L&T – Galfar Consortium
Main Contract 5 Development of Salalah Airport
METHOD STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FOR INSTALLATION OF HDPE PIPE
Aconex No: SA-LTG-05EL-MST-0014
Rev No
Date Description Prepared Checked Approved QA QC HSE
111.03.201
2
Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation
RN / APY RKR / NRVV UKN LKJ
SA-LTG-05EL-MST-0003 Page 1 of 19
L&T – Galfar Consortium
Contents Page No
1.0 Scope ---- 3
2.0 Purpose ---- 3
3.0 References ---- 3
4.0 Definitions ---- 3
5.0 Responsibilities ---- 3
6.0 Resources ---- 4
7.0 Procedure ---- 5
8.0 Quality assurance ---- 10
9.0 Health and Safety ---- 10
10.0 Environmental Issues ---- 11
11.0 Attachments ---- 11
SA-LTG-05EL-MST-0003 Page 2 of 19
L&T – Galfar Consortium
1.0 SCOPE
Horizontal Directional Drilling for High Density Polyethylene Pipe Installation at 132kV Cable Installation in necessary road crossing Area.
2.0 PURPOSE
The purpose of this method statement is to describe the sequential procedure for Installing the HDPE Pipe to be complete in a planned and safe manner by satisfying the project specifications and requirements for MC-5 Development of Salalah Airport.
3.0 REFERENCES
Contract Tender Specification SA-000-O-11139 (3902.132kV Cable Systems)
Approved vendor drawings / documents. Overall Equipment Layout, Plan & Section Details (The approved plan and section details will
be used at site.) Approved Material Approval Submittal (SA-LTG-05EL-MAS-0002) HSE Management Plan (Ref: SA-LTG-05AP-PLN-0003 Rev-2) HSE Guide lines for supervisors (Ref SA-LTG-05SC-PRO-0006).
4.0 DEFINITIONS
Manufacturer
Vendor / Supplier
IFCIRITPMIREngineerHSEQCIHEMPHDD
-
-
---------
The party responsible for the manufacture of equipment and services to perform the duties specified by the Consultant or Company.A party responsible for the supply of equipment, materials or product-related services in accordance with the Purchase Order issued by company or its nominated Purchasing Office.Issued For Construct ionInspection RequestInspection & Test PlanMaterial Inspection RequestCowi-Larsen JVHealth, Safety & EnvironmentQuality Control Inspector Hazards and Effects Management ProcessHorizontal Directional Drilling
HDPEBDAELCB
---
High Density Poly EthyleneBefore, During and After.Earth Leakage Circuit Breaker
5.0 RESPONSIBILITIES
Package Manager: Responsible for overall activities and ensure that the works are carried out as per Specifications, HSE and Quality Requirements.
SA-LTG-05EL-MST-0003 Page 3 of 19
L&T – Galfar Consortium
Construction Manager: Responsible for control of operation and ensure that the works are carried as per the specifications, Drawings and Method Statements. Shall ensure the specifications, Drawings, Method Statements are available on site and is communicated down to Site Engineer.
Project Engineer: Will coordinate with Site Engineers and ensure all the project activities are performed according to the scheduled program, HSE procedures and Quality procedures. Will ensure the Specification, Drawings, Method Statements are available on site and is communicated down to Site Engineer.
Site Engineer: Will be responsible to ensure site Construction activities are being executed as per approved Method Statement, Specifications, latest IFC drawing, relevant QC check list & formats are duly completed as per Inspection & test plan. Materials used at site are as per Approved Material submittal.
Land Surveyor: Shall coordinate with Construction Manager and Site Engineer for setting out (the site controls) using line & levels and approved coordinates as per IFC drawings.
QA/QC Engineer: Will be aware of the daily construction program. Will attend all inspection points, witness the results of the inspection on the appropriate forms and obtain the approval signatures. Compile and maintain all inspection records.
QC Inspector (QCI): Will be aware of the daily construction program. Will attend all inspection points, assist with the QA QC Engineer by record the results of the inspection on the appropriate forms and obtain the approval signatures. Compile and maintain all inspection records.
HSE Advisor: Shall advise the line staff & workers on HSE matters; organize / conduct HSE training, facilitate implementation of HSE requirements, monitor compliance and report performance and non-performance.
