02-2009 8.35 5.63 2.72
01-10-2009 8.35 5.88 2.47
21-12-2009 10.09 5.96 4.13
01-01-2010 10.09 6.65 3.44
01-07-2010 10.35 7.05 3.30
01-10-2010 9.57 7.19 2.38
01-11-2010 9.57 7.29 2.28
15-03-2011 9.57 7.44 2.13
06-05-2011 9.57 7.58 1.99
1818
Measures to mitigate Power Shortage
1-GENERATION ADDITION
19
Power Generation Additions March 2008 to July 2011
20
Sr. No.
Name of Project FuelInstalled Capacity /
Retirement (MW)1 Malakand-III , Dargai, KPK Hydel 812 Attock Gen, Rawalpindi, Punjab RFO 1633 Atlas Power, Sheikhupura, Punjab RFO 2194 Engro Power, Dharki, Sindh Gas 2275 Saif Power, Sahiwal , Punjab RFO/Gas 2256 Orient Power, Baloki, Punjab RFO/Gas 2257 Nishat Power, near Lahore, Punjab RFO 2008 Nishat Chunian,near Lahore, Punjab RFO 2009 Sapphire Power, Muridke, Punjab RFO/Gas 22510 Techno Power Faisalabad, Punjab RFO 6011 Liberty Tech, Faisalabad, Punjab RFO 20012 Gulf Rental, Gujranwala, Punjab RFO 6213 Hubco, Narowal, Punjab RFO 22514 Foundation Power, Dharki, Sindh Gas 20215 Halmore Power Project, Bhikki, Punjab Gas.HSD 22516 Chashnup-2, Mianwali, Punjab Nuclear 30017 Karkey Rental Power Plant, Karachi, Sindh RFO 23218 Khan Khawar, Besham, KPK Hydel 7219 Walter Naudero, Naudero Sindh Gas 51
Total 3394
1- Short Term Additions (2011-2013)
21
Sr.No. Name of ProjectCapacity
(MW)Expected COD
A. Public Sector Projects
1. Nandipur Power Project 425
One year after release
of equipment from
Karachi Port
2.UAE Gifted Power Plant at
Faisalabad320 Dec 2012
3. Guddu 750 Nov 2012
Sub-total (A) 1495
B. WAPDA Hydel Projects
1. Allai Khawar HPP 121 Feb 2012
2. Duber Khawar HPP 130 Dec 2012
3. Jinnah Low Head HPP 96 Dec 2012
4. Gomal Zam HPP 17 Feb 2013
Sub-total (B) 364
Sr.No. Name of ProjectCapacity
(MW)Expected COD
C. PPIB Projects (IPPs)
1. Coal Fired PP at Thar (UCG) 100 Jun 2012
2. Radian Energy PP 150 Jun 2013
Sub-total (C) 250
D. AEDB Projects (Wind)
1. Wind Power Projects (14 Projects) 700 2011 – 2013
Total (A+B+C+D) 2809
Short Term Additions (2011 -2013)
22
2-GENCOS’ REHABILITATION
23
2- GENCOS’ REHABILIATATION
Projects NameExisting
CapacityAddition
Expenditure
US$ Million
a. US AID Funded Projects 2055 315 51.621
b. Own Resources Projects 505 180 45.00
c. Projects in plan funding being arranged 550 722 123
G TOTAL 3110 1217 219.621
24
Hydro Power
25
Sr # Name of Project PC-I Cost(Rs. Billion)
Hydropower(MW)
Progress/ Completion
1. KHAN KHWARBesham, KPK 8.301 72 Substantially
Completed
2. DUBER KHWARKohistan, KPK 16.324 130 77%
(Dec 2012)
3. ALLAI KHWAR – Battagram, KPK 8.578 121 74%(Feb 2012)
4. JINNAH HYDROPOWER,Jinnah Barrage 13.546 96 85%
(Dec 2012)
5 GOMAL ZAM DAM 12829 17.4 71%Feb 2013
6 SATPARA DAMOriginal 2090Revised 4806 17.36 97%
Nov 2011
7 REPAIR AND MAINTENANCE OF UNITS 1, 3 & 4 OF TARBELA DAM 1.403 100 Dec 2011
8 NEELUM JHELUM Neelum, AJK 84.502 969 25%(Oct 2015)
9 GOLEN GOL –Khyber Pakhtunkhwa 7.035 106 Feb 2015
Total 156.998 1628.76
MAJOR PROJECTS UNDER EXECUTIONHYDROPOWER PROJECTS
27
HYDROPOWER PROJECTS TO BE UNDERTAKEN FOR IMPLEMENTATION DURING NEXT FIVE YEARS
S# Project RiverCapacity
(MW)Storage(MAF)
Estimated Cost (US$
Million)
