MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

47
MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd.

Transcript of MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Page 1: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF 4.0 in 60-minutesMSF 4.0 in 60-minutes

Milen PetrovGriffin Ltd.Milen PetrovGriffin Ltd.

Page 2: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Goal: A quick fly-by of what’s new… so thatyou can explore the details at a later time.

Page 3: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 4: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

A Brief HistoryA Brief History

1994 1995 1997 1999 2002 1994 1995 1997 1999 2002 2005-06 2005-06

MS

F O

fferi

ng

MS

F O

fferi

ng

MSF MSF v1v1

21 Rules21 Rules

““DynamicDynamics”s”

SolutionsSolutionsDevDevDisciplineDiscipline(SDD)(SDD)

MSF v2MSF v2Principles of …Principles of …App Dev (PAD)App Dev (PAD)Infra Deploy (PID)Infra Deploy (PID)Ent Arch (PEA)Ent Arch (PEA)Comp Des (PCD)Comp Des (PCD)

MSF MSF v2.5v2.5

MSF v3MSF v3

EssentialsEssentials+ Exam+ Exam

CoreCoreAgileAgileCMMICMMI……

MSF v4MSF v4

Page 5: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Why Can’t ProcessHelp Productivity?Why Can’t ProcessHelp Productivity?

PredictablePredictableRepeatableRepeatable

ProductiveProductive

FrameworkFramework MethodologyMethodology

GuidelinesGuidelinesRulesRules

CompleteCompleteSufficientSufficient

Page 6: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Process & Tools IntegrationProcess & Tools Integration

Visual Studio Visual Studio 2005 Team 2005 Team

SystemSystem

enactsenacts

guidesguides

Microsoft Microsoft Solutions Solutions

FrameworkFramework

How VSTS enables MSF?Productivity tools & processesIntegrated tools & processesExtensible tools & processes

Page 7: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 8: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSFv4 Family TreeMSFv4 Family Tree

FrameworkFramework

MethodologyMethodology

MSF for MSF for Agile Agile

Software Software DevelopmeDevelopme

ntnt

MSF for MSF for CMMICMMI®®

Process Process ImprovemenImprovemen

tt

InfrastructInfrastructureure

MSFv4 CoreMSFv4 Core

Application Application DevelopmeDevelopme

ntnt

DisciplineDiscipline

ProductProduct(instantiated)(instantiated)

FamilyFamily

Page 9: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Content RelationshipContent Relationship

MSFv4 MSFv4 “Core”“Core” DisciplineDiscipline

InfrastructurInfrastructuree

MSF for Agile MSF for Agile Software Software

DevelopmentDevelopment

MSF for CMMIMSF for CMMI®® Process Process

ImprovementImprovementProductProduct

Application Application DevelopmentDevelopment FamilyFamily

MSF v4MSF v4

MSF v3MSF v3

InfrastructureInfrastructureCMMICMMI

AgileAgile

Page 10: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Continuum of MethodologiesContinuum of Methodologies

Page 11: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 12: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

What is MSFv4?What is MSFv4?

RiskRiskManagementManagement

DisciplineDiscipline

Governance Governance ModelModel

TeamTeamModelModel

ProjectProjectManagementManagement

DisciplineDiscipline

ReadinessReadinessManagementManagement

DisciplineDiscipline

ModelsModels

DisciplinesDisciplines

A set of foundational principles, mindsets and proven practices with an adaptable framework for successfully delivering solutions faster, requiring fewer people, and involving less risk, while enabling higher quality results.

Page 13: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

FundamentalsFundamentals

Principles

MindsetsKey Concepts Mindsets

Proven Practices

Page 14: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

PlanningPlanning

Risk Analysis

Scheduling Process

Stakeholder Analysis

Readiness Management

Requirements PrioritizationSimpleKano Analysis

Page 15: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Team ModelTeam Model

Advocacy

GroupingsWas: Role Clusters

New: ArchitectureResponsibilities pulled from Proj Mgmt and Dev

Release

OperationsWas: Release Mgmt

More functional

areas in each

advocacy group

Page 16: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Governance ModelGovernance Model

GovernanceWhich projects should we do?Which features?How much capacity to allocate?How is value delivered?

CapacityEnactmentMeasurable productivityManageable deliveryHow to improve?