Vendor Representative: Shall coordinate with site engineer and supervisor for Installing the Transformer and accessories as per the General Arrangement Vendor drawing. Follow the procedures and HEMP control measures.
Foreman: Shall coordinate with the Site Engineer and will be responsible for individual activity. Ensure that latest IFC drawings are being used at site. Organizing all necessary material, tools, equipment to the work site and assigning workers prior to commencement of work. Follow the procedures and HEMP control measures. Ensures that all recommended PPE be used by the workers. Ensure that risk control measures are known to workers by arranging daily toll box meetings.
Technicians: Will receive the work instruction from the supervisor and carry out the activity in line with the IFC drawing & stipulated schedule.
Helper: Will receive the work instruction from the supervisor and carrying out the activity by assisting with the Technicians to complete the specified task in the stipulated period.
SA-LTG-05EL-MST-0003 Page 4 of 19
L&T – Galfar Consortium
6.0 RESOURCES6.1 Manpower
Manpower shall be used for Horizontal Directional Drilling work Includes but not limited to, Site Engineer HSE Advisor Foreman Land Surveyor Machine Operator Welders Helpers
6.2 Tools & Equipment’s
Tools and Equipments shall be used for HDD work, but not limited to:
Drilling System Drill Head Guidance System Drilling Fluid System Drilling Fluids Mud Delivery System Pipe rollers or cranes Welding machine
7.0 PROCEDURE7.1 MATERIAL DESCRIPTION
7.1.1 DRILLING SYSTEM
The directional drilling rig shall consist of a hydraulically powered system to rotate, push and pull hollow drill pipe into the ground at a variable angle while delivering a pressurized fluid mixture to a guidable drill head.
The rig shall be anchored to the ground to withstand the pulling, pushing and rotating force required to complete the crossing.
The hydraulic power system shall be self contained with sufficient pressure and volume to power drilling operations.
Rig shall have an automatic and continuous system to monitor and record maximum pull-back force during pull-back operations.
Pulling capacity of the drill rig shall be at least two times the calculated pulling force.
SA-LTG-05EL-MST-0003 Page 5 of 19
L&T – Galfar Consortium
7.1.2 DRILL HEAD
The drill head shall be steerable by changing its rotation and shall provide the necessary cutting surfaces and drilling fluid jets.
7.1.3 GUIDANCE SYSTEM
An electronic guidance system shall be used to provide a continuous and accurate determination of the location of the drill head during the drilling operation.
The guidance shall be capable of tracking at all depths and in any soil condition, including hard rock. It shall enable the steering engineer and the rig operator to guide the drill head by providing immediate information on the tool face, azimuth (horizontal direction) and inclination (vertical direction) and actual depth & pre-computed depth.
SA-LTG-05EL-MST-0003 Page 6 of 19
L&T – Galfar Consortium
7.1.4 DRILLING FLUID SYSTEM
A self-contained, closed drilling fluid mixing system shall be of sufficient size to mix and deliver drilling fluid composed of bentonite clay,clean water and appropriate additives.
The mixing system shall be able to molecularly shear individual bentonite particles from the dry powder to avoid clumping and ensure thorough mixing.
The drilling fluid reservoir tank shall be sized for adequate storage of the mud. The mixing system shall continually agitate the drilling fluid during drilling operations and
provide the drilling mud directly to the on-board mud pressure pump at the rig.
7.1.5 DRILLING FLUIDS
Drilling fluids shall be composed of clean water, appropriate additives and bentonite.
Water shall have a minimum pH of 8.0. Water of a lower pH or with excessive calcium shall be treated with the appropriate amount of sodium carbonate or equivalent.
Drilling fluid shall be maintained at a viscosity sufficient to suspend cuttings and maintain the integrity of the bore wall.
7.1.6 MUD DELIVERY SYSTEM
The delivery system shall have a minimum capacity to supply mud in accordance with the required drilling equipment and pull-back rating at a constant required pressure.
A berm of suitable height shall be maintained around drill rigs, drilling fluid mixing system, entry and exit pits and drilling fluid re-cycling system to prevent spills into the surrounding environment.