Earliest Project
InitiationStatus
1. DIAMER BASHA –Gilgit Baltistan Indus 4500 8.1 11178 2011 Ready for Construction
2. KURRAM TANGI –FATA/KPK Kurram 84 1.2 700 2011 Ready for Construction.
3. TARBELA 4 TH EXT. –Khyber Pakhtunkhwa Indus 1350 - 926 2011 Detailed Engineering and
Design is under process.
4. MUNDA –FATA/KPK Swat 740 1.3 1401 2012
Feasibility Completed. RFP under issue for Detailed Engineering and Design.
5. KOHALA –AJK Jhelum 1100 RoR 2212 2012
Feasibility Study, Detailed Engineering & Design completed. LOI issued by PPIB.
6. BUNJI –GIlgit Baltistan Indus 7100 RoR 6800 2012
Feasibility Study completed. Detailed Engineering & Design completed and under review by WAPDA experts.
7. DASU–Khyber Pakhtunkhwa Indus 4320 1.15 6000 2014
Feasibility Study completed. Selection of Consultants for Detailed Engineering & Design is under process.
8.Others (Bara, Tank Zam Matiltan & Palas Valley etc.) – KPK/GB/AJK
1500 RoR 2011-2015 Under Study.
9. Patan, Shyok, Akhori –KPK/Punjab Indus 3920 12 2015 Under Study.
Total ~ 24,614 23.75
RoR – Run of River
CATEGORY-WISE PLANNED GENERATION UP TO 2030
Plant TypeTotal
Capacity (MW)
1. Nuclear Power Projects 6300
3. Wind Power Projects 1050
4. Coal Fired Thermal Projects 37500
5. RFO/GAS Fired Thermal Projects
9113
6. Cross Border (C.A. & Iran) 2000
Total 55963
28
2929
4-Demand Side Management
Demand Side Management
Program Estimated Saving
(MW)
Replacement of 30 m ILs with CFLs 1000MW
•Replacement of inefficient tube-wells
pumps (230,000 tubewells in Country)
•Program being offered to ADB for funding
1500MW
30
IL : Incandescent lampsCFL : compact fluorescent lamps
� Building Energy Code (BEC), developedo Annual Energy Conservation Potential Approx 2.46 MTOEo Investment Required US$_________o Potential Annual Savings US$ 1.8 Billion
� Energy Conservation in Industry and Power Sectorso Annual Energy Conservation Potential Approx 4 MTOEo Investment Required US$_______o Potential Savings US$ 3 Billion (??)
� Energy Conservation in Water Pumping Systemso Annual Power Saving Potential Approx 1200 MWo Investment Required US$ 766 Million
� Energy Efficiency Standards and Labeling (ES&L) for Domestic Applianceso Annual Energy Conservation Potential Approx 7,000 GWHo Investment Required US$______o Annual Savings US$ 14 Million
� Solarization of Telecom Towerso Annual Power Saving Potential Approx 65 GWHo Investment Required US$______o Annual Savings US$ 11.5 Million
Energy Conservation
PEPCO CDM PROJECTS
Sr.
No
.