Page 17: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Process ModelProcess Model

Phases

Tracks

Develop Track

Build Track

Milestones

Checkpoints

EnvisionEnvision

PlanPlan

BuildBuild

StabilizeStabilize

DeployDeploy

Release 1Release 1

Page 18: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Time

Iterative ApproachIterative Approach

Minimize risks by breaking large projects into multiple versions

Solu

tion

S

olu

tion

C

om

ple

tion

Com

ple

tion

Ris

kR

isk

Kn

ow

led

ge

Kn

ow

led

ge

Page 19: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Envision TrackMSF Envision Track

Deliverables

Vision/scope document

Project structure document

Initial risk assessment document

Goals

Develop a clear understanding of what is needed within context of project

constraints

Assemble necessary team to envisage solution with options and approaches

that best meet those needs while optimally satisfying those constraints

Envision

Envision

Core Team OrganizedCore Team Organized

Vision/Scope BaselinedVision/Scope Baselined

Vision/Scope Vision/Scope ApprovedApproved

Page 20: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Plan TrackMSF Plan Track

Deliverables

Functional specifications

Master project plan

Master project schedule

Goal

Evolve conceptual solution into tangible designs and plans so it can

be build in the developing trackFind out as much information as possible, as early as possibleKnow when you have enough information to move forward

Technology Validation CompleteTechnology Validation Complete

Functional Specification BaselinedFunctional Specification Baselined

Master Project Plan BaselinedMaster Project Plan Baselined

Master Project Schedule BaselinedMaster Project Schedule Baselined

Supporting Environments Set UpSupporting Environments Set Up

Project Project Plans Plans ApprovedApproved

Pla

nP

lan

Page 21: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Deliverables

Completed SolutionTraining materialsDocumentationMarketing materialsUpdated master plan, schedule and risk document

GoalBuild various aspects of the solution in accordance with plan track deliverables (e.g., designs, plans, requirements)

Develop solution features and components, complete deliverables and other elements of the solutionTest the various aspects of the solution to assess the state of quality of the solution

MSF Build Track

BuildProof of Concept Proof of Concept CompleteComplete

Scope Scope CompleteComplete

Internal Release 1Internal Release 1Internal Release 2Internal Release 2

Internal Release Internal Release nn

Page 22: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Testing the SolutionTesting the Solution

GoalExpose issues, uncover design flaws and identify unexpected behavior

Role of testing:Proactive: Leads build effort (e.g., test-driven development)Supportive: Follows build effort (e.g., design a little, build a little, test a little)

Testing is not just for testersCan be performed by anyone helping improve the completeness and/or quality of work item deliverables

Page 23: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Stabilize TrackMSF Stabilize Track

DeliverablesPilot review Release-ready versions of solution and accompanying collateral Testing and bug reportsProject documents

GoalsImprove solution quality to meet release criteria for deployment to productionValidate solution meets stakeholder needs and expectationsValidate solution usability from a user perspectiveMaximize success and minimize risks associated with solution deployment and operations in its target environment(s)

Release Candidate Release Candidate nn

Release Release Readiness Readiness ApprovedApproved

StabilizeStabilize

Pilot CompletePilot Complete

Pre-Production Testing CompletePre-Production Testing Complete

User Acceptance Testing CompleteUser Acceptance Testing CompleteRelease Candidate 1Release Candidate 1

Issue Log ClearedIssue Log Cleared

Issue ConvergenceIssue Convergence11stst Functional Testing Pass Complete Functional Testing Pass Complete

User Interface StabilizedUser Interface Stabilized

nnthth Functional Testing Pass Complete Functional Testing Pass CompleteSystem Testing CompleteSystem Testing Complete

Page 24: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Deploy TrackMSF Deploy Track

Deliverables

Operations and support

information systems

Revised processes and

procedures

Repository of all solution

collateral

Goals

Place solution into production at designated environment(s)

Facilitate smooth transfer of solution from project team to operations

team as soon as possible

Deployment StabilizedDeployment Stabilized

Deployment Deployment CompleteComplete

Deplo

y

Deplo

y

Site Deployments Site Deployments CompleteComplete

Core Solution Core Solution Components Components DeployedDeployed

Page 25: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Governance TrackGovernance Track

Customer Customer AcceptanceAcceptance

User AcceptanceUser Acceptance

Operations AcceptanceOperations Acceptance

GoalsSecure approval from:

Users that the solution meets their needs and is sufficiently usableOperations that the solution is ready to deployCustomer that the project is complete