7.1.7 OTHER EQUIPMENT
Pipe rollers or cranes shall be of sufficient size to fully support the weight of the pipe during pull-back operations. Adequate number of rollers shall be used to prevent excess sagging of pipe. Rollers shall also have height adjustment feature, where required or the use of side booms or cranes.
Equipment for welding, field joint coating and filed hydro testing shall be used as per specifications.
7.2 WORK PROCEDURE
The working steps of Horizontal Directional Drilling (HDD) are as follows:
7.2.1 SITE SURVEY
A site survey shall be located for existing buried utilities and identify the intended location of the bore path and depths.
Environmental issues shall be addressed and permits shall be obtained for commencement of HDD works.
Crossing Survey shall be identified for clear bore path. Trial holes and utility identification shall be made for HDD works completed in a safe manner.
SA-LTG-05EL-MST-0003 Page 7 of 19
L&T – Galfar Consortium
Excavation shall be done both a launch pit at the entry side of the crossing and a reception pit of the crossing in the desired location according to utility identification and safety parameters of the site environment.
Safety guidelines shall be followed around both launch and reception pits. HDD cross section Profile drawing shall be made available for works to commence.
7.2.2 RIG SET-UP AND PILOT HOLE DRILLING
The directional drilling equipment shall consist of a directional drilling rig to perform the drilling and pullback the pipe, a drilling fluid mixing and delivery system to successfully complete the crossing, a guidance system to accurately guide drilling operations and trained and competent personnel to operate the system.
Equipment shall be made in good and safe operating condition with sufficient supplies, materials and spare parts on hand to maintain the system in good working order for the duration of the work.
Pilot Bore:
Horizontal Directional Drilling activity will involve the installation of 6 nos of 1x200mm HDPE pipe per boring with an estimated total length of 612 metres with 5 nos. of locations.
The pilot bore of the first hole shall be drilled continuously from launch to reception pit. The pilot bore shall be guided and steered throughout the pilot bore using radio location
equipment positioned in the drilling head itself, which indicates the angle and position of the drill head and shows the actual depth of the head and a pre-computed forecast of the drill head position.
The drill string is able tosteer and change direction with the use of a “slant nose” drilling bit. This acts as a wedge when thrusted through the surrounding soil without rotation or a motor for rock drilling.
The change in alignment and pitch shall be monitored by the steering supervisor. The desired deviation has been achieved, the drill stem shall be rotated constantly and thrusted through the soil to follow the new bore path.
During the pilot hole, the depth from ground level to every 3 meters shall be recorded by drilling record sheet.
The depth shall be confirmed with the drill head detector which will be calibrated prior to commencement of drilling and recorded in record sheet.
Note: The minimum clearance under any known existing utility shall be 1.5 meters. Bentonite fluid shall be pumped constantly through the drill string and used to clear the bore of
excavated material and also to fill the annulus around the drill pipe to maintain a positive
SA-LTG-05EL-MST-0003 Page 8 of 19
L&T – Galfar Consortium
pressure within the bore at all times. This shall be monitored visually in the launch pit by the quantity and quality of the bentonite returning to the pit.
Pilot Hole Drilling
HDD equipment shall be made set up approximately 10-15m back from the launch pit and then drills through the launch pit and continues the bore to the reception pit. When the back reaming commences, the launched pit shall be enlarged to receive the pipeline.
SA-LTG-05EL-MST-0003 Page 9 of 19
L&T – Galfar Consortium
7.2.3 COMMENCEMENT OF BACK REAMING STAGE
After the pilot bore has been completed, the drill head shall be removed from the drill string and the first back reamer (12 inches) shall be attached to the string to enlarge the hole.
The back reamer shall be rotated continuously in a clockwise direction through the bore from reception pit to launch pit.
After the back reamer reaches the launch pit, it will remove and the drill head shall be re-installed on the drill string and again rotated clockwise through the bore back to the reception pit.
During this process, the drill head shall be monitored continually and checked with equipment location to ensure that it is in the correct bore path (the reamer shall not be pushed back through the bore).
The reaming process shall be done until the desired final bore diameter has been achieved (during all the reaming stages, bentonite shall be pumped constantly through the drill pipe and the back reamer shall be prevented by wear and clears the bore of excavated material and the entire bore path shall be maintained a positive pressure).