Name of Project Power
Saving
(MW)
Carbon Emissions
Reduction per
Annum
(t CO2-eq)
Financing
Requirement
(Million $)
1 Installation of Energy Efficient
Distribution Transformers
700 25386.5 31.5349
2 Provision of LT Capacitors on
Industrial and Agricultural Loads
960.95 3485019 18.272
3 SF6 Gas Leakage Reduction - 7.889 ton SF6 0.4534
4 Conversion of Existing 366 MW
Street Lighting Load to Solar Power
System
366 553062.6 595.116
5 Replacement of Energy Inefficient
Irrigation Tube well Pumps/Motors
with Energy Efficient Standard
Pumps/Motors
1181 1784609 765.9884
Generation Mix %ageYear Hydel Thermal1995 50% 50%1996 47% 53%1997 41% 59%1998 41% 59%1999 42% 58%2000 34% 66%2001 29% 71%2002 31% 69%2003 35% 65%2004 40% 60%2005 35% 65%2006 37% 63%2007 36% 64%2008 33% 67%2009 34% 66%2010 32% 68%
Name of Company
2008-09 2009-10 2010-11
Actual % NEPRA Target % Actual % NEPRA
Target %Actual
%NEPRA
Target %
LESCO 13.3 12.3 13.8 12.0 13.3 12.0
GEPCO 11.0 11.3 11.0 10.5 12.0 10.5
FESCO 10.7 11.2 10.8 11.0 11.2 11.0
IESCO 10.8 11.0 9.8 10.0 9.8 10.0
MEPCO 18.4 17.5 19.0 15.0 18.3 15.0
PESCO
35.233.2
34.628.0
35.228.0
TESCO Not NEPRA licensee
HESCO
35.1 34.4
29.3
28.0
27.2
28.0SEPCO
40.7(34.8)
41.0(33.8)
QESCO 20.1 20.5 20.7 18.0 20.8 18.0
DISCOS Total 19.4 - 19.6 - 19.6 -
DISTRIBUTION LOSSES (%age)
(132KV & Below System)
35
35
Peak Demand Projections* (whole Country)2007–2030
*Projected demand includes captive power also. Average growth rate is expected to be about 8%
COUNTRY PEAK DEMAND & SUPPLY 2011–2030
POWER IMPORT PROJECTS
CASA-1000 PROJECT
M. WASEEMYOUNUS
KABUL
DATKA
DATKA TO KHUJAND PROPOSED 500kV A/C NETWORKKHUJANDTO SANGTUDA EXISTING 500kV A/C NETWORK
SANGTUDA TO KABAL PROPOSED 500kV D/C NETWORKKABALTO PESHAWAR PROPOSED 500kV D/C NETWORK
SUR KHAN TO PESHAWAR PROPOSED 500kV D/C NETWORK
MUHAMMAD DAUD
NISAR AHMADBAZMI
E. C. O. COUNTRIES
DRG# GMPP/
(Geographical)
DATE20-10-11
NTDC G M PLANNING SHAHID
MAHMOOD
D.M
DWN
C.E
G.M
AFGHANISTANIRANIRAQ
SYRIA
TURKEY TURKMENISTAN
CASACASACASACASA----1000 1000 1000 1000 IntroductionIntroductionIntroductionIntroduction
1. Project is designed to transmit 300 MW to Afghanistan and
1000MW to Pakistan
2. 500kV ac line (477 km) and 500kV DC line (750 km)
3. Total project cost US Dollars 873 million
4. Cost of project part in Pakistan US Dollars 182 million
5. Average cost of energy at source 1.75 cent/kwh
6. Levellized cost of transmission 5 cents /kwh
7. Cost at receiving end 6.75 cents/kwh