Optimize and continuously improve team performance and throughput, solution quality and process improvement

DeliverablesStatus reportsCustomer/user satisfaction dataFinal versions of all project documentsProject closeout report

Repackaged

Page 26: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 27: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Agile ManifestoAgile Manifesto

Individuals and interactions over processes

and tools

Working software over comprehensive

documentation

Customer collaboration over contract

negotiation

Responding to change over following a plan

Page 28: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Time-Boxed IterationTime-Boxed Iteration

Time Box =

Time limit in

which to

complete an

iteration

HowReduce functionalityReschedule features

Page 29: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

PersonasPersonas

On-siteCustomer

Actor

Persona

Page 30: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

ScenariosScenarios

Review

Working Software

Refine

Personas

Real Customers

Scenarios

Page 31: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

The Agile PatternThe Agile Pattern

Scenario ListScenario List

Iteration PlanIteration Plan

Scenario 1Scenario 1Scenario 2Scenario 2

Scenario 3Scenario 3

Iteration 1Iteration 1Scenario 4Scenario 4

Scenario 1Scenario 1

Scenario 2Scenario 2

Scenario 3Scenario 3

Page 32: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Requirements Prioritization (Kano Model)Requirements Prioritization (Kano Model)

MinimumMinimumAcceptanceAcceptanceLevelLevel

Iteration 1Iteration 1Iteration 2Iteration 2

Iteration 3Iteration 3

Page 33: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Visual Studio Team SystemVisual Studio Team System

Page 34: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Using VSTS Agile :Team Explorer WindowUsing VSTS Agile :Team Explorer Window

Page 35: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Using VSTS Agile :Sample ReportUsing VSTS Agile :Sample Report

Page 36: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 37: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

VSTS Template Key ConceptsVSTS Template Key Concepts

Role

Work ItemStates and TransitionsFields

Process GuidanceWork Streams

• Groups of activities that flow logically together• Often associated with a particular role

Activities• Described using EVTX format

Page 38: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile RolesMSF Agile Roles

Project Manager

Business Analyst

Architect

Developer

Tester

Release Manager

Page 39: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile WorkstreamsMSF Agile Workstreams

Capture Product Vision

Create a Scenario

Create a Quality of Service Requirement

Plan an Iteration

Create Solution Architecture

Implement a Development Task

Build a Product

Test a Scenario

Test a Quality of Service Requirement

Fix a Bug

Close a Bug

Release a Product

Guide Project

Page 40: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile “Scenario” :States & TransitionsMSF Agile “Scenario” :States & Transitions

StatesActiveResolvedClosed

TransitionsCompletedTest FailedReactivatedSplitetc.

Page 41: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile “Scenario” :FieldsMSF Agile “Scenario” :Fields

Page 42: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile “Scenario” :ActivitiesMSF Agile “Scenario” :Activities

Business AnalystDevelop lifestyle snapshotBrainstorm scenarios

Project ManagerDivide scenarios into tasks

DeveloperIntegrate code changes

TesterWrite validation testsSelect and run a test case

Page 43: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

MSF Agile “Scenario” :WorkstreamsMSF Agile “Scenario” :Workstreams

Role: DeveloperWorkstream: Fix a Bug

This activity affects the Scenario work item.

Page 44: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

Process Template ManagerProcess Template Manager

Work items

Work item instances

Reports

Security groups

Project portal

Documents / templates

Source control settings

Process guidance content

Iteration structure

Entry criteria and exit criteria views

Source check-in policies

Page 45: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

AgendaAgenda

Motivation

Where MSF fits in SDLC

What’s New in MSF v4.0

MSF for Agile Software Development

Extending VSTS Templates

Q&A

Page 46: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.
Page 47: MSF 4.0 in 60-minutes Milen Petrov Griffin Ltd. Milen Petrov Griffin Ltd.

For More InformationFor More Information

Stay Active In Your Local .NET Community!!

MSF Home Pagehttp://www.microsoft.com/msf

Randy Miller’s Blog (Agile)http://blogs.msdn.com/randymiller

Rob Caron’s Blog (VSTS)http://blogs.msdn.com/robcaron/

SCRUMhttp://www.controlchaos.com/about/VSTS plug-in available from Conchango

Capability Maturity Model Integration (CMMI)http://www.sei.cmu.edu/cmmi/

Microsoft Services QuickPlan for Team-Based Software Development