NOTE: The reaming stages could vary depending on the ground conditions on each individual crossing.
7.2.4 PIPE PULLING
HDPE pipes shall be joined together to make one for continuous installation.
The approved pipe shall be inspected by Engineer prior to installation. The HDPE pipe shall be lowered into a trench in line with the prepared bore and
connected to the back reamer with the use of a pulling swivel and steel pulling head which is fabricated onto the front of the pipeline.
The pipe shall be installed carefully into the bore behind the reamer. Bentonite shall be pumped continuously through the reamer to allow smooth insertion of
the pipe into the prepared bore path and allow enough access material to flow from the bore.
During this stage of works, the flow of bentonite from pipe side and rig side shall be monitored carefully for no undue build-up of pressure within the bore path.
The annulus between the pipe and the bore shall be grouted with a mixture of bentonite and the surrounding soil which quickly starts to set after completion of works.
SA-LTG-05EL-MST-0003 Page 10 of 19
L&T – Galfar Consortium
The bentonite shall be made for set and provide protection around the HDPE pipe. Bentonite is also used for lubrication to reduce the amount of friction enforced upon the HDPE pipe.
7.2.5 DEMOBILIZING SITE
After HDPE pipe has been installed, the HDD machine shall be disconnected from the pipe and safely removed.
while all other works are completed, The launch and reception pits shall be poured by surplus bentonite material.
The pulling head shall be removed from the installed pipe.
8.0 QUALITY ASSURANCE
The Quality Assurances encompass of following.
1. Check, hold points are followed and Works Execution inspection and Tests shall be monitored, witnessed and recorded as per ITP SA-LTG-05EL-ITP-0001
2. Work shall be executed as per the IFC drawings and specifications.3. Ensure materials used are as per approved Material Approval Submittals ( SA-LTG-05EL-
MST-0002)4. Inspection Request forms (IR) will be raised and approval from engineer will be obtain before
proceeding the next activity as per ITP.
SA-LTG-05EL-MST-0003 Page 11 of 19
L&T – Galfar Consortium
5. Marked up drawings, Final As built Drawing will be prepared and approval will be obtain from Engineer.
9.0 HEALTH AND SAFETY
All employees involved in the activity shall undergo site HSE induction course prior to deployment to the work site.
Site activities shall be carried out in a safe manner according to the approved “Project Health, safety and environment plan”.
9.1 Training (Workers & supervisors).
The following HSE training shall be delivered to the crew but not limited to:
Awareness about emergency response. Use of hand tools. Excavation Hazards. Hazards of HDD Rig operation. Access / Egress. Hot work. MSDS awareness.(Drilling Fluids)
9.2 Risk Assessment and control – through HEMP.
HSE Hazards involved in the activity has been assessed through Hazards & Effects Management Process (HEMP) for each and every activity and the outcome is recorded. (Refer attachment)
The contents in HEMP Register shall be disseminated within the crew by the shift supervisor / foreman, through Toolbox Talk.
Any new hazards identified other than in the HEMP with reference to site conditions shall be assessed and control measures shall be taken by the Site Engineer/Supervisor prior to commencement of any activity.
Following control measures generally apply to all hazards that shall be adopted as a proactive measure in addition to the specific controls identified in the HEMP Register: Correct use & maintenance of tools and equipment. Deployment of competent personnel for the task. Conduct daily toolbox talks prior to work commencement Provision of adequate hazard warning signage/ barricades etc. Provision of first aid and fire fighting appliances. Good Housekeeping. Adequate and effective supervision. Use of necessary PPE. Provision of welfare facility.
SA-LTG-05EL-MST-0003 Page 12 of 19
L&T – Galfar Consortium
9.3 Additional Personal Protective Equipment (PPEs).
Cotton hand Gloves – for manual handling, rubber hand gloves for handling of hazardous materials etc.
Ear plug if welder noise is above action levels.
Use of dust mask if required.
9.4 First Aid / Medical Facility / Emergency Response
Availability of First Aiders, with ready access to first aid boxes kept at site shall be ensured at worksite.
Site clinic will be manned with Doctor during working hours. In case of any emergency, call LTG emergency number 93216576 for help. Follow project wide LTG emergency response arrangements.