39
Annual Energy Flow
40
IMPORT OF POWER
FROM
UZBEKISTAN
42
The Map of Central AsiaThe Map of Central AsiaThe Map of Central AsiaThe Map of Central Asia
42
IMPORT OF POWER FROM UZBEKISTANIMPORT OF POWER FROM UZBEKISTANIMPORT OF POWER FROM UZBEKISTANIMPORT OF POWER FROM UZBEKISTAN
1. Project is designed to transmit 1000MW to Pakistan
2. 500kV DC line (900 km)
3. Total project cost US Dollars 638 million
4. Cost of project part outside Uzbekistan USD 460 million
5. Cost of project part in Uzbekistan US Dollars 178 million
6. Average cost of energy at source 6.0 cent/kwh
7. Levellized cost of transmission 1.5 cents /kwh
8. Cost at receiving end 7.5 cents/kwh
43
44
UCH - II P/H
MUHAMMAD DAUD
GWADAR
G. DOWNTOWN
G. INDUS
G. DEEP SEAG. SANGHAR
NISAR AHMADBAZMI
DATE21-05-11
MALL
MASHKAY
AWARAN
NOHSAR
KHANMEHTERZAI
1000 MWIMPORT FROM IRAN
DALBANDIN
NEAR QUETTASUB STATION±500kV HVDC/220kVHVAC
GHEB
N. T. D. C
D.M
DWN
C.E
G.M
MANDTUMP
TURBAT
HOSHAB
PASNIT.P.S
GWADAR220kV
PANJGOR
KHUZDAR
BAGHBANA
SURAB
GIDDER
KHARAN
KALAT
MANGOCHER
KHAD KUCHA
KIRD
SARYAB
SIBBI
BHAG
QUETTA
SORRANGE
SHARIG
HARNAI
LORALAIMEKHTER
KINGRI
S.SARWARBARKHAN
ZHOB
M.PUR
G.H.ZAI
UCH P/H
MUSLIM BAGH
PISHINGULISTAN
Q.ABDULLAH
CHAMAN
HABIBULLAH
ALIZAI
J.MAGSI
USTAMOHD
GHARIKHAIRO
R.JAMALI
JACOBABAD
ZEHRI
RAKHNI
IRAN
JIWANI
BELA
UTHAL
KARACHI
TUFTAN
WADH
NAL
CHAGAI
QUETTA
SH:MANDA
HABIBULLAH
MARRIABAD
MASTUNGMACH
SIBBI
QUETTARING
A R A B I A N S E A
M.K.BAZARQUETTA RING
GANDAKHA
MANJOSHORI
CHATTAR
DUKI
THULL
JACKIGOR BULEDA
DADU NEW
KASHMOR
SUI
DERABUGTI
KAHAN
MAWANDKOHLU
BAKHER
DRUG
KUCHLAK
SAMBAZA
ZIARAT
ORMARA
MASHKHEL
CHOBAHAR
121km
BASIMA
POLAN G/S
M. WASEEMYOUNUS
33KV
LEGEND
±500kV HVDC
PROPOSED
G/STN T/L
500kV THERMAL P/STN
500kV
220kV
EXISTING
G/STN T/L
220kV THERMAL P/STN
66KV
132KV
JEWA
CITY
INDUS.
PCSIRHAZAR GANJI
PISHIN
HABIB ZAI
D.K.ZAI
HUB
DARWAZA
EXPANSION PLAN UPTO 2020
Q E S C O
DRG# GMPP/Geog/Q/008
ELECTRICAL NETWORK(Geographical)
G. M. PLANNING POWERSHAHID
MAHMOOD
IMPORT FROM IRANIMPORT FROM IRANIMPORT FROM IRANIMPORT FROM IRAN
1. Project is designed to transmit 1000MW to Pakistan
2. 500kV DC line (678 km)
3. Total project cost US Dollars 656 million
4. Cost of project part in Pakistan USD 413 million (585 KM)
5. Cost of project part in Iran US Dollars 243 million
6. Average cost of energy at source 5.3 cent/kwh
7. Levellized cost of transmission 1.5 cents /kwh
8. Cost at receiving end 6.8 cents/kwh
46
47