10.0 ENVIRONMENTAL ISSUES
Dust.
Noise.
10.1 Mitigation Measures
Dust control by water spraying around the area.
Ensure use of Ear plug, if required.
11.0 ATTACHMENTS
HSE Hazards and Effects Management Process (HEMP)
SA-LTG-05EL-MST-0003 Page 13 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
HDD route survey for road crossing.
Health Dehydration /
sunstroke.2 B L
Drinking water at a rate of up to 1 liter / hr if condition required it.
Ensure to use survey umbrella / Shade net shelter wherever required.
Intermittent rest breaks ensured. Eye protection and wearing of dust protection
ensured shall be worn if condition required it.
L
Medical Aid. (while out in the heat and son.)
Safety Hit by vehicle Vehicle collision Slip, trip and fall Bites from poisonous
creatures
3 B M
Provide appropriate sign board, caution board, diversion boards wherever necessary.
Ensure to have flagman with red / green flag and whistle to control the traffic.
Awareness on the site geographical nature. Awareness training to crew on the territorial
dangerous creature and safety precautions and emergency responses.
Ensure a vehicle presence at the survey site for emergency requirements.
First aid facility is available at place. The access / egress shall be free from obstacles. Stop job in the event of adverse weather
conditions.
L
Emergency response
EnvironmentNA
NA NA
Manual handling.
Health Body pain. Strain / Fatigue.
2 B L Intermittent rest breaks. Access to welfare facilities along the survey route. L
Medical Aid
Safety Injury due to sliding of
tray.
3 B M Refer the HSE Guidelines to supervisors – Ref: SA-LTG-SC-PRO-0006– Item No. 7.0 ( 1 )
Tool box talk prior to start of job.
L Medical Aid and Emergency response
SA-LTG-05EL-MST-0003 Page 14 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
Slip, trip and fall injury. Injury from sharp ends. Property damage.
Appropriate hand gloves use for the task. Entry restriction to other personnel. Display of caution / warning signage at site. Awareness training ensure to site personnel.
EnvironmentNA
NA NA
Access / Egress.
(General)
Safety Ergonomic issues Slip, Trip and fall
Injuries. Injury to other
personnel working nearby.
Cut injury due to contact with Sharp edges.
4 B M
Refer the HSE Guidelines to supervisors – Ref: SA-LTG-SC-PRO-0006– Item No. 7.0 ( 7 )
Ensure suitable access with handrails and intermittent landings is provided to reach work locations.
Ensure intermittent rest breaks. The access / egress shall be free from obstacles. HSE monitoring. Good housekeeping shall be maintained at site.
L
Medical Aid and Emergency response
Unloading the HDD Rig Machine and accessories..
Health Strain / Fatigue. 2 B M
Intermittent rest breaks. Ensure welfare facility on site. L
Medical Aid
Safety Crush injury. Property damage Property damage Injury / fatality to
operatives in the area. Injury from sharp ends.
4 B M Competent equipment operator for the unloading activities.
Proper access & egress arrangements. Ensure Yellow flashing beacon on the vehicle
cabin. Provide guidelines while unloading of Rig. Restrict access to authorised personnel only.Good housekeeping shall be maintained at place.
L Medical Aid and Emergency response
SA-LTG-05EL-MST-0003 Page 15 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
EnvironmentNA
NA NA
HDD Rig set -up.
Health Fatigue Body pain
2 B L Intermittent rest breaks. Welfare facility available at site. L
Medical Aid
Safety Slip, Trip and fall. Injuries Finger pinch, pierce
and crush injury. Cuts from Sharp
edges.
2 B M
Competent personal for the task Proper access & egress arrangements. Restrict access to authorised personnel only. Ensure use of suitable hand gloves. Ensure Rig set-up place shall be well compacted
and leveled. Barricade the Rig set-up area and display caution/
warning signs. Good housekeeping shall be maintained at site.
L
HDD Drill Machine Operation.
Health Dehydration Fatigue
2 B L Ensure the use of appropriate PPE Provision of welfare facility on site Periodic rest breaks for the operators.
L Medical aid
Safety Injury due to flying
objects. Property damage Personal Injury Personal injury Slip, Trip and falls Contact with sharp
bends. Injury /fatality due to
entrapment in rotating parts.
4 B M Competent personal for the task Proper access & egress arrangements. Restrict access to authorised personnel only. collection & disposal of wastes Keep material at 1 Meter away from the edge of
the pit Inspect excavations daily and subsequent to rain
or ingress of water from other sources to confirm stability of the sides prior to allowing personnel to work.
Barricade the area & place caution/ warning signs Ensure emergency response awareness to the
L Emergency response
SA-LTG-05EL-MST-0003 Page 16 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
Adverse weather Loss of reputation Splash of chemical
(bentonite)
crew Equipment and tools are inspected and certified
prior to deployment. High visibility jacket shall be used always. Awareness against the use of mobile phone
during road crossing. Reflective sticker and flickering lights to be used
during nights. Prior inspection and authorization to start the HDD
Drill machine and the machine is serviceable. A floor is compacted for keeping the HDD
machine and operates. HDD rig operator is competent and experienced
for the task for drilling fluids. MSDS kept at site and the content is known to all
site operatives. No oil leak is ensured from machine and spill trays
are kept stand by for use. Environment Waste generation Noise Dust
2 B L
Waste collection and periodic disposal Periodic water spraying to suppress the dust
nearby area. Ensure Dark glass & dust mask usage for the site
personnel if site condition required it. Use of ear plug ensured and used if require.
L
Waste Management
Hot Work.(Welding & Grinding)
Health Fatigue 2 B L
Ensured welfare facilities on site. Intermittent rest breaks. L
Medical Aid
Safety Personal injury Contact with hot
surface
4 B H
Refer the HSE Guidelines to supervisors Ref: SA-LTG-SC-PRO-006, Ref.No:7.0 –.Item 11 on Guidelines on Hot works.
Competent Personnel for the task
L
Emergency response
SA-LTG-05EL-MST-0003 Page 17 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
Fire hazard Electrocution. Adverse weather
Obtain applicable LTG permit prior to start of hot work.
Ensure ELCB fitted in power distribution board. Use of appropriate hand gloves for handling hot
surfaces. Remove reflective jacket during hot work. Ensure used face shield during grinding operation. Ensure Fire extinguisher is available at site. Ensure fire warden is available at site. Barricade the area & display caution/ warning
signs. Access restricted to authorised personnel only. Awareness training on emergency response. Good housekeeping shall be maintained at site.
Environment Noise 2 B L
Ensure use of ear plug if required.L
Environment management .
Pipe pulling in underground hole.
Health Fatigue Body pain
1 B L Intermittent rest breaks. Welfare facility available at site. L
Medical Aid
Safety Injury to personnel. Property damage. Finger pinch, pierce
and crush injury Slip, trip and fall. Injury to other
personnel working nearby.
Bites from poisonous
4 B M Selection of workers with respect of competency and health fitness.
The access / egress shall be free from obstacles. Barricade the area & display caution/ warning
signs. Provision of adequate supervision and HSE
monitoring. Emergency response to be known to all people. Care shall be taken while working near to other
services.
L Emergency Response
SA-LTG-05EL-MST-0003 Page 18 of 19
MC-5 DEVELOPMENT OF SALALAH AIRPORT
HSE Hazards and Effects Management Process (HEMP)
Activity: Horizontal Directional Drilling for High Density Poly Ethylene Pipe Installation MS: SA-LTG-05EL-MST-0012
CO
NS
EQ
UE
NC
E
(0,1
,2,3
,4,5
)
PR
OB
AB
ILIT
Y(A
,B,C
,D,E
)
RIS
K R
AN
KIN
G
CONTROL MEASURES
RESIDUALRISK
RE
CO
VE
RY
M
EA
SU
RE
S
SIGNIFICANT SAFETY HAZARD
HAZARD EFFECT
creatures. Keep the materials properly and away from work site.
Ensure use of suitable hand gloves. Awareness training on emergency response. Good housekeeping shall be maintained at place.
EnvironmentNA.
NA NA
APY MK UNK
HSE Advisor HSE Manager - PABS HSEM - LTG
Prepared by Checked by: Approved by
Revision Date Hemp ref:
1 11.03.2012 PABS / SA-LTG-05EL-MST-0012
SA-LTG-05EL-MST-0003 Page 19 of 19